Daily Site diary & Progress Report
THE DESIGN, PROCUREMENT , FURNISHING AND EXECUTION OF ETHIOPIAN SKYLIGHT 5-STAR HOTEL PHASE-II PROJECT
Project No. & Title: Ref: 392
Employer Engineer: Contractor
ON SITE STAFF & LABOUR RECORD Day: Thursday Date: 2020/11/12 ON SITE PLANT & EQUIPMENT RECORD
No. Trade No. Hrs No. Trade No. Hrs No. Category No. Hrs No. Category No. Hrs
1 Generl Manager 1 9 Weather Sunny Cloudy Rainy Windy Dusty 1 Loader 1 9
2 DGM 1 9 ● 2 Lorry 1 9
3 Contract manager 1 9 3 Mobile Crane 1 9
4 Engineering manager 1 9 Temperature Minimum 9C
:8 C Maximum28C
: 25 C 4 Generator 2 9
5 Safety director 1 9 5 Bar bender machine 2 9
6 MEP iManager 1 9 DELIVERY OF MATERIALS 6 Bar cutter machine 2 9
7 Construction manager 1 9 No. Material Qty. Unit 7 Concrete Pump 2 9
8 Commercial manager 1 9 1 8 Concret boom placer 2 9
9 Civil Engineer 4 9 2 9 Tower Crane 3 9
10 Financial Manager 1 9 3 10 Truck Mixer 4 9
11 Construction Staff 9 9 4
12 Office Staff 7 9 5
13 Site Works 183 7 6
14 7
15 8
VISITORS ON SITE DESCRIPTION OF WORKS DONE
No. Name Organization No. Qty.
1 1 Scaffolding work for the forth floor “H” block part 1 area 70%
2 2 Reinforcement work for the forth floor shear walls and columns “H” block part 1 area 85%
3 3 Formwork for the the fifth floor beams and slabs “H” block part 1 area 50%
4 Scaffolding work for the forth floor “F” block 40%
5 5 Reinforcement work for the forth floor shear walls and columns “F” block 30%
6 Scaffolding work for the “E” block sixth floor. 20%
REMARKS 7 Steel truss assembly for the swimming pool roof . 90%
8 Block work for the ID mock up “E” block second floor 90%
The confirmed cases of COVID-19 in Ethiopian have seriously affected
the project progress .And it has resulted the mobilization delay of chinese 9 Defect column repair basement 2 20%
1
technican and local labor based the site progress and the local workers 10 Steel truss assembly for the ball room .
have decreased rapidly at site. 30%
11
Working time of the local workers has to be decreased from 9 hours to 7 hours
12
2 for one day due to transportation problem caused by COVID-19 and they also
need more payments such as special transportation fee for their work. 13
14
3 Submission : Noted :
Signed by: Song Baoliang Signature Signed by: Signature :