0% found this document useful (0 votes)
35 views1 page

Avic Et Hotel02 DSR 392 00

This daily site diary and progress report summarizes the activities on the Ethiopian Skylight 5-Star Hotel Phase-II construction project for November 12, 2020. It documents the on-site staff and equipment, deliveries, work completed, and remarks. Confirmation of increasing COVID-19 cases in Ethiopia has seriously impacted the project's progress through delays in mobilizing Chinese technicians and reducing the local workforce due to safety restrictions and transportation issues caused by the pandemic.

Uploaded by

baolaing song
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views1 page

Avic Et Hotel02 DSR 392 00

This daily site diary and progress report summarizes the activities on the Ethiopian Skylight 5-Star Hotel Phase-II construction project for November 12, 2020. It documents the on-site staff and equipment, deliveries, work completed, and remarks. Confirmation of increasing COVID-19 cases in Ethiopia has seriously impacted the project's progress through delays in mobilizing Chinese technicians and reducing the local workforce due to safety restrictions and transportation issues caused by the pandemic.

Uploaded by

baolaing song
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Daily Site diary & Progress Report

THE DESIGN, PROCUREMENT , FURNISHING AND EXECUTION OF ETHIOPIAN SKYLIGHT 5-STAR HOTEL PHASE-II PROJECT
Project No. & Title: Ref: 392

Employer Engineer: Contractor

ON SITE STAFF & LABOUR RECORD Day: Thursday Date: 2020/11/12 ON SITE PLANT & EQUIPMENT RECORD

No. Trade No. Hrs No. Trade No. Hrs No. Category No. Hrs No. Category No. Hrs

1 Generl Manager 1 9 Weather Sunny Cloudy Rainy Windy Dusty 1 Loader 1 9

2 DGM 1 9 ● 2 Lorry 1 9

3 Contract manager 1 9 3 Mobile Crane 1 9

4 Engineering manager 1 9 Temperature Minimum 9C


:8 C Maximum28C
: 25 C 4 Generator 2 9

5 Safety director 1 9 5 Bar bender machine 2 9

6 MEP iManager 1 9 DELIVERY OF MATERIALS 6 Bar cutter machine 2 9

7 Construction manager 1 9 No. Material Qty. Unit 7 Concrete Pump 2 9

8 Commercial manager 1 9 1 8 Concret boom placer 2 9

9 Civil Engineer 4 9 2 9 Tower Crane 3 9

10 Financial Manager 1 9 3 10 Truck Mixer 4 9

11 Construction Staff 9 9 4

12 Office Staff 7 9 5

13 Site Works 183 7 6

14 7

15 8

VISITORS ON SITE DESCRIPTION OF WORKS DONE

No. Name Organization No. Qty.

1 1 Scaffolding work for the forth floor “H” block part 1 area 70%

2 2 Reinforcement work for the forth floor shear walls and columns “H” block part 1 area 85%

3 3 Formwork for the the fifth floor beams and slabs “H” block part 1 area 50%
4 Scaffolding work for the forth floor “F” block 40%

5 5 Reinforcement work for the forth floor shear walls and columns “F” block 30%
6 Scaffolding work for the “E” block sixth floor. 20%

REMARKS 7 Steel truss assembly for the swimming pool roof . 90%
8 Block work for the ID mock up “E” block second floor 90%
The confirmed cases of COVID-19 in Ethiopian have seriously affected
the project progress .And it has resulted the mobilization delay of chinese 9 Defect column repair basement 2 20%
1
technican and local labor based the site progress and the local workers 10 Steel truss assembly for the ball room .
have decreased rapidly at site. 30%

11
Working time of the local workers has to be decreased from 9 hours to 7 hours
12
2 for one day due to transportation problem caused by COVID-19 and they also
need more payments such as special transportation fee for their work. 13

14
3 Submission : Noted :

Signed by: Song Baoliang Signature Signed by: Signature :

You might also like