Oyu Tolgoi Project Technical Specification Overview - Underground Explosives Updated March 2017
Oyu Tolgoi Project Technical Specification Overview - Underground Explosives Updated March 2017
1. Project Background
The Oyu Tolgoi mine site is located 550 km south of Ulaanbaatar in the Omnogovi province of Mongolia. The
Oyu Tolgoi mine site consists of a series of ore bodies actively being developed and mined with open pit and
underground mining methods.
The Hugo-Dummett deposit will be mined in a series of lifts. The first stage being Hugo North Lift 1
(500Mtonnes) will be mined utilizing the panel caving mining technique. Mine development includes 203
kilometers of lateral development with principal production levels located 1300m below surface. Mine access
and ventilation of workings is enables by a series of five shafts. Mine life is schedule to extend to 2036, with
potential for additional production panels to prolong mine life more than 50 years.
After early mine development, Hugo North Lift 1 (HNL1) as shutdown since September 2013 and was placed
into care and maintenance. Mining scope completed included:
• 15.7km pre-production mine development from a single shaft access (Shaft #1)
• Shaft #2 at 1166m depth
• Shaft #5 at 207m depth.
2. Scope
The scope of this technical specification is to present an overview the explosive quantities and technical
support requirements for the HNL1 pre-production and production ramp-up period from 2016 - 2022.
Table 2
HNL1 mining occurs in two general geological areas defined by the West Bat fault (Figure 1). Mine
infrastructure is located in barren rock west of the West Bat fault. The rock type is largely defined by volcanic
rock types with intact joints and an Unconfined Compressive Strength (UCS) of 150 MPa. The ore body
comprises a range of rock types with UCS values between 75 and 150 MPa and contains a large quantity of
joint and fault sets.
Barren Rock
(HWS)
Ore Body
Drill patterns have utilized 45mm drill holes on 800mm hole and row spacing. Four 127mm reamer holes are
drilled in the burn cut. Figure 2 illustrates an example drill plan layout.
Typical drill hole lengths are 3.0m, 5.2m, and 6.2m drilled with Atlas Copco M2C and E2C boomer jumbos.
Average break length is greater than 90% of drilled length. Historical charging practices have utilized a lower
density explosive or trim product on the perimeter to manage over-break.
There is an opportunity to improve all aspects of the drill, blast and charging steps of the development cycle.
A wide range of development techniques are anticipated for mass excavation blasting including benching,
slashing, drop raises, and bin development. Excavation envelope tolerance and over-break control is of high
importance.
14m 12m
20m
Current development practice utilizes a wedge cut blast pattern with 48mm holes, 3.2 drill depth and average
round break of 3.0m. Figure 5 outlines an example shaft sinking drill and blast pattern.
5. Technical Support
Technical support is required to integrate the selected explosive product line into all prescribed mining
requirements. This includes but is not limited to:
• Optimization of drill patterns through fragmentation and Velocity of Detonation (VOD) calculations.
• Expertise in draw bell and undercut design and blast pattern planning
• Cost reduction and business improvement
• Training courses in safe and efficient blasting
• Assist with forecasting explosive quantities
• Guidance on fit for purpose perimeter products
• Initiation systems
• MMU operation and maintenance
• Operational support
6. Explosive Management
The supplier will be required to provide management of explosive products from the point of manufacture
until issue to contractor crews underground. This includes provision of surface and underground magazine
management including employment of magazine keepers. Figure 6 outlines the ownership and supply chain.
7. Summary of Requirements
The explosive supplier is to provide a range of products and services that demonstrate capability to fulfill all
mining requirements of Hugo North during the pre-production development and production ramp-up
timeframe. The explosive supplier is expected to provide technical guidance and implementation of a digital
blasting solution that integrates with the site fibre optic system. This system will require
training/maintenance/trouble shooting at a site level.
7.1. Products
The explosive supplier is to provide the necessary explosives (bulk and packaged) and accessories required for
safe, cost efficient blasting. The product range will include fit for purpose products for all aspects of required
development. This includes lateral development, mass excavation, shaft sinking, and production blasting. The
following list of products provides as a minimum the product range that will be required- though not limited
to.
ANFO
Prilled (not powdered) porous ANFO, suitable for use in pneumatically operated air kettles, in an
underground environment.
Product to be gassed at the point of use underground, through the use of a mobile mixing unit or
equivalent. The product will be waterproof and have the material characteristics to be utilised and
remain in vertical up-holes and suitable for use in an underground environment.
Boosters
Cast boosters, to be used to initiate bulk explosives in an underground environment, the dimensions
of the boosters must accommodate a “double locked“ method of priming with detonators. Boosters
must be initiated by a #8 strength detonator, and be suitable for underground environment and use
in both development (<45mm) and production holes (>64mm diameter).
#8 strength detonators suitable for use in underground mining environments with length ranges from
5m-35, suitable for use with boosters and packaged emulsion. The detonators should have coloured J-
hooks for ease of identification, and numbered to clearly indicate the initiation sequence. The
detonators should be suitable for use with 5g detonating cord as a minimum. The range of available
delay numbers should be sufficient to allow controlled blasting for large diameter tunnels or
rises/shafts.
#8 strength detonators suitable for use in underground mining environments with length ranges from
5m-35, suitable for use in boosters and packaged emulsion. The detonators should have coloured J-
hooks for ease of identification, and numbered to clearly indicate the initiation sequence. The
detonators should be suitable for use with 5g detonating cord as a minimum. The range of available
delay numbers should be sufficient to allow controlled blasting for large diameter tunnels or
rises/shafts.
Electric detonators-
#8 strength, suitable for initiation of 5g/m detonation cord. The detonators will be suitable for use in
underground mining environment and water resistant. Zero millisecond delay time available in a
selection of sensitivity (amps required to initiate).
Electronic detonators-
#8 strength detonators, suitable for wet underground environments. Detonators to have capacity to
programme to allow highly accurate timing and scalable blast sizes 1 to 200 holes. The digital
detonators should be available with a proprietary proven means of logging/programming and firing
mechanism.
PETN based signal tube suitable for extending non-electric detonators in length for remote firing
through the use of “stinger” units or equivalent.
Emulsion based packaged explosives suitable for use in lifter holes in development faces or use as
primers in development headings with blast hole size <45mm.
Products to allow effective stemming of holes including but not limited to:- inflatable bags, bottle
brushes or similar
Booster spiders-
Suitable for use in electronic firing, with site based support for the use and initiation of such items.
Hole liners-
Non-static liners suitable for use in wet holes. Hole sizes 64mm, 76mm, 89mm.
Bell wire-
Copper based single strand low resistance wire suitable for use in extending electric detonators to
localised electrical trunk lines.
Full technical and operational specifications of each product to be utilized must be provided for review, these
specification and data sheets must be substantiated from internationally qualified and approved testing
facilities. Items to be included as a minimum are:-
An outline of how each product will be utilized at Hugo North is to be provided. An outline of bulk product and
pumping unit specifications is to be provided for development and production applications discussed.