Practical Guide Sequelec
Practical Guide Sequelec
PRACTICAL GUIDE
for public Distribution facility building
1- PREAMBULE
This fascicule completes the Fascicule N°1 : GP06 « Basic principles » which puts together the
applicable common rules to different types of facilities related to public distribution.
It is an helping guide to build the HTA/BT substation establised in a building (out of IGH). It is
intended for the client (owner) of the operation (who can be the promoter or developer, all
precisions are indicated in the glossary)
SUMMARY
1-Préambule
2- substation présentation
2.1- generaly
2.2- subtation and equipments choice
3- work study
3.1-choice of the place
3.1.1-characterictis of the local
3.1.2- fire risks
3.1.3- Accoustic level
3.2- Plan of Application
3.2.1- common provision
3.2.2- traditional masonry station
3.2.3- prefabricated subtation integrated into a building
3.3- projet implimention study
4- work implimentation
4.1- work to do
4.1.1-execution of civil engineering works
4.1.2- construction of pits and penetrations of cables
4.1.3-layout and acces
4.1.4-prefabricated substation (setting) instalationg
4.1.5- electric equipment instalation and connection
4.1.6-regulatary labels and posters
4.2- Equipe reception and checking
4.3- commissioning and power up
2.4- interviewing
5- glossary
annexe 1 : mass type plan
annexe 2 : Equipment pits
annexe 3 : penetrations of cables
annexe 4 : samples of door and ventilation
annexe 5 : samples of substation equipments
annexe 6 : self-control card
2- SUBSTATIONS PRESENTATION
2- Substation Presentation
2.1- General Aspects
Powered up through an underground piping the HTA/BT (MV/LV) subsations incorporated in
buildings are dimensioned for unitary power of transformation going up to 1000 KVA.
It is made of :
- The civil ingeneering, essentielly made of the substation enveloppe, the door and
ventilations
- The electric devices , mainly made of one MV device, one HV/LV transfomer, an LV board
and some cable connections.
Each element constituting these items , individually must be subject of a declaration of suitability
for rexploitation issued by the GRD. The reference technical documentation of the GRD is
available on the website (www.camae. Enedis.fr)
2.2- substantions and equipements choice
For the substations integtretad in a building, we have two cases :
- The prefabricated substations integrated in buldings. This substation is equiped with the
appropriate civil engeneering equipement both technical and environmental suitable.
These device allow a great ease of implementation and adaptation during their installation.
- The substation is built in traditional masonry and is to be integrated into a building. The
civil engeneering provisions are common to those of the building and each component in
compliance with the technical design rules in force.
The choice of equipment to install is determined by electrnic considerations such as :
- The characteristics of the MV and LV desiccation networks,
- The power and the type of transformer to use.
-
For example : diagram, length and section of the existing electricity network
3- Work study
3. work study
As soon as the project is lauched, the project owner and the GRD work together to determine :
- The location of the room given to the GRD,
- The characteristics of civil engineering according to the type of post chosen
To do this, the project owner submits for appoval a local project to the GRD. After validation, the
GRD draws up a plan for the electrical equipment of the MV/LV substations to be realized (or at
least, a lay-out study of the main components of the substation)
3.1- choice for the premise
The premise proposed by the owner of the operation for the implementation of the substation
incorporated in the building must meet the requirements of the technical device regulations in
force, NF C11-201 ; and additional technical rules of the CRD and compliments below (see
previous mentions in fascicle n°1 : GP06 « basic principles »).
3.1.1-characteristics of the Premise
The Premise must :
- Be reserved to knowledgeble and qualified people.
- Have a straight and permanent access from the way opened on public trafic for any car allowing the transportation ,
handing and lifting of station equipements.
- Be devoted to qualified and warned persons
- Have direct and permanent access from an open trafic way for cars permiting transportation monitoring and lefting
of the substation materials.
If the distance between the way of access and the poste is inferior to 5m, a 1.2 m wide rectilinear
passage and an additional 4 m free can be admitted (transformer unloading) .
- be watertight and protected from a penetration of water.
No conduit or pipe other than that intended for the station shall cross the canal.
In the case of prefabricated substations integrated into the civil enginneering of the building, it is
essential as far as the choice of the premise is concerned , the manufacturer ‘s documents
specifying the installation rules of the substation, the dimensions of its envelope, the position
fans, accesses , etc …. Those datas, integrated into the interior and exterior of the building allow
to validate the ability to integrate the position in the built complex.
3.1.2- Fire risks
As complement to the disposition mentioned in the fascicles n°1 : GP06 « Basic principles » the
owner must justify :
- a two hours fire-cut protection degree for 2 hours for floors, ceilings or walls,
- a two hours fire-cut protection degree for the door if exceptionnaly it opens on the local,
- a transformer container pit with watertight cuveling ready to contain all the dilectic liquide and having a device insuring its quick
national extincteur.
Depending on the main use of the building, additional, elementary provisions are applied. For
example when the room is integrated in an Public Hoster Room (PHR). This bylow , specifically
states that transformer substations must not be in direct communication with premises or
clearences accessible to the public.
3.1.3- Accoustic level
The poste must not constitute a source of accoustic gene for the building dwellers and the
residents according to the technical judgement of may 17th 2001 article 12 ter.
Special attention must be paid by the owner of the operation in order to respect the imposed
noise level (transmission by air or solid)
The contracting authority of the operation can consult the GRD to know the sound level of the
equipment of the substation, the tools and the means available to limit these sound
transmissions.
Upon receip of the promises, the client of the operation must certify that the building meets the
criteria of standardized sound insulation in force corresponding to the use of the building (house,
professionnal public hosting)
3.2- PLAN OF APPLICATION
3.2.1- Common provision
The structure of the premises is in fonction of the structure of the building with however special
provisions for the lay-out and the walls of separation with the other permises.
The substation shall be erected at a height of 0.10 m above the finished exterior ground level,
taking into account the development plans of the latter and the substation’s floor shall be
established above the level of the highest known water level (according to the PPRI). It consists
of a reinforced concrete floor calculated for a rolling laod of 3 tons. The floors and the walls of
the post must be separated from all the adjoining walls of the building.
Exits or necessary clearance must be established to allow for rapid evacuation if necessary. The
upper and lower ventilation grids of a model authorized for use distribution system operator are
preferably located near the transformer and on two different walls of the substation.
3.2.2- traditional masonry station
The areas of exploitation and acces are privileged on the HTA and BT devices. The transformer is
placed preferentially at the bottom of the room. A transformer circulation area with a minimum
width of 1.2 m is maintained between the entrance door and the transformer Pit.
It must allow manual handling by rolling (at most the need for a change of direction to 90° is
allowed). From the operating side of the equipment the width of the manoeuvring area is 0.80 m
minimum.
The refered interior dimensions are 4 m x 4 m and 2.50 m for the ceiling height.
Transformer HTA LV board (8 LV max start
BT cable
The work consistes of integrating a PAC type prefabricated substation with a work permit issued
by the GRD into a construction volume of a building. An upstream consultation between the prime
contractor of the operation and the GRD is essential to take into consideration, from the ouset,
all the requirments (tronsformer, HTA and BT switchboards etc..) the sizing of openings (including
ventillation) and the internal civil engineering contrainst (floor, pits,etc…).
The dimension of the post are indicated in the plans of the manufacturers and vary according to
the internal equipment to be installed.
The floor load of the floor receiving the station shall be calculated according to the total load of
the prefabrication station.
The common provisions indicated above must be respected as well as the requirements on the
common walls. Vis-à-vis a standar prefabricated post, it is up to the project manager to upstream
study a relationship based on the project with the supplier of the post :
- isolation of the walls and other parts of the building
- a device assuring the extinction of the transformer’s dielectric
- maintening the effectiveness of the post breakdowns
- a technical solution ensuring the fire resistance for 2 hours
- the conditions of setting up the position (work planning, protection of internal
equipement….)
- the links between the different protection circuit (inter connection and quipentialty).
- The input of HTA and BT cables.
- The point between the facades of the post and that of the building.
All of these provisions must be communicated and validated by the GRD.
One of the steels of the raft reinforcement or the reinforced concrete floor was about 0.30
vertically above the floor, in the immediate vicinity of the door of the room, on the HTA
switchgear side.
Next to this steel, a coopper conductor with a minimum cross section of 25 mm² connected
by an unmountable connection to the general grounding of the building, emerges 0,5 m
above the level of the floor.
The general grounding of the building and the interconnected reinforcing steel via the
main earth terminal of the substation constitut the protective circuit of the building post.
All the metal reinforcement of the concrete constructing the slabs, floors and walls must
be electrically connected to each other.
For traditional masonry workstations, the floor is made of reinforced concrete of 0.10 m
thick minimum and sized to support a rolling load of 3 tons.
For prefabricated substations, the rooms of location on which it is installed must meet the
requierements of construction mentioned above especially for :
- The walls common to the substation and other premises which must be doubled
and separated,
- The cables penetration rules given below and in appendix 3.
4.1.3.3-Ventilation
The breakdowns selected must be the subject of a declaration of suitability issued by the
GRD according to the technical level in force.
With a useful surface of approximatly 1 m² each (see NFC 11-201), the high and low air
vents are preferably arranged on two different faces, avoiding the immediate proximity of
the HTA switchgear 12 and seeking a difference of maximum level between the fresh air
inlet and the hot air outlet.
Of ‘’natural’’ type, they must ventilate directly on the outside.
4.4 : maintenance
The provision mentioned in issue 1 : GP 64 basic principles are implemented.
If the GRD is exceptionally obliged to accept premises presenting particular difficulties, the
corresponding facilities and their maintenance (access, ventilation, special sound-proofing
devices, sealing…) are the responsability of the project owner of the operation. This rule,
which is independant to the financing terms of the operation, is to be included in the
specifications of the real estate complex.
5- GLOSSARY
BL : Background Loop
LV : Low Voltage between 50 v and 100 v (UTEC 11-001)
PLC : Power Line Carrier
STBC : Scientific and Technical Building Publi establishment of industrial commercial
character created in 1947 under indistrial supervision
DFD : Directional Fault Detector
AFD : Ampere – metric Fault Detector
SIF : Subsequent Intervention File
PD : Publi Lighting
DNM : Distribution Network Manager
NB : the French public electricity distribution network belongs to the authorities
concedents – municipalities. Though the conscession agreements, they delegate the
operation, the maintenance and the developpement of the network present on their
service areas to a GRD.
Conducting, use, maintenance, troubleshooting, monutoring, access etc…
HV High voltage A. between 1000v and 50,000v (UTE 11-001)
TB Tall Building
SGB Standardized Girder and defined as an I section.
Project Means in this document, as the case may be :
Manager of the work AODE acting within the framework of its project management in
eonr of rural electrification.
A promoter or developer acting as master of its real estate operation when the public
distribution post is included in his operation ;
Or a provider of the GRD for the realization of a position outsider any real estate operation.
PEW possibility of the exploitation of the work
RPSC removable potentially for separable connector.
FRPP Flood Risk Prevention Plan
PV Minute
STN : Switched telecol Netwok
PIT : Power and Information Interface Table
SGDU : Standardized Girder and defined as all Profile, with flanges with inclined faces
FU : Functional Unit
Annex 1 : Typical ground plan
Note : the wall angles must be as straight as possible, otherwise you will have to increase its
dimensions preferential for installation and positioning of equipement. It is the same for the
vertical of walls and flatness of the soil.
Annex 2 : Equipments Pits
HTA Switchgear
The pit depth of the HTA switchgear is set to 0.80 m minimum. The lengths and widths of the HTA
pits will be determined by the type and brand of equipment selected, ensuring compliance with
the following points.
- Pit dimensions : sufficient size to respect the radii of curvature of the cables and sufficient
distance between the edge the pit and the points of fixing of the board on the ground ;
- Distances to the walls (rear and side) recommended by the manufactuer of the board
recommandations, maintaining a distance between 20 and 100 mm from the side wall to
the device. The back of the device will be positioned against the wall while maintaining a
minimum distance of 100 mm.
- In absence of manufacturer data, a typical
example of HTA pit (SUF) is proposed below
Metal frame
The volume of dielectric retained is 600 liters below the level of a bed rollers of 50mm caliber
about 3000mm thick above a fire screen (see c11-201 figure 30), a low point is formed in the
bottom of the pit to a low a possible pumping.
NB : any other dielectric retention and extinguishing système may be used subject to agreement
of the GRD prescription service
The support and the grid will be dimensiened to support a thickness of 0.30m of rollers (caliber 50).
BT Table Pit
In the absence of manufaturer data, a typical example of BT pit is proposed below.
Side in mm
Metal frame
metal frame
BT cable setting
The ten sheaths will be aranged in two
superposed layers. Their ends will be
cut in such a way that the principles of
penetration described next page can be
implemented. Providing an additional liner for
CPL
R : location of the passage of the HTA link between the HTA board and the transformer
T : location of the main land terminal.
PENETRATIONS REALIZATION PRINCIPLES
The products must be the subject of a declaration of suitability issued by the GRD.
On the door, a location must be reserved internally and externally to allow the posting of safety
signs.
HTA SWITCHGEAR
The installed HTA (MV) switchgear must consist of compact type of
equipment, or compact expandable, insensitive to its environment, in
accordance with HN64-S-52.
HTA / BT TRANSFORMER
The installed transformer must have protection upstream of the HTA
(MV) winding (technical order Article 19, NFC 17300 and amendment
A1 issue 7) and complies with EU regulation 548/2014.
- Conventional transformer type cabin (ex HN52-5-27)
protection is provided by a HTA device. L1 L2 L3
HTA DEVICE
BT protection device
Any HTA / BT substation must have a low protection device
voltage whose degree to protection is IP2X. It is chosen according
to :
- the type of station installed,
- The power of the installed transformer. Only one HTA
protection device per transformer will be connected,
- The number of BT starts to feed (eg : TIPI 4-500A
- 4 departures, TIPI 8-1200 A8 departures)
Remote control box and default detector. Some substantions
may require the installation of a remot control and information
Interface (ITI) box or a permutation cabinet Automatic Power
Sources (PASA) : double branche network exclusively). To
facilitate the operation of the distribution network, the
distribution network manager can intall a fault detector.
Public Lighting integrated into the prefabricated substation boxes
containing the equipment necessary for the control and control
of public lighting can be installed in a post accessible only from
outside. The diet of these equipment can be realized :
- From the three-phases ACG protection module
incorporated in the TIPI, the maximum admissible current
on this circuit is 60 A.
- From a BT departure of the TIPI, if the intensity is greater
than 60 A.
ANNEX 6 : SELF-CHECK CARD
Non Conveniant
Non
Conveniant
conveniant
N°objet
object or
observation
Signature of the agreement on the post (recording to be defice)
Civil engineering
Generality
Decennial garantee certificate of civil engineering
Conformity of the realization presented with the draft of the mass plan
submitted and accepted by the GRD
Delivery plan
Ground circuit
Presence and conformity of the ohmic value of the building general ground
floor (ground of evacuaion /slab of the building) emerging from 0.5 m
above the level of the floor.
Presence of rebar reinforcing steel or reinforced concrete floor near the
building’s general ground and emerging 0.3 m bellow the floor level.
Access and clearance
Permanent access to the post from public road
Access to electric cable lining
Enough clearance for the opening of door of the post without obstacles
(frome public roar, trees…)
No obstacle in front of the ventillations (high ard low) and cable hatch.
Pits / penetrations / vetilations
Pits and locksmith conformity (HTA board, transformer HTA/BT, BT board
Compliance of the transformer casing with self extinguishing system.
Compliance of the high ventilation and (ow ventilations surfaces with the
power of the transformer
No ventilation device turned toward housing
Presence and complaince of the sheathes (HTA/BT) reminding : the
sheathes not used must be obtured.
compliance of deep penetration of cables
Presence of adapted mechanical protection above the warning grill at the
arrival of cables on the post.
Soil and walls
Soil flatness conformity
Presence of constructive provisions to ensure the conformity of the fully
equipped premises to the noise levels authorized by the regulations.
Spacing of 5 cm and doubling the walls common to the post and other
premises for partitions
Visual aspect of the civil engineering envelope and the joint of the post with
the bulding
Realization of the specific external arrangements requested by the project
manager of the operation and authorized by the GRD
No room and / or station lighting
No pipes going through the premise
No duct passing through the room door and regulatory signs outside the
station (PR10, PR11, AF 20B…)
Regulatory signs inside the station
Electrical equipment part
Non
Non Conveniant
Conveniant
N° Object
conveniant
object or
observation
HTA Switchgear
Presence of instruction for use and instructions for the HTA board
Presence of manoeuvering accessoirs
Rating of HTA fuses in line with the rated power of the transformer
Mounting and connecting th fault detector
Presence of blanking plates on cable ducts
Presence of phases comparator
HTA depature identification
Connect of the switchboard to the earth circuit
Remote control box (connection and marking)
Transformer
Visibility of the name plate
Power in adequacy with the project
Voltage in adequacy with U network HTA.
Position of the setting
HTA connection (plag-in and socket lock)
BT Link : the number of drivers matching the intensity assigned table
TIPI
Installation of insulating protection on BT connection parts
BT Switchgear
Type of TIPI in adequacy with the power of the transformer
Location departures
Fuse rating check
Control of public lighting
Without earth outlet
Connection of departures
Short-circuit in open position, compliant position indicator
Connecting the classis to the ground circuit
Attaching the linky hub
Others (CPL…)
Grounding
Connection of all the elements to be connected to the ground on the
terminal of the land (neutral BT also urban area)
Neutral grounding connected to the TIPI switchboard
Verification of the continuity of the earth circuit
Access to the connection device (‘’C’’ connector)
Coupling coefficient (15%) between the earthing of the BT neutral
and the earth ground of the sudstation.
Resistance of the earth connection