SECTION 07 27 27 Fluid-Applied Membrane Air Barriers, Vapor Retarding
SECTION 07 27 27 Fluid-Applied Membrane Air Barriers, Vapor Retarding
SECTION 07 27 27
FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR RETARDING
PART 1 - GENERAL
1.1.1.1 SUMMARY
A. Section Includes:
1. Fluid-applied vapor-retarding air barrier at exterior above grade
wall assemblies.
2. Connection to adjacent air barrier components providing a durable,
continuous, full building air barrier.
07 27 27 - 1
02-01-16
07 27 27 - 2
02-01-16
1.1.1.4 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES.
1. Indicate size, configuration, and fabrication and installation
details.
B. Manufacturer's Literature and Data:
1. Description of each product.
2. Installation instructions.
C. Sustainable Construction Submittals:
G. Installation Audit:
1. Submit audit report.
07 27 27 - 3
02-01-16
3. Accreditation by ABAA.
C. Installer Qualifications:
1. Regularly and presently installs specified products.
2. Approved by manufacturer.
3. Accredited by ABAA.
4. Applicators certified according to ABAA Quality Assurance Program.
07 27 27 - 4
02-01-16
1.1.1.6 DELIVERY
A. Deliver products in manufacturer's original sealed packaging.
B. Mark packaging, legibly. Indicate manufacturer's name or brand, type,
production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted,
damaged, or opened packaging.
07 27 27 - 5
02-01-16
1.1.1.9 WARRANTY
PART 2 - PRODUCTS
07 27 27 - 6
02-01-16
2.1.1.4 ACCESSORIES
A. Primer: Waterborne primer complying with VOC requirements, recommended
air barrier manufacturer to suit application.
B. Counterflashing Sheet: Modified bituminous, minimum 1.0 mm (40 mils)
thick, self-adhering composite sheet consisting of minimum 0.8 mm
(33 mils) of rubberized asphalt laminated to polyethylene film.
C. Substrate Patching Material: Manufacturer's standard trowel-grade filler
material.
D. Sprayed Polyurethane Foam Sealant: Foamed-in-place, 24 to 32 kg/cu. m
(1.5 to 2.0 pcf) density, with maximum flame-spread index of 25 when
tested according to ASTM E84.
07 27 27 - 7
02-01-16
PART 3 - EXECUTION
3.1.1.1 PREPARATION
A. Examine and verify substrate suitability for product installation.
B. Protect existing construction and completed work from damage.
C. Correct substrate deficiencies:
1. Remove projections and excess materials and fill voids with
substrate patching material.
2. Remove contaminants capable of affecting subsequently installed
product's performance.
D. Prepare and treat substrate joints and cracks according to ASTM C1193
and membrane air barrier manufacturer's instructions.
07 27 27 - 8
02-01-16
07 27 27 - 9
02-01-16
C. Field Tests:
1. Qualitative air-leakage testing according to ASTM E1186.
2. Quantitative air-leakage testing according to ASTM E783.
D. Inspection and Test Frequency: Determined by installed air barrier
surface area.
1. Up to 900 sq. m (10,000 sq. ft.): One inspection.
2. 901 - 3,300 sq. m (10,001 - 35,000 sq. ft.): Two inspections.
3. 3,300 - 7,000 sq. m (35,001 - 75,000 sq. ft.): Three inspections.
4. 7,001 - 11,600 sq. m (75,001 - 125,000 sq. ft.): Four inspections.
5. 11,601 - 19,000 sq. m (125,001 - 200,000 sq. ft.): Five inspections.
6. Over 19,000 sq. m (200,000 sq. ft.): Six inspections.
E. Submit inspection and test reports to Contracting Officer’s
Representative within seven calendar days of completing inspection and
test.
F. Audit:
1. Provide installer and site inspection audit by ABAA.
2. Coordinate scheduling of work and associated audit inspections.
3. Cooperate with ABAA’s testing agency. Allow access to work and
staging areas.
4. Notify ABAA in writing of schedule for Work of this Section to allow
sufficient time for testing and inspection.
5. Pay for site inspections by ABAA to verify conformance with the
ABAA Quality Assurance Program.
G. Defective Work:
1. Correct deficiencies, make necessary repairs, and retest as required
to demonstrate compliance with specified requirements.
07 27 27 - 10
02-01-16
3.1.1.4 CLEANING
A. Remove masking materials.
B. Clean spills and overspray using cleaning agents recommended by
manufacturers of affected construction.
3.1.1.5 PROTECTION
A. Protect air barrier from construction operations.
B. Protect air barrier from exposure to UV light exposure exceeding
manufacturer's recommendation.
C. Replace overexposed materials and retest.
- - E N D - -
07 27 27 - 11