New Operations Manual - General
New Operations Manual - General
BIOMASS GASIFIER
I.A INTRODUCTION
Since prehistoric times, biomass has been the single major source for meeting the
energy needs of mankind. Only after the late 18 th Century, have fossil fuels such as
coal and petroleum displaced wood as an energy source. Even now, biomass is still
widely used to meet the domestic and community cooking needs and for limited
industrial use in most developing countries. Wood and other bio-residues, besides
being used in solid form, can be gainfully converted into gaseous form through
gasification route. Gasification technology thus affords more precise control over
energy levels and can cater to various thermal and electrical energy needs. The
following sections provide information on the present state of the art of biomass
gasification technology and its applications.
In the reactor, biomass feedstock, after undergoing drying and de-volatilisation in the
upper zones, leaves behind char. The volatiles undergo oxidation in the combustion
zone, with air being partially supplied by the surrounding nozzles, and the remaining
being drawn from the open top.
The product gases further get reduced in the bed of charcoal and yield a
combustible gas called producer gas, having calorific value of 4.5- 5.0 MJ/m 3 (1000
– 1200 kcal/ m3).
Producer gas has the following average chemical composition.
CO: 20 + 2%;
* Biomass is any botanical derivative with bulk density greater than 250 kg/m 3 and
ash content less than 2 - 3%. Typical examples are various species of wood such
as Casuarina, Acacia, Eucalyptus, Prosopsis Juliflora, coconut shell, cotton
stalks, mulberry twigs and weeds such as Ipomoea. Powdery and loose
bioresidue such as rice husk, De-Oiled Bran, saw dust etc. should be compacted
to achieve higher density. Such agro-residue generally tends to have higher ash
content of 6% to 20%.
I.C APPLICATIONS
Producer gas, obtained by the process of gasification, can be employed in thermal
application or for mechanical/electrical power generation. Like any other gaseous
fuel, producer gas affords much better control over power levels when compared to
solid fuel. This also paves the way for more efficient and cleaner operation. Producer
gas can be conveniently used in a number of applications as detailed below
I.C.1 THERMAL
Thermal energy of the order of 4.5 to 5.0 MJ is released, by burning 1 m 3 of producer
gas in the burner. Flame temperatures as high as 1500 K can be obtained by
optimal pre-mixing of air with gas. For thermal applications, gasifiers are a good
option as a gas generator and can be retrofitted with existing devices. Producer gas
can thus replace fossil fuels in a wide range of devices. A few of the devices which
could be retrofitted with gasifiers are furnaces for melting non-ferrous metals and for
heat treatment, tea dryers, ceramic kilns, boilers for process steam and thermic fluid
heaters.
In the oxidation zone, the volatiles undergo oxidation with the release of CO 2 and
H2O. These product gases further undergo reduction in the presence of hot bed of
charcoal and yield a combustible gas mixture. The hot gases exiting the reactor
bottom pass through a series of Cooling and Cleaning Equipment. The first is an
Indirect Cooler, where the product gas loses some of its sensible heat to a
circulating jacket. It then passes through a dry Cyclone, where most of the
particulate matter entrained in the gas stream is removed by centrifugal action. The
gas then passes through a counter current direct cooler, where the gas is thoroughly
scrubbed by a water spray. In this process the gas is cleaned and cooled to near
ambient temperature. The gas is further led through a water scrubber, a wet cyclone,
a DCC and a blower.
The Piping & Instrumentation Drawing of the gasifier system is shown in Fig. 1
(Please refer to Part II for specifications).
II.D.2 REACTOR
The reactor is a cylindrical vessel with outer walls made of mild steel, which is
internally insulated with cold face insulation bricks, hot faced insulation bricks and
ceramic tiles composed largely of alumina.
II.F.5 DCC
The gas from the Wet Cyclone is then sent through a DCC, where the gas is given a
thorough diesel wash. This process substantially reduces the particulate and tar
content in the gas and facilitates trouble free operation of the Client’s furnace control
devices such as ratiotrol further downstream.
II.K.6 CENTRIFUGE
Backwash water from the Water Treatment Plant is periodically passed through 16”
high-speed centrifuge to separate the dregs and particulates from the water, which is
then recycled. The dregs being mainly carbon can be disposed of as fuel after sun
drying.
II.L CONTROLS
The gasifier System is provided with an advanced Control system consisting of a
PLC based Control Panel and an Operation Control desk with manual override
capabilities.
II.M.5.3 PNEUMATIC 2”
Two 2” Pneumatic Control Valves (PV3, PV4) are provided at the flame trap.
II.M.5.4 PNEUMATIC 1”
One common 2” Pneumatic Control Valve (PV5) is provided for flooding of drain
cups of the Air Nozzles.
II.M.5.5 SOLENOID 1”
Two 1” solenoid valves (SV1, SV2) are provided. The first is common for draining of
air nozzles and the second is for flooding of Ash Dump with water during ash
extraction as indicated earlier.
OPERATION
&
MAINTENANCE
1. Fill large sized pieces in small bags (3-5 kg holding capacity) and lower it by
means of a rope into the reactor from reactor top (use two ropes, one tied to the
top edge and the other to the bottom edge of the bag).
3. Repeat the above procedure several times until a bed/layer is formed across the
reactor.
4. Subsequently, the charcoal could be loaded by emptying large bags directly from
the reactor top.
5. Avoid using conveyor for loading charcoal, as it will be broken into pieces.
13 Switch on the main burner valve selector switch to on this will open the valve by
energising K9contactor through main selected contactor K3.
The bottom water collector is of header and lateral type. The header lateral collecting
system consists of a mild steel header pipe with socket connections at the bottom
into which threaded PVC laterals are screwed. Each lateral has a number of holes
along its length through which the water can pass.
The vessel is painted inside with a special bituminous paint for corrosion resistance.
In the case of carbon filters used for de-chlorination, epoxy coating is generally
employed.
The filter media sand is supported on layers of inert under-bed material (pebbles and
gravel of various sizes). An air release pipe is provided for releasing the air from the
unit. Pressure gauges are provided on the inlet and outlet to ascertain the pressure
loss across the filters.
The raw water is distributed by means of an inlet bell mouth pointing in an upward
direction inside the vessel.
The bottom water collector is of header and lateral type. The header lateral collecting
system consists of a mild steel header pipe with socket connections at the bottom
into which threaded PVC laterals are screwed. Each lateral has a number of holes
along its length through which water can pass.
The filter media activated carbon is supported on layers of inert under-bed material
(pebbles and gravel of various sizes.) An air release pipe is provided for releasing
the air from the unit. Pressure gauges are provided on the inlet and outlet to
ascertain the pressure loss across the filters.
A micrometer type internal cylinder can be rotated through 10 turns to set the precise
dosing rate even when the pump is in use.
ONE Vertical, welded mild steel pressure vessel, complete with dished ends and
internally painted with anti-corrosive bituminous paint and externally with two coats
of primer.
ONE Set of internals for the above, comprising of raw water distributor and filter
water collecting system
ONE Set of frontal pipe work of mild steel, complete with vent piping and valves
Valves type : CI diaphragm flanged ends
Size : 40 NB
Air vent valve : 20NB
ONE Initial charge of filter media comprising of graded washed sieved gravel and
filtering sand
ONE Vertical, welded mild steel pressure vessel, complete with dish ends and
internally painted with anti-corrosive bituminous paint and externally with two coats
of primer.
ONE Set of frontal pipe work of mild steel, complete witH bend piping and valves
Valves type : CI diaphragm flanged ends
Size : 40 NB
Backwash inlet : 25NB
Air vent valve : 20NB
ONE Initial charge of filter media comprising of graded, washed, sieved gravel and
activated carbon
2. Filter cleaning should be done whenever the pressure drop across the filter
exceeds the normal operating pressure drop by 0.35 kg/cm2 in the case of
sand filters.
4. Open the wash outlet valve. Slowly open the wash inlet valve taking care to
see that filter media is not carried along with the water.
5. Continue until the wash water is clear. Then close the wash outlet valve and
open the air release valve.
6. When all the air is removed close the wash inlet and air release valve.
7. Open the inlet and drain valves. When the water becomes clear close the
drain valve and open the outlet valve. Set the flow at the desired value by
controlling the outlet valve.
8. The wash water flow is specified on the technical data sheet. It is essential
that it is not exceeded; otherwise filter media would be lost to the drain. Too
low a flow would mean incomplete cleaning of the bed.
III.F.4 MAINTENANCE
The routine maintenance of the PLANT should include the following:
1. VALVES
At periodic intervals (say once a month) open the valves and check seating and
gate. Attend to gland packing, replace if necessary, do routine lubrication of the
spindle.
2. EXTENDED BACKWASH
Once in a week extend the backwash operation to at least 45 minutes to keep the
bed clean.
3. ANNUAL SERVICING
Once in a year, check the condition of the paint inside the unit. If any signs of
corrosion are noticed, remove the media, clean the surface and apply 2 coats of
anticorrosive bituminous paint for sand filters and epoxy paint for activated
carbon filter.
4. STERLISATION OF CARBON FILTERS
a. During the initial starting up of the plant it is necessary to sterilise the sand
and carbon filters one after other (wherever provided). Operate the treatment
plant until approximately correct treatment is obtained. With all valves on
filters closed, proceed as follows:
g. Allow water to run downwards through the carbon to drain until the effluent is
free from chlorine. The treated water can then pass to service provide that
the other chemical tests are satisfactory.
Procedure 2:
1) Connect the gasifier to the blower on flare mode (without lighting in the flare).
3) Mend all such leakages found and repeat the leakage test.
DO’S
Ensure that
1 The charcoal/biomass does not have any extraneous material such as stones,
metal, mud etc.
3 Water is being sprayed continuously in the cooler prior to and during the run.
4 Coolant water temperature does not exceed + 5C above ambient during run.
5 Correctly sized biomass is loaded into the reactor and safe working level
maintained.
6 There is water in the top cover water seal when the top cover is shut.
8 There is charcoal available at least 1 metre above the air nozzle before the start
of the run (if the gasifier is run for the first time or after unloading, the reactor
should be completely filled with dry char coal).
9 Water at indicated flow rates flows through the coolers and scrubbers.
10 Diesel at indicated flow rates flows through the DCC. Maintain the pressure drop
at 120mm to 150mm WG at all times across the DCC.
11 The flame is ignited at start-up only when the O2 level in the gas is below 2%.
12 Dust from the dry cyclone is removed/ discharged once every 24 hours of
operation.
1) Pour water into the reactor under any circumstance, to shut off the reactor.
3) Expose the bottom of the reactor to atmosphere when the reactor is hot.
4) Operate the gasifier at higher load/flow rate immediately after fresh start. Then
there is a possibility of biomass not totally converting into char by the time it reaches
the air nozzle. Hence follow start up procedure meticulously.
The reactor has to be unloaded once the pressure drop across the reactor shoots
beyond 350-400 mm of WG. It is better to allow the reactor to cool down, say a day,
before attempting unloading. Additional care has to be exercised while handling as
the reactor bed could be hot and may cause injury/burns.
4. Feed stock Any sun dried solid biomass whose density is over 300
kg/m3, having moisture content of 10 - 15%, max
(20%)* cut to sizes up to 150 mm - a mix of sizes
upwards of 25 mm. Briquette of any agro residue mix
< 24 hrs 140 to 150 hrs 500 to 700 hrs > 2500 hrs
1. Shut down 1. Open and scrape out 2. Remove and check for 1. Replace
the gasifier, adhered particles in: damages on central air Gear Oil
open the a. Direct cooler nozzles nozzle water jackets. (SAE ISO
bottom b. Water scrubber Replace if damaged. Grade 150)
flanges and c. Diesel scrubber and filter TIME 2 HR of Screw
remove dust d. Inside of flame trap. Conveyor
particles from TIME 8 HR. 3. Remove and check for Geared
dry cyclone. damages on secondary air motor after
TIME 20 MIN. 2. Empty left over charcoal nozzles, and replace first 50/100
from ash extraction sealed nozzles as required hrs of
2. Open and tank. TIME 4 HR geared
drain water TIME 4 HR. Motor
from wet 3. Change water for the top 4. Tighten all nuts & bolts of operation
cyclone cover seal. all system components. and after
TIME 5 MIN. TIME 10 MIN TIME 4 HR every 12
months
3. Open and 4. Grease ash extraction 5. Replace 50 % water in thereafter.
release bearing housings with SAE the Main Cooling Water TIME 8 HR
moisture from sufficiently Sump and Wash Water
moisture trap TIME 10 MIN Sump should the quality of 2. Unload
every 3 hours water deteriorate. the reactor
TIME 5 MIN. 5. Open and check for TIME 3 HR & check
loosening of nuts and bolts in thoroughly
4. Back wash bucket elevator. 6. Make up Gear Oil to for
Sand Bed TIME 4 HR required level in the Screw damages
Filter every 4 6. Open and clean foot valves Conveyor Geared Motor. on high
hrs. of main cooling water, wash TIME 1HR alumina
TIME 10 MIN. water and treatment plant tiles.
pumps. TIME 2 HR Replace
the tiles in
7. Clean all holes on the case of
cooling tower water damage.
distribution headers TIME 24 HR
TIME 1 HR