Hitachi Medical Systems America, Inc.: OASIS Mark II - Standard Details
Hitachi Medical Systems America, Inc.: OASIS Mark II - Standard Details
OASI S
Contents:
PAGE 01 of 27: Typical Planning Process PAGE 14 of 27: Electrical - Panel Schematic
PAGE 02 of 27: Typical Planning Process (cont) PAGE 15 of 27: Electrical - General Notes
PAGE 03 of 27: General Siting Criteria PAGE 16 of27: Wireways n ,
PAGE 04 of 27: Representative Suite Layout PAGE 17 of 27: Wireways (cent)
PAGE 05 of 27: Minimum Suite Layout PAGE 18 of 27: Wireways (cent)
PAGE 06 of 27: General Suite Criteria PAGE 19 of 27: Safety
PAGE 07 of 27: Floor Loading Structural PAGE 20 of 27: Cryogen Vent - Sizing
PAGE 08 of 27: RF and Magnetic Shielding PAGE 21 of 27: Cryogen Vent - Notes
PAGE 09 of 27: Environmental PAGE 22 of 27: Magnet Proximity
PAGE 10 of 27: Chiller Requirements PAGE 23 of 27: Rigging and Delivery
PAGE 11 of 27: Chiller Installation Checklist PAGE 24 of 27: Gauss Fields
PAGE 12 of 27: Chiller Installation Specifications PAGE 25 of 27: System Components
PAGE 13 of 27: Electrical - Lighting PAGE 26 of 27: System Components (cent)
PAGE 27 of 27: Pre-Delivery Checklist
DOCUMENT ESTABLISHED- 04/30/2012
SPD-GDE-OAS2-1 OM# 84149 v3
OASIS Mark II REVISIONS
PREVIOUS REVISION - 05/18/2012
REVISIONS
SITE SELECTION AND EVALUATION (3 WEEKS) CUSTOMER REVIEW AND PRELIMINARY PRE-CONSTRUCTION (CON'T)
A) SITE SELECTION (1 WEEK) PLANS (VARIES) C) SELECTION OF CONTRACTOR
1) SALES: 1. THE DRAWINGS GO OUT TO BID AND A GENERAL CONTRACTOR WILL BE CHOSEN
a. SUBMITS COMPLETED/PARTIALLY COMPLETED SITE SELECTION SURVEY WITH A) SITE EVALUATION REPORT BY THE CUSTOMER. THE CUSTOMER/ARCHITECT MUST PROVIDE SITE PLANNING
CUSTOMER INFORMATION 1) SALES: WITH A CONTACT AND TELEPHONE NUMBER. THE ARCHITECT OR GENERAL
b. PROVIDES A SCALED DRAWING OR A DIMENSIONED SKETCH a. REVIEWS THE REPORT WITH THE CUSTOMER (SITE PLANNING IS AVAILABLE VIA CONTRACTOR IS RESPONSIBLE FOR SECURING THE BUILDING PERMITS DURING
c. REQUESTS EVALUATION ASSISTANCE FROM SITE PLANNING TELEPHONE IF NECESSARY) THIS TIME.
d. PROVIDES AN OPPORTUNITY NUMBER b. REVIEWS REVISED LAYOUT WITH THE CUSTOMER
2) SITE PLANNING: D) PRE-CONSTRUCTION MEETING (SCHEDULED BY
a. RECORDS DATA AND ASSIGNS OPPORTUNITY TO A REGIONAL SITE PLANNER B) SITE DRAWING AND DETAILS CUSTOMER/ARCHITECT)
b. PROVIDES STANDARD DETAILS TO CUSTOMER AS REQUIRED 1) SITE PLANNING: 1. PLANS ARE REVIEWED AND OUTSTANDING QUESTIONS ARE ADDRESSED.
c. PREPARES A PRELIMINARY EQUIPMENT LAYOUT WITH CLEARLY IDENTIFIED a. PREPARES A FINAL LAYOUT AND FOLLOWS UP ON THE SITE CONCERNS. A CONSTRUCTION SCHEDULE SHOULD BE AGREED UPON AT THIS MEETING AND A
ISO-CENTER THAT MAY INCLUDE: DELIVERY DATE IDENTIFIED. THE HMSA FIELD SERVICE ENGINEER WILL ALSO BE
d. REVIEWS PRELIMINARY DATA FOR SITING CONCERNS 1. REQUESTING A MAGNETIC SHIELD DESIGN FOR FRINGE FIELD CONTROL INTRODUCED TO THE CUSTOMER AND CONTRACTOR AT THIS MEETING.
e. SCHEDULES A SITE VISIT WITH THE CUSTOMER AND SALESPERSON, 2. REQUESTING A MAGNETIC SHIELD DESIGN TO CONTROL INTERFERENCE
INCLUDING SITE TESTING 3. PROVIDING THE CUSTOMER WITH A CONTACT TO ADDRESS VIBRATION ISSUES
SITE CONSTRUCTION (6-8 WEEKS)
B) SITE EVALUATION (1 WEEK) C) ON SITE MEETING (SCHEDULED BY CUSTOMER) A) ON SITE EVALUATION
1) SITE PLANNING: 1) SALES AND SITE PLANNING: 1) FIELD SERVICE ENGINEER:
a. VISITS SITE AND VERIFIES PREVIOUSLY SUBMITTED INFORMATION a. MEET WITH THE CUSTOMER AND THEIR DESIGN TEAM TO: a. VISITS SITE ON A ROUTINE BASIS TO VERIFY PROGRESS
b. PREPARES A SITE EVALUATION REPORT WITH RECOMMENDATIONS AND 1. REVIEW AND FINALIZE THE EQUIPMENT LAYOUT b. ADVISES SITE PLANNING OF SITE STATUS AND ANY CONCERNS
FORWARDS IT TO THE SALESPERSON TO PRESENT TO THE CUSTOMER 2. REVIEW STANDARD DETAILS 2) SITE PLANNING:
c. CONFIRMS SUITE DIMENSIONS, MODIFY AS NEEDED 3. ADDRESS OUTSTANDING QUESTIONS OR CONCERNS a. ADDRESSES CONCERNS WITH ARCHITECT OR CONTRACTOR AS NEEDED
d. ASSISTS CUSTOMER I CONTRACTOR IN IDENTIFYING A 600 SF AREA TO BE 4. IDENTIFY PRELIMINARY DELIVERY SCHEDULE b. COORDINATE AND SCHEDULE DELIVERY OF CHILLER IF PROVIDED BY HMSA
DESIGNATED FOR CLEAN AND SECURE STORAGE OF COVERS AND ANCILLARY
EQUIPMENT AT TIME OF DELIVERY
e. COORDINATES AND COMPLETES SITE TESTING
B) PRIOR TO DELIVERY
f. DISCUSSES CONCERNS WITH THE CUSTOMER (AND DESIGN TEAM I PRE-CONSTRUCTION (VARIES) 1. CUSTOMER CONTRACTED RIGGER PERFORMS ON-SITE INSPECTION 1-4 WEEKS
CONTRACTOR IF AVAILABLE) A) ARCHITECT PREPARES CONSTRUCTION DRAWINGS PRIOR TO THE DELIVERY TO VERIFY OFF LOAD CONDITIONS.
g. ASSIST IN IDENTIFYING POSSIBLE ALTERNATE LOCATIONS IF APPROPRIATE 2. CUSTOMER/CONTRACTOR INSTALLS R1200 CHILLER UNIT, COMPLETES
1. INPUT MUST BE COORDINATED WITH VARIOUS CONSULTANTS
h. REVIEW STANDARD DETAILS WITH CUSTOMER (AND DESIGN TEAM I INSTALLATION CHECKLIST AND RETURNS IT TO HASKRIS (SEE PG 11) AND
a. HMSA
CONTRACTOR IF AVAILABLE) SCHEDULES CHILLER STARTUP PRIOR TO DELIVERY DATE.
b. ENGINEERS (STRUCTURAL, HVAC, ELECTRICAL)
3. FINISH FLOORING MUST BE COMPLETELY INSTALLED. IT IS THE
c. RF SHIELDING VENDOR (REQUIREMENTS VARY WITH DIFFERENT VENDORS)
NOTE: CUSTOMER/CONTRACTOR'S RESPONSIBILITY TO PROVIDE A PROTECTIVE
B) HMSA REVIEW OF ARCHITECTURAL DRAWINGS COVERING (MASONITE IS RECOMMENDED) DURING THE INSTALLATION. IF
1) ALL TESTING MUST BE DONE DURING PERIODS OF TYPICAL ACTIVITY IN THE 1. IT IS HIGHLY RECOMMENDED THE ARCHITECT SEND BID OR PERMIT DOCUMENTS FLOORING IS NOT INSTALLED PRIOR TO DELIVERY, IT MAY NOT BE LAID UNTIL
SURROUNDING AREA TO HMSA SITE PLANNING FOR GENERAL REVIEW TO HELP AVOID ERRORS OR AFTER THE OASIS MARK II INSTALLATION IS COMPLETE. FLOORING
2) ACTIVITY IN THE IMMEDIATE AREA OF THE PROBE MUST BE RESTRICTED OMISSIONS PRIOR TO CONSTRUCTION INSTALLED AFTER
DURING THE TEST
THE INSTALLATION, MUST BE TRIMMED AROUND THE BOTTOM OF THE SYSTEM
3) THERE ARE LIMITATIONS TO THE AMOUNT OF INTERFERENCE THAT THE
OASIS MARK II SYSTEM CAN CORRECT FOR. IF THE INTERFERENCE(S) EXCEED NOTE: THIS IS A REVIEW AND NOT AN APPROVAL. HMSA ACCEPTS NO LIABILITY FOR COVERS AND MAY NOT BE SLID UNDER THEM. THE MAGNET WILL BE LIVE AND AT
ERRORS OR OMISSIONS. IT IS THE RESPONSIBILITY OF THE CUSTOMER AND THEIR DESIGN FIELD AT THAT TIME. NON FERROUS TOOLS WILL BE REQUIRED.
CORRECTABLE LEVELS, THE FOLLOWING MAY BE REQUIRED.
TEAM TO PREPARE THE SUITE TO MEET THE GUIDELINES PRESENTED IN THIS DOCUMENT 4. THE CUSTOMER OR THEIR AUTHORIZED REPRESENTATIVE IS RESPONSIBLE FOR
a. DETERMINE AND ELIMINATE SOURCE OF INTERFERENCE
ENSURING THE PRE-DELIVERY CHECKLIST IS FILLED OUT AND ALL ITEMS ARE
b. INSTALL MAGNETIC SHIELDING
EITHER COMPLETED OR SCHEDULED FOR COMPLETION PRIOR TO DELIVERY OF
c. SELECT NEW SITE
THE SYSTEM. THE CHECKLIST MUST BE SUBMITTED TO HMSA 14 DAYS PRIOR
TO THE REQUESTED SYSTEM DELIVERY DATE. IF THE CHECKLIST ITEMS ARE NOT
C) INFORMATION CONSOLIDATION (1 WEEK) COMPLETED AS REQUIRED, THE DELIVERY MAY HAVE TO BE DELAYED.
1) SITE PLANNING:
a. REVISES PRELIMINARY DRAWING/SKETCH AS NEEDED NOTE: THE OASIS MARK II SYSTEM IS DELIVERED PRE-FILLED WITH
b. SUBMITS TEST RESULTS AND CONFIRMED SITE DATA TO TECH SUPPORT FOR CRYOGENS. THIS REQUIRES THAT THE CHILLER AND ELECTRICAL POWER
REVIEW
c. PREPARES SITE EVALUATION REPORT AND VIA TELEPHONE, DISCUSS BE OPERATIONAL AND READY FOR CONNECTION TO THE OASIS MARK II
ACTIONS AND RECOMMENDATIONS WITH SALESPERSON SYSTEM TO AVOID A POTENTIAL AND COSTLY BOIL-OFF.
OPERATIONS
A. STRONG VISUAL CONTACT BETWEEN THE OPERATOR AND THE PATIENT MUST BE MAINTAINED.
B. SUFFICIENT AND CONVENIENT WORK SURFACES AND STORAGE MUST BE INCLUDED IN AND NEAR THE MRI SCAN AND CONTROL
ROOMS. VIEW BOXES SHOULD BE CONSIDERED IN THE CONTROL ROOM.
HITACHI MEDICAL SYSTEMS AMERICA
1959 SUMMIT COMMERCE PARK TWINSBURG, OH 44087-2371
C. A SINK SHOULD BE LOCATED NEARBY, BUT IS NOT RECOMMENDED IN THE MRI SCAN ROOM UNLESS REQUIRED BY CODE. SINKS PLACED
IN THE MRI SCAN ROOM MUST BE COORDINATED WITH THE RF VENDOR. (800) 800-3106 WWW.HITACHIMED.COM
D. THE ENVIRONMENT WITHIN THE SCAN SUITE MUST BE MAINTAINED 24 HOURS PER DAY, 7 DAYS PER WEEK. REFER TO THE
ENVIRONMENTAL SECTION OF THIS GUIDE FOR SPECIFICATIONS REGARDING ALLOWABLE RANGES FOR TEMPERATURE AND
GENERAL SITING CRITERIA
HUMIDITY.
DATE: 04/30/2012 I REVISION: 01/19/2015
OASIS MARK II STANDARD DETAILS I PAGE 03 OF 27
REPRESENTATIVE SUITE LAYOUTS LEGEND
========
= RF SHIELD. ARCHITECT TO VERIFY WALL
CONSTRUCTION WITH RF VENDOR.
(TYPICAL 5" RF WALL THICKNESS REFLECTED.)
=~~~~~E= RF VIEW WINDOW, TYPICALLY 4'w X 3'h (TYP 36" AFF)
===:::;7'\;::::===
L..:>.
PHONE LINES- ONE (1) REQUIRED IN EQUIPMENT ROOM AND
ONE (1) REQUIRED IN THE CONTROL ROOM.
9
~
1!] @ ®
--··-- 6" X 24" ON-WALL WIREWAY WITH REMOVABLE COVER
AND THREE (3) DIVIDERS. METAL ONLY. MUST BE
NON-FERROMAGNETIC IN SCAN ROOM.
I
EQUIPMENT ROOM ®
::::--==-_==--==- == AND THREE (3) DIVIDERS. METAL ONLY. MUST BE
_____.:::.:::.:::..= NON-FERROMAGNETIC IN SCAN ROOM.
~~~~~~~~~ 6" X 3" OVERHEAD CABLE TRAY (WALKER SPMA-A-6-3S
\ MINIMUM CEILING OR EQ). MUST BE NON-FERROMAGNETIC.
HEIGHT 8'-0"
~ 1G
~ MAGNETISOCENTER
"'
EQUIPMENT BY HMSA
EQUIPMENT/ACCESORIES BY OTHERS
"NOT TO SCALE"
_: ·· REMOTE
OUTDOOR
_
. · ..
2. IN ORDER TO ENSURE ADEQUATE CLEARANCE TO INSERT THE TRANSFER LINE INTO THE HELIUM DEWARS, A 2'x2'
AREA WITH A MINIMUM CLEAR HEIGHT OF 10'-6" MUST BE PROVIDED EITHER IN, OR IN CLOSE PROXIMITY TO THE
, - - ---- --H-~:iH~~HIS I
SCAN ROOM. THIS CLEARANCE MAY BE OBTAINED VIA THE REMOVAL OF A DROP-IN CEILING TILE. UNDER NORMAL
I 1..----.1 AREA 9'-4" - 1
OPERATING CONDITIONS, AFTER THE INITIAL MAGNET FILL, HELIUM REPLENISHMENT OCCURS ONLY ONCE EVERY
12-24 MONTHS. I
3. OUTSIDE OF THE GANTRY SERVICE AREA MARKED "MIN. CLG HEIGHT THIS AREA 9'-4", THE MINIMUM SCAN ROOM
CEILING HEIGHT IS 8'-0". ANY CEILING OR OTHER OBSTRUCTION WITH A HEIGHT OF LESS THAN 8'-6" ALONG THE @ I
DELIVERY PATH WILL NEED TO BE REMOVED FOR THE DELIVERY OF THE OASIS GANTRY
4. ALL DOORS IN THE DEWAR AND SERVICE EQUIPMENT DELIVERY PATH MUST BE A MINIMUM OF 36" WIDE
(34 1/2"CLEAR OPENING STOP TO STOP). THE DOORS MUST BE ABLE TO OPEN IN SUCH A MANNER THAT A
STRAIGHT PATHWAY THROUGH THE DOOR FRAME IS NOT OBSTRUCTED IN ANY WAY BY THE HANDLE, PUSH BAR, I ®
HINGES, OTHER ACCESSORIES OR THE DOOR SLAB ITSELF.
EQUIPMENl.___.....
I
ROOM\ I
5. A CLEAN AND SECURE STORAGE AREA OF APPROXIMATELY 600 SF (20' X 30') IS REQUIRED FOR SYSTEM COVERS MINIMUM CEILING
HEIGHT
--_j
AND ANCILLARY EQUIPMENT AT THE TIME OF DELIVERY. THIS AREA SHOULD BE NEAR AND HAVE CONVENIENT
ACCESS FROM THE OASIS SUITE. THIS STORAGE AREA IS TYPICALLY EMPTIED OF HMSA MATERIALS BY THE END
---+++4------L-
OF THE SECOND WEEK OF THE SYSTEM INSTALLATION. ADDITIONALLY, SECURE STORAGE, EITHER INDOOR OR
OUTDOOR, WILL BE NEEDED FOR UP TO SIX (6) HELIUM DEWARS DURING THE FIRST TWO WEEKS AFTER DELIVERY.
A LEVEL ACCESS PATH FROM THIS STORAGE AREA TO THE SCAN ROOM IS REQUIRED.
6. CUSTOMER'S ARCHITECT IS RESPONSIBLE FOR VERIFYING ALL POWER AND HVAC SPECIFICATIONS FOR
EQUIPMENT NOT SUPPLIED BY HMSA.
7. THIS DRAWING IS NOT FOR CONSTRUCTION PURPOSES. CUSTOMER IS RESPONSIBLE FOR HIRING QUALIFIED
DESIGN PROFESSIONALS TO PREPARE CONSTRUCTION DOCUMENTS. CONSTRUCTION SHALL BE PERFORMED IN
ACCORDANCE WITH ALL APPLICABLE CODES AND REGULATIONS.
8. HMSA RESERVES THE RIGHT TO HOLD THE APPROVAL OF A SITE PENDING AN ON-SITE REVIEW AND APPROPRIATE
QUALIFICATION TESTING BY HMSA PERSONNEL.
9. CONSTRUCTION DRAWINGS ARE TO BE SUBMITTED TO THE HMSA SITE PLANNING DEPARTMENT FOR REVIEW
PRIOR TO CONSTRUCTION.
10. THE LAYOUTS ON THESE PAGES ARE REPRESENTATIVE OF A TYPICAL AND MINIMUM SIZE OASIS SUITE. FINAL
SUITE CONFIGURATION IS DEPENDENT ON PHYSICAL SITE CONDITIONS AND MAY VARY FROM THOSE SHOWN.
CONTACT THE SITE PLANNING DEPARTMENT AT 800-800-3106 FOR ASSISTANCE.
11. THESE DRAWINGS ARE THE PROPERTY OF HITACHI MEDICAL SYSTEMS AMERICA, INC. (HMSA) AND ARE NOT FOR
CONSTRUCTION PURPOSES. THE DRAWINGS IN THESE STANDARD DETAILS ARE TO BE USED BY THE CUSTOMER'S
DESIGN PROFESSIONALS TO PREPARE APPROPRIATE CONSTRUCTION DOCUMENTS. HMSA RESERVES THE RIGHT : ~.~ 0 .... ....
'•
TO REFUSE TO INSTALL ANY OR ALL EQUIPMENT WHEN THE ROOM PREPARATION DOES NOT MEET REMOTE .•
SPECIFICATIONS. THE CURRENT STANDARD DETAILS MAY BE OBTAINED ON LINE AT www.hitachimed.com. CONTACT OUTDOOR
.... ·•·
.. ....
LOCATION
THE HMSA SITE PLANNING DEPARTMENT FOR THE CURRENT ACCESS CODES.
.
..~~··. ,
~ . ·.
·.·
1) CARE MUST BE TAKEN TO ENSURE THE OPERATOR'S WORKSTATION, RFIP CABINET, GRADIENT AMPLIFIER, AND
B PATIENT TABLE 2'-9" 8'-3" 1'-8" - 3'-0" 1,619*
HELIUM REFRIGERATOR ARE LOCATED MORE THAN 9'-0" FROM THE MAGNET ISOCENTER.
2) SOME COMPONENTS ARE FIXED IN PLACE. CARE MUST BE TAKEN TO ENSURE SUFFICIENT SERVICE AREA IS
c OPERATORS CONSOLE ** 4'-0" 2'-6" 2'-6" 75 PROVIDED.
3) CLEAR ACCESS TO THE FILTER PANELS AND POWER PANELS MUST BE MAINTAINED IN ACCORDANCE WITH
NATIONAL ELECTRICAL CODE (NEC) AND LOCAL CODES.
CPU 1'-1" 1'-6" 1'-7" 44 4) POWER CONDITIONERS/UPS UNITS, AIR CONDITIONERS AND CHILLERS ARE POTENTIAL SOURCES OF
INTERFERENCE. THESE SHOULD BE REMOTELY LOCATED AND MOUNTED ON VIBRATION DAMPENING PADS AS
SWITCH UNIT 9" 8" 2" 7 REQUIRED.
5) FDA REGULATIONS REQUIRE RESTRICTED/LIMITED ACCESS TO AREAS WHERE THE MAGNETIC FIELD IS 5 GAUSS OR
GREATER. IT IS THE RESPONSIBILITY OF THE CUSTOMER AND THEIR DESIGN PROFESSIONALS TO ENSURE THAT
MONITOR 1'-11" 9" 1'-7" 33 THE FACILITY IS IN COMPLIANCE WITH THIS REGULATION. HMSA WILL PROVIDE A SITE SPECIFIC MAGNETIC SHIELD
DESIGN TO REDUCE THE SIZE OF THE MAGNETIC FIELDS TO THE EXTENT POSSIBLE BASED ON THE FINAL LAYOUT.
KEYBOARD 1'-8" 10" 2" 5 6) CUSTOMER PROVIDED COMPONENTS (i.e. LASER IMAGER) SHOWN IN THE TYPICAL LAYOUT CAN GREATLY AFFECT
THE ACCEPTABILITY OF YOUR PLANS AND THE SYSTEM OPERATION. COMPONENT SELECTIONS AND THEIR
PLACEMENT MUST BE VERIFIED WITH SITE PLANNING PRIOR TO FINALIZATION OF THE DESIGN.
MULTIPLE TAP UNIT 9" 8" 3" 7 7) CONSTRUCTION MATERIALS (CEILING GRID, LIGHTS, STUDS, ETC.) SHOULD BE CHOSEN TO MINIMIZE THE FERROUS
MATERIALS IN THE SCAN ROOM.
8) THE MINIMUM FINISH CEILING HEIGHT FOR THE SCAN ROOM IS 9'-4" (10'-0" RECOMMENDED) IN A 12'-0" x 12'-0" AREA
D RFIP CABINET 2'-8" 4'-0" 6'-2" 1,654
CENTERED ABOVE ISO-CENTER. THE MINIMUM CEILING HEIGHT IN THE REMAINDER OF THE SCAN ROOM AND ALL
OTHER ROOMS IS 8'-0".
E GCPA CABINET 2'-4" 2'-8" 6-2" 1,158 9) HMSA WILL PROVIDE A COIL STORAGE CABINET FOR THE CONVENIENCE OF THE CUSTOMER. THE CUSTOMER MAY
CHOOSE TO HAVE CUSTOM STORAGE AND CASEWORK DESIGNED.
10) AN INTERCOM BETWEEN THE OPERATOR AND PATIENT IS PROVIDED INTERNALLY AS PART OF THE OASIS MARK II
F MCU FILTER PANEL 1'-11" 1'-1" 2'-1" 67 SYSTEM. A FACILITY INTERCOM, IF DESIRED, SHOULD BE LINKED ONLY TO THE CONTROL ROOM.
11) DUE THE THE RISK OF STATIC SHOCK AND ISSUES REGARDING DUST, CLEANLINESS, AND SERVICEABILITY, CARPET
G ERDU 6" 3" 6" 5 SHOULD NOT BE USED IN THE MRI SUITE.
12) COMPUTER FLOORING MAY BE USED AS AN ALTERNATIVE TO WIREWAYS IN THE EQUIPMENT ROOM. THIS PROVIDES
ADDITIONAL FLEXIBILITY IN EQUIPMENT PLACEMENT. IF COMPUTER FLOORING IS USED, A MINIMUM OF 8" CLEAR
H RFIP FILTER PANEL 3'-0" 1'-6" 5'-1" 440 MUST BE AVAILABLE UNDER THE FLOOR. THE UNDER FLOOR SPACE MAY ALSO BE USED AS A SUPPLY PLENUM FOR
THE HVAC SYSTEM.
J COIL CABINET 7'-0" 2'-3" 4'-3" 100 13) A TABLE FOR THE OPERATOR'S WORKSTATION IS TYPICALLY PROVIDED WITH THE SYSTEM. CUSTOM
CASEWORK WITH A BUlLT-IN DESK FOR THE MONITOR, KEYBOARD AND CPU BELOW IS RECOMMENDED TO IMPROVE
WORK AREA FUNCTIONALITY, ADD STORAGE SPACE AND ENHANCE SUITE AESTHETICS.
K HELIUM COMPRESSOR 1'-6" 1'-11" 1'-9" 265 14) A MINIMUM 3'-6"W X 7'-0"H FLAT ACCESS PATH MUST BE DESIGNED INTO THE SUITE FOR DELIVERY OF THE CRYOGEN
DEWARS AND GRADIENT LOADER. THIS PATH WILL BE USED THROUGHOUT THE LIFE OF THE SYSTEM AS PART OF
ITS ROUTINE MAINTENANCE (SEE NOTES "PLANNING" B-4 ON PG 3 AND 4 ON PG 5 REGARDING DOORWAYS)
M SENSE UNIT 2'-8" 1'-4" 3'-6" 111
NOTE: HMSA WILL PERFORM AN INITIAL VIBRATION TEST FOR THE CONVENIENCE OF THE CUSTOMER AT THE SAME
TIME THAT THE MAGNETIC FLUCTUATION TEST IS PERFORMED, THIS WILL HELP TO IDENTIFY SITES WHERE A CONCERN
ABOUT VIBRATION EXISTS. IF THERE IS A CONCERN, THE CUSTOMER WILL NEED TO HAVE A QUALIFIED
CONSULTING/ENGINEERING FIRM THAT SPECIALIZES IN VIBRATION CONTROL PERFORM A SEPARATE TEST AND
1'-6 3/4" DIAMETER (TYP.) PROVIDE A REPORT WITH RECOMMENDATIONS FOR REMEDIATION THROUGH THE SLAB/ FOUNDATION/STRUCTURAL
SUPPORT DESIGN.
THE TEST THAT HMSA (AND THE INDEPENDENT CONSULTING/TEST FIRM IF REQUIRED) PERFORMS CAN ONLY MEASURE
EXISTING CONDITIONS. AS MODIFICATIONS ARE MADE TO THE BUILDING IN THE FUTURE (ADDITION OR EXCHANGE OF
NOTE: FOR SITES IN SEISMIC ZONES THAT HVAC EQUIPMENT, CHILLERS, ETC.), THE CHANGES MUST BE REVIEWED TO ENSURE THAT ANY COMPONENT THAT MAY
REQUIRE ANCHORAGE TO THE FLOOR, A INDUCE VIBRATION IS PROPERLY MOUNTED ON SHOCK ABSORBING MOUNTS TO PREVENT POTENTIAL INTERFERENCE.
SEISMIC KIT MUST BE PURCHASED FROM HMSA
R1200
MAIN CONTROLS P4 198
WEIGHT P5 P9
AND CONNECTIONS P5 202
COMPONENT FEET TOTAL
(lbs) ;.,. ~ OUTDOOR THIS SIDE P6 204
MAGNET
PATIENT TABLE
A
B
c
7,900
663*
31,600
1,619*
L_j_
('t) ~
P4
P3
CHILLER
P2
P1C
P1
- SUPPLY/RETURN LINES
AND POWER, THIS AREA
P7
P8
P9
222
198
193
956*
P10 HS~
DATE: 04/30/2012
PAGE 7 OF 27
RF AND MAGNETIC SHIELDING
RF SHIELDING
A RADIO FREQUENCY (RF) SHIELD IS REQUIRED FOR THE OPERATION OF THE OASIS MARK II SYSTEM AND IS NOT PROVIDED BY
HMSA. THIS SIX (6) SIDED SHIELD IS REQUIRED FOR ALL MRI SYSTEMS. COORDINATION WITH THE SHIELDING VENDOR IS OF THE
UTMOST IMPORTANCE. CONTACT SITE PLANNING FOR A LIST OF RF VENDORS. THE FOLLOWING IS A LISTING OF SOME OF THE
DESIGN REQUIREMENTS AND CRITERIA WHICH MUST BE CONSIDERED.
1) THE RF SHIELDED ROOM MUST HAVE AN INSULATION RESISTANCE OF MORE THAN 1000 OHMS (AS MEASURED WITH A 500 V-DC
0
MEGGER), WITH RESPECT TO THE BUILDING GROUNDING FACILITY AND OTHER EQUIPMENT INSTALLED IN THE BUILDING.
3) IF A SPRINKLER SYSTEM IS REQUIRED, THE DESIGN AND CONSTRUCTION MUST BE COORDINATED WITH THE RF VENDOR TO
ENSURE ITS ISOLATION FROM THE SHIELDING. HMSA RECOMMENDS THAT ANY PORTION OF THE SPRINKLER SYSTEM THAT
PENETRATES THE RF SHIELD BE DRY. FINAL DESIGN APPROVAL AND ACCEPTANCE IS THE RESPONSIBILITY OF THE RF
0
VENDOR.
4) SINKS AND OTHER PLUMBING FIXTURES SHOULD BE AVOIDED IN THE SCAN ROOM UNLESS REQUIRED BY CODE. IF A SINK IS
REQUIRED, THE PLUMBING MATERIALS, ROUTING AND INSTALLATION MUST BE COORDINATED BETWEEN THE PLUMBING
CONTRACTOR AND RF SHIELDING VENDOR TO ENSURE THAT THE INTEGRITY OF THE RF SHIELD IS MAINTAINED.
9) IF OXYGEN OR OTHER MEDICAL GAS LINES ARE DESIRED IN THE SCAN ROOM, THE PENETRATIONS MUST BE INTEGRATED INTO
THE RF SHIELD AND OCCUR WITHIN FOUR (4) FEET OF THE RFIP FILTER PANEL. CONSULT WITH THE RF SHIELD VENDOR. ® FILTER PANEL FOR SYSTEM INTERCONNECTION. PROVIDED BY HMSA AND
INSTALLED BY RF VENDOR PRIOR TO FINAL ROOM TEST.
10) ADDITIONAL AND OPTIONAL CONCERNS SUCH AS (OUTSIDE WINDOWS, EXTRA DOORS, ETC. SHOULD BE DISCUSSED WITH THE
RF VENDOR AND REVIEWED BY HMSA PRIOR TO FINALIZATION OF THE PLANS.
0 RF WINDOW: 4'-0"W X 3'-0"H (TYP.), MOUNTED AT 36" AFF
11) IF NECESSARY, IT IS THE CUSTOMERS RESPONSIBILITY TO COORDINATE SUITE CONSTRUCTION, THE RF VENDOR AND 0 RF DOOR: 4'-0''W X 7'-0"H (REQ.)
SIX (6) 1 3/4" WAVE GUIDES PROVIDED AND INSTALLED BY RF VENDOR
DELIVERY TIMING TO ACCOMMODATE AN INDIRECT DELIVERY PATH.
® FOUR (4) LOCATED IN LOWEST SECTION OF WIREWAY, TWO (2) LOCATED
ABOVE MCU PANEL. MOUNTED FLUSH WITH SCAN ROOM WALL
2) ALL ROOMS MUST BE MAINTAINED AT THE RELATIVE HUMIDITY (NON-CONDENSING) LISTED BELOW.
3) CHANGES TO THE SCAN ROOM TEMPERATURE WILL AFFECT THE SYSTEM IMAGING. THEREFORE, THE ENVIRONMENT MUST BE
-THREE-WAY DIFFUSER DUJJ
MAINTAINED AT ALL TIMES (24HRS/DAY; 7DAYS/WEEK).
lZ1
4) THERMOSTATS MAY NOT BE USED IN THE SCAN ROOM. A REMOTE SENSOR IN THE RETURN AIR DUCT OUTSIDE OF THE RF
0
8
SHIELD MUST BE UTILIZED FOR CONTROLLING THE SCAN ROOM ENVIRONMENT. THE REMOTE SENSOR MUST BE LOCATED
WITHIN FIVE FEET (5') OF THE OUTSIDE OF THE WAVEGUIDE. THE THERMOSTAT SHOULD BE LOCATED IN THE CONTROL AREA.
-FOUR-WAY DIFFUSER
5) IT IS THE RESPONSIBILITY OF THE HVAC DESIGNER TO ENSURE THERE IS ADEQUATE AIRFLOW ACROSS THE REMOTE SCAN
ROOM SENSOR TO MAINTAIN PROPER ENVIRONMENTAL CONDITIONS. THIS TYPICALLY REQUIRES CONTINUOUS AIR
CIRCULATION ACROSS THE REMOTE SCAN ROOM SENSOR TO MAINTAIN PROPER ENVIRONMENTAL CONDITIONS 24/7.
6) AC UNITS, CONDENSERS, AND AIR HANDLERS MUST BE LOCATED OUTSIDE OF 20 FEET FROM MAGNET ISO-CENTER AS SHOWN
ON THE SITE SPECIFIC DRAWING AND SHOULD BE MOUNTED ON VIBRATION ISOLATORS. -RETURN AIR
7) A FLEXIBLE, NON-CONDUCTIVE BOOT PROVIDED BY THE HVAC CONTRACTOR MUST BE USED TO CONNECT DUClWORK TO THE
EXTERIOR SIDE OF HVAC WAVEGUIDES TO PREVENT GROUNDING OF THE RF SHIELD BY THE EXTERNAL DUClWORK.
8) DUClWORK AND DIFFUSER GRILLS WITHIN THE SCAN ROOM MUST BE NON-FERROMAGNETIC. d\1\lllil\1\1\, -ACOUSTIC INSULATION
(OPTIONAL)
9) CARE SHOULD BE TAKEN TO ENSURE THE SUPPLY AIR IS DIRECTED AWAY FROM THE GANTRY AND PATIENT TABLE. DIFFUSER
PLACEMENT SHOULD BE DESIGNED TO ENSURE EVEN AIR DISTRIBUTION.
10) IF A FLOOR MOUNTED COMPUTER ROOM HVAC SYSTEM IS USED, PLEASE NOTIFY HMSA SITE PLANNING TO ENSURE ADEQUATE -ACOUSTIC PANELS
SERVICE SPACE IS AVAILABLE FOR THIS UNIT AS WELL AS THE OASIS MARK II COMPONENTS IN THE EQUIPMENT ROOM. (OPTIONAL)
11) COMPUTER FLOORING IN THE EQUIPMENT ROOM MAY BE USED FOR A SUPPLY PLENUM.
12) IT IS THE CUSTOMER'S RESPONSIBILITY TO ENSURE THAT A PROPER ENVIRONMENT IS CONTINUOUSLY MAINTAINED FOR THE
OASIS MARK II SYSTEM. THE CHART BELOW MUST BE USED BY THE ARCHITECT/ENGINEER DESIGNING THE HVAC SYSTEM.
CUSTOMER SUPPLIED AND OPTIONAL COMPONENTS MUST BE IDENTIFIED. THE HVAC DESIGNER IS RESPONSIBLE FOR VERIFYING
THE LOADS BASED ON ACTUAL UNITS TO BE USED. OTHER LOADS (i.e.: PEOPLE, LIGHTS, OUTSIDE CONDITIONS, ETC ... ) MUST
ALSO BE CONSIDERED IN THE DESIGN. ALTHOUGH THE DESIGN OF THE HVAC SYSTEM IS THE RESPONSIBILITY OF THE
CUSTOMER, HMSA STRONGLY SUGGESTS THE USE OF A ZONED SYSTEM DUE TO THE LARGE VARIANCE OF HEAT LOADS FROM
ROOM TO ROOM. ACOUSTICAL NOTES
1) SIMILAR TO OTHER MR IMAGING SYSTEMS, THE OASIS MARK II PRODUCES NOISE LEVELS (WHILE SCANNING)
THAT ARE GENERALLY CONSIDERED UNACCEPTABLE FORA NORMAL OFFICE ENVIRONMENT.
DAILY PERMISSIBLE NOISE EXPOSURE LEVELS SHOULD BE CONSIDERED WHEN PLANNING A
LOCATION COMPONENT HEAT LOAD TEMP. (F) HUMIDITY dB LEVEL
FACILITY. THE ADJACENT CHART PROVIDES THE MAXIMUM NOISE LEVELS CREATED DURING THE
(MAX)
SCAN PROCESS.
CONTROL © OPERATOR'S WORKSTATION 3,405 BTUH CONSTRUCTED OF NON-FERROUS MATERIALS (WOOD FRAMES, VELCRO HANGING SYSTEMS). THE
ARCHITECT MAY WISH TO CONSULT AN ACOUSTICAL ENGINEER FOR ADDITIONAL METHODS OF SOUND
ROOM
68-82° 20-60% 55 DAMPENING.
(J) LASER IMAGER BY CUSTOMER
3) IF SURFACE MOUNTED ACOUSTIC PANELS ARE SPECIFIED IN THE SCAN ROOM, HMSA RECOMMENDS
@ RFIP 21,707 BTUH THAT FINAL FIELD MEASUREMENTS BE DELAYED UNTIL AFTER THE FILTER PANELS HAVE BEEN INSTALLED
TO ENSURE PROPER FITMENT. THE EXTENT OF WALL COVERAGE MAY VARY FROM THAT SHOWN ABOVE
EQUIPMENT ® GCPA 6,495 BTUH DEPENDENT ON ROOM LAYOUT, PANEL CONSTRUCTION AND AMOUNT OF ACOUSTIC DAMPENING DESIRED.
ROOM 20-60% 4) SOME RF SHIELDING VENDORS OFFER OPTIONS THAT INTEGRATE SOUND REDUCTION MATERIALS INTO
® MCU 1,389 BTUH
THE RF SHIELD ITSELF. CONTACT THE RF SHIELDING VENDOR FOR FURTHER INFORMATION.
(IF TEMP IS
® RFIP FILTER PANEL 1,468 BTUH 39,816 BTUH 65-78° ABOVE 77• 86
20-53%)
® HELIUM COMPRESSOR 5,556 BTUH
HMSA RESPONSIBILITIES
1) COORDINATE WITH THE CUSTOMER I CONTRACTOR TO ARRANGE DELIVERY DATE AND ADDRESS FOR THE R12000
CHILLER AT THE APPROPRIATE TIME DURING THE CONSTRUCTION PHASE OF THE PROJECT.
2) PROVIDE AND INSTALL ALL PLUMBING AND CONNECTIONS BETWEEN THE HEAT EXCHANGER AND THE OASIS MARK II MRI
SYSTEM.
~
HEAT EXCHANGER TO SENSE UNIT @GRADIENT COIL LOOP
SENSE UNIT TO HELIUM COMPRESSOR @HELIUM LINES
GRADIENT POWER AMPLIFIER LOOP
SUPPLY AND RETURN WATER
LINES BETWEEN CHILLER AND
HEAT EXCHANGER BY HVAC
CONTRACTOR. TOTAL
CHILLER CONNECTION SCHEMATIC
MAXIMUM LENGTH OF NOT TO SCALE
200' ONE WAY -----<1:::::1>
NOTE: RUNS SHOWN ARE SCHEMATIC ONLY AND DO NOT INDICATE ACTUAL CONNECTION POINTS
CHILLER FOOTPRINT. RIGHT- 24", LEFT- 6", REAR- 12", ABOVE- 36" 3 MCA*, 15 MOCP**
Company: ______________________________________________
Service Tech: _______________________________ Title:_____________________________
Phone: _________________________________ E-mail: ______________________________
Signature ________________________________________ Date: _______________________
Please Contact Hitachi Medical Systems America, Inc. if you have any questions.
Phone: 800-800-4925 Fax: 978-313-6145 E-mail- [email protected]
CHILLER INSTALLATION SPECIFICATIONS
PIPE SIZE CALCULATION CHILLER ANTI-FREEZE
IT IS CRITICAL THAT THE R1200 CHILLER BE FILLED WITH A PROPER MIXTURE PROPYLENE GLYCOL ANTI-FREEZE AND DISTILLED
THE CUSTOMER'S ARCHITECT/ENGINEER IS RESPONSIBLE FOR UTILIZING THE FOLLOWING INFORMATION TO CALCULATE WATER (35% PROPYLENE GLYCOL BY VOLUME). AN IMPROPERLY MIXED SOLUTION WILL HAVE A NEGATIVE IMPACT ON THE
THE APPROPRIATE NOMINAL SIZE OF THE COPPER WATER LINES BETWEEN THE R1200 OUTDOOR CHILLER UNIT AND THE EFFICIENCY OF THE CHILLER. ONLY APPROVED BRANDS MAY BE USED (SEE CHART BELOW). DO
HEAT EXCHANGER LOCATED IN THE EQUIPMENT ROOM.
NOT USE AUTOMOTIVE ANTIFREEZE. USE OF AUTOMOTIVE ANTIFREEZE WILL DAMAGE THE
SYSTEM.
PIPE CALCULATION FACTORS
NOMINAL PIPE HEAD LOSS go• LONG RADIUS
go• ELBOW 45• ELBOW
SIZE FACTOR ELBOW PROPYLENE GLYCOL SUPPLIER LIST
1 1/2" 3.72 4.1 2.7 1.g
2. FIND THE TOTAL NUMBER OF FITTINGS (LONG RADIUS go• ELBOWS SHOULD BE USED WHERE POSSIBLE)
6. MULTIPLY (G) BY 1.26 (GLYCOL FACTOR)=_ _ _ _ (I) (MAXIUM ALLOWABLE VALUE: 335) SUPPLY FROM .._
CHILLER -1.,..
...- - - ' BY-PASS PIPE w/
5. IF "I" IS LESS THAN OR EQUAL TO 335, THEN YOUR PIPE SIZE IS 11/2". IF "I" IS GREATER THAN 335, REPEAT THE
BALL VALVE
CALCULATIONS AGAIN USING THE NEXT LARGER NOMINAL PIPE SIZE. CONTINUE IN THIS MANNER UNTIL "I" IS LESS THAN
OR EQUAL TO 335 TO FIND THE REQUIRED PIPE SIZE.
EQUIPMENT ROOM PIPING
SEE CUTOMER/INSTALLING CONTRACTOR'S
RESPONSIBILITIES (PG11 OF 27) FOR COMPLETE
BALL VALVE BALL VALVE
DETAILS.
2" 16.75
21/2" 26
HOSE BARB~.-------------------------------------------~
HOSE BARBw/ ~
3 36.5 DOUBLE CLAMP DOUBLE CLAMP HITACHI MEDICAL SYSTEMS AMERICA
1959 SUMMIT COMMERCE PARK TWINSBURG, OH 44087-2371
(800) 800-3106 WWW.HITACHIMED.COM
12'- 1-1/2" DIAMETER
REINFORCED HOSE CHILLER INSTALLATION SPECIFICATIONS
DATE: 04/30/2012 I REVISION: 01/19/2015
OASIS MARK II STANDARD DETAILS I PAGE 12 OF 27
ELECTRICAL - LIGHTING
r.---------------------------~
LIGHTING NOTES
EQUIPMENT THE LIGHTING IN THE SUITE SHOULD BE DESIGNED TO ALLOW MULTIPLE LEVELS OF BRIGHTNESS. THE FOLLOWING
ROOM POINTS MUST BE REVIEWED TO ENSURE THE PROPER DESIGN OF THE LIGHTING AND ELECTRICAL SYSTEMS FOR THE
SUITE.
1) RECESSED CANS AND/OR WALL SCONCES ARE RECOMMENDED. WALL SCONCES SHOULD HAVE THE MINIMAL
AMOUNT OF FERROUS MATERIALS POSSIBLE. REMOVABLE ACCESSORIES (SHADES, GRILLS, BAFFLES) MUST BE
NON-FERROMAGNETIC. WHEN USING RECESSED CAN LIGHTS, ONLY HMSAAPPROVED UNITS MAY BE USED. SEE
OEM VENDOR PAGE (BACK COVER OF THIS DOCUMENT) FOR APPROVED UNITS. THESE FIXTURES MAY BE
ORDERED THROUGH ANY ELECTRICAL SUPPLY HOUSE.
2) WALL SCONCES MAY BE HELPFUL WHEN THE CEILING HEIGHT IS A CONCERN OR TO OBTAIN LOW LEVEL AMBIENT
LIGHT.
3) CARE SHOULD BE TAKEN WHEN LOCATING LIGHT FIXTURES. LIGHTS SHOULD NOT BE POSITIONED DIRECTLY ABOVE
THE MAGNET GANTRY OR OVER THE TABLE WHERE THEY MIGHT SHINE DIRECTLY INTO THE PATIENT'S EYES.
4) TRACK LIGHTING IS NOT PERMITTED IN THE SCAN ROOM. REMOVABLE LIGHT FIXTURES CAN CREATE A SAFETY RISK.
ADDITIONALLY, FIXTURES TEND TO LOOSEN SLIGHTLY IN THE TRACK OVER TIME, ALLOWING MINOR VIBRATIONS
THAT MAY CAUSE IMAGE QUALITY ISSUES.
5) FLUORESCENT LIGHTS (INCLUDING COMPACT FLUORESCENT BULBS) ARE NOT PERMITTED IN THE SCAN ROOM.
USE ONLY INCANDESCENT OR MRI RATED L.E.D. LIGHTING. REDUCED INCANDESCENT BULB LIFE CAN BE EXPECTED
DUE TO THE PULSING OF THE MAGNETIC FIELD IN THE SCAN ROOM. ROUGH USAGE BULBS ARE RECOMMENDED.
FLUORESCENT LIGHTS IN THE CONTROL AND EQUIPMENT ROOMS SHOULD NOT BE ON WHEN SCANNING.
6) IF L.E.D. LIGHTS ARE USED, THEY MUST BE TRUE 120V UNITS AND NOT HAVE ANY TYPE OF INTERNAL
TRANSFORMER IN EITHER THE BULB OR FIXTURE. WHEN CONFIGURING LIGHTING SCHEMES UTILIZING L.E.D.
LIGHTING, CARE MUST BE TAKEN TO ENSURE THE NUMBER OF FIXTURES AND THEIR LOCATION WILL PROVIDE THE
LUMEN LEVELS DESIRED. EXTERNAUREMOTE TRANSFORMERS FOR LED LIGHTING FIXTURES MUST BE LOCATED
OUTSIDE OF THE SCAN ROOM AND ELECTRICAL LINES INTO THE SCAN ROOM MUST PASS THROUGH AN EMI FILTER.
7) STANDARD INCANDESCENT RHEOSTAT TYPE AC DIMMERS ARE NOT PERMITTED IN THE MRI SUITE (SCAN, CONTROL
AND EQUIPMENT ROOMS). A MULTI-SWITCH DESIGN SHOULD BE USED TO ADJUST LIGHTING LEVELS IN THE SCAN
ROOM. LIGHTING NEEDS RANGE FROM LOW LEVELS FOR PATIENT COMFORT DURING SCANNING (BELOW 20
LUMENS/SF), TO MID LEVELS (20-30 LUMENS/SF) FOR PATIENT TRANSFER AND HOUSEKEEPING FUNCTIONS, TO
HIGHER LEVELS (40+ LUMENS/SF) FOR PATIENT INJECTIONS AND EQUIPMENT MAINTENANCE, PER THE
RECOMMENDATIONS OF THE ILLUMINATION ENGINEERING SOCIETY OF NORTH AMERICA (IESNA).
8) LIGHTING CIRCUITS MUST NOT CREATE A PERIPHERAL LOOP AROUND THE MAGNET. THIS WILL CAUSE
INTERFERENCE TO THE SYSTEM WHEN IMAGING.
10) THE ELECTRICAL POWER FOR THE LIGHTING AND RECEPTACLES IN THE SUITE IS TO BE DERIVED FROM THE MRI
SUB PANEL AND SHARE A COMMON GROUND (SEE THE ELECTRICAL SHEETS FOR FURTHER DETAILS). THE
INCANDESCENT FIXTURES ELECTRICAL CONTRACTOR MUST COORDINATE BOTH THE NUMBER AND LOCATION OF EMI FILTERS WITH THE RF
(SEE NOTE 1 THIS PAGE) VENDOR.
11) WHILE SPECIFIC COMPONENTS MAY REQUIRE OUTLETS AS NOTED, ADDITIONAL CONVENIENCE OUTLETS ARE
FLUORESCENT LIGHTS REQUIRED IN THE SUITE (MINIMUM ONE PER WALL) FOR SERVICING AND MAINTENANCE.
(SEE NOTE 5 THIS PAGE)
12) OUTLETS LOCATED ON WALLS WITH SURFACE MOUNTED WIREWAYS MUST BE INSTALLED HIGH ENOUGH TO
ENSURE THEY WILL NOT BE COVERED BY THE WIREWAY (TOP AT 24" AIFF).
120V, 20 AMP DUPLEX OUTLET
13) LOCATION OF NETWORK CONNECTIONS, TELEPHONE LINE JACKS, REQUIRED OUTLETS, ETC. WILL VARY. NETWORK
TELEPHONE OUTLET CONNECTIONS AND TELEPHONE LINE JACKS ARE NOT PERMITTED IN THE SCAN ROOM. REFER TO SITE SPECIFIC
DRAWING FOR ACTUAL PLACEMENT.
SWITCH
14) REQUIREMENTS FOR ALL NON HITACHI SUPPLIED COMPONENTS MUST BE VERIFIED WITH EQUIPMENT VENDOR OR
480V, 30A, 3 PHASE, 4 WIRE MANUFACTURER FOR ACTUAL PLACEMENT.
NEMA L 16-30R RECEPTACLE FOR RAMP-UP TOOL
INSU::~SOUND ~SCAN
~~-r~+f-----~H~OT~--_, CUSTOMER/
SIZE AS CONTRACTOR
J ROOMLIGifTS
REQUIRED
SIZED BY
~0--H~+f--~~H=OT~---;rr=a----i
SITE SPECIFIC DRAWING
v
VENDOR AS REQ'D GROUND
~~-Hrttt----~:~=~~------__, r--------rtir-~~~
! .r
0 FOR OX'f MONITOR
---------r~r--~~0
~6--Hrft+-,N-SU-~-T~~o~;~G-RO_U_N_D_____, r--------r~r--~oo OXYGEN MONITOR (POWER
RF FILTER AND WIRING TO REMOTE PROBE
PER MANUFACTURER'S SPECIFICATIONS
PER MANUFACTURER'S
~ HOT
HEAT EXCHANGER
MAIN GROUND
~6-;;-+. .----~HO=T~---------i
<10 ohm IMPEDANCE
~~~Ctn
~~-Hrttt~,N~S~U~~~=~T~G=R=ou~N=D------i MCA-3.3
MOCP-15 ~O--triti--~NE~:~~~---------1
REQ'D INSULATED GROUND
n CONTROL AND EQUIPMENT ROOM LIGHTS
n
BUILDING STEEL
COLDWATERPIPE ~
~~-H-+~--~H~m~--------~
HOT
NEUTRAL AND GROUND BUS MUST BE
ISOLATED FROM THE PANEL FRAME
GROUNDING ELECTRODE
~0--H~+f-IN_S_U~-T~~O~:~G-ROU~N~D------i RECEPTACLE FOR MAGNET RAMP-UP TOOL
480V 3P 30A L 16-30R RECEPTACLE
I"'"
2) IF A UPS SYSTEM IS TO BE INSTALLED, FOR THE OASIS MARK II, THE AMPACITY OF
THE CIRCUIT MUST BE ADJUSTED TO COMPENSATE FOR THE POWER CONSUMPTION
OF THE UPS. CONTACT SITE PLANNING DEPARTMENT FOR MORE INFORMATION.
5) ALTHOUGH THE MRI SUB-PANEL SHOWN ON THIS PAGE MAY BE LOCATED IN CLOSE
GROUND PROXIMITY TO THE GANTRY, IT DOES NOT EFFECT SYSTEM PERFORMANCE. OTHER
THREE PHASE PANELS OR WIRING WITHIN THE 20' RESTRICTED AREA ON THE SITE
Ir---
NEUTRAL
SPECIFIC PLAN MAY HAVE AN ADVERSE EFFECT ON IMAGE QUALITY. REFER TO
HOT
HOT - WEATHER-PROOF DISCONNECT AS REQUIRED BY CODE.
SIZED AND INSTALLED BY ELECTRICAL CONTRACTOR
PROXIMITY CHARTS FOR FURTHER INFORMATION.
HOT 6) THE USE OF STANDARD FERROUS RIGID CONDUIT AND WORK BOXES WITHIN THE
I R1200 OUTDOOR
CHILLER SCAN ROOM IS ACCEPTABLE. WHIPS TO AND BETWEEN LIGHT FIXTURES WITHIN
THE SCAN ROOM SHOULD BE FLEXIBLE ENT IF PERMISSIBLE. THE ELECTRICAL
480V
CONTRACTOR IS RESPONSIBLE FOR SECURING ALL CONDUITS (INCLUDING FLEXIBLE
I MCA- 32.6 MOCP - 45
WHIPS) TO PREVENT CONTACT WITH OTHER METALLIC ITEMS (I.E.: CEILING GRID, RF
(w/TIME DELAY BREAKER)
PIGTAIL AS REQUIRED. BY
SHIELD) OR MOVEMENT CAUSED BY THE PULSATION OF THE MAGNETIC FIELD. HITACHI MEDICAL SYSTEMS AMERICA
ELECTRICAL CONTRACTOR
7) IF A FACILITY'S ONLY POWER IS 208V, 3 PHASE, AN ALTERNATE PANEL SCHEMATIC
1959 SUMMIT COMMERCE PARK TWINSBURG, OH 44087-2371
CHILLER PANEL ABOVE IS CONCEPT ONLY
BREAKER SIZE AND ACTUAL LAYO LIT FOR UTILIZING 208V, 3 PHASE AS THE PRIMARY POWER IN CONJUNCTION WITH STEP-UP (800) 800-3106 WWW.HITACHIMED.COM
CHILLER PANEL IS TO BE DETERMINED BY
ELECTRICAL ENGINEER I ARCHITECT
TRANSFORMERS IS AVAILABLE. CONTACT THE SITE PLANNING DEPARTMENT TO
OBTAIN A COPY. ELECTRICAL- PANEL SCHEMATIC
DATE: 04/30/2012 I REVISION: 01/19/2015
RACEWAY AND ENCLOSURE GROUNDING SHALL BE PROVIDED AS REQUIRED BY NEC FOR ALL FEEDER AND BRANCH
CIRCUIT WIRING AS FOLLOWS:
PROVIDED BY THE ELECTRICAL CONTRACTOR: 1) ALL FEEDER AND BRANCH CIRCUIT CONDUCTORS SHALL BE INSTALLED IN STEEL CONDUIT AND BOXES TO SHIELD
THE ELECTRICAL CONTRACTOR WILL BE RESPONSIBLE FOR SUPPLYING AND INSTALLING THE FOLLOWING: CONDUCTORS FROM MAGNETIC INTERFERENCE. ALL CONDUITS SHALL BE SECURED IN SUCH A MANNER AS TO
1) CIRCUIT BREAKER PANEL (MRI SUB-PANEL) TYPICALLY LOCATED IN THE EQUIPMENT ROOM. THIS PANEL SHALL ONLY PREVENT POTENTIAL MOVEMENT AND ENSURE PROPER GROUNDING.
SERVE LOADS AS SHOWN ON THE WIRING SCHEMATIC (PG. 14 OF 27). THE MRI SUB-PANEL SHALL BE PROVIDED 2) METALLIC CONDUIT AND BOXES SHALL BE BONDED TOGETHER BY MEANS OF APPROVED CONNECTORS INSTALLED IN
WITH BOLT-ON BRANCH CIRCUIT BREAKERS AND AN ISOLATED GROUND BUS. ACCORDANCE WITH NEC REQUIREMENTS WITH BONDING JUMPERS WHERE NECESSARY TO PROVIDE A CONDUCTIVE
2) THE MRI SUB-PANEL FEEDER SHALL BE COPPER CONDUCTOR, SIZED AS REQUIRED BY NEC AND AS REQUIRED TO GROUNDING PATH FROM EACH OUTLET BACK TO MAIN SYSTEM GROUND AT ELECTRICAL SERVICE OR SOURCE OF
PROVIDE NECESSARY VOLTAGE LEVEL AT RFIP CABINET. THE FEEDERS SHALL BE FROM A CIRCUIT BREAKER OR SEPARATELY DERIVED SYSTEM.
FUSED SWITCH SIZED PER NEC IN A DISTRIBUTION PANEL AT THE SERVICE ENTRANCE OR THE SOURCE OF THE 3) GROUNDED METALLIC RACEWAY SYSTEM SHALL BE ISOLATED FROM THE RFIP CABINET AND OTHER SYSTEM
SEPARATELY DERIVED SYSTEM. COMPONENTS AS WELL AS EMI FILTERS BY COUPLING WITH DIELECTRIC CONNECTORS OR NON-METALLIC CONDUIT.
3) BRANCH CIRCUIT WIRING FROM THE MRI SUB PANEL TO THE RFIP CABINET AS SHOWN ON THE SCHEMATIC (PG14 OF THE GROUNDING OF EQUIPMENT ISOLATED FROM METALLIC RACEWAY SYSTEM SHALL BE BY MEANS OF ISOLATED
27), A PIGTAIL LONG ENOUGH TO ALLOW THE RFIP TO BE MOVED 6' PLUS AN ADDITIONAL 5' FOR USE INTERNAL GROUNDING SYSTEM CONDUCTOR.
TO THE CABINET IS REQUIRED. A 2" FLEXIBLE CONDUIT FROM THE JUNCTION BOX TO THE CABINET WITH A 4) RF SHIELD GROUNDING SHALL BE PROVIDED BY INSTALLATION OF AN INSULATED #4 AWG COPPER CONDUCTOR RUN
DIELECTRIC UNION AT ONE END IS ALSO REQUIRED. FROM RF ROOM GROUND STUD TO THE ISOLATED GROUND BUS IN THE MRI SUB-PANEL GROUNDING OF THE BUS IN
4) INSTALL CRIMP TERMINAL LUGS ON POWER WIRING TO RFIP CABINET. SIZE AS APPROPRIATE FOR WIRE GAUGE AND FILTER PANEL TO RFIP CABINET WILL BE PROVIDED BY HMSA.
MOUNTING TO 3/8" ATTACHMENT STUD IN RFIP CABINET. 5) ELECTRICAL SYSTEM GROUNDING SHALL BE VERIFIED BY ELECTRICAL CONTRACTOR. THE SYSTEM NEUTRAL
5) IF THE MRI SUB PANEL IS NOT LOCATED IN THE EQUIPMENT ROOM, A SURFACE MOUNTED DISCONNECT SWITCH SHALL BE GROUNDED AT ONE POINT ONLY. THE NEUTRAL MAY BE GROUNDED AT EITHER THE SERVICE ENTRANCE OR
(NON-FUSED) IS REQUIRED IN CLOSE PROXIMITY TO THE RFIP CABINET. SIZE AS REQUIRED BY CODE. AT THE SOURCE OF THE SEPARATELY DERIVED SYSTEM BY CONNECTION TO A NEC REQUIRED GROUNDING ELECTRODE
6) BRANCH CIRCUITS AND WIRING TO BOTH THE OUTDOOR COMPONENT OF THE CHILLER SYSTEM (TYPICALLY SUPPLIED SYSTEM.
BY HMSA) AND THE HEAT EXCHANGER IN THE EQUIPMENT ROOM (PG 14 OF 27). 6) GROUNDING ELECTRODE SYSTEM SHALL BE VERIFIED AND SUPPLEMENTED IF NECESSARY BY THE ELECTRICAL
7) L 16-30R RECEPTACLE FOR MAGNET RAMP UP TOOL LOCATION AS SHOWN ON SITE SPECIFIC DRAWING. CONTRACTOR. THE GROUNDING ELECTRODE SYSTEM SHALL BE PROVIDED AS REQUIRED BY NEC AND SHALL INCLUDE
8) LIGHTING AND CONTROLS IN MRI SCAN, CONTROL, AND EQUIPMENT ROOMS (PG.13 OF 27). THE FOLLOWING (WHERE AVAILABLE) AND BONDED TOGETHER: METAL UNDERGROUND WATER SERVICE PIPE, METAL
9) 120V RECEPTACLES WITH ISOLATED GROUND TERMINALS IN MRI SCAN, CONTROL, AND EQUIPMENT ROOMS. FRAME OF BUILDING AND OTHER ELECTRODES REQUIRED BY NEC. IF NOT EXISTING, THE ELECTRICAL CONTRACTOR
10) ISOLATED GROUNDING SYSTEM FOR ALL LOADS FED BY MRI SUB-PANEL (SEE GROUNDING NOTES). SHALL PROVIDE ONE OR MORE DRIVEN GROUND ROD OR PLATE ELECTRODES BONDED TO THE EXISTING GROUNDING
11) RF SHIELD GROUNDING WITH AN INSULATED #4 AWG COPPER GROUNDING CONDUCTOR FROM RF SHIELD ELECTRODE SYSTEM BY MEANS OF A CONDUCTOR SIZED PER NEC. THE RESISTANCE TO GROUND OF THE MAIN
GROUND STUD TO THE FILTER PANEL OR TO ISOLATED GROUND BUS IN MRI SUB-PANEL ELECTRODE SHALL BE NO MORE THAN 10 OHMS.
12) 1" x 1/8" FLAT BRAIDED GROUND STRAP FROM FILTER PANEL TO SCAN ROOM WIREWAY AND BONDING BETWEEN
WIREWAY SECTIONS IN SCAN ROOM.
13) CONDUIT AND ENCLOSURE GROUNDING FOR ALL FEEDER AND BRANCH WIRING PER NEC REQUIREMENTS (SEE
GROUNDING NOTES).
14) CONFIGURATION AND INSTALLATION OF ANY POWER CONDITIONING OR UPS EQUIPMENT. SEE NOTE BELOW AND
CONTACT THE SITE PLANNING DEPARTMENT FOR FURTHER INFORMATION.
15) BRANCH CIRCUIT WIRING FROM BUILDING DISTRIBUTION SYSTEM FOR LASER IMAGER AND EMERGENCY EXHAUST
FAN PER MANUFACTURER'S SPECIFICATION AS REQUIRED PER NEC REQUIREMENTS.
16) WIREWAYS AS SPECIFIED ON HMSA SITE SPECIFIC DRAWING. WIREWAYS MUST BE NON-FERROUS METAL AND ARE
TYPICALLY 6 "X 24" WIREWAY WITH THREE (3) DIVIDERS (FOUR [4]- 6" X 6" SECTIONS) WITH REMOVABLE COVERS.
17) OUTLETS, CONDUITS, JUNCTION BOXES AS NOTED ON HMSA SITE SPECIFIC DRAWING.
18) THE USE OF STANDARD FERROUS RIGID CONDUIT AND WORK BOXES WITHIN THE SCAN ROOM IS ACCEPTABLE.
WHIPS TO AND BETWEEN LIGHT FIXTURES WITHIN THE SCAN ROOM SHOULD BE FLEXIBLE ENT (ELECTRICAL
HITACHI MEDICAL SYSTEMS AMERICA
NON-METALIC TUBING) IF PERMISSIBLE. THE ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR SECURING ALL 1959 SUMMIT COMMERCE PARK TWINSBURG, OH 44087-2371
CONDUITS (INCLUDING FLEXIBLE WHIPS TO PREVENT CONTACT WITH OTHER METALLIC ITEMS (i.e.: METAL STUDS, (800) 800-3106 WWW.HITACHIMED.COM
CEILING GRID, RF SHIELD) OR MOVEMENT CAUSED BY THE PULSATION OF THE MAGNETIC FIELD.
ELECTRICAL- GENERAL NOTES
NOTE: SHOULD A UPS SYSTEM BE REQUIRED, ONLY SYSTEMS THAT HAVE BEEN TESTED AND FOUND ACCEPTABLE BY
HMSAARE RECOMMENDED. RECOMMENDED MINIMUM CAPACITY, 112.5 'tWA. CONTACT THE SITE PLANNING DEPARTMENT DATE: 04/30/2012 I REVISION: 01/19/2015
FOR ADDITIONAL INFORMATION.
OASIS MARK II STANDARD DETAILS I PAGE 15 OF 27
WIREWAYS
WIREWAY NOTES
ALL WORK IS TO CONFORM TO APPLICABLE BUILDING CODES. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR PROVIDING ALL 6"X24"WALL 6" X 24" ON-FLOOR
WIREWAYS, JUNCTION BOXES, AND CONDUITS AS INDICATED IN THESE STANDARD DETAILS AND AS SHOWN ON THE CUSTOMER'S SITE MTD. WIREWAY WIREWAY
SPECIFIC HMSA DRAWING.
1) THE WIREWAYS PROVIDE THE METHOD AND MEANS TO HOUSE AND PROTECT THE SYSTEM INTERCONNECTION CABLING. EACH
WIREWAY COMPARTMENT HOUSES CABLES THAT PERFORM DIFFERENT SPECIFIC FUNCTIONS. FOR THE EXACT RUNS REQUIRED,
REFER TO YOUR HMSA SITE SPECIFIC DRAWING.
2) THE WIREWAYS FOR THE SYSTEM MUST BE METALLIC AND PROVIDE FOR RF SEPARATION OF THE CABLES. WOOD AND PVC
WIREWAYS ARE NOT ACCEPTABLE. NON-FERROMAGNETIC (ALUMINUM OR STAINLESS STEEL) WIREWAYS MUST BE USED IN THE SCAN
0 LL.LU
3" x 6" OVERHEAD CABLE TRAY
ROOM. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT THE MATERIAL CHOSEN COMPLIES WITH APPLICABLE BUILDING
CODES. SEE NOTE 11
0
3) THE WIREWAY MUST PROVIDE FOUR (4) INDIVIDUAL COMPARTMENTS. THIS MAY BE ACCOMPLISHED USING A SINGLE 6" x 24" DUCT
WITH THREE (3) DIVIDERS. THE DIVIDERS MUST BE CAPABLE OF SUPPORTING FOUR POUNDS PER LINEAR FOOT. AT THE DIRECTION
OF THE HMSA INSTALLER, THE ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR CUTTING OUT DIVIDERS OR DUCTS FOR ALL CABLE
TRANSITION AREAS. ELECTRICAL CONTRACTOR SHALL ALSO PROVIDE GROMMET MATERIAL FOR ALL OPENINGS CUT IN WIREWAY.
4) THE WIREWAY MUST HAVE A REMOVABLE COVER. THE DIVIDERS MUST MAKE CONTACT WITH THE COVER TO FORM RF TIGHT
COMPARTMENTS. NOTE: SCREWS USED TO SECURE COVER MUST BE AS SHORT AS POSSIBLE AND SELF TAPPING SCREWS ARE NOT
ALLOWED. CAUTION MUST BE USED WHEN SECURING COVERS TO ENSURE SCREWS DO NOT PENETRATE CABLES, WATER LINES OR EQUIPMENT
HELIUM LINES. ROOM
5) ALL WIREWAYS MUST BE BONDED TO THE RF SHIELD. A FLAT GROUND STRAP (MIN. 1") TO THE HMSA FILTER PANEL MUST ALSO BE
PROVIDED.
6) AN ON-FLOOR OR IN-FLOOR WIREWAY WITH REMOVABLE COVER TO THE REAR OF THE GANTRY IS REQUIRED FOR SYSTEM
INTERCONNECT CABLES.
- S E E WIREWAY ISOMETRIC
7) A WIREWAY WITH A REMOVABLE COVER AND ONE (1) DIVIDER (MIN. 3 1/2" X 6") IS REQUIRED FROM THE EQUIPMENT ROOM WIREWAY AND SCAN ROOM ELEVATION
TO THE OPERATOR WORKSTATION LOCATION (REFER TO SITE SPECIFIC DRAWING FOR EXACT CONFIGURATION). MOUNTING HEIGHT PG 17 OF 27 SCAN ROOM
MUST BE BETWEEN 3 1/2" AIFF (MIN.) AND 24" AIFF (MAX.). FOR SITES WHERE THE EQUIPMENT ROOM IS REMOTE FROM THE CONTROL
ROOM, A 4" CONDUIT WITH MINIMUM 3'-0" RADIUS BENDS MAY BE UTILIZED. THE CONDUIT IS RUN FROM THE EQUIPMENT ROOM
WIREWAY AND MUST TERMINATE IN A 8" X 8" X 6"d (MINIMUM, LARGER AS REQ'D BY CODE) JUNCTION BOX AT THE OPERATOR
WORKSTATION LOCATION. THE JUNCTION BOX MOUNTING HEIGHT IS AS SPECIFIED ABOVE FOR WIREWAY. MAXIMUM CABLE LENGTH
AVAILABLE FORA CONDUIT RUN IS 39' BETWEEN THE REAR OF THE RFIP CABINET AND THE OPERATOR WORKSTATION LOCATION. A
FISH LINE MUST BE PROVIDED BY THE ELECTRICAL CONTRACTOR IF CONDUIT IS USED.
CONTROL ROOM
8) THE ROUGH OPENING FOR THE FILTER PANEL IS BASED ON THE TOP OF THE WIREWAY BEING AT 24" AIFF (SEE PG. 17 OF 27).
DIFFERENCES BETWEEN WIREWAY MANUFACTURERS MAY EFFECT ACTUAL HEIGHT. AFTER SELECTING AND DESIGNING WIREWAY
BASED ON CUSTOMER'S SITE SPECIFIC HMSA DRAWING, CONFIRM AND ADJUST FILTER PANEL ROUGH OPENING HEIGHT ABOVE FLOOR
D
AS REQUIRED. COORDINATE ROUGH OPENING LOCATION WITH RF VENDOR.
9) A COMPUTER FLOOR MAY BE UTILIZED IN THE EQUIPMENT ROOM IN LIEU OF WIREWAYS. IN SOME INSTANCES, A COMPUTER FLOOR
MAY BE REQUIRED DUE TO INTERCONNECTING CABLE LIMITATIONS (SEE CUSTOMER'S SITE SPECIFIC HMSA DRAWING). IF A
COMPUTER FLOOR IS USED, A MINIMUM CLEAR HEIGHT OF 8" BELOW THE FLOOR IS REQUIRED. ADDITIONALLY, IT IS THE
CUSTOMER'S/CONTRACTOR'S RESPONSIBILITY TO PROVIDE THE NECESSARY KNOCKOUTS (WITH PROTECTIVE GROMMET MATERIAL)
AT ALL EQUIPMENT LOCATIONS, AS DIRECTED BY THE HMSA INSTALLER. THE CONTRACTOR, OR HIS REPRESENTATIVE MUST BE
l
AVAILABLE DURING THE FIRST WEEK OF SYSTEM INSTALLATION.
10) ALL WIREWAYS, JUNCTION BOXES, CONDUITS, AND COMPUTER FLOOR MUST BE IN PLACE AND COMPLETE PRIOR TO DELIVERY OF THE
SYSTEM. WIREWAY PLAN
11) A 3" X 6" OVERHEAD CABLE TRAY (WALKER WIREMOLD SPMA-A-6-3S OR EQ.) IS REQUIRED INSIDE THE SCAN ROOM, SUSPENDED 6" OR NOT TO SCALE
MORE BELOW THE RF CEILING. 3 1/2" X 6" WIREWAY RUNS FROM THE MCU PANEL, UP THE WALL TO THE CABLE TRAY ABOVE THE
CEILING, WHICH TERMINATES ABOVE THE GANTRY BEHIND THE CRYOGEN VENT CONNECTION. THIS OVERHEAD CABLE TRAY MUST
FOLLOW THE PATH INDICATED ON THE SITE SPECIFIC LAYOUT TO PREVENT THE MAGNETIC FIELD FROM CAUSING INTERFERENCE.
TWO 1 3/4" WAVEGUIDES FOR THE HELIUM LINES ARE ALSO REQUIRED FROM THE EQUIPMENT ROOM TO THE OVERHEAD CABLE TRAY
AT THE HEIGHT OF ITS HORIZONTAL RUN TO THE GANTRY. IF SCAN ROOM HAS A HARD (DRYWALL) CEILING RATHER THAN DROP
CEILING, A CHANGE TO THE OVERHEAD TRAY SPECIFICATION MAY BE REQUIRED. CONSULT WITH SITE PLANNING DEPARTMENT.
12) THE WIREWAY FOR CUSTOMER SITES WILL VARY FROM THAT SHOWN ON THESE PAGES. REFER TO THE SITE SPECIFIC HMSA OASIS
MARK II DRAWING FOR FURTHER CLARIFICATION AND EXACT REQUIREMENTS. REFER TO THE ELECTRICAL SECTION OF THESE
STANDARD DETAILS FOR THE OASIS MARK II A. C. POWER WIRING SPECIFICATIONS.
HITACHI MEDICAL SYSTEMS AMERICA
13) THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ALL WORK CONFORMS TO APPLICABLE BUILDING CODES. 1959 SUMMIT COMMERCE PARK TWINSBURG, OH 44087-2371
(800) 800-3106 WWW.HITACHIMED.COM
14) REFER TO HMSA DRAWING FOR SITE SPECIFIC WIREWAY LAYOUT.
WIREWAYS
DATE: 04/30/2012
PAGE 16 OF 27
WIREWAYS {CONT)
2- 1 3/4" WAVEGUIDES FOR HELIUM LINES FROM
EQUIPMENT ROOM INTO OVERHEAD CABLE TRAY. MUST
FILTER PANEL NOTES
3 1/2" x 6" WIREWAY RISER FROM MCU
BE FLUSH WITH INSIDE OF WW ON SCAN RM SIDE SEE PANEL TO OVERHEAD CABLE TRAY
SITE SPECIFIC DRAWING FOR EXACT WAVE GUIDE LOCATION. --........_ 1) THE FILTER PANEL SHOULD BE SURFACE MOUNTED ON THE SCAN ROOM FINISHED
WALL. THIS ASSURES THE CABLES WILL DROP CLEANLY INTO THE WIREWAY.
3" x 6" CABLE TRAY FROM MCU PANEL TO
GANTRY. ROUTE MUST BE AS SHOWN 2) THE FILTER PANEL SHOULD BE MOUNTED SO THAT AN RF TIGHT SEAL IS PROVIDED
ON CUSTOMER SITE SPECIFIC DRAWING AROUND THE PERIMETER . THE RF VENDOR MUST EXTEND THE RF SHIELD TO THE
MUST BE NON-FERROUS FINISHED SIDE OF THE SCAN WALL TO ENSURE A PROPER SEAL IS POSSIBLE.
EQUIPMENT 3) THE FILTER PANEL SHOULD BE MOUNTED USING NON-CONDUCTIVE FRAMING TO
MAINTAIN THE GROUNDING INTEGRITY.
ROOM
4) IF METAL STUDS ARE USED, ROUGH OPENING (R.O.) MUST BE FRAMED IN WOOD ON
SWITCH BOX IN SCAN ROOM WALL W/ BOTH SCAN AND EQUIPMENT ROOM SIDES.
STRAIGHT 1/2" CONDUIT TO~ABOVE
DROP CEILING FOR ERDU 5) FILTER PANEL ROUGH OPENING HEIGHT AFF SCAN ROOM FLOOR IS BASED ON TOP OF
WIREWAY BEING 24" AT AFF. IF TOP OF WIREWAY IS DIFFERENT, ADJUST OPENING
ACCORDINGLY. 3" GAP BETWEEN TOP OF WIREWAY AND FILTER PANEL ROUGH
OPENING MUST BE MAINTAINED TO ENSURE FILTER PANEL COVER FITS PROPERLY.
3 1/2" x 6" WIREWAY TO 6) FILTER PANELS MUST BE PLACED AS INDICATED ON THE SITE SPECIFIC DRAWING IN
OPERATOR CONSOLE ORDER TO ENSURE PROPER FUNCTIONING OF THE SYSTEM
SCAN ROOM 7) WIREWAYS MUST BE RUN AS SHOWN ON THE SITE SPECIFIC DRAWING IN ORDER TO
ENSURE PROPER FUNCTIONING OF THE SYSTEM
WIREWAY ISOMETRIC
RF CEILING SUPPORT
f
(!)
rc RF CEILING
ff
zo SWITCH BOX W/1/2" CONDUIT TO
-w
::::!o
wz
I 3 1/2" x 6" WIREWAY RISER TO 3" x 6" OPEN
~
ABOVE DROP CEILING FOR ERDU
I
Uw
lr- CABLE TRAY (ABOVE CLG.) TO GANTRY
MCU
To
11..:::!: 40"1.1 PANEL
0::::::!:
-lQ 0:::
MIN.
RFWINDOW
3'-Q" X 4'-0''
I
<u :::ro
I TYPICAL RF DOOR
Qw c;,::!: 4'-0" X 7'-0"
a..c::: ::J I FILTER TYPICAL I
~. ~
PANEL 60" +/-
J
54"+/-
= 0 z TYPICAL
TYPICAL
~~
~ ..... ~ I I
~27" TO FILTER PNL TYPICAL RFFLOORl
l l R.O. (TYP)
l JJ '----
WIREWAYS (CONTINUED)
DATE: 04/30/2012
PAGE 17 OF 27
WIREWAYS (CONT)
EXTENSION OF RF SHIELD TO
FACE OF FRAMING FOR ROUGH
OPENING - - - - - - - - - '
ROOM
REMOVABLE COVER
ROOM
REMOVABLE COVER TYPICAL FINISH DETAIL
NOTE: IF METAL STUDS ARE USED, ROUGH
OPENING (R.O.) MUST BE FRAMED
NOTE: IF METAL STUDS ARE USED, ROUGH
OPENING (R.O.) MUST BE FRAMED AT BOTH PANEL OPENINGS
INWOOD. INWOOD.
R.O. IN RF SHIELD
& EQUIP RM WALL ~---RF SHIELD
COLLAR FROM RF ~---AIR GAP
SHIELD TO FACE OF __...---HOST WALL
DRYWALL BY RF
VENDOR ---If-....
I
:'------NON-CONDUCTIVE
WOOD FRAMING (TYP)
COLLAR FROM RF SHIELD
27" FROM SCAN RM
FINISH FLOOR TO OVERLAPPING FACE OF
BOTTOM OF R.O. DRYWALL BY RF VENDOR
24" FROM SCAN RM FILTER PANEL COVER
FINISH FLOOR TO
TOP OF WIREWAY. C..----- MAINTAIN MINIMUM 3" GAP FILTER PANEL COVER
IF HEIGHT OF BETWEEN TOP OF WIRE WAY
WIREWAY VARIES, AND BOTTOM OF R.O. ON
DISTANCE TO BTM BOTH SIDES OF SCAN WALL
OF R.O. MUST BE
ADJUSTED 1-3/4" WAVEGUIDES
COMPUTER FLOOR (OPTIONAL) COMPUTER FLOOR (OPTIONAL)
EQUIP EQUIP
ROOM ROOM
....... .... :
CLEARANCE CLEARANCE
WIREWAYS (CONTINUED)
DATE: 04/30/2012
PAGE 18 OF 27
SAFETY
THE OASIS MARK II SYSTEM IS A HIGH FIELD SUPER CONDUCTIVE MAGNET THAT USES Oasis Mark II Safety Information for Police, Fire,
CRYOGENS FOR OPERATION. THE FOLLOWING MUST BE REVIEWED BY THE ARCHITECT OR
ENGINEER, AND THE APPROPRIATE DESIGN SOLUTIONS INCORPORATED INTO THE SUITE. Emergency Service and Cleaning/Maintenance Personnel
1) A CRYOGEN VENT PIPE TO THE OUTSIDE MUST BE PROVIDED. THE VENT IS A
MULTI-RESPONSIBILITY ITEM TO BE CONSTRUCTED AS FOLLOWS: All Magnetic Resonance Imaging (MRI) cannot be held back nor removed from
a. HMSA WILL PROVIDE AND INSTALL THE CONNECTION TO THE MAGNET WITH equipment operates using a large the magnet. Standard tools containing
FLEXIBLE VENT PIPE. magnet. MRI magnets are very powerful iron, such as hammers, pipe,
b. THE RF VENDOR WILL PROVIDE A WAVE GUIDE (A PIPE WITH FLANGES) TO MAKE and pose a serious danger for police, screwdrivers, knives, pliers, nails,
THE PENETRATION THROUGH THE RF ROOM FOR ATTACHMENT TO THE VENT. firefighters and EMS, as well as cleaning screws, and staples, will similarly be
c. THE CONTRACTOR WILL CONNECT TO THE WAVE GUIDE USING NON-CONDUCTIVE and maintenance personnel. drawn into the magnet.
FASTENERS AND TAKE THE VENT TO THE OUTSIDE.
d. REFER TO THE SIZING CALCULATIONS ON PAGES 20 AND 21 FOR SIZE REQUIREMENTS.
2) FILLING THE OASIS MARK II WITH CRYOGEN (LIQUID HELIUM) IS ACCOMPLISHED USING
LL Warning Electronic equipment not specifically
made for use in a MRI environment may
"DEWARS" DELIVERED TO THE SITE. THESE DEWARS, BOTH FULL AND EMPTY, PRESENT Obey the warning signs posted at the not work properly if brought close to the
A SAFETY CONCERN WHILE ON SITE. THE AMOUNT OF TIME ON SITE WILL VARY entry of the magnet scan room to avoid magnet. This includes pacemakers or
WITH LOCATION AND THE CUSTOMER MUST IDENTIFY A SECURE AND SAFE CRYOGEN potential injury. other implanted devices.
STORAGE AREA. THIS MUST BE ADDRESSED DURING THE PLANNING STAGES OF THE
PROJECT. A CLEAR AND LEVEL DELIVERY ROUTE (3'-6"w X 7'h) FROM THE STORAGE AREA
MRI systems pose a serious danger for
personnel carrying metallic objects into
LL Warning
TO THE SCAN ROOM MUST BE PROVIDED. Do not enter the magnet room if you
the scan room. These objects can be
3) FOR PROTECTION OF ALL OCCUPANTS AND IN ACCORDANCE WITH OSHA REGULATIONS, have a pacemaker or other implanted
uncontrollably attracted to the
HMSA REQUIRES AN EMERGENCY EXHAUST FAN IN THE SCAN ROOM. THE DUCT MUST device. The implanted device may fail
magnetic field. The force is stronger the
EXTEND TO THE FINISHED CEILING. USE OF A CEILING PLENUM IS NOT ACCEPTABLE. and cause a serious injury.
closer the object is to the magnet and
THIS FAN SHALL BE CONTROLLED BY A MANUAL SWITCH LOCATED OUTSIDE OF THE SCAN
ROOM. AN AIR INLET MUST ALSO BE INSTALLED IN THE RF SHIELD TO MAINTAIN A the larger the object. This facility has a MRI system that uses
BALANCED ROOM PRESSURE WHEN THE FAN IS OPERATING AND WHEN THE SCAN ROOM
DOOR IS OPENED OR CLOSED.
®
®
MANUAL FAN SWITCH (OUTSIDE SCAN ROOM DOOR)
RF FILTER FOR TELEDYNE 3350 (9 PIN, D
CONNECTOR BY RF VENDOR OR SUPPLIER
®
®
CRYOGEN VENT
AIR INLET
LL Warning a super-conducting magnet containing
liquid helium. Because it is super-
4) HELIUM IS CONSIDERED A SIMPLE ASPHYXIANT BY OSHA. IN ORDER TO ENSURE A Do not enter the scan room with metallic conducting, the magnet is difficult to
FACILITY'S COMPLIANCE WITH OSHA REGULATIONS, HMSA HIGHLY RECOMMENDS THAT REQUIRED) OR~· WAVE GUIDE FOR MSA ® 120V, 20A, REQUIRED POWER
objects. Such objects become "missiles" turn off In some cases, the liquid
TOXGARD II (BY RF VENDOR)
AN OXYGEN MONITOR CAPABLE OF AUTOMATICALLY OPERATING THE EXHAUST FAN BE Q) CONTACTORIRELAY that could cause serious injury. helium can escape the magnet. The
@ OXYGEN PROBE (IF INSTALLING OPTIONAL - 120V CONTACTOR WITH 120V
INSTALLED IN ADDITION TO THE MANUAL SWITCH. IF AN OXYGEN MONITOR IS INSTALLED, OXYGEN MONITOR): 7'-0" AIFF MINIMUM COIL FOR PULL IN helium turns to gas that can cause
THE CONTRACTOR WOULD BE RESPONSIBLE FOR SUPPLYING AND INSTALLING ALL OF
Firefighters' equipment containing iron,
ITS COMPONENTS. THE OXYGEN MONITOR SHOULD HAVE A BATTERY BACK-UP. THE ® OXYGEN MONITOR (OPTIONAL) ® MAIN PANEL
such as axes, tools, oxygen bottles, fire
severe burns on skin contact.
SAFETY
DATE: 04/30/2012
PAGE 19 OF 27
QUENCH VENT SIZING
CALCULATING PIPE LENGTH AND DIAMETER:
MAXIMUM PERMISSABLE VENT
THE CUSTOMERS ARCHITECT I ENGINEER IS RESPONSIBLE FOR UTILIZING THE FOLLOWING LENGTHS
INFORMATION TO CALCULATE AND DESIGN THE CRYOGEN VENT LINE.
(a) SMOOTH PIPE ~~13/32" (10mm) MINIMUM
1) CALCULATE THE TOTAL APPARENT LENGTH OF THE QUENCH VENT. START THE MAXIMUM LENGTH OF
DIAMETER OF PIPE
,~
CALCULATION ASSUMING A SMOOTH ELBOW (SEE TABLE 2) AND 4" ID PIPE.
l
PIPE
A. L 1 + E1 + (L2 + L3) =LA (26'-0") + (3'-g" (FROM TABLE 2)) + (12'-0") = 41'-10"
INCHES FEET
2) APPARENT LENGTH (LA)= 41'-10". FROM TABLE 1, 6"1D PIPE IS REQUIRED. 4 18
D1 D2
5 40
3) PIPE SIZES MAY BE MIXED.
A. THE PERCENTAGE OF ACTUAL TO ALLOWABLE LENGTH FOR EACH DIAMETER
OF PIPE MUST BE CALCULATED.
6
7
8
77
135
226
L 1------ J
LB~
B. THE COMBINED TOTAL OF PERCENTAGES MUST NOT EXCEED 100%. g 374
C. WHEN CHANGING PIPE SIZES, A DIFFUSER IS REQUIRED (SEE DIFFUSER SIZING
10 602
DIAGRAM THIS PAGE).
D. THE LENGTH OF THE DIFFUSER IS INCLUDED IN THE LENGTH OF THE SMALLER
(b) FLEXIBLE CONVOLUTED TUBE
DIAMETER PIPE TO WHICH IT IS ATTACHED.
MAXIMUM LENGTH OF
QUENCH PIPE DIFFUSER
DIAMETER OF PIPE
4) FROM THE MAXIMUM PERMISSIBLE LENGTH CHART, THE ALLOWABLE LENGTH OF 4" PIPE
PIPE IS 18'. A DIFFUSER IS USED WHENEVER AN INCREASE IN PIPE DIAMETER IS REQUIRED.
INCHES FEET
A. THE 8' SECTION SHOWN IN THE ADJACENT DIAGRAM ACCOUNTS FOR DESIGN CRITERIA: DISTANCE "B" MUST BE GREATER THAN 2.5 x (D2- D1)
4 5
8/18 = 44.44% OF THIS ALLOWABLE LENGTH.
5 11
5) THE REMAINING LENGTH OF 6" PIPE MUST BE LESS THAN 55.56% OF THE ALLOWABLE 6 22
6" LENGTH. 7 41
A. 77' X 55.56% (.5556) = 42'-g", 8 75
~
go• go• 45° 45°
26'-0" INCHES MITERED
SMOOTH SEGMENTED SMOOTH SEGMENTED
~~---~----- (L1) ----.J-~--............~
7 4 3'-9'' 6'-8" 2'-6" 4'-4'' 22'-2"
_;·~CALCULATED
5 4'-9" 8'-3" 3'-2'' 5'-6" 27'-10"
--+ 6 5'-8'' g'-11" 3'-9'' 6'-8" 33'-5" \.....____ M1g BOLT (TYP)
, . .i
( ( ...,_
L_l MAXIMUM OR 4 '-0" 7 6'-10" 11'-11" 4'-6" 7'-7'"' 3g'-1" *DIMENSIONS SHOWN IN MILl METERS
8 8'-0'' 13'-11" 5'-2'' g'-1" 44'-4"
g 8'-g" 15'-3" 5'-g" g'-11" 50'-11"
CRYOGEN VENT FLANGE
8'-0" TABLE 2.
(L3)
EFFECTIVE LENGTH OF BENDS
I NOTE: INTERPOLATE FOR VALUES BETWEEN o•- 45• AND 45•- go•.
I DATA ONLY TO BE USED FOR BENDS WHERE THE RADIUS TO DIAMETER
RATIO IS IN THE RANGE OF 1.5 TO 5.0, EXCEPT FOR RIGHT ANGLE MITERED
JOINTS.
I SHIELD
CALCULATIONS.
HITACHI MEDICAL SYSTEMS AMERICA
NOTE THAT A SECOND QUENCH VALVE ELBOW WOULD TAKE 17% OF THE
1959 SUMMIT COMMERCE PARK TWINSBURG, OH 44087-2371
MAXIMUM PERMISSABLE LENGTH
(800) 800-3106 WWW.HITACHIMED.COM
DATE: 04/30/2012
PAGE 21 OF 27
MAGNET PROXIMITY
MAGNET PLACEMENT
THE AREA COVERED BY THE MAGNET'S FRINGE FIELDS IS OF PRIME CONCERN WHEN SELECTING AN MRI SITE.
CONSIDERATION MUST BE GIVEN TO THE FOLLOWING CONCERNS:
1) USE OF THE SURROUNDING AREAS, INCLUDING SPACE ABOVE AND ADJACENT TO THE MAGNET. IT MAY BE
POSSIBLE TO REDUCE THE INFLUENCE OF THE MAGNETIC FIELD ON ADJACENT SPACES WITH THE USE OF
MAGNETIC SHIELDING. CONSULT WITH THE SITE PLANNING SPECIALIST FOR FURTHER INFORMATION.
2) TYPE OF CONSTRUCTION MATERIALS USED IN THE EXISTING STRUCTURES, PARTICULARLY COLUMNS,
BEAMS, JOISTS, REINFORCEMENT STEEL, AND CAST IRON PIPES.
DEVICES AFFECTED BY MAGNETIC FIELDS 3) LOCATION OF MECHANICAL EQUIPMENT AND OTHER MEDICAL MODALITIES.
4) LOCATION OF ELEVATORS, LOADING DOCKS, PARKING LOTS, DRIVEWAYS, AND ELECTRICAL SERVICES (INCLUDING
NUCLEAR CAMERAS, PET SCANNER, COLOR MONITORS, IMAGE INTENSIFIER, LINEAR
1 GAUSS BURIED UTILITIES).
ACCELERATOR, ULTRASOUND, CT SCANNER, MRI SCANNER, ELECTRON MICROSCOPE 5) A MAGNETIC FLUCTUATION TEST MUST BE PERFORMED AT ALL SITES TO ASSIST IN IDENTIFYING POSSIBLE
SOURCES OF INTERFERENCE. A SITE CANNOT RECEIVE FINAL APPROVAL BY HMSA SITE PLANNING WITHOUT THIS
MULTI FORMAT CAMERA (LASER IMAGER), COMPUTER HARD
3GAUSS TEST.
DRIVES, ELECTRONIC MEMORY CARD, FERROUS CARD, WATCH
5GAUSS PACE MAKER, CREDIT CARDS, ANALOG CELLULAR PHONE, DEFIBRILLATORS, IMPLANTS MAGNETIC SHIELDING
RF SHIELDING (PG 8 OF 27) WHICH ELIMINATES RADIO SIGNALS FROM REACHING THE SYSTEM IS DIFFERENT THAN
MAGNETIC SHIELDING AND IS REQUIRED FOR AN OASIS MARK II MRI SYSTEM WHETHER MAGNETIC SHIELDING IS USED
OR NOT. MAGNETIC SHIELDING PROVIDES A MEANS OF LIMITING THE DISTANCE THE GAUSS FIELDS EXTEND OUT FROM
AN OASIS MARK II SYSTEM'S ISO-CENTER OR DAMPING THE EFFECTS THE SURROUNDING ENVIRONMENT (SEE CHART
THIS PAGE) MAY HAVE ON IT.
MAGNETIC SHIELDING IS CONSTRUCTED OF FERROUS METAL AND IS TYPICALLY MOUNTED TO THE EXTERIOR OF THE RF
REQUIRED DISTANCE FROM ISOCENTER TO ITEMS SHIELD. IT IS NORMALLY SUPPLIED AND INSTALLED BY THE RF SHIELDING VENDOR AT THE TIME THE RF SHIELD IS
THAT MAY AFFECT MAGNET INSTALLED. LIKE ANY OTHER FERROUS OBJECT, ITS MAGNETIC PROPERTIES AFFECT THE SHIM OF THE MAGNET (SEE
MAGNETIC SHIMMING THIS PAGE)
10' LARGE FERROUS OBJECTS OVER 400 LBS., MAJOR STRUCTURAL STEEL, FERROUS CART
AUTOMOBILES, SMALL TRUCKS, HVAC AIR HANDLERS, HVAC CONDENSERS, WATER CHILLERS,
MAGNET SHIMMING
20' ONCE THE MRI SYSTEM IS INSTALLED, THE MAGNETIC FIELD IS SHIMMED TO COUNTERACT THE EFFECT OF ANY
ELECTRICAL SUB-PANELS OVER 50 AMP, LARGE MOTORS (GAS AND ELECTRIC)
PERMANENT FERROMAGNETIC OBJECTS AROUND IT. THE WEIGHT OF THE OBJECT AND ITS DISTANCE FROM THE
ISO-CENTER OF THE GANTRY DETERMINE THE INFLUENCE IT WILL HAVE ON THE MAGNETIC FIELDS. IN ORDER TO
LARGE TRUCKS AND BUSES, ELEVATORS, ESCALATORS, LARGE ELECTRICAL TRANSFORMERS, PROPERLY EVALUATE A SITE AND DETERMINE THE AFFECT OF SUCH OBJECTS ON THE ABILITY TO SHIM THE MAGNET,
40'
LARGE ELECTRICAL PANELS (OVER 200 AMP), MAIN ELECTRICAL FEEDER LINES (INCLUDING THE FOLLOWING INFORMATION MUST BE PROVIDED:
UNDERGROUND) 1) THE SIZE (I.E.: W24 X 76) AND LOCATION OF STRUCTURAL STEEL COLUMNS AND BEAMS ADJACENT TO THE SCAN
ROOM. THIS INFORMATION IS NORMALLY FOUND ON THE STRUCTURAL DRAWINGS FOR A BUILDING.
200' HIGH TENSION ELECTRICAL LINES, RAILROAD TRACKS, HELICOPTER PAD 2) THE THICKNESS AND LOCATION OF MAGNETIC SHIELDING THAT WILL REMAIN IN PLACE IF THE OASIS MARK IllS TO
BE INSTALLED IN AN EXISTING MRI SCAN ROOM. THIS INFORMATION CAN BE NORMALLY BE FOUND ON THE RF
SHIELD DRAWINGS OR BY CONTACTING THE RF SHIELDING VENDOR WITH THE SERIAL NUMBER OF THE ROOM.
3) THE WEIGHT OF ANY OTHER LARGE PERMANENT FERROUS OBJECTS (I.E. WALK-IN SAFE) ADJACENT TO THE SCAN
ROOM.
NOTE:
THE ABOVE CHARTS ARE INTENDED SOLELY AS A GUIDELINE AND NOT AS AN MAGNET AFFECT ON LOOSE OBJECTS
ALL-INCLUSIVE CHECKLIST. IT MAY BE POSSIBLE TO DAMPEN THE EFFECT OF SOME OF ATTRACTION OF LOOSE FERROMAGNETIC OBJECTS IS OF CONCERN WITHIN THE MRI SCAN ROOM. THE MAGNET'S FIELD
THE DC TYPE INFLUENCES (CAUSED BY MOVING OBJECTS) THROUGH THE USE OF STRENGTH IS CAPABLE OF ACCELERATING UNRESTRAINED FERROUS OBJECTS. THE GREATER THE MASS OF THE
MAGNETIC SHIELDING. THE EFFECT OF MAGNETIC SHIELDING AGAINST A. C. TYPE OBJECT AND THE CLOSER IT GETS TO THE MAGNET, THE STRONGER THE ATTRACTION. NEAR THE MAGNET, HUMAN
INTERFERENCE (ELECTRICAL POWER) IS SIGNIFICANTLY LESS THAN FOR D.C. TYPES. STRENGTH MAY NOT BE SUFFICIENT TO RESTRAIN FERROUS OBJECTS SUCH AS OXYGEN TANKS AND CRASH CARTS.
CONSULT WITH THE HMSA SITE PLANNER FOR FURTHER INFORMATION. SUCH OBJECTS WILL BE DRAWN INTO (OR ONTO) THE MAGNET, POTENTIALLY CAUSING INJURY OR DEATH TO PERSONS
AND DAMAGE TO THE MRI SYSTEM. SUCH OBJECTS MUST NOT BE ALLOWED IN THE SCAN ROOM. SPECIAL NONFERROUS
EQUIPMENT SHOULD BE OBTAINED AND IDENTIFIED FOR USE IN THE SCAN ROOM.
ACCESS RESTRICTION
FDA REQUIREMENT RESTRICTS PUBLIC ACCESS WITHIN THE 5 GAUSS FIELD UNLESS INDIVIDUALS HAVE BEEN
PROPERLY SCREENED.
MAGNET PROXIMITY
DATE: 04/30/2012 I REVISION: 01/19/2015
OASIS MARK II STANDARD DETAILS I PAGE 22 OF 27
RIGGING AND DELIVERY
T
DURING THE INITIAL PLANNING OF THE OASIS MARK II SUITE, A SYSTEM DELIVERY PATH
MUST BE IDENTIFIED. THE DESIGN TEAM SHOULD REVIEW THE INFORMATION
PRESENTED ON THIS PAGE TO ENSURE A STAGING AREA AND A CLEAR DELIVERY PATH
IS AVAILABLE. WHILE THE MAGNET IS THE MAJOR CONCERN, CLEARANCES MUST ALSO
BE ASSURED FOR THE DELIVERY OF ANCILLARY SYSTEM COMPONENTS, SERVICE I
INSTALLATION TOOLS AND THE ONGOING REQUIREMENT OF HELIUM DEWARS. SITE
l
PLANNING WILL ASSIST IN IDENTIFYING THE MOST APPROPRIATE DELIVERY PATH.
NOTE: SITE PLANNING WILL NOT CONFIRM A SCHEDULED DELIVERY DATE WITHOUT: RIGGING AND DELIVERY
1. A SUBMITTED PRE-DELIVERY CHECKLIST
2. ADMINISTRATIVE APPROVAL DATE: 04/30/2012
PAGE 23 OF 27
..,.,..- --,
.,.,...----------.....
/
/
/
..,.,..- ------ ' ' -''' ''
' ' ' ''
/ /
I
/
/
/
/
/
/
,..,.,.. - - - -
/
'
------
- -,' '
I I / /"' - - - - - '' \
I I / / /"' ', ' ' \ \
I I 1 / / ----, ' '' \ \
I I I I I /"'---' ' ' \ \ \ \
I I I I I 1// ',, \ \\ \ \
I I I I I I 1 \\ \ \ \
I I I II 11 \\ \ I
.5G 1G 3G 5G 1oG 5oGI I I I
I
\
\
I
\
\
I \ \
\ \ \
\ \ \
,,,,
\ 1~0G
I I
\ '
-
................
'' " "
' .........
................ ........ _ HITACHI MEDICAL SYSTEMS AMERICA
1959 SUMMIT COMMERCE PARK TWINSBURG, OH 44087-2371
(800) 800-3106 WWW.HITACHIMED.COM
'' ........
- ..,.,..
1---------.~.......:jg·.a" - - - - - - - 1
i= s·-~2·
,------------------,
.I
r-···-···-···-···-···-···-···-···1 L_____ ,
. \
\
\
\
L \l====l=====r=:::;r \
ll
I'F=-~===~LJ;;;;;;;;;;;;;;;
::
_j )
~
I
I
I
I
I I
8'-11"
I I I
8'-376
/
1--
I
' v \ '
~ ~
ll
-q)\
'=- I .....
0
_.,_
~
tt- ""'\ J
.....
I
F-.
/ f--
r--
---t
3'-3 3/8"
2'-7"
7'-6"
t- 6'·11'
1'~0"
3'-4"
!
~2'-7 1/2"-1-2'-8 1/4"j ~2'-4'Y- 2'-0" ~
JJ 0
.__________,jj
-+---+1
2'~0"
6'-0"
1- 5'-33/4" 1-4'-4"-l
. . II
r =·
0~ 0 6" Ll_2'-6"J_2'-0"J
~
i :·~··--··. 0 Cs·-o. :..:J
·II 0 . .
6'-2" 6'-2" 1·~ r I
o~ ·I=i 11111111111 1·
l
0
0
==
;;
"""
~
SIDE VIEW
0
RFIP CABINET
.
FRONT VIEW
.
L• FRONT VIEW
HEAT EXCHANGER
SIDE VIEW
MULTIPLE CABLE CONNECTIONS AND MAIN POWER MULTIPLE CABLE CONNECTIONS, GRADIENT CABLE CONNECTIONS, AND WATER HOSE CONNECTIONS FROM R-1200 CHILLER AND TO SENSE UNIT.
CONNECTION WILL LIMIT CABINET MOVEMENT FOR SERVICING. WATER HOSE CONNECTIONS WILL LIMIT CABINET MOVEMENT FOR SERVICING. SERVICE AREA MUST BE MAINTAINED WHEN SITING.
SERVICE AREA MUST BE MAINTAINED WHEN SITING. SERVICE AREA MUST BE MAINTAINED WHEN SITING.
8"
•
14'.()"=fl
==~Eio
f 1'-4"
+-
3'-8"
! t 1'-8"
2'-10"
fL
~
18"~2'-8"-18"1
TOP VIEW
THIS CHECKLIST MUST BE COMPLETED AND RETURNED TO HMSA TWINSBURG A MINIMUM OF FOURTEEN (14)
CALENDAR DAYS AND TEN (10) WORKING DAYS PRIOR TO DELIVERY
Done To be completed by
GENERAL CONSTRUCTION
All Rooms are clean of construction dust and debris (broom clean)
Contractor / Customer advised no construction may take place during shimming process (days 4 - 7 after delivery)
Contractor advised and prepared for system delivery/room closure schedule (see pg 2 of 27 OASIS Standard Details) NOTE:
Please be advised that the site preparations as outlined in Site Planning Standard Details and related checklists are essential for
RF SHIELD delivery and installation. Because all arrangements for the delivery of your system must be completed two weeks in advance of
Preliminary test completed and shield verified ground free delivery, any delay caused by incomplete site preparation will result in unavoidable additional cost related to scheduling and
Floor levelness verified by RF vendor: +/- 1/8” over entire area of gantry and patient table transportation of Riggers, delivery and installation personnel, cryogens, re-filling costs, storage costs, rescheduling fees, etc.
3”+ distance from top of wireway to bottom of filter panel rough opening on scan room side These additional charges could exceed $25,000.
Wave Guides (4) installed in btm. wireway compartment. Must be flush to inside face of wireway on scan room side
Wave Guides (2) installed above MCU. Must connect to (flush to inside face on scan rm side) overhead ww to gantry Planned Delivery Date:_____________________________
Filter Panel frames installed and ready for panel installation
st
RF Vendor scheduled by contractor for access panel and filter panel installation and final test on 1 day of delivery Site Name:_________________________________________________________________________________________
Phone: ________________________________
Done To be completed by
CONTROL and EQUIPMENT ROOMS Date:____________ HMSA FSE Signature: ____________________________________
Walls sanded and painted (except access opening if required)
Flooring complete Name printed____________________________________________
Ceiling Installed
Cabinetry installed
Wireway installed (with min 3” distance from top of ww to btm of filter panel rough opening on scan room side) Date:____________ Customer Signature:______________________________________
Customer/contractor advised that only pre-approved punch list items may be addressed after delivery (or authorized representative) .
Floor drain in equipment room (located so it will NOT be directly under a system cabinet) Name printed____________________________________________
Notes:
1. Scan and e-mail PDF file to: [email protected]
CHILLER AND HEAT EXCHANGER
Chiller installed (hard-wired, plumbed and ready for no-load startup)
2. Contact assigned Site Planner with any questions
Chiller checklist completed and returned to Haskris (fax 847-956-6595)
3. If MedRad injector has been purchased (optional), customer/contractor must schedule installation with MedRad for day 4 or 5 of Oasis installation
No load start-up scheduled with Haskris (completed chiller checklist required) 847-956-6420 prior to magnet delivery HITACHI OASIS MARK II PRE-DELIVERY CHECKLIST (REV 06/18/12) DM# 84477 v2 3 of 3
ELECTRICAL
480 V, 30 Amp, 3 phase receptacle for Magnet Ramp supply (NEMA L16-30R outside of scan room door)
480 V, 100 Amp, 3 phase supply line pulled to planned location of RFIP cabinet
480 V, 3MCA, 15 MOCP, 3 phase supply line pulled to planned location of Heat Exchanger
Single Point ground has been verified for MRI sub-panel
nd
Electrician scheduled to connect power to RFIP cabinet on 2 day of delivery
ENVIRONMENTAL
HVAC operational in all rooms
COMMUNICATIONS
Phone lines available in control and equipment rooms for use by service personnel Phone #
Network interface information sent to [email protected] (pg 3 of 27 Oasis Standard Details)
Network connections in place and functional with access to internet Network contact name:
FACILITIES
HMSA has 24 hour access
Functional restroom facilities available in work area
nd
Empty 40 yd. dumpster on site morning of delivery with empty scheduled for 2 morning
Storage area for 6 cryogen dewars (36” x 48” each) available with unrestricted path to the Scan Room (42” width)
Storage area approximately 600 sq. ft. (20’x30’) available near scan room for misc. equipment and parts
OASIS MarkⅡ
White
7.2Y 8.6/0.3
Pure White
3.5Y 9.0/0.3 White
7.2Y 8.6/0.3