Report No:
NEW HORIZON DESIGN & CONSTRUCTION 125
MANAGEMENT CO. LTD. DAILY REPORT
CONTRACT NUMBER: W911KB-17-D-0035 USACE HA In Nepal
(ATTACH ADDITIONAL SHEETS Report Date:
: W911KB18F0168 IF NECESSARY)
19th March ,2020
PROJECT NAME / LOCATION : DESIGN BUILD SERVICES, FAR WEST
TASK ORDER NO: N/A
BLOOD BANK (27481),KAILALI, DHANGADI, NEPAL
PROJECT DESCRIPTION:
Design Build Services ,Far West Blood Bank (27481), kailali, Dhangadi, Nepal
PROJECT NUMBER: W911KB-17-D-0035 The building is 2 storied ground floor and first floor consisting of blood storage area, blood distribution
area, hemoglobin screening area , washing and sterilize room, counseling , store room ,laboratory , staff
: W911KB18F0168 break room, training and conference ,refreshment room, blood disposal room, courier waiting area and
night duty guard , data base collection and management
Utilities Include: 3 Phase Power supply system, Water supply system,
QA REPRESENTATIVES: Director -
John R. Troha: Project Manager, Rohan PREPARED BY: Er. Dhirendra raj ojha
PROJECT MANAGER: katie.M.Archer
shrestha : Dhirendra raj ojha : site New Horizon QA Engineer
Engineer
AM WEATHER: sunny PM WEATHER: sunny MAX TEMP:310C MIN TEMP: 160C
TAILGATE TOPICS:(List of all meetings in the date about: safety, quality, schedule, design, shop drawings)
none
SAFETY ACTIONS TAKEN TODAY/SAFETY INSPECTIONS CONDUCTED (Include Safety Violations, Corrective Instructions Given, Corrective Actions Taken, and
Results of Safety Inspections Conducted):
1. Safety violations as the workers do not use PPE during work time throughout the day
EQUIPMENT USING IN THE DATE
Description of Equipment Make/Model/Manufacturer Equipment ID Number Inspection Performed By
Hammer, wheel barrow, hoe , pick axe, spade,
measuring tape ,masonry trowel, float , measuring Local Made Not Applicable Er. Dhirendra raj ojha
box, sprit level ,vibrators, cube mould
Rebar cutter machine
Made in India Not applicable Er. Dhirendra raj ojha
Concrete mixer machine Made in India Not applicable Er. Dhirendra raj ojha
Vibrator (50mm needle )
Made in India
Plywood cutter machine Made in India “ ‘’
Level Machine Made in India ‘’ ‘’
Aluminum Staff Made in India ‘’ ‘’
Drilling machine Made in India “ “
“
Cube mould Made in india “
COMMENTS (Acceptance Status, Inspection Findings, etc.):
• All the equipment’s delivered on site are in working condition.
MATERIALS DELIVERED TO JOB SITE
Number/ Volume/
Description of Materials Received Make/Model/Manufacturer Equipment Lot Number Inspection Performed By
Weight
Brick N/A N/A Dhirendra raj ojha 3000nos.
Page 1 of 7
COMMENTS (acceptance status, inspection findings)
1 ) 2nd class brick is arrived at site
2) Instruction for lab test of brick in the presence of New Horizon Site Engineer
WORK FORCE – CONTRACTOR AND SUB-CONTRACTOR (All the people who works onsite)
Employer Employee Employee Number Title/Trade Work Performed Hours
New Horizon Dhirendra 01 QA Site Engineer Supervision 8
Himalayan builders Roshan/Ravi 02 Site Engineer/ supervisor Supervision 16
Himalayan builders Skilled manpower 4 Construction worker Formwork /site cleaning 40
Himalayan builders Unskilled manpower 10 Construction Worker Formwork/site cleaning 100
Total 17 164
WORK AND TESTS ACCOMPLISHED OR IN PROGRESS:
SUB- STRUCTURE:
SN DESCRIPTION STATUS Approx. Quantity Remarks
1 Site Mobilization with CGI sheet fence, Completed
Electricity Supply and construction of
labour camp , site office , store room ,site
rest room , site clearance
2 Gravel piling (7.5 m deep, 500mm Dia, Completed 81 nos.
3 Earthwork in excavation for foundation completed 165.8861 m3
footing
4 Rammed earth completed
5 150 mm thick gravel packing and completed 35.1886m3
compaction work at foundation footing
6 75mm thick PCC (1:3:6)at foundation Completed 17.8064m3 M10
footing
7 Rebar fabrication for foundation footing completed 18000kg
, column, and shear wall
8 Layout of building foundation footing completed
and column
9 Rebar installation for foundation footing completed 18000kg
,column and shear wall
10 Formwork/shuttering preparation at completed
foundation footing level
11 Pouring of concrete at foundation completed 120m3 M20
footing level
12 Rebar fabrication for footing beam completed 2400kg
13 Excavation work at foundation footing completed 36m3
beam
14 Flat brick soling at foundation footing completed 90m2
beam
15 PCC at foundation footing beam completed 6m3 M10
16 Rebar installation for footing beam completed 2400kg
17 Rebar fabrication for plinth beam completed 3000kg
Page 2 of 7
18 Formwork/shuttering preparation for completed
footing beam
19 Pouring of concrete at footing beam completed 24 m3 M20
3
20 Brick wall construction work at sub completed 23.14m
structure
21 Formwork preparation and installation completed 100%
for short columns and shear wall
22 Pouring of concrete at short column completed 2.36m3 M30
23 Pouring of concrete at shear wall of completed 1.98m3 M20
brick wall level
24 Rebar installation for plinth beam completed 3000kg
25 Formwork installation for plinth beam completed 100%
26 Concreting of shear wall and plinth completed 19.440m3 M20
beam
27 Concreting of column at plinth level completed 1.559m3 M30
28 Back filling of floors with compaction completed 100%
29 Anti termites works on floor completed 100%
30 Gravel packing and compaction on floor completed 60m3
31 Rebar installation for SOG slab completed 2025kg
32 Concreting work for SOG slab completed 57m3 M25
SUPER STRUCTURE
First floor detail works
1 Rebar fabrication and installation for Completed 2800kg
column
2 Formwork preparation for first floor Completed 100%
column and first floor beam
3 Rebar fabrication for first floor beam Completed 100%
4 Rebar installation for shear wall and Completed 2250kg
shear wall beam
5 Formwork installation for column and Completed 100%
shear wall
6 Concreting of First floor column and Completed 27m3 M30
shear wall
7 Formwork /shuttering installation for Completed 100%
first floor Main beam and secondary
beam
8 Formwork installation for staircase Completed 100%
,staircase beam
9 Rebar installation for staircase ,staircase Completed 700kg
beam , main bar binder bar , stirrups
,chair nosing bar, hanger bar, extra bar
10 Formwork installation for First floor Completed 100%
slab / Centering of slab
11 Concreting work of staircase completed Completed 4M3 M20
Page 3 of 7
12 Rebar installation for first floor beam Completed 4500kg
and column junction ties
13 Rebar installation for first floor slab, Completed 4400kg
slab tough, and duct
14 Electrical work pipe laying for first Completed
floor slab
15 Concreting work of first floor slab , Completed 76M3 M20
beam ,slab tough , duct
Second floor detail works
1 Layout of column Completed
2 Ties preparation for column Progress /running 1700kg
3 Ties installation and rebar lapping for completed 3600 kg
column
4 Shear wall and shear wall beam rebar Progress/running 1000kg
installation
5 Formwork for column and shear wall Progress/running 93%
6 Concreting work of column and shear Progress/running 22m3 M30
wall
7 Formwork installation for 2nd floor beam Progress/running 45%
Performed Work / Test for Today
Curing of column
Formwork installation for 2nd floor beam bottom and side surface
Site cleaning work
Page 4 of 7
Planned Work / Test for Tomorrow
Curing of column
Formwork installation for beam bottom and side surface
Formwork installation for 2nd floor slab
Brick wall construction work at 1st floor
Planned Work / Test for Next week
Curing of column
Formwork ,rebar work, concreting work of staircase
Formwork for 2nd floor beam bottom and side surface
Formwork for slab
INSPECTIONS PERFORMANCE:
Task/Activity Inspection Performed Findings
Site development works Curing of column and shear wall , site cleaning work 1.Meet the design requirement for construction
Formwork of 2nd floor beam Checking the line and layout of formwork 1.Meet the design requirement for construction
SUBMITTALS INSPECTION / REVIEW
Submittal No. Submittal Description Specification/Plan Submittal Approved? Comment/Reason/Action
Reference
None Today None Today None Today Yes No
Yes No
Yes No
Page 5 of 7
CHANGED CONDITIONS/DELAY/CONFLICTS ENCOUNTERED (List any conflicts with the delivery order [i.e., scope of work and/or drawings], delays to the project
attributable to site and weather conditions, etc.
none
VISITORS AND DISCUSSIONS:
• N/A
TRANSPORTATION AND DISPOSAL
1) None.
GENERAL COMMENT
1. Curing of column and shear wall only by using spraying method
2. Instruction for curing of vertical surface by using wet covering jute bags
ATTACHMENTS: Design Build Services Far West Blood Bank CENTER , Dhangadi Nepal construction photos
Formwork remove of shear wall Formwork installation and providing support for beam bottom surface
Site cleaning work Site cleaning work
Formwork installation for column Formwork installation for beam bottom surface
Page 6 of 7
Formwork/shuttering installation for beam bottom and side surface Overall view of sight
2NOTE: Write all entries legibly in ink. Line out all unused portions or designate as “not
applicable”. Preparer signs first name, middle initial and last name on each completed daily
Inspection record. This form may be filled out electronically and signed electronically.
PREPARER’S SIGNATURE Date:
Er. Dhirendra raj ojha 19th March, 2020
(signed)
Page 7 of 7