Activities Table

The document outlines the activities and schedule for constructing a 20km road from Bhiwandi to Mumbai over an 11 week period from November 1st to December 11th. It involves 5 main stages - permission and design, foundation, plastic process, final road works, and quality checks. Each stage contains sub-activities with assigned start and end dates to be completed by 7 resources.

Uploaded by

Chahat Jaura
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views8 pages

Activities Table

The document outlines the activities and schedule for constructing a 20km road from Bhiwandi to Mumbai over an 11 week period from November 1st to December 11th. It involves 5 main stages - permission and design, foundation, plastic process, final road works, and quality checks. Each stage contains sub-activities with assigned start and end dates to be completed by 7 resources.

Uploaded by

Chahat Jaura
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

ID Activity Inicial Date

1 Permission 1 Permission
1.1 Department Approval 1.1 Department Approval 1-Nov
1.2 Close Road 1.2 Close Road 1-Nov
2 Designs 2 Designs
2.1 Survey 2.1 Survey
2.1.1 Calculate traffic Volume 2.1.1 Calculate traffic Volume 3-Nov
2.1.2 Study Of soil properties 2.1.2 Study Of soil properties 3-Nov
2.2 Preliminary Design 2.2 Preliminary Design 5-Nov
2.3 Final Design 2.3 Final Design 8-Nov
3 Foundation 3 Foundation
3.1 Excavation 3.1 Excavation 10-Nov
3.2 Mounting 3.2 Mounting
3.2.1 Place large stones and stand 3.2.1 Place large stones and stand 12-Nov
3.2.2 Pebbles and gravel 3.2.2 Pebbles and gravel 14-Nov
3.2.3 Paving Stones 3.2.3 Paving Stones 16-Nov
3.3 Bitumen coat 3.3 Bitumen coat 17-Nov
4 Plastic Process 4 Plastic Process
4.1 Plastic Procurement 4.1 Plastic Procurement 19-Nov
4.2 Segregation 4.2 Segregation 21-Nov
4.3 Process into plastic mix 4.3 Process into plastic mix
4.3.1 Cut plastic into 2.36mm, 4.75mm 4.3.1 Cut plastic into 2.36mm, 4.75m 24-Nov
4.3.2 Heating plastic 4.3.2 Heating plastic 27-Nov
5 Final road 5 Final road
5.1 Place plastic bitumen mix 5.1 Place plastic bitumen mix 30-Nov
5.2 Roller operation 5.2 Roller operation 5-Dec
5.3 Quality Check 5.3 Quality Check 9-Dec
SME
End Date Duration Effort Resource 1 Resource 2 Resource 3 Resource 4 Resource 5

2-Nov -1.00 2 2 2
2-Nov 1.00 1 1 1
0.00 0
0.00 0
4-Nov 1.00 2 4 2 2
4-Nov 1.00 2 4 2 2
7-Nov 2.00 3 9 3 3 3
9-Nov 1.00 2 6 2 2 2
0.00 0
11-Nov 1.00 2 10 2 2 2 2 2
0.00 0
13-Nov 1.00 2 8 2 2 2 2
15-Nov 1.00 2 8 2 2 2 2
16-Nov 0.00 1 2 1 1
18-Nov 1.00 2 8 2 2 2 2
0.00 0
20-Nov 1.00 2 1 1
23-Nov 2.00 3 3 3
0.00 0
26-Nov 2.00 3 3 3
29-Nov 2.00 3 3 3
0.00 0
4-Dec 4.00 5 25 5 5 5 5 5
8-Dec 3.00 4 8 4 4
10-Dec 1.00 2 6 2 2 2
Resource 6 Resource 7
Project Name: Construction of a 20Km Road - Bhiwandi to Mumbai

ID Activity Inicial Date


1.1 Department Approval 1.1 Department Approval 1-Nov
1.2 Closed Road 1.2 Closed Road 2-Nov
2.1.1 Calculate traffic Volume 2.1.1 Calculate traffic Volume 3-Nov
2.1.2 Study Of soil properties 2.1.2 Study Of soil properties 3-Nov
2.2 Preliminary Design 2.2 Preliminary Design 5-Nov
2.3 Final Design 2.3 Final Design 8-Nov
3.1 Excavation 3.1 Excavation 10-Nov
3.2.1 Place large stones and stand 3.2.1 Place large stones and stand 12-Nov
3.2.2 Pebbles and gravel 3.2.2 Pebbles and gravel 14-Nov
3.2.3 Paving Stones 3.2.3 Paving Stones 16-Nov
3.3 Bitumen coat 3.3 Bitumen coat 17-Nov
4.1 Procurement Plastic 4.1 Procurement Plastic 19-Nov
4.2 Segregation 4.2 Segregation 21-Nov
4.3.1 Cut plastic into 2.36mm, 4.75mm 4.3.1 Cut plastic into 2.36mm, 4.75mm 24-Nov
4.3.2 Heating plastic 4.3.2 Heating plastic 27-Nov
5.1 Place plastic bitumen mix 5.1 Place plastic bitumen mix 30-Nov
5.2 Roller operation 5.2 Roller operation 5-Dec
5.3 Quality Check 9-Dec

1-Nov 6-Nov 11-Nov 16-Nov 21-Nov 26-Nov 1-Dec 6-Dec 11-Dec


1.1
1.2
2.1.1
2.1.2
2.2
2.3
3.1
3.2.1
3.2.2
3.2.3
3.3
4.1
4.2
4.3.1
4.3.2
5.1
5.2
5.3
4.1
4.2
4.3.1
4.3.2
5.1
5.2
5.3
End Date Duration Predecessor Successors
1-Nov 1 1.2
2-Nov 1 1.1 2.1.1, 2.1.2
4-Nov 2 1.2 2.2
4-Nov 2 1.2 2.2
7-Nov 3 2.1.2,2.1.2 2.3
9-Nov 2 2.2 3.1
11-Nov 2 2.3 3.2.1
13-Nov 2 3.1 3.2.2
15-Nov 2 3.2.1 3.2.3
16-Nov 1 3.2.2 3.3
18-Nov 2 3.2.3 4.1
20-Nov 2 3.3 4.2
23-Nov 3 4.1 4.3.1
26-Nov 3 4.2 4.3.2
29-Nov 3 4.3.1 5.1
4-Dec 5 4.3.2 5.2
8-Dec 4 5.1 5.3
10-Dec 2 5.2

6-Dec 11-Dec