Construction Productivity

This document outlines various construction works and their estimated daily productivity rates measured in square meters or cubic meters per day. It includes excavation, backfilling, concrete works, reinforcement works, shuttering, plastering, painting, tile works and more. Crew sizes for each task are also provided and typically include some combination of skilled masons, helpers, riggers, painters, etc. along with necessary equipment like excavators, rollers, pumps.

Uploaded by

Raif
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views4 pages

Construction Productivity

This document outlines various construction works and their estimated daily productivity rates measured in square meters or cubic meters per day. It includes excavation, backfilling, concrete works, reinforcement works, shuttering, plastering, painting, tile works and more. Crew sizes for each task are also provided and typically include some combination of skilled masons, helpers, riggers, painters, etc. along with necessary equipment like excavators, rollers, pumps.

Uploaded by

Raif
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Earth Works

Excavation work in soft soil 120 m3/day


Excavation Work in Hard Soil 50 m3/day

In layer of 150 mm thickness with 95% MDD


Back Filling + Compaction 150 m2/day
value

Concrete Protection Works

Bitumen Priming Works Including surface preparation 200 m2/day


Bitustic works Horizontal/Vertical surface 150 m2/day
Protection works (torch applied) Horizontal/Vertical Surface 80 m2/day

Concrete Blinding Works 75/100 mm thick Blinding works 120 m2/day

Screed Works 40/50 mm thick C/S Screed 200 m2/day


75/100 mm thick screed with welded steel
fabric 120 m2/day

Reinforcement Works
Isolated/ Strap Footing Up to 16 mm dia bars 200 kg
Above 16 mm dia bars 300 kg
Column/Corewall/Staircase 200 kg
Slab with beam/Raft Up to 12 mm 300 kg
16 mm and Above 400 kg

Shuttering
Footing With Ordinary(Ply wood) shutter 8 m2/day
Column/Core Wall/Staircase " m2/day
6
Slab m2/day
" 12

Concrete Pumping Works


Placing with concrete Pump m3/hr
60
Boom Placer 40 m3/hr

Concrete Works
Footings Concrete Placing and Trowel Finishing m3/day
160
Staircase " 60 m3/day

Slab " 150 m3/day

Placing Precast/Hollow Core Slab Placing in line and level 400 m2/day

Block works 10/15/20 cm thick Block works 10 m2/day

Plaster Works 15 mm thick Plaster Works with Acc. 12 m2/day


20 mm thick Plaster Works with Acc. 10 m2/day

Ordinary Painting
Priming Works Including Surface preparation works 150 m2/day
Putty Works 75 m2/day
Painting Works First Coat 250 m2/day
Second Coat 350 m2/day
Epoxy Paint Surface Prep + Priming 50 m2/day
Painting 100 m2/day

Gypsum Partition Works Frame + Gypsum Partition Installation 120 m2/day

False Ceiling Frame + False Ceiling Fixing 30 m2/day

Tile Works On Floor 15 m2/day


On Walls 12 m2/day

Marble/Granite Works on Floor 20 m2/day


Excavator (bucket type)
Rock breaker

1 Skilled, 4 Unskilled, 1 shovel,1 Roller


compactor

1 skilled + 1 unskilled
1 skilled + 1 unskilled
1 skilled + 1 unskilled

1 Mason + 2 Helper

1 Mason + 2 Helper

1 Mason + 2 Helper

1 SF + 1 Helper
1 SF + 1 Helper
1 SF + 1 Helper
1 SF + 1 Helper
1 SF + 1 Helper

1 Carpenter + 1 Helper
1 Carpenter + 1 Helper
1 Carpenter + 1 Helper

1 Mason + 3 helper
1 Mason + 2 helper

2 Mason + 3 Helper

2 Rigger + 1 Mason + 2 Helper

1 mason + 1 Helper

1 Plaster Mason + 1 Helper


1 Plaster Mason + 1 Helper

1 Painter + 1 Helper
1 Painter + 1 Helper
1 painter
1 Painter
1 Painter + 1 Helper
1 Painter + 1 Helper

1 Mason + 1 Helper

1 Mason + 1 Helper

1 Mason + 1 Helper
1 Mason + 1 Helper

2 Mason + 1 Helper