Earth Works
Excavation work in soft soil 120 m3/day
Excavation Work in Hard Soil 50 m3/day
In layer of 150 mm thickness with 95% MDD
Back Filling + Compaction 150 m2/day
value
Concrete Protection Works
Bitumen Priming Works Including surface preparation 200 m2/day
Bitustic works Horizontal/Vertical surface 150 m2/day
Protection works (torch applied) Horizontal/Vertical Surface 80 m2/day
Concrete Blinding Works 75/100 mm thick Blinding works 120 m2/day
Screed Works 40/50 mm thick C/S Screed 200 m2/day
75/100 mm thick screed with welded steel
fabric 120 m2/day
Reinforcement Works
Isolated/ Strap Footing Up to 16 mm dia bars 200 kg
Above 16 mm dia bars 300 kg
Column/Corewall/Staircase 200 kg
Slab with beam/Raft Up to 12 mm 300 kg
16 mm and Above 400 kg
Shuttering
Footing With Ordinary(Ply wood) shutter 8 m2/day
Column/Core Wall/Staircase " m2/day
6
Slab m2/day
" 12
Concrete Pumping Works
Placing with concrete Pump m3/hr
60
Boom Placer 40 m3/hr
Concrete Works
Footings Concrete Placing and Trowel Finishing m3/day
160
Staircase " 60 m3/day
Slab " 150 m3/day
Placing Precast/Hollow Core Slab Placing in line and level 400 m2/day
Block works 10/15/20 cm thick Block works 10 m2/day
Plaster Works 15 mm thick Plaster Works with Acc. 12 m2/day
20 mm thick Plaster Works with Acc. 10 m2/day
Ordinary Painting
Priming Works Including Surface preparation works 150 m2/day
Putty Works 75 m2/day
Painting Works First Coat 250 m2/day
Second Coat 350 m2/day
Epoxy Paint Surface Prep + Priming 50 m2/day
Painting 100 m2/day
Gypsum Partition Works Frame + Gypsum Partition Installation 120 m2/day
False Ceiling Frame + False Ceiling Fixing 30 m2/day
Tile Works On Floor 15 m2/day
On Walls 12 m2/day
Marble/Granite Works on Floor 20 m2/day
Excavator (bucket type)
Rock breaker
1 Skilled, 4 Unskilled, 1 shovel,1 Roller
compactor
1 skilled + 1 unskilled
1 skilled + 1 unskilled
1 skilled + 1 unskilled
1 Mason + 2 Helper
1 Mason + 2 Helper
1 Mason + 2 Helper
1 SF + 1 Helper
1 SF + 1 Helper
1 SF + 1 Helper
1 SF + 1 Helper
1 SF + 1 Helper
1 Carpenter + 1 Helper
1 Carpenter + 1 Helper
1 Carpenter + 1 Helper
1 Mason + 3 helper
1 Mason + 2 helper
2 Mason + 3 Helper
2 Rigger + 1 Mason + 2 Helper
1 mason + 1 Helper
1 Plaster Mason + 1 Helper
1 Plaster Mason + 1 Helper
1 Painter + 1 Helper
1 Painter + 1 Helper
1 painter
1 Painter
1 Painter + 1 Helper
1 Painter + 1 Helper
1 Mason + 1 Helper
1 Mason + 1 Helper
1 Mason + 1 Helper
1 Mason + 1 Helper
2 Mason + 1 Helper