100% found this document useful (1 vote)
301 views2 pages

Quantity Surveying Lesson Plan

The document outlines a lesson plan for a course on Quantity Surveying and Contract Management. It is divided into 5 modules that will be taught between February and April. The modules cover topics like quantity estimation, rate analysis, contract management, specifications, and valuation. Each module lists the dates different topics will be discussed along with space for signatures from staff, the head of department, and the principal to sign off that the lessons have been completed.

Uploaded by

rajaanwar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
301 views2 pages

Quantity Surveying Lesson Plan

The document outlines a lesson plan for a course on Quantity Surveying and Contract Management. It is divided into 5 modules that will be taught between February and April. The modules cover topics like quantity estimation, rate analysis, contract management, specifications, and valuation. Each module lists the dates different topics will be discussed along with space for signatures from staff, the head of department, and the principal to sign off that the lessons have been completed.

Uploaded by

rajaanwar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

LESSON PLANNING

QUANTITY SURVEYING AND CONTRACT MANAGEMENT (15CV81)

SL.NO DATE TOPIC DATE SIGNATURE


SCHEDULED EXECUTED

STAFF HOD PRINCIPAL


MODULE- 1
1 4/2/2019 Quantity Estimation for Building; study of various drawing attached
with estimates, important terms, units of measurements, abstract,
2 5/2/2019 Types of estimates - Approximate, detailed, supplementary and revised
3 6/2/2019 Contd...
4 7/2/2019 Estimation of building - Short wall and long wall method - centre line
method.
5 10/2/2019 Contd...
6 11/2/2019 Contd...
7 12/2/2019 Contd...
8 Estimate of R.C.C structures including Slab, beam, column, footings,
13/2/2019 with bar bending schedule.
9 18/2/2019 Contd...
10 19/2/2019 Contd...

MODULE- 2
11 20/2/2019 Estimate of Steel truss, manhole and septic tanks.
12 21/2/2019 Contd...
13 Quantity Estimation for Roads: Road estimation, earthwork fully in
25/2/2019 banking,
14 26/2/2019 Contd...
15 27/2/2019 Contd...
16 28/2/2019 cutting, partly cutting and partly Filling,
17 4/3/2019 Contd...
18 5/3/2019 Contd...
19 6/3/2019 Detailed estimate and cost analysis for roads
20 7/3/2019 Contd...

MODULE- 3
21 11/3/2019 Specification for Civil Engineering Works:
22 12/3/2019 Objective of writing specifications essentials in specifications,
23 13/3/2019 Contd...
24 general and detail specifications of different items of works in
14/3/2019 buildings,
25 18/3/2019 Contd...
26 Analysis of Rates :Factors Affecting Cost of Civil Works , Concept of
19/3/2019 Direct Cost , Indirect Cost and Project Cost
27 20/3/2019 Contd...
28 Rate analysis and preparation of bills,
21/3/2019
29 Data analysis of rates for various items of Works, Sub-structure
25/3/2019 components,
30 26/3/2019 Rate analysis for R.C.C. slabs, columns and beams.
MODULE- 4
31 27/3/2019 Contract Management-Tender and its Process:
32 Invitation to tender, Prequalification, administrative approval &
28/3/2019 Technical sanction. Bid submission and Evaluation process.
33 1/4/2019 Contd...
34 2/4/2019 Contd...
35 Contract Formulation: covering Award of contract, letter of intent,
3/4/2019 letter of acceptance and notice to proceed.
36 4/4/2019 Contd...
37 Features / elements of standard Tender document (source: PWD /
CPWD / International Competitive Bidding - NHAI / NHEPC / NPC).
8/4/2019 Law of Contract as per Indian Contract act 1872,
38 Types of Contract, Entire contract, Lump sum contract, Item rate,
% rate, Cost plus with Target, Labour, EPC and BOT, Sub
Contracting. Contract Forms : FIDIC contract Forms , CPWD , NHAI
9/4/2019 , NTPC , NHEPC
39 10/4/2019 Contd...
40 Contd...
11/4/2019

MODULE- 5
41 Contract Management-Post award :Basic understanding on
definitions, Performance security, Mobilization and equipment
advances, Secured Advance, Suspension of work, Time limit for
completion, Liquidated damages and bonus, measurement and
15/4/2019 payment,
42 16/4/2019 Contd...
43 17/4/2019 Contd...
44 18/4/2019 Contd...
45 additions and alterations or variations and deviations, breach of
contract, Escalation, settlement of account or final payment,
claims, Delay’s and Compensation, Disputes & its resolution
22/4/2019 mechanism, Contract management and administration
46 23/4/2019 Contd...
47 Valuation: Definitions of terms used in valuation process, Cost,
24/4/2019 Estimate, Value and its relationship, Capitalized value.
48 Concept of supply and demand in respect to properties ( land ,
25/4/2019 building , facilities’), freehold and lease hold ,
49 29/4/2019 Sinking fund, depreciation-methods of estimating depreciation,
Outgoings, Process and methods of valuation : Rent fixation,
valuation for mortgage, valuation of land.
50 30/4/2019 Contd...

Staff HOD Principal

You might also like