Methodology - Form Work (R)
Methodology - Form Work (R)
FORM WORK
Assembly of formwork:
Place the floor forms along the line and connect the same with form clamps/assembly pin
and floor form corners or external/internal corner plates.
Fix the Pipe Whalers with floor forms by using Whaler clamps/C-clip with floor forms.
Fix the soldiers vertically behind the pipe Whaler by using Whaler connectors with
accessories.
Fix the alignment struts and adjust according to the dimension and verticality.
If required provide through tie rods through the holes already provided in floor forms. If
not plug the holes with PVC threaded plugs.
To meet the structural plan dimension (in case of gap between the floor forms) use
lapping plate or Timber/plywood piece.
Dismantling of formwork.
Assembly of formwork
Place the plywood shutters along the line and connect the same with wire nails/bolts and
nuts.
Fix the Pipe Whalers/Timbers horizontally behind shutters as per the drawing.
Fix the soldiers/Whalers vertically behind the pipe Whaler/timbers by using Whaler
connectors with accessories.
Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)
Fix the alignment struts/timbers and adjust according to dimension and verticality.
Dismantling of formwork.
Remove soldiers, Whalers, pipe Whalers, Whaler connectors & pipe Whaler clamps.
Assembly of Formwork:
Place shutter panel and check the edges with plumb, then place other shutter panels
continuously along one side of the wall
Insert the Tie rods (up to other side wall surface) covered by PVC pipe at the (i.e.
Maximum spacing 1.20 m c/c horizontally and vertically 900mm c/c in shutter panels) at
waling positions.
Place the other side shutter panel and check the edges with plumb, then place other
shutter panels continuously.
Extend the tie rods and fix the same with anchor plate & wing nut.
Join the shutter panels together by using joint plate (i.e. for standard panels; for panels of
non-standard size, clamp arrangement with pins to be provided without fail.
Check the straight line of the both shutters with the help of line thread.
Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)
Wherever required fix inside corners and outside fixing arrangements according to the
requirements (for Inner and outside corners).
Wherever necessary fix coil nuts or anchors, water barriers etc.covered with PVC sleeves
at 350 mm from the top of concrete level.
Removal of formwork:
First remove wing nut, anchor plates, and tie rod, in all the panels
Remove shutters (each separately) with the help of crane, Prop (alignment strut) should
be removed only at the time of lifting the panel
In case of shutter being used for subsequent lifts the alignment struts, supporting brackets
need not be removed.
In case of subsequent lifts remove climbing brackets, suspended platforms handrail post,
accessories.
Clean and shift shutter panels (with alignment props/supporting brackets) to next
Lift/length.
Assembly of formwork:
Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)
Mark Cup lock location according to the design parameters, shall be calculated based on
good for construction drawings however we will maintain 1800X900 grid in standard
practice
Place main Cup lock verticals with required horizontals, keep the 50mm thick timber
planks without fail before going for 2 nd level.– I step, fix the 40NB ledgers on both
directions in two levels - II step, Drop head with adjustable base plate – III step.
Place metri forms and adjust the spacing as per the drawing/Specs, design given at a
given intervals.
Place the infill beams in-between metriforms at an interval of 900c/c
Place waffles according to the drawings given.
Place Intermediate supports with supporting heads to support the slab before placing the
concrete as per the given specifications.
Maintain the required level of slabs by adjusting the bottom & top adjustment.
Apply shutter release agent over waffle surface & fix masking tape in joints of waffles
and slab and waffle junctions.
Dismantling of formwork:
Release the waffles by using pressure from the concrete and lower it gently.
Remove metri forms and infill beam with disturbing the supporting locations
Clean and stack the materials for next level.
Shift the materials to next portion.
Use Stacking pallets/bins for loose components.
FOR BEAMS
Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)
Place primary ISMC 100B/b) & secondary layers of Adjustable telescopic spans or Metri
forms and adjust the infill beam/ 50 sqm tube spacing as per the drawing.
Place Intermediate props with supporting heads for ISMC 100 B/B
Maintain the required level of beams by adjusting the props.
Fix the masking tape in joints of plywood/steel forms & apply shutter release agents.
Cut and fix 12 mm plywood with Timber 2X3 or 2X4 for beam sides. Use the timber
section in both the case as 3” or 4” direction to carry the designed loads.
Fix the timber spacers on the top of the beams.
Fix forming support according to the requirements given in designs, normally at an
interval of 1200mm c/c max
If backup strips are required mark the location and provide the plywood strips.
FOR SLABS
Dismantling of formwork:
SLABS
Place the props below the plywood/Steel Forms surface strip touching the strip.
Lower the props using prop nut.
Remove ISMC 100 or timber below slab bottom.
Remove the Plywood/ Steel Forms (beam sides)
Remove four way heads/Supporting heads, without disturbing the intermediate props.
Remove main props, Four way heads and other supports viz. 40 NB ledger Pipes and
Swivel couplers.
Clean and stack the plywood/Steel Forms or ISMC 100 if required for next portion.
Shift the materials to next portion.
BEAMS
Place the props below the plywood/steel forms strip touching the strip.
Lower the props height.
Remove the side shutters after removing the beam support and ISMC 100 from the
beams.
Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)
Form work