Methodology - Form Work (R)

The document provides instructions for assembling and dismantling various types of formwork used in construction projects. It describes how to assemble and dismantle formwork for foundations using steel, plywood or a combination. It also provides details on assembling and dismantling formwork for walls, columns, slabs and beams using materials like shutters, whalers, tie rods and alignment props. The instructions aim to ensure formwork is constructed accurately according to structural plans and dismantled safely for reuse on subsequent projects.

Uploaded by

azhustuddying
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
137 views

Methodology - Form Work (R)

The document provides instructions for assembling and dismantling various types of formwork used in construction projects. It describes how to assemble and dismantle formwork for foundations using steel, plywood or a combination. It also provides details on assembling and dismantling formwork for walls, columns, slabs and beams using materials like shutters, whalers, tie rods and alignment props. The instructions aim to ensure formwork is constructed accurately according to structural plans and dismantled safely for reuse on subsequent projects.

Uploaded by

azhustuddying
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

NCC LIMITED

(Formerly Nagarjuna Construction Company Limited)

FORM WORK

FOUNDATION FORMWORK (ALL STEEL).

1. Mark the Layout of foundation.

2. Lower the formwork materials to the foundation level from NGL.

Assembly of formwork:

 Place the floor forms along the line and connect the same with form clamps/assembly pin
and floor form corners or external/internal corner plates.

 Fix the Pipe Whalers with floor forms by using Whaler clamps/C-clip with floor forms.

 Fix the soldiers vertically behind the pipe Whaler by using Whaler connectors with
accessories.

 Fix the alignment struts and adjust according to the dimension and verticality.

 If required provide through tie rods through the holes already provided in floor forms. If
not plug the holes with PVC threaded plugs.

 To meet the structural plan dimension (in case of gap between the floor forms) use
lapping plate or Timber/plywood piece.

Dismantling of formwork.

 Remove the Tie rods and its accessories alignment struts.


 Remove soldier’s Whaler clamps/C-clips, pipe Whalers.
 Remove the assembly pins, floor form corner and floor forms.
 Clean and shift the formwork materials to next foundation or stack the same in a proper
position

FOUNDATION FORMWORK (WITH PLYWOOD)

1. Mark the layout of foundation.

2. Lower the formwork materials to the foundation level from NGL.

Assembly of formwork

 Place the plywood shutters along the line and connect the same with wire nails/bolts and
nuts.

 Fix the Pipe Whalers/Timbers horizontally behind shutters as per the drawing.

 Fix the soldiers/Whalers vertically behind the pipe Whaler/timbers by using Whaler
connectors with accessories.

Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)

 Fix the alignment struts/timbers and adjust according to dimension and verticality.

Dismantling of formwork.

 First remove the alignment struts.

 Remove soldiers, Whalers, pipe Whalers, Whaler connectors & pipe Whaler clamps.

 Remove the shutters.

 Clean and shift the formwork materials to next foundation.

Wall/Column Formwork (With Crane 1 Lift operations)

1. Starter with timber sides to suit wall dimensions.

2. Remove the forms of starter after the concreting is over.

Assembly of Formwork:

 Place shutter panel and check the edges with plumb, then place other shutter panels
continuously along one side of the wall

 Insert the Tie rods (up to other side wall surface) covered by PVC pipe at the (i.e.
Maximum spacing 1.20 m c/c horizontally and vertically 900mm c/c in shutter panels) at
waling positions.

 Place the other side shutter panel and check the edges with plumb, then place other
shutter panels continuously.

 Extend the tie rods and fix the same with anchor plate & wing nut.

 Place alignment props/supporting bracket with necessary assembly at interval of 1200mm


c/c max and wherever joining are available between panels.

 Join the shutter panels together by using joint plate (i.e. for standard panels; for panels of
non-standard size, clamp arrangement with pins to be provided without fail.

 Fix timber spacers (for maintaining the wall thickness) at


beam/Timber sections locations on the top between the shutter panels.

 Adjust the shutter verticality by using alignment struts/plumb bobs

 Check the straight line of the both shutters with the help of line thread.

 Check the wall thickness at the top.

Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)

 Wherever required fix inside corners and outside fixing arrangements according to the
requirements (for Inner and outside corners).

 Wherever necessary fix coil nuts or anchors, water barriers etc.covered with PVC sleeves
at 350 mm from the top of concrete level.

Removal of formwork:

 First remove wing nut, anchor plates, and tie rod, in all the panels

 Remove Joint plates/waling extn. & connecting pins.

 Remove shutters (each separately) with the help of crane, Prop (alignment strut) should
be removed only at the time of lifting the panel

 In case of shutter being used for subsequent lifts the alignment struts, supporting brackets
need not be removed.

 In case of subsequent lifts remove climbing brackets, suspended platforms handrail post,
accessories.

 Clean and shift shutter panels (with alignment props/supporting brackets) to next
Lift/length.

WALL FORMWORK (without Crane) for I LIFT

 Cast starter with timber sides.


 Remove the forms of starter after the concreting is over.

Assembly of formwork:

 For manual handling panel size shall be restricted to maximum of 1200 mm


 Place Shutter panel and check the edges with plumb, then place other shutter panels
continuously along the one side of the wall.
 Fix steel Whalers with shutter panels using Flange claw assembly at every stage.
 Join the shutter panels together by using std.splice plate (i.e. for standard panels; for
panels of non-standard size with clamp arrangement, with pins.
 Insert the Tie rods (up to other side wall surface) covered by PVC pipe at the required
locations in shutter panels
 Place other side shutter panel and check the edges with plumb, then place other
 Shutter panels continuously.
 Fix steel Whalers with shutter panels using flange claw assembly at every stage.
 Join the shutter panels together by using Std. Splice plate (i.e. for standard panels when
used) for panels of non standard size clamp arrangement and with pins.
 Extend the Tie rods and fix with Anchor plate & wing nut.
 Place alignment props /supporting bracket with Head adaptor assy. & foot adaptor
assembly at every stage.
 Place timber spacers (for wall thickness) on the top between the shutter panels

Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)

 Adjust the shutters to verticality by using alignment props/plumb bobs


 Check the straight line of the both shutters with the help of line thread.
 Place Timber spacers (for wall thickness) on the top between the shutter panels.
 Adjust the shutter verticality by using alignment props/plumb bobs
 Check the straight line of the both shutters with the help of line thread.
 Check the wall thickness at the top. Wherever required fix inside
 Corner and outside fixing according to the requirements (For inner and outside corners
of walls).

SLAB FORMWORK (Slab with Waffle)

Assembly of staging & formwork:

 Mark Cup lock location according to the design parameters, shall be calculated based on
good for construction drawings however we will maintain 1800X900 grid in standard
practice
 Place main Cup lock verticals with required horizontals, keep the 50mm thick timber
planks without fail before going for 2 nd level.– I step, fix the 40NB ledgers on both
directions in two levels - II step, Drop head with adjustable base plate – III step.
 Place metri forms and adjust the spacing as per the drawing/Specs, design given at a
given intervals.
 Place the infill beams in-between metriforms at an interval of 900c/c
 Place waffles according to the drawings given.
 Place Intermediate supports with supporting heads to support the slab before placing the
concrete as per the given specifications.
 Maintain the required level of slabs by adjusting the bottom & top adjustment.
 Apply shutter release agent over waffle surface & fix masking tape in joints of waffles
and slab and waffle junctions.

Dismantling of formwork:

 Lower the drop head assembly by loosening the locking nut.


 Before removing the waffles check the drop head assembly should not be disturbed in
given locations

 Release the waffles by using pressure from the concrete and lower it gently.
 Remove metri forms and infill beam with disturbing the supporting locations
 Clean and stack the materials for next level.
 Shift the materials to next portion.
 Use Stacking pallets/bins for loose components.

SLAB FORMWORK (Slabs & Beams – up to 5.00 m Height)

FOR BEAMS

 Mark Props location.


 Place main Props – I step, Keep the Timber Planks of 50 mm thick below props - II step,
Four way heads/Stirrup heads – III step.

Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)

 Place primary ISMC 100B/b) & secondary layers of Adjustable telescopic spans or Metri
forms and adjust the infill beam/ 50 sqm tube spacing as per the drawing.
 Place Intermediate props with supporting heads for ISMC 100 B/B
 Maintain the required level of beams by adjusting the props.
 Fix the masking tape in joints of plywood/steel forms & apply shutter release agents.
 Cut and fix 12 mm plywood with Timber 2X3 or 2X4 for beam sides. Use the timber
section in both the case as 3” or 4” direction to carry the designed loads.
 Fix the timber spacers on the top of the beams.
 Fix forming support according to the requirements given in designs, normally at an
interval of 1200mm c/c max
 If backup strips are required mark the location and provide the plywood strips.

FOR SLABS

 Mark Props location.


 Place main Props – I step, Keep the timber planks of 50mm thick below props - II step,
Four way heads/Stirrup heads – III step.
 Use four way/stirrup heads over props at the lapping points of primary ISMC 100 b/b.
 Place primary & secondary layers of adjustable spans, metri forms and adjust the spacing
as per the drawing/Specs, design given at an intervals of 750mm c/c
 Place the infill beams in-between Metriforms at an interval of 900c/c
 Place waffles according to the drawings given.
 Place Intermediate props with supporting heads to support the slab before placing the
concrete
 Maintain the required level of slabs by adjusting the props.
 Apply shutter release agent over waffle surface & fix masking tape in joints of waffles
and slab and waffle junctions.
 If backup strips are required mark the location and provide the plywood strips.

Dismantling of formwork:

SLABS

 Place the props below the plywood/Steel Forms surface strip touching the strip.
 Lower the props using prop nut.
 Remove ISMC 100 or timber below slab bottom.
 Remove the Plywood/ Steel Forms (beam sides)
 Remove four way heads/Supporting heads, without disturbing the intermediate props.
 Remove main props, Four way heads and other supports viz. 40 NB ledger Pipes and
Swivel couplers.
 Clean and stack the plywood/Steel Forms or ISMC 100 if required for next portion.
 Shift the materials to next portion.

BEAMS

 Place the props below the plywood/steel forms strip touching the strip.
 Lower the props height.
 Remove the side shutters after removing the beam support and ISMC 100 from the
beams.

Form work
NCC LIMITED
(Formerly Nagarjuna Construction Company Limited)

 Remove ISMC 100 beams below beam bottom.


 Remove Plywood or steel forms from slab.
 Remove four way heads/supporting heads without disturbing the Intermediate props.
 Remove main props, four way heads or stirrup heads.