Sshinemaster User Manual: Shenzhen Growatt New Energy Technology Co.,Ltd
Sshinemaster User Manual: Shenzhen Growatt New Energy Technology Co.,Ltd
,LTD
No.28 Guangming Road, Shiyan Street, Bao’an District,
Shenzhen, P.R.China
T
F
+ 86 755 2747 1942
+ 86 755 2747 2131
S hineMaster User Manual
E [email protected]
W www.ginverter.com
CONTENT
2 Product description
2.1 Device Overview
2.2 Unpacking
2.3 ShineMaster Network
Introduction
3 Installation and
Connection
3.1 ShineMaster installation
environment
3.2 ShineMaster installation method
3.3 Connect to the photovoltaic device
1
2 Product description
F
A POWER Power supply port
C Table 2-1
A
B
Fig.2-1
ShineMaster is equipped with seven LED indicators. The status of the ShineMaster can be
2.1.1 Interface
displayed by the LED indicator. As shown in figure 2-1 and table 2-2 above.
2 3
A B C
Item Name Function
Network light:
1: off means fail to obtain IP address;
H Network LED
2: flashing means connecting to the server ;
3:on means connection to the server successfully
Fig 2-2
L WiFi WiFi signal indicator(temporarily unavailable)
A ShineMaster 1 pcs
table 2-2
B 5V power adapter 1 pcs
Table 2-4
4 5
2 .2.2 Serial No. and Check Code
The ShineMaster serial No. (S/N) and check code(C/C)is ticked on the ShineMaster’s
package box, which have 10 digits mixed up with letters and numbers. the serial No. and
check code for each device are unique, to identify each ShineMaster. When you want to
upload the data of ShineMaster to the server, you need the serial No. and ‘check code’
corresponding to register on the server
ShineMaster monitors the photovoltaic devices through RS485 and RF(temporarily not
supported). The diagram below shows the schematic diagram of network monitoring
through wired RS485.
Note: The precondition of local access is that the address of PC and ShineMaster must be
in the same domain, thereby building up a local monitoring system.
Fig 2-5
6 7
3 Installation and Connection
The installation steps are as follows:
(1) Install ShineMaster on a vertical plane or horizontal plane.
(2) Connect cables between RS485 interface and RS485 interface on ShineMaster (please
refer to 3.3.1 below for details)
(3) Connect the network cable (insert the network line into the LAN interface on
ShineMaster).
(4) Connect the Power supply (connect the power cord to the Power interface on
3.1 ShineMaster installation
ShineMaster).
The installation environment of ShineMaster and communication with other devices: 3.3 Connect to the photovoltaic device
(1) Indoor installation, temperature - 40 ~ 60℃ , avoid moisture and direct sunlight.
(2) Cable RS485 in maximum 500m.
ShineMaster can communicate with the inverter, weather station, smart meter, combiner
box and other photovoltaic devices to achieve the purpose of data collection.
3.2.1 Installation Procedure 1.ShineMaster (master) communicates with slave devices via RS485 wired connection.
485A+ on the RS485 port of the slave device corresponds to A1+ or A2+ on the
ShineMaster 485 port, 485B- and ShineMaster 485 on the RS485 port of the slave device.
Corresponding to B1- or B2-. The following is a schematic diagram of the connection
between the ShineMaster and the inverter:
Note: the RS485 shielded wire must be ground (PE) for long distance communication, so
as not to affect the communication stability.
8 9
2. Note that the inverter also has an interface like the one below: 2. Go to the router's management page and check the "Internet host list" to query the IP
address of the ShineMaster IP address with the serial number of the ShineMaster as the
device name. This IP address is the IP address assigned by the router to the ShineMaster. If
you do not know how to do this, contact your network administrator to perform the
operation.
Note: The router needs to enable automatic IP assignment, that is, open the DHCP
function
3. Enter the ShineMaster IP address in the browser to enter the ShineMaster internal page
Fig 4-1
1. Connect the PC computer and the ShineMaster LAN port to the network port of the
router through the network cable so that they are in the same LAN. 2.Enter the user name and password, the default login user name: admin password:
admin, fill in and click on login to enter the Growatt ShineMaster system page.
10 11
4 .3 ShineMaster Status View 4.4.1 Add device
Click the ShineMaster datalogger Status to view information such as the “System Status (1) Before ShineMaster monitors photovoltaic equipment, it is necessary to enter the
Information”, “Serial Number”, “Server Address”, “Number of Connected Devices”, “ShineMaster Data Collector Settings” page of the built-in page to add devices.
etc. of the ShineMaster
(2) In the second drop-down list, select the type of monitored device
4.4 ShineMaster Datalogger managing
Device types parameter information :
INVERTER : GROWATT Inverter;
Devices should be added in ‘ShineMaster datalogger setting’ interface in internal page
SDM120 : single phase meter;
prior to monitoring
SDM630 : three phase meter;
BatterBox : battery Box;
Surveymeter : Survey Meter.
12 13
(4) Select "Add" and click Save.
(5) After successfully saving, enter the "Device Status" page to confirm whether the
device is added successfully.
(3) In the third drop-down list, fill in the communication address of monitored device 4 .4.2 Remove device
(1) Select the monitoring method for monitoring PV devices in the first drop-down list of
"Add or Remove Devices".
(2) In the second drop-down list, select the type of PV plant being monitored.
(3) Fill in the PV device communication address in the third drop-down list.
(4) Select "Del" and click Save to finish removing of the device.
(5) After successfully saving, enter the "Device Status" page to confirm whether the
device is successfully deleted.
As shown in the picture:
14 15
Add and delete device: (1) ShineMaster’s Default setting of the DHCP function is “ON” it will automatically get IP
1. When you need delete a device, all the options should be the same with the momemet address.ShineMaster
you add this device like: 485 channel, device type, address, if you are not sure about this
you can check the device status first.
2. When one address is occupied, you cannot just paste the new device, you have to delete
the old device and use this address.
16 17
5 Server: Shineserver’s operation
If needed to the datalogger and all monitoring devices for data display, monitoring, and
set up parameters by the server, you need to first add datalogger to the server, when
Shinemaster added to the server, if the subsequent need to modify some parameters of
The datalogger or enable, disable a function can be done through the server.
(1) Enter the address of the server on the computer browser to enter the ShineServer
login page. If you are logging in for the first time, register the user name first. Enter the
domain name access page, as shown in Figure 5-1.
Server port name and data upgrade interval are fixed cannot be changed
Caustion:
1)If you add a device, after saving there is no refreshment, please disconnect the data
logger and restart it.
18 19
Figure 5-1 Shine Server login page Fig 5-2
20 21
5.3.1 Add or Delete Monitoring device
(1) In the Server page click the “Device Management” and then click “Data Logger”.
In this page click set the device updating icon.
(2) Add one device, add one Growatt inverter set the 485 communication address is 1.
Fig 5-3
(2) Click "plant" → "Device list" to see real-time data monitored by datalogger,
"Inverter", "Weather station", "Smart Meter", and "Combined Box" "MAX" .
22 23
(3) Delete one device, just like following figure. (1) In the Server page click “Device Management” then click “Data Logger”, click the
Baud rate setting icon.
(4) Above adding or deleting devices if success following figure will pop out.
Note: The second channel of Baud rate setting would be the same as the fist channel.
24 25
6 Device Maintenance
6.3 Maintenance
6.1 Reset ShineMaster 1. Avoid frequent switching of power supply, gently handle, to prevent damage;
2. ShineMaster is a product for indoor use. Do not place ShineMaster in a humid
If you press the “reset” button for five seconds, it will erase all the registered device
environment or in direct sunlight.
information. All the information for the server communication part will be kept.
26 27
Communication
8 Contact us
Growatt New Energy provides customers with a full range of technical support. Users can
contact the nearest Growatt new energy office or customer service point, or they can
contact the company's customer service center directly.
Address: No.28 Guangming Road, Shiyan Street, Bao’an District, Shenzhen, P.R.China
E-mail:[email protected]
28