Manual PH JKR Road Sector - Version 3.0 PDF
Manual PH JKR Road Sector - Version 3.0 PDF
MANUAL
Road Sector - RS
Version 3.0
JKR 20801‐0022‐18
CONTENTS
FOREWORD
ACKNOWLEDGEMENTS
JKR 20801‐0022‐18 2
FOREWORD
The initiative to provide a sustainable development rating scheme for the use of government projects
was developed in order to integrate initiatives made separately by different branches in PWD. The scheme
serves as a tool for integrating all the initiatives that has been taken, measured and used as a benchmark
in developments implemented by PWD. This will make the initiatives to be more comprehensive and
impactful.
Version 1.0 of the Penarafan Hijau JKR (pH JKR) Manual for New Federal Roads category was produced
in 2012. However, the usage of this manual was not very rampant as not many projects was deemed
suitable. In the year 2013, version 1.0 of pH JKR manual for Upgrading of Roads category, was
consequently produced. However, this manual was also minimally used due to the unsuitability of the
criteria allocated.
Realising this problem, the pH JKR Committee decided to revisit both manuals and make it more
practical and user friendly. In order to achieve this, more designers, project managers and implementers
were engaged in the development of this pH JKR Manual Version 2.0. In this version, criteria for new and
upgrading of roads were combined and simplified.
In order to make this manual more practical with current trends, the pH JKR Committee again revise this
manual to pH JKR Version 3.0 – Road Sectors with involvements of previous and new committee from
various disciplines, in order to develop and improve this manual & its scorecard.
There is much hope that this effort will enable more users of pH JKR to benefit from its outcomes.
JKR 20801‐0022‐18 3
ACKNOWLEDGEMENTS
Version 3.0 of the Penarafan Hijau JKR (JKR pH) Road Sector manual is an addition and improvement to the
version 2.0. The production of this version was made possible by the efforts of these PWD staff:
JKR 20801‐0022‐18 4
1.0 INTRODUCTION
pH JKR is a tool that can be used by government projects to measure the sustainability of a development. It
was built based on the operation of the existing government development and also the requirements set by
government projects. Therefore, this scheme is friendlier to government developments.
2.0 OBJECTIVES
pH JKR objectives are:
i. To gauge sustainability level achieved by government development projects;
ii. To facilitate improvements to be made from time to time;
iii. To encourage projects to be developed and operated sustainably
3.0 BENEFITS
4.0 METHODS
Stage 1 ~ Application & Registration (refer to the work process P1)
Stage 2 ~ Assessment of Design (see the working process P2)
Stage 3 ~ Verification of Scoring (see the working process P3)
JKR 20801‐0022‐18 5
STAGE 1 - APPLICATION AND REGISTRATION
Start
No
Application Secretariat Check if registration form is
Additional
form Information complete.
complete?
Yes
Continue
next Stage
1. Registration can be made by submitting an application form JKR/pH JKR/BRG02 (Appendix A) to the
Secretariat. This form can be downloaded via the official JKR website www.jkr.gov.my. Applicants are
required to provide relevant documents (projects brief, site inventory, etc.) to assist in determining the
suitability of the project for certification.
2. Project team needs to make sure project is suitable for certification and registration form is
completed before submitting to the Secretariat.
JKR 20801‐0022‐18 6
STAGE 2 – DESIGN ASSESSMENT
Start
Yes
No
Checklist Additional
Secretariat Check the completeness of
complete? Information
documents according to the
checklist.
Yes
Confirmation of
application Secretariat Record the application for
Design Assessment Session.
Continue
next Stage
JKR 20801‐0022‐18 7
Design Assessment Flow
Start
No
Final result and Design Secretariat Issue final result and Design
Assessment Assessment Certification (if
Certification issued applicable) to project team
Continue
next Stage
JKR 20801‐0022‐18 8
STAGE 3 –VERIFICATION OF SCORING
Start
Yes
Yes
Continue
next Stage
JKR 20801‐0022‐18 9
Verification Assessment Flow
Start
No
Verification
session
End
JKR 20801‐0022‐18 10
ROLES & RESPONSIBILITIES
ASSESSOR pH
SECRETARIAT
ROLES
FACILITATOR
NO.
pH JKR
HODT
HOPT
RESPONSIBILITIES
JKR
Application for pH JKR registration
1.
using form JKR / JKR pH / BRG02
Check the registration application
2.
form JKR / JKR pH / BRG02
3. Coordination of pre-assessment session
Application for design evaluation using
4.
form JKR/pH JKR/BRG02.1
Complete scorecard and prepare
5. documents for design evaluation &
verification assessment
Design evaluation & verification
6.
assessment
Compilation and notification of
7.
assessment result
Application for verification assessment
8. using form JKR/pH JKR/BRG03.1
Issue final assessment result and
9.
Certification
ACRONYM
ASSESSOR : Appointed JKR officers from various discipline to evaluate the design &
verification assessment stage
JKR 20801‐0022‐18 11
5.0 PROJECT SELECTION CRITERIA
Projects fulfilling any of these criteria are subjected to pH JKR rating scheme.
Project cost ≥ RM 50 million
Federal Road
Site located within the Environmentally Sensitive Areas (ESA) and/or project is subjected to EIA.
PT ~ Pavement Technologies
The latest technology in design and construction of roads which can increase the sustainability of a road
should be adopted.
CA ~ Construction Activities
Quality of roads can be improved by the use of ISO 9001 for the duration of ongoing development. User safety
level also needs to be improved during road maintenance or upgrading.
IN ~ Innovation
Initiatives and innovative designs that are in line with the government's mission is encourage
JKR 20801‐0022‐18 12
7.0 RATING SYSTEM
7.1 ASSESSMENT STAGE
The assessment for certification is divided into 2 stages, which is design & construction.
DESIGN ASSESSMENT
MAXIMUM POINTS
NO MARKING CRITERIA UPGRADING
NEW ROAD
ROAD
1 SM Sustainable Site Planning & Management 16 18
2 PT Pavement Technologies 12 12
3 EW Environment & Water 4 4
4 AE Access & Equity 3 3
5 CA Construction Activities 19 19
6 MR Material & Resources 11 12
TOTAL POINTS (CORE) 65 68
7 EC Elective Criteria 27
8 IN Innovation 5
TOTAL POINTS (ELECTIVE + INNOVATION) 15* 15*
TOTAL POINTS (CORE + ELECTIVE + INNOVATION) 80 83
VERIFICATION ASSESSMENT
MAXIMUM POINTS
NO MARKING CRITERIA UPGRADING
NEW ROAD
ROAD
1 SM Sustainable Site Planning & Management 16 18
2 PT Pavement Technologies 12 12
3 EW Environment & Water 5 5
4 AE Access & Equity 5 5
5 CA Construction Activities 22 22
6 MR Material & Resources 11 12
TOTAL POINTS (CORE) 71 74
7 EC Elective Criteria 27
8 IN Innovation 5
TOTAL POINTS (ELECTIVE + INNOVATION) 15* 15*
TOTAL POINTS (CORE + ELECTIVE + INNOVATION) 86 89
JKR 20801‐0022‐18 13
8.0 MANUAL GUIDE
The Penarafan Hijau (pH JKR) manual shall serve as a guidance to help project teams to understand the
fundamental aims and requirements of each criteria as well as the benefits of its implementation in the local
environment.
Sub-criteria
Sub-criteria code
Maximum marks
for new roads
To quantify project scoring for certification, project team are required to submit the scorecard (Appendix C)
for assessment. The scorecard consists of criteria & sub criteria which have different points.
JKR 20801‐0022‐18 14
9.0 CLASSIFICATION RATING
40 ‐ 49 Potential Recognition
70 ‐ 84 National Excellence
JKR 20801‐0022‐18 15
11.0 NORMATIVE
11.1 LIST OF RESPONSIBLE PARTIES
Each of the points applied should be confirmed by the relevant experts before points are accounted (refer to
scorecard in Appendix C)
ABB. BRANCHES
CJ Cawangan Jalan
There are a number of terms abbreviated to facilitate the assessment of this document. This is also
based on the habits of industry.
CBA – Cost–benefit analysis. A systematic process for calculating and comparing benefits and costs of a
decision, policy (with particular regard to government policy) or (in general) project.
VE– Value Engineering, a systematic method to improve the "value" of goods or products and services by
using an examination of function
EIA‐ Environmental impact statement, a process of evaluating the likely environmental impacts of a
proposed project or development, taking into account inter‐related socio‐economic, cultural and human‐
health impacts, both beneficial and adverse.
RSA‐ Road Safety Audit, the formal safety performance examination of an existing or future road or
intersection by an independent, multidisciplinary team. It qualitatively estimates and reports on potential
road safety issues and identifies opportunities for improvements in safety for all road users.
TMP – Traffic Management Plan, a site-specific plan that covers the design, implementation,
maintenance and removal of temporary traffic management (TTM) measures while work or activity
is carried out in the road corridor (road, footpath or berm).
JKR 20801‐0022‐18 16
SUSTAINABLE SITE PLANNING & MANAGEMENT
JKR 20801‐0022‐18 17
REQUIREMENTS FOR ROAD WORKS DESIGN
SM 1
OBJECTIVES
To study and review requirements for upgrading an existing road or Design / Verification
DOCUMENTATION
JKR 20801‐0022‐18 18
viii. Site Investigation Data/ Report
ix. Survey Data/ Drawing
x. Forensic Report
JKR 20801‐0022‐18 19
REFERENCES
JKR 20801‐0022‐18 20
ROAD ALIGNMENT
SM 2
OBJECTIVES
Design / Verification
DOCUMENTATION
i. Drawings
ii. Penilaian Awal Tapak (PAT) report
iii. Mitigation Plan report
i. As-built Drawing
JKR 20801‐0022‐18 21
APPROACHES & STRATEGIES
REFERENCES
JKR 20801‐0022‐18 22
EXAMPLE
Standard Typical Cross‐Section, Plan & Longitudinal
JKR 20801‐0022‐18
23
Figure 1: Typical cross‐section
JKR 20801‐0022‐18
24
Figure 2: Plan & Longitudinal Profile
SITE VEGETATION
OBJECTIVES SM 3
To study and review requirements for upgrading an existing road or Design / Verification
construction of new roads. The outcomes will be used to determine the
viability of the project. N3 U3
CREDIT REQUIREMENT
BENEFITS
NEW ROAD & UPGRADING ROAD
DOCUMENTATION
i. As‐built drawing
JKR 20801‐0022‐18 25
APPROACHES & STRATEGIES
i. Use JKR guidelines and specification. Arahan Teknik Jalan 16/03 Pindaan
2015
ii. In the absence of existing guidance, it may be necessary to have an
expert develop an entirely new site‐specific vegetation plan.
iii. Long term maintenance plan and goals must be established for the
plant community.
REFERENCES
JKR 20801‐0022‐18 26
EXAMPLE :
JKR 20801‐0022‐18 27
Figure 5: Hydro-seeding (refer Garis Panduan Bio Engineering, Cerun JKR)
POTENTIAL ISSUES
i. Site planting without proper integration with other road activities (e.g. maintenance,
roadside safety).
ii. Not considering the suitability of a plant species specific for site condition salt tolerance and
soil pH, pest susceptibility and maintenance requirement. The roadway environment might
be significantly different from surrounding area, and may not necessarily support its
indigenous plant species.
iii. Site vegetation must be considered in the context of soils, compaction, slopes and
hydrology in order to be successful on road projects.
iv. Disturbed soil condition must be modified to create condition that will sustain native plant
growth. Planting beds should be prepared based on disturbed condition and specified in
project documents.
v. There are few current studies on the vegetation of less maintenance that designer
shall refer before choosing the appropriate vegetation.
vi. Hydro seeding with Bio-degradable Erosion Control Blanket (BECB) on slope is relatively
cost effective reducing soil erosion loses by 85% or greater, less labour and fast installation.
JKR 20801‐0022‐18 28
NOISE MITIGATION PLAN
OBJECTIVES
SM 4
Reduce or eliminate annoyance or disturbance to surrounding neighborhoods Design / Verification
N2 U2
and environments from road construction noise during construction.
CREDIT REQUIREMENT
BENEFITS
2 Points: Supply and install noise barrier including maintenance during the
construction and defects liability period for urban area/ residential
area.
OR
2 Points: to ensure that all site equipment is using low decibel to control noise
pollution.
OR
Limiting Sound Level (LAreq) From Road Traffic (For Proposed New Roads and/
or redevelopment of existing Roads)
Receiving Land Use Category Day Time Night time
7am – 10 pm 10pm‐7am
Noise sensitive Areas 55 dBA 50 dBA
Low Density Residential Areas
Suburban Residential 60 dBA 55 dBA
(Medium Density)
Urban Residential 65 dBA 60 dBA
(High Density)
Commercial, Business 70 dBA 60 dBA
Industrial 75 dBA 65 dBA
JKR 20801‐0022‐18 29
DOCUMENTATION
JKR 20801‐0022‐18 30
POTENTIAL ISSUES
i. Without adequate prior testing on the surface course mix design, there
is some risk that the constructed surface course will not meet the
required limit noise level.
ii. Life‐cycle costing of the road surface using quiet pavement should be
considered.
iii. Method to measure sound level during construction.
REFERENCES
JKR 20801‐0022‐18 31
SM 5 - EC
SERVICES FOR DISABLED USERS
Design / Verification
(ELECTIVE CRITERIA)
OBJECTIVES N3 U3
Providing dedicated facilities for disabled users. BENEFITS
CREDIT REQUIREMENT
1 Point : Crossing for disabled users with noise making devices installed.
1 Point : Walkway access for disabled users by providing sidewalks sloped
for easy access.
1 Point : Tactile on the pedestrian pathway and access for disabled users.
DOCUMENTATION
EXAMPLE :
i. Ramp for disabled users at zebra crossing
ii. Tactile in pedestrian walk
JKR 20801‐0022‐18 32
POTENTIAL ISSUES
REFERENCES
JKR 20801‐0022‐18 33
Figure 7: Tactile on pedestrian walkway
JKR 20801‐0022‐18 34
NOISE CONTROL
(ELECTIVE CRITERIA) SM 6 - EC
OBJECTIVES
Design / Verification
AFTER CONSTRUCTION
OR
OR
Limiting Sound Level (LAreq) From Road Traffic (For Proposed New Roads And/
Or Redevelopment of Existing Roads)
JKR 20801‐0022‐18 35
Source: Schedule 4 from The Planning Guidelines for Environmental Noise Limits
and Control (Jabatan Alam Sekitar, NRE)
DOCUMENTATION
i. Related drawing
i. As build drawing
ii. Sound Testing report
EXAMPLE :
i. Porous Asphalt
ii. Concrete Pavement
iii. Open‐Graded Friction Course
Noise barrier is an exterior structure designed to protect sensitive land area from
noise pollution. Noise barrier shall be provided in sensitive areas such as housing
situated beside busy roads or highways, schools and hospitals.
The type of noise barrier used shall be either absorptive, reflective, dispersive or
mixed depending upon the noise level survey conducted and recommendations
made by noise barrier experts.
JKR 20801‐0022‐18 36
POTENTIAL ISSUES
i. Without adequate prior testing on the surface course mix design, there
is some risk that the constructed surface course will not meet the
required limit noise level
ii. Life‐cycle costing of the road surface using quiet pavement should be
considered
iii. Site constraint
iv. Cost effectiveness
REFERENCES
JKR 20801‐0022‐18 37
PAVEMENT TECHNOLOGIES
JKR 20801‐0022‐18 38
PT 1
EXISTING PAVEMENT EVALUATION
OBJECTIVES
To determine the strength and residual life of the existing pavement structure Design / Verification
as a basis for rehabilitation design
N3 U3
CREDIT REQUIREMENT BENEFITS
Carry out the following test and integrated data analysis to identify the
current functional and structural existing road condition.
DOCUMENTATION
JKR 20801‐0022‐18 39
capacity of the pavement as measured by deflection, layer thickness,
and material properties.
iii. At the network level, routine evaluations can be used to develop
performance models and prioritize maintenance or rehabilitation efforts
and funding. At the project level, evaluations are more focused on
establishing the root causes of existing distress in order to determine the
best rehabilitation strategies.
iv. Pavement evaluation report should include the following test categories
or other relevant evaluations:
a) Surface condition survey
b) Non‐destructive testing
o Deflection test
o Surface Regularity Test
c) Destructive Testing
o Dynamic Cone Penetrometer (DCP)
o Trial Pit & Laboratory Test
Ideally, for any given section of roads, two or more evaluators would arrive at the
same assessment of the section’s current condition. However, there are still
many aspects of pavement evaluation that are highly subjective. For example,
in visual condition surveys, the percent of surface area affected by cracking is
highly dependent upon the visual acuity of the evaluator.
JKR 20801‐0022‐18 40
Destructive Testing
Destructive testing provides more detailed data about the pavement not
possible to obtain through non‐destructive testing. Such detailed data include
laboratory mechanical, physical, and chemical properties and visual inspection
of pavement layers through that obtained through coring or trial pit.
Design Elements
The selection of pavement rehabilitation method should refer to the Pavement
Evaluation report. The rehabilitation method should be determined using an
established pavement rehabilitation system or it can be designed manually. e.g.
Elmod, Rubicon, Circly.
JKR 20801‐0022‐18 41
Figure 10: Coring
REFERENCES
i. ATJ 5/85 (Rev 2013): Manual for the Structural Design of Flexible
Pavement
ii. A Guide to the Visual Assessment of Flexible Surface Conditions JKR
20709‐2060‐92
iii. Interim Guide to Evaluation and Rehabilitation of Flexible Road
Pavement JKR 20709‐0315‐94
JKR 20801‐0022‐18 42
PERMEABLE PAVEMENT
OBJECTIVES
PT 2
Improve flow control and quality of stormwater runoff through use of Design / Verification
permeable pavement.
CREDIT REQUIREMENT
N3 U3
BENEFITS
1 Point : Use of permeable (porous) pavement mix design with higher range
of air void (18 ‐25%)
1 Point : Pavement crossfall 2.5% and min unpaved shoulder to drain gradient
0.7%-4%
DOCUMENTATION
JKR 20801‐0022‐18 43
APPROACHES & STRATEGIES
Following some of the key design and maintenance elements will promote
maximum performance of permeable pavements:
i. Design Elements
ii. Maintenance Repairs
Design Elements
i. Use mix design for the pavement with significant permeability
2
10 liter/minute for 54cm area, 50mm thickness.
ii. Use open graded wearing course with range of air void (18 ‐25%)
iii. Permeable should be laid on impermeable and relatively even
bituminous surface with adequate cross fall (minimum 2.5%)
iv. Existing cracks and depression shall be sealed and patched prior
to application of porous asphalt.
v. Only used static steel wheel tandem roller to compact porous
asphalt pavement layer.
vi. Attempt to make periodic maintenance easy for owners in the
design process. Pavement areas should be accessible and slope
gradually to accommodate standard maintenance vehicles.
EXAMPLE :
i. Porous Asphalt
ii. Open graded aggregate
iii. Stone mastic asphalt
POTENTIAL ISSUES
JKR 20801‐0022‐18 44
REFERENCES
JKR 20801‐0022‐18 45
PAVEMENT PERFORMANCE TRACKING
OBJECTIVES
PT 3
Allow for more thorough performance tracking by integrating construction Design / Verification
N2 U2
quality and pavement performance data.
CREDIT REQUIREMENT
BENEFITS
2 Points : Use a process that allows construction quality measurements and
long‐ term pavement performance measurements to be spatially
located and correlated to one another. This implies four
requirements
i. Construction quality measurements must be spatially located such
that the location of the quality measurement is known
ii. Pavement condition measurements must be taken at least every
3 years and must be spatially located to a specific portion of roadway
or location within roadway
iii. An operational system, computer based or otherwise that is
capable of storing construction quality measurements, pavement
condition measurement and their spatial locations.
iv. The designated system must be demonstrated in operation, be
capable of updates and have written plans for its maintenance in
perpetuity.
Details
JKR 20801‐0022‐18 46
Examples of pavement condition measurement include, but not limited to the
extent and severity of:
i. Cracking
ii. Permanent deformation (rutting)
iii. Bleeding
iv. Faulting
v. Joint Spalling
vi. Pavement strength
DOCUMENTATION
EXAMPLE :
JKR 20801‐0022‐18 47
POTENTIAL ISSUE
i. The general trend in road construction is to dispose of construction
records after a prescribed amount of time set by legal obligations.
ii. It is difficult to define the concepts of performance and quality in
simple terms.
iii. It is difficult to trace pavement performance issues back to construction
quality due to lack of integration between construction quality control
data with long‐term pavement performance data.
REFERENCES
ii. ATJ 5/85 (Pindaan 2013) Manual for the Structural Design of Flexible
Pavement
JKR 20801‐0022‐18 48
PT 4
LONG‐LIFE PAVEMENT
OBJECTIVES Design / Verification
1 Point : Meet the requirements of Arahan Teknik Jalan 5/85 (Pindaan 2013),
for the structural design of flexible pavement.
1 Point : Pavement design is in accordance with a design procedure that is
formally recognized, adopted and documented by the agency.
1 Point : Drainability surface runoff by providing scupper drain with hinge
grating or equivalent to ensure no debris blockage and
maintainability.
2 Points : Rigid Pavement > 40 years design life
OR
OR
DOCUMENTATION
JKR 20801‐0022‐18 49
B. Verification Scoring Stage
i. As‐built drawings
ii. Inspection Testing Plan
iii. Project Quality Plan (PQP)
EXAMPLE :
i. Hot Mix Asphalt (HMA Pavements)
ii. Cold In-Place Recycling Method
iii. Rigid Pavements
JKR 20801‐0022‐18 50
Figure 13: (HMA Pavement)
REFERENCES
JKR 20801‐0022‐18 51
ENVIRONMENT & WATER
JKR 20801‐0022‐18 52
ENVIRONMENTAL MANAGEMENT SYSTEM EW 1
(EMS)
OBJECTIVES Design
CREDIT REQUIREMENT
N3 U3
2 Points : Provision of EPW in contract
3 Points : MS ISO 14001: 2015 certification for the main contractor
BENEFITS
DOCUMENTATION
i. Submit copy of the valid MS ISO 14001: 2015 certification from the
main contractor.
JKR 20801‐0022‐18 53
POTENTIAL ISSUES
i. Smaller firms may not be able to afford the ISO certification process.
ii. Documentations of an EMS are not the same as having an effective
EMS, however collection of documentations is an efficient way of
gathering evidence of an effective EMS.
REFERENCES
JKR 20801‐0022‐18 54
STORMWATER MANAGEMENT
EW 2
OBJECTIVES
Design / Verification
To have best management practices for stormwater design & construction
stage of road project N2 U2
CREDIT REQUIREMENT BENEFITS
1 Point: Develop a stormwater management plan for the site using stormwater
Best Management Practices (BMP) for water quality control in
conformance to the Manual Saliran Mesra Alam (MSMA) / MSMA 2nd
Edition and MS ISO 14001: 2015. Demonstrate that the planned BMPs
to conform to all applicable 5% above minimum water quality
standards set by MSMA / MSMA 2nd Edition and MS ISO 14001: 2015.
DOCUMENTATION
JKR 20801‐0022‐18 55
APPROACHES & STRATEGIES
i. Refer Manual Saliran Mesra Alam (MSMA) and MSMA 2nd Edition
ii. Preserve native vegetation.
iii. Protect soil with good infiltration capacity.
iv. Assess the feasibility of infiltration and evapotranspiration to reduce
the needs for retention pond outside the right of way.
v. Convey stormwater in swales to promote infiltration.
vi. Consider geometric design for erosion control and flow moderation.
POTENTIAL ISSUES
EXAMPLE :
JKR 20801‐0022‐18 56
Figure 15: Silt Curtain
JKR 20801‐0022‐18 57
Figure 17: Check dam
JKR 20801‐0022‐18 58
Figure 19: Silt fence
JKR 20801‐0022‐18 59
Figure 21: Drive through wash trough
REFERENCES
JKR 20801‐0022‐18 60
ECOLOGICAL CONNECTIVITY
(ELECTIVE CRITERIA) EW3 - EC
OBJECTIVES
Design / Verification
OR
DOCUMENTATION
JKR 20801‐0022‐18 61
APPROACHES & STRATEGIES
POTENTIAL ISSUES
EXAMPLE :
CCTV
Trackpads
Camera traps
JKR 20801‐0022‐18 62
Figure 23: Animal Viaduct
REFERENCES
JKR 20801‐0022‐18 63
ACCESS & EQUITY
AE
JKR 20801‐0022‐18 64
SAFETY AUDIT
OBJECTIVES
AE 1
Improve road safety through review by an accredited Road Safety Auditor Design
registered with JKR.
N3 U3
CREDIT REQUIREMENT Verification
N5 U5
3 Point : Road Safety Audit Stage (During Design Stage)
3 Point : Road Safety Audit Stage 4 (Construction Stage)
1 Point : Additional Audit For Traffic Management Safety Report During BENEFITS
Construction
1 Point : Road Safety Audit Stage 5 (Operational Stage)
DOCUMENTATION
i. Submit a copy of the Road Safety Audit (RSA) Report and Contractor’s
Response report for Stage 4 to Stage 5
ii. Submit additional Audit Report for Traffic Management during
construction
JKR 20801‐0022‐18 65
APPROACHES & STRATEGIES
Follow decision agreed upon RSA Meeting and incorporate in the design.
POTENTIAL ISSUES
REFERENCES
i. Road Safety Audit : Guidelines For The Safety Audit of Roads And Road
Project In Malaysia
ii. Nota Teknik (Jalan) 25/07 : Guidelines On The Contents Of A Road Safety
Audit Report
iii. Interim Guide on Identifying, Prioritising and Treating Hazardous Locations
on Roads In Malaysia
iv. Arahan Teknik (J) 8/86 (Pindaan 2015) : A Guide On Geometric Design Of
Roads
v. Manual Fasiliti Keselamatan Jalan 2014
JKR 20801‐0022‐18 66
SCENIC VIEWS
OBJECTIVES
AE 2 - EC
Feature scenic, natural and recreational qualities into roadways Design / Verification
CREDIT REQUIREMENT N2 U2
2 Points : Provide designated parking area for road user to stop and BENEFITS
experience the scenic views at strategic location.
DOCUMENTATION
Provide locations, such as lookout point or pullouts, where road user can stop
to enjoy a scenic, historic, cultural, natural, recreational or archaeological
feature of the roadway area.
POTENTIAL ISSUES
Provision of access and parking area to the lookout point often not taken into
consideration due to area and budgetary constraint.
REFERENCES
JKR 20801‐0022‐18 67
PEDESTRIAN ACCESS
(ELECTIVE CRITERIA) AE 3 - EC
OBJECTIVES
Design / Verification
N5 U5
Promote walkable communities by providing pedestrian safe and friendly
roads.
DOCUMENTATION
i. As‐built drawings
i. Consider how a new road will impact the existing or planned pedestrian
networks and integrate design elements with other facilities to
mitigate overall impacts. This may mean providing connection or
adaptability for future pathway, sidewalks and crossing within
pedestrian networks.
ii. Design the road to accommodate existing new and planned pedestrian
facilities.
JKR 20801‐0022‐18 68
EXAMPLE :
REFERENCES
JKR 20801‐0022‐18 69
MOTORCYLE LANE
(ELECTIVE CRITERIA) AE 4 - EC
OBJECTIVES
Design / Verification
N6 U6
Provide safe motorcycle lane within the project right of way.
CREDIT REQUIREMENT
BENEFITS
1 Point : Paved shoulder, non‐exclusive motorcycle lane and end treatment at
junction
2 Points : Exclusive motorcycle lane
2 Point : Overhead Motorcycle Bridge
1 Point : Motorcycle shelter
i. As‐built drawings
i. Consider how a new road projects will impact the existing or planned
motorcycle lane networks and integrate design elements with others
facilities to mitigate overall impacts. This may mean providing
connection or adaptability for future motorcycle lane, crossing or other
facilities within motorcycle lane network.
ii. Design the road to accommodate existing new and planned motorcycle
lane facilities.
JKR 20801‐0022‐18 70
POTENTIAL ISSUES
EXAMPLE :
REFERENCES
JKR 20801‐0022‐18 71
REST AREA
(ELECTIVE CRITERIA)
OBJECTIVES AE 5 - EC
Provide access to public rest area facilities
Design / Verification
CREDIT REQUIREMENT
N2 U2
2 Points : Provide or maintain existing rest area facilities along the road
BENEFITS
DOCUMENTATION
JKR 20801‐0022‐18 72
POTENTIAL ISSUES
Provision of transit shelters and stop amenities often not taken into
consideration due to area and budgetary constraint.
EXAMPLE :
REFERENCES
JKR 20801‐0022‐18 73
BICYCLE ACCESS
(ELECTIVE CRITERIA) AE 6 - EC
OBJECTIVES
Design / Verification
N2 U2
Promoting bicycling in communities by providing dedicated cycling facilities
within project right of way
CREDIT REQUIREMENT
BENEFITS
DOCUMENTATION
JKR 20801‐0022‐18 74
planned, roadway transportation, and bicycle and pedestrian systems.
This may include shared-use pathways or park plans.
iii. Include local bicycle planners and advocates in advisory committees,
project development or management teams, or decision-making
committees as appropriate. Consult with planners to understand how
the project can support the development of the bicycle network and to
promote cycling in communities.
iv. Design roadway improvements and new roadways to accommodate
existing, new and planned bicycle facilities.
v. Rely on the assessment of local planners and advocates where no
existing bicycle plan exists about how to integrate existing and future
multimodal facilities into the project’s design.
vi. Consider how a new or redesigned roadway will impact the existing or
planned bicycle networks and integrate design elements with other
modal facilities (e.g. bicycle and transit) to mitigate overall impacts.
This may mean providing connections or adaptability for future bicycle
lanes, shared-use pathways, crossings or other facilities within the
bicycle network.
EXAMPLE :
Examples of appropriate signage for dedicated bicycle access
JKR 20801‐0022‐18 75
Figure 28: Access for bicycles in a motorized vehicle lane
REFERENCES
JKR 20801‐0022‐18 76
CONSTRUCTION ACTIVITY
JKR 20801‐0022‐18 77
REQUIREMENT FOR ROAD WORK DESIGN CA 1
OBJECTIVES
Design
Improve construction quality by using a contractor that has a formal project
quality management system. N0 U0
Verification
CREDIT REQUIREMENT
N3 U3
3 Points : MS ISO 9001 (latest version) certification for main contractor.
BENEFITS
DOCUMENTATION
EXAMPLE :
REFERENCES
i. MS ISO 9001
JKR 20801‐0022‐18 78
OCCUPATIONAL HEALTH AND SAFETY
MANAGEMENT SYSTEM
CA 2
OBJECTIVES
Design / Verification
DOCUMENTATION
EXAMPLE :
REFERENCES
i. OHSAS 18001
JKR 20801‐0022‐18 79
CONSTRUCTION WASTE MANAGEMENT PLAN
OBJECTIVES CA 3
Create an accounting and management plan for road construction waste
materials. Design / Verification
CREDIT REQUIREMENT
N4 U4
BENEFITS
2 Points : Create, establish, implement and maintain a formal construction
waste
2 Point : Provision of Waste Management Plan in the contract (BQ).
1 Point : Provide a designated location to segregate construction waste on‐
site.
1 Point : Appoint the licensed contractor(s) to collect the construction waste
from the site to approved locations for disposal.
DOCUMENTATION
JKR 20801‐0022‐18 80
APPROACHES & STRATEGIES
The project team shall ensure all waste generated on site shall be managed in
accordance with the Solid Waste and Public Cleansing Management Act 2007
and Environmental Quality Act 1974 as follow: ‐
JKR 20801‐0022‐18 81
Figure 30: Recycled Material (Reinforcement Steel)
JKR 20801‐0022‐18 82
Figure 32: Segregation containers for recycled materials
JKR 20801‐0022‐18 83
Figure 34: Segregation containers for recycled materials
REFERENCES
JKR 20801‐0022‐18 84
TRAFFIC MANAGEMENT PLAN (TMP)
OBJECTIVES
CA 4
Develop traffic management plan for road project Design / Verification
CREDIT REQUIREMENT N4 U4
2 Points : Create, establish and implement a formal traffic management plan BENEFITS
during Design and Road Construction Stages.
1 Point : Provision of Traffic Management Officer in the contract document
(BQ)
1 Point : Provision of third party auditor for Traffic Management Plan (TMP)
DOCUMENTATION
JKR 20801‐0022‐18 85
APPROACHES & STRATEGIES
EXAMPLE :
All JKR’s road projects (standard template)
REFERENCES
JKR 20801‐0022‐18 86
SITE ROUTINE MAINTENANCE PLAN
OBJECTIVES
CA 5
To implement a proper site routine maintenance for road project Design / Verification
CREDIT REQUIREMENT N2 U2
2 Points: Create, establish, implement routine maintenance for road project. BENEFITS
DOCUMENTATION
POTENTIAL ISSUES
i. Not following the site routine maintenance programs as required
ii. Lack of awareness over site routine maintenance practices
during construction.
iii. Inadequate provision of routine maintenance.
REFERENCES
JKR 20801‐0022‐18 87
HOUSEKEEPING
OBJECTIVES CA 6
To ensure the site is neat, tidy and accessible
Design / Verification
N2 U2
CREDIT REQUIREMENT
DOCUMENTATION
REFERENCES
i. Akta Pengurusan Sisa Pepejal dan Pembersihan Awam 2007 (Akta 672)
JKR 20801‐0022‐18 88
SUSTAINABLE CONSTRUCTION
OBJECTIVES CA 7
To ensure a proper erosion and sediment control plan (ESCP) on road project and
machineries are regularly maintained for optimal operation that contribute to Design / Verification
reduce carbon emission to the environment (e.g. air, land, water, noise).
N4 U4
CREDIT REQUIREMENT
BENEFITS
2 Points : Perform scheduled maintenance of construction machineries.
2 Points : Use high performance machineries with low fuel consumption and
low air emission.
2 Point : Provision of ESCP and Environmental Monitoring Report (EMR) – (e.g.
Water/ Air/ Noise Quality) in the contract.
DOCUMENTATION
i. For foundation system, method of pile installation that can be opted are:
Jack in pile which use hydraulic hammer
Other pile type / system that emit low carbon / noise
ii. Preparation and submission of Environmental Monitoring Report
(EMR)
JKR 20801‐0022‐18 89
REFERENCES
JKR 20801‐0022‐18 90
MATERIAL RESOURCES
JKR 20801‐0022‐18 91
MATERIAL REUSE
OBJECTIVES MR 1
Optimize construction material and reduce carbon footprint.
Design / Verification
CREDIT REQUIREMENT N5 U5
2 Points : Reuse at a minimum 30% of existing pavement materials and soil by BENEFITS
estimated volume for upgrading road.
1 point : Earthwork balance
1 Point : Fiber roll netting using biodegradable material at site for erosion
control (e.g. wooden dust, coconut fiber)
1 Point : To use reusable formwork for structure (e.g. steel/ fiber formwork)
1 Point : Reuse of existing material other than the above
DOCUMENTATION
JKR 20801‐0022‐18 92
APPROACHES & STRATEGIES
i. Use in place recycling technique such as hot in‐place recycling, cold in‐
place recycling and full depth reclamation. These methods qualify as reuse
because the material has not crossed project boundaries.
ii. Evaluate the structural condition of existing elements such as bridges and
retaining walls. This typically determined by a structural engineer. Do not
reuse elements that have been damaged by corrosion or natural hazards
without review by a structural engineer.
iii. any elements are determined to be inadequate for reuse, consider salvaging
them or deconstructing them for use on another project or purpose (road
furniture).
iv. Reuse of excavated rock materials on site for the road construction (e.g.
crushed rock for rock base)
v. Reuse cut material for filling work (e.g. suitable materials).
EXAMPLE CALCULATION:
Calculation of existing pavement reused percentage for widening an existing
roadway.
Description:
5 km of an existing two‐lane road with 7 m wide lanes and no shoulder is to be
widened to include a 3 m wide two‐way left turn lane and 2.5 m shoulders. The
existing pavement structure consists of 12 cm of HMA over 20 cm of crushed
aggregate. The existing pavement is kept in place except that the top 4 cm of
HMA is removed by a milling machine. New pavement of the same structure is
built on either side of the existing pavement structure to accommodate the
wider final alignment.
Calculation logic:
All 20cm of the base material and 9cm of the HMA are reused. The 4cm
removed by the milling machine is not considered “reused”. If it is recycled, then
it may qualify for consideration under MR‐5 Recycled Materials.
Formula:
JKR 20801‐0022‐18 93
Example of calculation:
EXAMPLE:
JKR 20801‐0022‐18 94
Figure 36: Re‐usage of existing signboard
JKR 20801‐0022‐18 95
Figure 38: Cold in Place Recycling (CIPR)
REFERENCES
JKR 20801‐0022‐18 96
GREEN PRODUCT MR 2
OBJECTIVES
Design / Verification
To encourage the usage of green products in the construction industry
CREDIT REQUIREMENT
N4 U4
4 Points : Green Products Scoring System (GPSS) achieve 70% ‐ 100% BENEFITS
3 Points : Green Products Scoring System (GPSS) achieve 50% ‐ 69%
2 Points : Green Products Scoring System (GPSS) achieve 40% ‐ 49%
1 Point : Green Product Scoring System (GPSS) achieve < 40%
DOCUMENTATION
Identify the green products available in the market by considering the major
product components listed in the Green Product Scoring System Manual (GPSS).
The product shall have any of the following criteria:
JKR 20801‐0022‐18 97
1. Durable product
2. Environmental protection
3. Renewable Energy
4. Recycled content
5. Local product
6. Recyclable materials
7. Improved water quality/efficiency
8. Energy efficiency
9. Improved indoor air quality (IAQ)
The GPSS calculation for building considers only the superstructure elements and
M&E systems. Substructure components for the building and all temporary
works shall be removed from the GPSS calculation. The GPSS calculation for road
excludes electrical works, mechanical works and road furniture.
REFERENCES
JKR 20801‐0022‐18 98
ROAD INVENTORIES
OBJECTIVES MR 3
Proper documentation and records of road assets for future references.
Design / Verification
N1 U2
CREDIT REQUIREMENT
DOCUMENTATION
REFERENCES
JKR 20801‐0022‐18 99
EFFICIENT ROAD LIGHTINGS
OBJECTIVES MR 4
To promote optimal usage of energy through installation of energy efficient
and energy saving devices for road lightings Design / Verification
N1 U1
CREDIT REQUIREMENT
DOCUMENTATION
i. Specifications
ii. Drawings
iii. Catalogue
ii. Incorporate latest energy efficient road lighting (LED, induction, ceramic
metal halide, plasma, etc.) and energy saving device technologies.
REFERENCES
CREDIT REQUIREMENT
N5 U5
BENEFITS
5 Points: Come up with an idea for a design or construction best practice for
road that is not currently included in Manual pH JKR and is more
sustainable than standard or conventional practices. The innovations
that can be applied for road project is:‐
DOCUMENTATION
POTENTIAL ISSUES
i. Cost constrains
ii. Subject to approval by top management
REGISTRATION FORM
pH JKR BORANG PERMOHONAN & PENDAFTARAN
Maklum at Projek
Nama Projek
Dokum en Sokongan
Borang JKR.PK(O).O1.1 - Senarai Semakan Brif
Borang JKR.PK(O).O1.2 - Borang Verifikasi Harta Pelanggan
Borang JKR.PK(O).O1.3 - Senarai Semakan Law atan Tapak
Lain - lain dokumen yang perlu
Sila kem ukakan borang dan dokum ensokongan kepada: Untuk Kegunaan Pejabat
HODT Alam Sekitar (Pemudahcara) No. Daftar pH JKR:
Caw angan Alam Sekitar dan Kecekapan Tenaga
Ibu Pejabat JKR Malaysia Tarikh terima permohonan:
Tingkat 22, Menara PJD, Ulasan
50, Jalan Tun Razak
50400 Kuala Lumpur
Maklum at Projek
Nama Projek
2 Permohonan perlu dihantar selew at-lew atnya 2 minggu sebelum sesi PRB
*Sila rujuk Manual pH JKR untuk keterangan terperinci bagi setiap pengem ukaan
Dokumen perlu dihantar dalam folder dinamakan dan disusun didalam folder mengikut
4
kriteria.
Pengemukaan dokumen yang lengkap perlu dihantar selewat-lewatnya 1 minggu
sebelum sesi PRB (Pihak urusetia berhak untuk membatalkan permohonan atau
5
menunda permohonan ke sesi penilaian yang lain sekiranya dokumen diberi tidak
lengkap)
*Sila rujuk Manual pH JKR untuk keterangan terperinci bagi setiap pengemukaan
…………………………………………
Nama (Pemudahcara)
Tarikh :
Ulasan :
…………………………………………
Nama:
Tarikh :
VP-1
BORANG PERMOHONAN VERIFIKASI PEMARKAHAN pH JKR
Maklum at Projek
Nama Projek
*Sila rujuk Manual pH JKR untuk keterangan terperinci bagi setiap pengem ukaan
Pengemukaan Scorecard Penilaian dan Pensijilan Peringkat Reka Bentuk ( bagi projek
2
yang menjalankan PRB sebelum tahun 2018 )
*Sila rujuk Manual pH JKR untuk keterangan terperinci bagi setiap pengemukaan
…………………………………………
Nama (Pemudahcara)
Tarikh :
Ulasan :
…………………………………………
Nama:
Tarikh :
APPENDIX ‐ C
SCORECARD SUMMARY
pH JKR ROAD SECTOR
Complete version of this Scorecard can be downloaded from WikiGREEN, at https://jpedia.jkr.gov.my.
APPENDIX ‐ D
PAST DEVELOPMENT
Version 1.0 of the Penarafan Hijau JKR (JKR pH) Manual has been completed successfully due
to continuous and dynamic efforts of these PWD staff: