Inspection and Test Plan

The document outlines an inspection and test plan for the replacement and rehabilitation of perimeter security fencing and sand removal at QP MesaiEed Operations. It lists 3 inspections - a visual inspection, installation inspection, and manual function test - that will be conducted once at 100% along with site installation. The inspections will verify that the work meets project specifications and will be reference against controlling documentation. Different parties are assigned for inspections and various approval roles are defined for hold points, witness points, and reviews.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
130 views1 page

Inspection and Test Plan

The document outlines an inspection and test plan for the replacement and rehabilitation of perimeter security fencing and sand removal at QP MesaiEed Operations. It lists 3 inspections - a visual inspection, installation inspection, and manual function test - that will be conducted once at 100% along with site installation. The inspections will verify that the work meets project specifications and will be reference against controlling documentation. Different parties are assigned for inspections and various approval roles are defined for hold points, witness points, and reviews.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

GULF ENERGY TECHNOLOGY & PROJECT'S Project Owner:

Contract No:LT20102800 Descipline:


ITP NO: GETP/ITP/R/01
INSPECTION AND TEST PLAN REV NO: 0
SHEET: 1 of 1

REPLACEMENT AND REHABILITATION OF PERIMETER SECURITY FENCING AND SAND REMOVAL AT QP MESAIEED DATE:
OPERATIONS.

Person Inspection Controlling Inspection


SN Description of inspection Frequency Inspection Stage Refrence Standard
Incharge Requirement Document GETP Third party QP
Visual Inspection Site One Time 100% Along with the site Project Specification Verification RFI H N W&M
1 Engg/QC installation visually
Installation Inspection Site One Time 100% Along with the site Project Specification Verification RFI H N W&M
2 Engg/QC installation Mechanically
Manual Function Test Site One Time 100% Along with the site Project Specification Verification RFI H N W&M
3 Engg/QC installation Electrically
Prepared By: Reviewed By: Approved By: Owner By:

DATE: Name: DATE: Name: DATE: Name: DATE: Name:


(N) Notification (w) witness (H) Hold point (M) Monitor

H - Hold Point: Second and third parties shall request for QP inspection and review of the activity and associated deliverables. Manufacturing or construction shall not progress until satisfactory acceptance by
the QP QC Team.

W - Witness Point: Second and third parties shall request for QP inspection and review of the activity and associated deliverables. Manufacturing or construction may progress if QP do not attend to the notified
inspection activity.

M - Monitor: Qaftar Petroleum reserves the right to conduct surveillance and monitoring of third party manufacturing or construction activities to confirm that requirements are properly adhered to.
R - Review: Second and third parties shall provide the relevant Inspection and Test Record to the QP QC Team for review and approval after completion of the inspection activity.