Inspection & Testing Requirements Scope:: Test and Inspection Per
Inspection & Testing Requirements Scope:: Test and Inspection Per
0020 R X Raw Material Test Report for Carbon Steel Backing Pipe for lined Per 01-SAMSS-048 (note 2)
pipe and weld overlayed pipe
0030 R X Welding Procedure Specification (WPS) and Procedure Per API 5LD and 01-SAMSS-48. Required company approval.
Qualification Records (PQR)
0040 R X Raw Material Verification including Plates Per 01-SAMSS-48, P.O. requirement and MTC’s. The clad
plates intended for manufacturing Metallurgical clad pipes shall
be procured from Saudi Aramco latest approved steel mills list.
0050 R Welder Qualification Records Shall be qualified per ASME section IX and API 5L or
equivalent. Performance records shall show acceptable
rejection rate level.
0052 R Welding Inspector Qualification Shall be certified to AWS (CWI) or CSWIP3.1 or equivalent.
0070 R Manufacturing Procedure Specification Per API 5LD and 01-SAMSS-048 Annex B. Required company
approval.
0020
0010
***
H R
In process inspection & test requirement
Manufacturing Procedure Qualification Test
Specification Details / Notes:
Per API 5LD Annex-D
0030 W X a) Chemical Composition (Backing Steel and CRA) Per API 5LD Para 6.3, 01-SAMSS-048.
0040 W R X b) Tensile Tests, Impact test, Drop weight tear test, Flattening Per API 5LD Para 7, API 5L table 18 and 01-SAMSS-048
test, and Guided bend test.
0050 W R X c) Hardness test and Metallographic Examination Per API 5LD Para 7, API 5L table 18. and 01-SAMSS-048
0060 W X d) Corrosion Test Per API 5LD Para 8 and 01-SAMSS-048 para 8 and API 5LC
Para 8
IR011000 Continued...
INSPECTION & TESTING REQUIREMENTS REVISION: 07/12/2017 CODE NUMBER: PAGE:
SAUDI ARAMCO FORM-175 REPLACES: 04/27/2017 IR011000 2 of 3
(1).VISUAL INSPECTION BY BUYER INSPECTION REPRESENTATIVE
(2) REVIEW AND VERIFICATION OF MATERIAL CERTIFICATES AND INSPECTION RECORDS
(3) SUBMISSION OF MANUFACTURING, INSPECTION AND QUALITY RECORDS
0070 W X e) Cladding bond strength test/Liner tightness test Per Para 8.3 of API 5LD and 01-SAMSS-048.
0080 W X f) Residual magnetism Per Para 8.4 of API 5LD and 01-SAMSS-048.
0090 X g) Ferrite/Austenite Ratio for DSS Per Para 8.1 of API 5LD and APL 5LC
0100 W R X Heat Treatment Per Para 5.4 of API 5LD and 01-SAMSS-048
0130 W R X Non Destructive Testing Per Para 11 of API 5LD and 01-SAMSS-048
0030
0010
***
H R
Final inspection & test requirements
Workmanship and Visual Inspection
Specification Details / Notes:
Per Para 12 of API 5LD and 01-SAMSS-048
0020 H X Dimensions, Weights, Lengths, Weld Seam and pipe ends Per Para 10 of API 5LD and 01-SAMSS-048
0030 W X Marking, Handling, Packing and Transportation Per Para 13 of API 5LD and 01-SAMSS-048
0040 R X Mill Test Certificate / Documentation Per 01-SAMSS-048and applicable ASTM std.
IR011000 Continued...
INSPECTION & TESTING REQUIREMENTS REVISION: 07/12/2017 CODE NUMBER: PAGE:
SAUDI ARAMCO FORM-175 REPLACES: 04/27/2017 IR011000 3 of 3
(1).VISUAL INSPECTION BY BUYER INSPECTION REPRESENTATIVE
(2) REVIEW AND VERIFICATION OF MATERIAL CERTIFICATES AND INSPECTION RECORDS
(3) SUBMISSION OF MANUFACTURING, INSPECTION AND QUALITY RECORDS
Notes:
(1)Refer detailed instruction sheet SA175 form IR000003 of inspection requirement for ideal use of this form.
(2)In process inspection required at pipe manufacturing facility for carbon steel pipe intended for mechanically lined pipe and weld overlayed pipe
Unless carbon steel pipes are supplied by Saudi Aramco. Carbon steel backing pipes must be from Saudi Aramco approved source.