CHAPTER 2 PETROLEUM ENGINEERING
The Oil Business
1
CHAPTER 2 PETROLEUM ENGINEERING
Major Segments of Oil & Gas Industry
Upstream Activities
Exploration and production of oil and natural gas
Midstream Activities
Transportation, storage and trading of crude oil, refined products
and natural gas
Downstream Activities
Refining and marketing of crude oil
Local distribution companies
Participants
Majors –integrated oil and gas companies, which are involved in
every aspect of the business integrated
Pure-play companies in various areas.
2
CHAPTER 2 PETROLEUM ENGINEERING
Upstream Operations: Oil & Gas E & P Process
Exploration
Search for oil and natural gas by geologists and geophysicists
Once such areas are found, subsurface conditions are
investigated using seismological or other techniques
Drilling & Logging
To drill –only way to know about the presence of resources
Move to next stage, if commercial amounts are encountered
Continue if the well contains commercialquantities
Completion
One or more flow paths must be constructed for the hydrocarbons
to travel between the reservoir and Earth‟s surface
Lifting
Bringing energy resources to Earth‟s surface
3
CHAPTER 2 PETROLEUM ENGINEERING
Midstream Operations: Transportation and Storage
Once Extracted, crude oil&gas must be moved from the wellhead to the
refinery or distributors.
Transportation Methods (means):
Internationally:
Oil:Crude Tankers or barges. Global tanker fleet –2750 tankers
with total capacity of 287,400 dead weight tones (As of October
2002 )
Gas: Occasionally natural gas is liquefied and
transportedinternationally in LNG tankers.
On Land
Oil:Delivered to refineries with pipeline, truck or rail
Gas: Delivered to LDCs (Local Distribution Companies) with trunk
pipelines, or CNG
Storages
Essential function of an efficient and reliable pipeline network,
managing fluctuation in supply and demand
4
CHAPTER 2 PETROLEUM ENGINEERING
Downstream Operations: Refining and Marketing of Oil Products
Refining –creating a variety of final products
Refining Steps: Hydro treating, Cracking, Reforming,
Alkylation
Gasoline Marketing
Direct marketing by integrated oil companies at a retail station
bearing the company‟s name and emblem
Selling gasoline through independent marketers
Self-Serve business
24-hour point-of-sale terminals, Self service gas station
5
CHAPTER 2 PETROLEUM ENGINEERING
6
CHAPTER 2 PETROLEUM ENGINEERING
Upstream Competition Creates „Super Majors‟
7
CHAPTER 2 PETROLEUM ENGINEERING
Exploring for Oil
8
CHAPTER 2 PETROLEUM ENGINEERING
Once the Exploration Site is Selected
Getting the land ready
The area is surveyed to determine its boundaries.
Environmental studies are said to be done.
The land is cleared and then access roads are built.
Water is drilled if there are no natural sources available.
A reserve pit is dug to dispose of rock cuttings and mud. It is lined
with plastic to “protect” the environment only if the area is considered
to be “ecologically sensitive.”
Making way for the rig
Several holes are dug to make way for the rig and main hole
A rectangular pit (cellar) is dug around the location of the drilling hole.
(This provides a workspace)
The crew drills a main hole
Additional holes are dug to the side to store equipment
9
CHAPTER 2 PETROLEUM ENGINEERING
Seismic: Searching for Geological Traps
Any Traps! May be oil, or water or empty traps
The Government and Oil companies
usually assign finding oil to contracted
geologists
Oil geologists examine surface features,
surface rock, reservoir rock, entrapment,
satellite images, sensitive gravity meters
and magnometers. They can also detect
the smell of hydrocarbons using
electronic noses called sniffers.
The most common technique for finding
reserves is seismology which uses
shock waves that interpret waves
reflected back to the surface.
Despite all the technologies, modern oil
exploration methods
10
CHAPTER 2 PETROLEUM ENGINEERING
Oil Exploration -Seismic
11
CHAPTER 2 PETROLEUM ENGINEERING
Setting Up the Rig
Once the land is ready, several holes
are dug to make way for the rig and
main hole.
A rectangular pit called a cellar is dug
around the location of the actual drilling
hole.
The cellar provides a workspace
around the hole. The crew then drills a
main hole.
The following is how a rig is set up.
12
CHAPTER 2 PETROLEUM ENGINEERING
Drilling
Place the drill bit, collar and drill pipe in
the hole.
Attach the Kelly and turntable and begin
drilling.
As drilling progresses, circulate mud
through the pipe and out of the bit to
float the rock cutting out of the hole.
Add new sections (joints) of drill pipes
ad the hole gets deeper.
Remove (trip out) the drill pipe, collar
and bit when the pre-set depth
(anywhere from a few hundred to a
couple thousand feet) is reached.
13
CHAPTER 2 PETROLEUM ENGINEERING
Horizontal Well
14
CHAPTER 2 PETROLEUM ENGINEERING
Horizontal Drilling Avoids Surface Hazards
15
CHAPTER 2 PETROLEUM ENGINEERING
Confirming the Presence of Oil
After the pre-wet depth is reached, the
workers run and cement the casing –
pipe sections into the hole to prevent it
from collapsing.
Drilling continues in stages. When the
rock cuttings from the mud reveal the oil
sand from the reservoir rock, they may
have reached the final depth.
At this point, they remove the drilling
apparatus from the hole and perform
several tests to confirm the presence of
oil.
These tests are Well logging, Drill-stem
testing, and Core samples.
16
CHAPTER 2 PETROLEUM ENGINEERING
Extracting the Oil
Once the well is completed, the
operators must start the flow of oil into
the well.
For limestone reservoir rock, acid is
pumped down the well and out the
perforations.
For sandstone reservoir rock, a special
blended fuel containing proppants is
pumped down the well and out the
perforations.
The pressure from this fluid makes
small fractures in the sandstone that
allow oil to flow into the well, while the
proppants hold these fractures open.
Once the oil is flowing, the oilrig is
removed from the site and production
equipment is set up to extract the oil 17
from the well.
CHAPTER 2 PETROLEUM ENGINEERING
What Are the Four Life Stages of a Reservoir?
18
CHAPTER 2 PETROLEUM ENGINEERING
Oil Drilling Equipments
19
CHAPTER 2 PETROLEUM ENGINEERING
Drilling Rig & Oil Well Components
20
CHAPTER 2 PETROLEUM ENGINEERING
Oil Drilling Equipment
Power System
Mechanical System
Casing
Rotating Equipment
Circulating System
21
CHAPTER 2 PETROLEUM ENGINEERING
Circulating System
Pump
Pipes and Hoses
Mud-Return Line
Shale Shaker
Shale Slide
Reserve Pit
Mud Pits
Mud-Mixing Hopper
22
CHAPTER 2 PETROLEUM ENGINEERING
An Oil Drilling Bit
23
CHAPTER 2 PETROLEUM ENGINEERING
Cutaway of Drill Bit
24
CHAPTER 2 PETROLEUM ENGINEERING
Soft Rock Bits
25
CHAPTER 2 PETROLEUM ENGINEERING
Pipe Grappler
26
CHAPTER 2 PETROLEUM ENGINEERING
Drilling Floor
27
CHAPTER 2 PETROLEUM ENGINEERING
Christmas Tree
28
CHAPTER 2 PETROLEUM ENGINEERING
Offshore Drilling & Platform System
29
CHAPTER 2 PETROLEUM ENGINEERING
Offshore Deepwater Drilling Rig Technology
30
CHAPTER 2 PETROLEUM ENGINEERING
Anchor Link for Deep Water Rig… BIG
31
CHAPTER 2 PETROLEUM ENGINEERING
Type of Offshore Drilling Rigs
32
CHAPTER 2 PETROLEUM ENGINEERING
Offshore Drilling Platform
33
CHAPTER 2 PETROLEUM ENGINEERING
Offshore Drilling Rig -TLP
34
CHAPTER 2 PETROLEUM ENGINEERING
Offshore Drilling Platform -Spar
35
CHAPTER 2 PETROLEUM ENGINEERING
Jackups Drlling Rig
36
CHAPTER 2 PETROLEUM ENGINEERING
What is a Jack-Up Rig ?Mobile Offshore Self-elevating drilling unit
37
CHAPTER 2 PETROLEUM ENGINEERING
Semi-submersible Rigs
38
CHAPTER 2 PETROLEUM ENGINEERING
Drillships and Swamp Barge
39