DN NAGAR - Report
DN NAGAR - Report
located at DN Nagar
Report
by
For
April 2018
CONTENTS
1. Introductory Remarks 2
5. References 111
1
Structural Audit of ONGC Residential Buildings
located at DN Nagar
(Job No.: DRD/CE/SB-12/17-18)
1. INTRODUCTORY REMARKS
Oil and Natural Gas Corporation Limited, Mumbai approached Indian Institute of
during April 2018 as per Dean R&D approval letter …… dated 20/10/2017 and after
clarification of TDS issues between ONGC and IITB. The buildings were reinforced
cement concrete (RCC) framed structure constructed in the year 1994 and about
23 years old. Each building has built up area of 4598.25m2. The building had shown
sign of severe distress; therefore, it was decided by ONGC to carry out detailed
structural audit of the buildings to have an expert technical opinion on its current
structural conditions.
condition and stability of the residential building was under-taken by IITB. The
1. Carry out the visual inspection of the buildings to see the extent of distress in
Ultrasonic Pulse Velocity Tests (UPVT), Carbonation Tests (CT) and Half Cell
2
Potentiometer Tests (HCPT) of the building to assess the current quality and
3. Investigate the possible reasons for deterioration of the structural health of all
the buildings based on the above NDT tests and visual inspections.
3
2. SITE INSPECTION AND TESTING
The site was visited by a team of four members from IIT Bombay during April 2018.
The team consisted of two faculty member, two laboratory engineer, and one
technician and one research scholar. The team was supported by the ONGC engineers
and casual labours for testing work of the buildings. The building was first inspected
to identify accessible locations for NDT measurements. The plastering work at the
identified RCC elements was removed and surface preparations were carried out at
The markings were carried out based on the locations since no building plan
was available appropriate. The details of various tests conducted and their guiding
Rebound hammer test is done to find out the likely compressive strength of concrete
by using rebound hammer as per IS 13311 (Part 2): 1992. The underlying principle of
the rebound hammer test is “the rebound of an elastic mass depends on the hardness of
the surface against which its mass strikes”. When the plunger of the rebound hammer
is pressed against the surface of the concrete, the spring-controlled mass rebounds and
the extent of such a rebound depends upon the surface hardness of the concrete. The
surface hardness and therefore, the rebound are taken to be related to the compressive
strength of the concrete. The rebound value is read from a graduated scale and is
designated as the rebound number or rebound index. The compressive strength can be
read directly from the graph provided on the body of the hammer.
4
2.2 Ultrasonic Pulse Velocity Test (UPVT)
This test helps in assessing the quality of concrete. The time of travel for an ultrasonic
pulse through a given path length of concrete is measured. For this purpose two
probes (transducers) are used one transmitting and the other receiving. Thus,
It is best to have the two probes on opposite faces of concrete members. Thus,
the signal passes through the entire thickness of the member. This is the direct (D)
method of test and the same was used for the investigations of the RCC elements.
On the other hand, when only one face of the structural element is available the
two probes are kept on the same inspected face. This is the indirect (ID) method and
the same was used when both sides of the RCC member was not accessible. Indirect
method is not as efficient as direct method due to reduced signal amplitude and the
test results are greatly influenced by the surface layers of concrete which may have
different properties from that of concrete inside the structural member.As per the IS
13311 (Part 1): 1992, the measured indirect velocity is invariably lower than the direct
velocity on the same concrete element. This difference may vary from 5 to 20 percent
depending largely on the quality of the concrete under test. Thus, the measured
indirect velocity obtained from equation (1) is increased at least by 20 percent in the
results reported. The UPV depends on the quality of concrete and is affected by all its
ingredients. The IS 13311 (part 1):1992 uses only qualitative interpretation as given in
5
Table 2.1 Concrete Quality Grading Based on Ultrasonic Pulse Velocity
Measurements as per IS 13311 (part 1):1992
reinforcement corrosion problems. The carbonation test is carried out to determine the
depth of concrete affected due to combined attack of atmospheric carbon dioxide and
of concrete to pink indicates that the concrete is in the good health, and where no
is conducted by drilling a hole on the concrete surface to different depths upto cover
physician’s injection syringe and needle on such freshly drilled broken concrete and
6
observing change in colour. The depth of carbonation is estimated based on the
The instrument measures the potential and the electrical resistance between the
reinforcement and the surface to evaluate the corrosion activity as well as the actual
condition of the cover layer during testing. The electrical activity of the steel
reinforcement and the concrete leads them to be considered as one half of weak
battery cell with the steel acting as one electrode and the concrete as the electrolyte.
The name half-cell surveying derives from the fact that the one half of the battery cell
is considered to be the steel reinforcing bar and the surrounding concrete. The
electrical potential of a point on the surface of steel reinforcing bar can be measured
comparing its potential with that of copper – copper sulphate reference electrode on
the surface. Practically, this is achieved by connecting a wire from one terminal of a
voltmeter to the reinforcement and another wire to the copper sulphate reference
electrode. This method may be used to indicate the corrosion activity associated with
steel embedded in concrete and can be applied to members regardless of their size or
the depth of concrete cover. It should be clearly noted that the test does not actual
corrosion rate or whether corrosion activity has already started, but it indicates the
probability of the corrosion activity depending upon the actual surrounding conditions
the higher the gradient, and the higher risk of corrosion. The test results can be
7
Table 2.2 Corrosion Chance Based on Half Cell Porential
The ONGC Building is located near at DN Nagar is a G+4 storied RCC frame
structure with flat roof as shown in the Figure 3.1,3.12 and 3.25. It is about 23 years
old. The building has one main entrance for each wing. The structures was first
inspected to identify accessible locations for NDT measurements. Points for NDT
measurements.
The detailed visual inspection of the C-10 building leads to the following important
observations:
8
2. Some External Column reinforcements were corroded (Refer Figure 32, 3.13,
3.26).
1. Common areas:
a. Heavily distressed and cracked stair case landings, slabs and beams can be
observed in the interior portions (Refer Figure 3.3, 3.14, 3.28).
b. Slightly distressed slabs, cracks on parapet walls, slight fungal growth on the
stair case room on terrace, parapet wall and water tank, slightly damaged terrace
floor. (Refer Figure 3.4,3.15,3.27).
Floor Figure
Location Observation
Level Reference
4th Floor Room No - Minor cracks 3.5 and 3.6
(A-wing) 19&20,17&18 Seepage of Water through Wall
4th Floor Room No - Minor cracks on walls 3.16 and
(B-wing) 39&40,37&38 Seepage of Water through Wall 3.17
Minor cracks on walls
4th Floor Room No -
Seepage of Water through Wall 3.29
(C-wing) 59&60
and roof slab
Minor cracks on walls and slabs
3rd Floor Room No -
Seepage of Water through Wall 3.6 and 3.7
(A-wing) 15&16,13&14
and roof slab
Heavy seepage, wide cracks on
3rd Floor Room No -
walls, Spalling of plaster from 3.18
(B-wing) 35&36,33&34
walls and slabs 3.19
2nd Floor Room No -
Seepage of water through walls
(A-wing) 11&12 3.9
9
Seepage of water through walls, 3.20
2nd Floor Room No -
Minor cracks on walls, Spalling of 3.21
(B-wing) 31&32,29&30
plaster concrete from walls
1. The Rebound Hammer Test results of the columns, beams and slabs of the
Building are tabulated in the Tables 3.1, Table 3.2 and Table 3.3 respectively.
10
in the Figure 3.35, 3.37 to 3.39, 3.43 to 3.45, 3.49 to 3.51. Based on rebound
beams and slabs is observed as 27.1 MPa, 28.0 MPa and 32.2 MPa
respectively. The rebound hammer strength above 20MPa for the RCC
2. The UPVT results of the columns, beams and slabs of the building are shown
in the Tables 3.4 to 3.6 (refer Figures 3.36, 3.40 to 3.42,3.46 to 3.48,3.52 to
3.54 for the photographs of the UPVT of the structural members). The average
recorded velocity in column, beam and slab are 2.1km/s, 2.2km/s and 2.3 km/s
respectively. These test results are indicative that the concrete of columns,
beam and slab can be given doubtful quality grading. The same doubtful
the Building are given in the Table 3.7. These test results indicate that of
moderate carbonation of the concrete had taken place in the external members
of the building (refer Figure 3.55 to 3.57 for the spots of carbonation test).
4. The Half Cell Potential for all structural member is in between 200 to 350
which indicates 50% chance of corrosion activity in the reinforcing bars. Table
3.8 shows the half-cell potential values of the columns, and slab. The
corresponding photographic views of the testing work are shown in Figure 3.58
to 3.59.
11
3.2 DISTRESS ANALYSIS AND CURRENT STRUCTURAL STATUS:
The visual inspection and NDT of various structural members of the ONGC Building
located at DN Nagar Mumbai has suggested that the building is in a partially distressed
condition.
Externally the RCC members., e.g extended beam and slabs, pardis/projections are
showing severe cracks/spalled concrete along the main reinforcement directions due to
corrosion. Inside the building, mainly RCC slab has been distressed and have rebar
exposed to atmosphere. The internal rooms are also seen to have been affected
some places. In particular, major distress was observed on the 7th floor. The primary
source for the seepage and leakages are found to be deteriorated plumbing lines
around the toilet lines, additionally erected toilet adjacent to office rooms,
distressed/failed roof water proofing and projected areas from the windows with
inadequate slope/water proofing. It is further observed the RCC elements are cut to
take the AC lines , which should have been taken through brickwork. It is desirable
that the heavy book racks be moved to the ground floor. It is also desirable that
The residual strength of concrete in columns, beams and slabs is just adequate but
have doubtful grading exhibiting some degree of looseness. The doubtful grading in
some structural members is indicative of aging and corrosion related events. The beam
carbonation has taken place with about 50% chances corrosion activity. The repeated
12
drying and wetting cycles caused by excessive seepage and leakages, inadequate cover
reasons for corrosion of steel reinforcements. Internal plumbing leakage add more
detrimental effects.
It is observed that major repairing work has not been taken up at all. This, in turn,
safety and stability of the building. Therefore, the rehabilitation of the building to
restore its strength will require major structural and as well as non-structural repairs,
13
Table 3.1: Rebound Hammer Test Results of Columns of Building
Gr.Flr.Column-01 (T) 31 26 24 32 28 20
Gr.Flr.Column-01 (B) 31 28 30 29 30 23
Gr.Flr.Column-02 (T) 39 34 36 32 35 32
Gr.Flr.Column-02 (B) 32 38 34 33 34 30
Gr.Flr.Column-03 (T) 31 32 30 29 31 25
Gr.Flr.Column-03 (B) 32 34 36 32 34 30
Gr.Flr.Column-04 (T) 24 22 27 26 25 16
Gr.Flr.Column-04 (B) 24 28 26 30 27 19
Gr.Flr.Column-05 (T) 34 39 38 38 37 35
Gr.Flr.Column-05 (B) 32 34 36 30 33 28
Gr.Flr.Column-06 (T) 27 32 31 31 30 23
Gr.Flr.Column-06 (B) 30 32 34 28 31 25
Gr.Flr.Column-07 (T) 34 29 30 34 32 26
Gr.Flr.Column-07 (B) 28 32 30 30 30 23
Gr.Flr.Column-08 (T) 36 44 39 38 39 39
Gr.Flr.Column-08 (B) 41 38 40 37 39 39
Gr.Flr.Column-09 (T) 33 33 36 29 33 28
Gr.Flr.Column-09 (B) 32 30 34 37 33 28
Gr.Flr.Column-10 (T) 28 29 26 24 27 19
Gr.Flr.Column-10 (B) 30 32 28 26 29 22
Gr.Flr.Column-11 (T) 26 22 26 25 25 16
Gr.Flr.Column-11 (B) 28 30 28 24 28 20
A-Wing
st n
1 Flr.Column (Bet Flat N0.7&8)
38 34 38 36 37 35
(T)
1st Flr.Column (Betn Flat N0.7&8)
32 38 34 40 36 33
(B)
2nd Flr.Column (Betn Flat
38 36 34 32 35 32
N0.11&12) (T)
2nd Flr.Column (Betn Flat
40 34 32 38 36 33
N0.11&12) (B)
3rd Flr.Column (Betn Flat
40 42 36 34 38 37
N0.15&16) (T)
3rd Flr.Column (Betn Flat
38 36 38 40 38 37
N0.15&16) (B)
14
4th Flr.Column (Betn Flat
23 24 22 23 23 13
N0.19&20) (T)
4th Flr.Column (Betn Flat
23 28 26 30 27 19
N0.19&20) (B)
B-Wing
Gr.Flr.Column (In Flat
26 24 28 30 27 19
N0.21,Hall) (T)
Gr.Flr.Column (In Flat
27 19
N0.21,Hall) (B) 30 24 26 28
Gr.Flr.Column (In Flat
30 30 26 26 28 20
N0.24,Centre) (T)
Gr.Flr.Column (In Flat
23 26 28 30 27 19
N0.24,Centre) (B)
1st Flr.Column (Betn Flat
32 26
N0.27&28) (T) 32 29 31 34
1st Flr.Column (Betn Flat
31 25
N0.27&28) (B) 30 28 32 34
C-Wing
Gr.Flr.Column (Betn Flat
32 34 30 30 32 26
N0.43&44) (T)
Gr.Flr.Column (Betn Flat
36 32 30 36 34 30
N0.43&44) (B)
1st Flr.Column (Betn Flat
32 28 36 34 33 28
N0.47&48) (T)
1st Flr.Column (Betn Flat
32 30 30 32 31 25
N0.47&48) (B)
2nd Flr.Column (Betn Flat
30 34 36 34 34 30
N0.51&52) (T)
2nd Flr.Column (Betn Flat
36 34 38 40 37 35
N0.51&52) (B)
3rd Flr.Column (Betn Flat
32 30 30 26 30 23
N0.54&55) (T)
3rd Flr.Column (Betn Flat
28 30 28 28 29 22
N0.54&55) (B)
4th Flr.Column (Betn Flat
48 44 42 46 45 50
N0.59&60) (T)
4th Flr.Column (Betn Flat
44 42 40 43 42 44
N0.59&60) (B)
Mean 27.1
Standard Deviation 7.8
15
1st Flr.Beam (Over staircase) (N) 36 34 32 38 35 32
1st Flr.Beam (Over staircase) (S) 32 34 30 38 34 30
2nd Flr.Beam (Over staircase) (N) 34 36 38 40 37 35
2nd Flr.Beam (Over staircase) (S) 34 32 34 38 35 32
3rd Flr.Beam (Over staircase) (N) 36 34 40 36 37 35
3rd Flr.Beam (Over staircase) (S) 40 32 32 38 36 33
4th Flr.Beam (Over staircase) (N) 20 24 20 24 22 12
th
4 Flr.Beam (Over staircase) (S) 26 24 28 30 27 19
B-Wing
Gr.Flr.Beam (Over staircase) (N) 34 36 32 36 35 32
Gr.Flr.Beam (Over staircase) (S) 30 32 30 32 31 25
1st Flr.Beam (Over staircase) (N) 38 42 36 40 39 39
1st Flr.Beam (Over staircase) (S) 40 42 40 40 41 42
2nd Flr.Beam (Over staircase) (N) 30 26 28 28 28 20
2nd Flr.Beam (Over staircase) (S) 28 26 30 34 30 23
3rd Flr.Beam (Over staircase) (N) 34 39 36 32 35 32
3rd Flr.Beam (Over staircase) (S) 40 36 32 40 37 35
4th Flr.Beam (Over staircase) (N) 38 38 40 36 38 37
4th Flr.Beam (Over staircase) (S) 34 32 32 38 34 30
C-Wmg
Gr.Flr.Beam (Over staircase) (N) 30 28 26 30 29 22
Gr.Flr.Beam (Over staircase) (S) 30 26 28 27 28 20
1st Flr.Beam (Over staircase) (N) 28 30 32 30 30 23
st
1 Flr.Beam (Over staircase) (S) 32 30 34 32 32 26
2nd Flr.Beam (Over staircase) (N) 28 32 34 32 32 26
2nd Flr.Beam (Over staircase) (S) 26 30 34 32 31 25
3rd Flr.Beam (Over staircase) (N) 30 24 26 28 27 19
3rd Flr.Beam (Over staircase) (S) 24 26 24 30 26 17
4th Flr.Beam (Over staircase) (N) 32 30 32 36 33 28
4th Flr.Beam (Over staircase) (S) 34 36 34 30 34 30
Mean 28.0
Standard Deviation 7.1
16
Table 3.3: Rebound Hammer Test Results of Slab of Building
C-Wing
Gr.Flr.Slab (Over staircase) (E) 40 40 40 36 39 32
Gr.Flr.Slab (Over staircase) (W) 38 38 36 34 37 28
2nd Flr.Slab (Over staircase) (E) 42 45 43 50 45 43
2nd Flr.Slab (Over staircase) (W) 48 46 42 44 45 43
3rd Flr.Slab (Over staircase) (E) 44 36 40 42 41 35
3rd Flr.Slab (Over staircase) (W) 44 40 40 40 41 35
17
4th Flr.Slab (Over staircase) (E) 44 40 40 46 43 39
4th Flr.Slab (Over staircase) (W) 42 48 46 40 44 41
Mean 32.2
Standard Deviation 7.8
Table 3.4: Ultrasonic Pulse Velocity Test Results of Columns of Building C10.
B-Wing
Gr.Flr.Column (In Flat N0.21,Hall) 230 556.0 0.5
Gr.Flr.Column (In Flat N0.24,Centre) Cracked
1st Flr.Column (Betn Flat N0.27&28) 260 293.0 1.1
C-Wing
Gr.Flr.Column (Betn Flat N0.43&44) 300 98.5 3.7
1st Flr.Column (Betn Flat N0.47&48) 250 153.8 2.0
2nd Flr.Column (Betn Flat N0.51&52) 300 136.6 2.6
18
3rd Flr.Column (Betn Flat N0.54&55) 250 258.4 1.2
4th Flr.Column (Betn Flat N0.59&60) 250 99.8 3.0
Mean 2.1
Standard Deviation 1.0
(*Direct Method,Indirect Method)
19
Table 3.6:Ultrasonic Pulse Velocity Test Results of Slab of Building.
BUILDING N0.10
Gr.Flr.Column-01 10
Gr.Flr.Column-02 5
Gr.Flr.Column-03 5
Gr.Flr.Column-04 5
Gr.Flr.Column-05 >30
20
Gr.Flr.Column-06 5
Gr.Flr.Column-07 >30
Gr.Flr.Column-08 >30
Gr.Flr.Column-09 5
Gr.Flr.Column-10 >30
Gr.Flr.Column-11 >30
A-Wing
1st Flr.Column (Betn Flat N0.7&8) >30
2nd Flr.Column (Betn Flat N0.11&12) >30
3rd Flr.Column (Betn Flat N0.15&16) >30
4th Flr.Column (Betn Flat N0.19&20) >30
B-Wing
Gr.Flr.Column (In Flat N0.21,Hall) >30
Gr.Flr.Column (In Flat N0.24,Centre) >30
1st Flr.Column (Betn Flat N0.27&28) >30
C-Wing
n
Gr.Flr.Column (Bet Flat N0.43&44) >30
1st Flr.Column (Betn Flat N0.47&48) >30
2nd Flr.Column (Betn Flat N0.51&52) >30
3rd Flr.Column (Betn Flat N0.54&55) >30
4th Flr.Column (Betn Flat N0.59&60) >30
(*excluding surface plaster)
Table 3.8: Corrosion Analysis Test Results of Column and slab of Building
AVERAGE
HALF CELL
RCC MEMBER STRUCTURE HALF CELL POTENTIAL -mV
POTENTIAL
-mV
21
Standard Deviation 28
(*excluding surface plaster)
22
(b)
(a)
Figure. 3.1. Photographs showing exterior views of A-Wing at DN Nagar
(a) (b)
23
(c) (d)
(e) (f)
24
(g) (h)
(i)
Figure. 3. 2. Photographs showing heavily distressed and cracked Sunshades, walls at exterior
portions of A-Wing
25
(a) (b)
(c) (d)
26
(e) (f)
27
(g) (h)
(i) (j)
28
(k) (l)
Figure. 3. 3. Photographs showing heavily distressed and cracked landings and stair case slabs and
beams of A-Wing
29
(a) (b)
(c) (d)
30
(e) (f)
(g) (h)
31
(i) (j)
Figure. 3. 4. Photographs showing Slightly distressed slabs, parapet walls, slight fungal growth on
Parapet walls, slightly damaged terrace floor, water tank in A-wing
(a) (b)
32
(c) (d)
(e) (f)
33
(g) (h)
Figure 3.5. Photographs showing seepage/leakage problems along with some distress in the
RCC members/Walls of the various rooms of the Room No. 19&20, A-Wing
(a) (b)
34
(c) (d)
(e) (f)
35
(g) (h)
(i) (j)
Figure 3.6. Photographs showing seepage/leakage problems along with some distress in the
RCC members/Walls of the various rooms of the Room No. 17&18, A-Wing
36
(a) (b)
(c ) (d)
37
(e) (f)
Figure 3.7. Photographs showing seepage/leakage problems along with some distress in the
RCC members/Walls of the various rooms of the Room No. 15&16, A-Wing
(a) (b)
(c ) (d)
Figure 3.8. Photographs showing seepage/leakage problems along with some distress in the
RCC members/Walls of the various rooms of the Room No. 13&14, A-Wing
38
(a) (b)
(c)
Figure 3.9. Photographs showing seepage/leakage problems along with some distress in the
Walls of the various rooms of the Room No. 12&11, A-Wing
39
(a) (b)
(c) (d)
40
(e) (f)
Figure 3.10. Photographs showing seepage/leakage problems along with some distress in the
RCC members of the various rooms of the Room No. 5&6, A-Wing
(a) (b)
41
(c ) (d)
(e) (f)
(g) (h)
42
(i) (j)
Figure 3.11. Photographs showing seepage/leakage problems along with some distress in the
RCC members/Walls of the various rooms of the Room No. 3&4, A-Wing
43
EXTERIOR VIEWS (B-Wing)
44
Figure. 3.12. Photographs showing exterior views of B-Wing at DN Nagar
(a) (b)
45
(c) (d)
(e) (f)
46
(g) (h)
(i) (j)
47
(k) (l)
Figure. 3.13 Photographs showing heavily distressed and cracked Walls, fungal growth on walls at
exterior portions and Corrosion of reinforcement of columns of B-Wing
(a) (b)
48
(c) (d)
(e) (f)
(g) (h)
Figure. 3.14 Photographs showing heavily distressed and cracked landings and stair case slabs and
beams of B-Wing
49
50
(a) (b)
(c) (d)
(e) (f)
Figure 3.15. Photographs showing slight distress in the parapet wall, slight fungal growth on
Parapet walls, slightly damaged terrace floor, water tank in B-wing
51
Internal Common areas
52
(a) (b)
(c) (d)
(e) (f)
53
Figure 3.16. Photographs showing seepage/leakage problems along with some distress in the
Walls of the various rooms of the Room No. 39&40, B-Wing
(a) (b)
(c) (d)
Figure 3.17. Photographs showing seepage/leakage problems along with some distress in the
Walls of the various rooms of the Room No. 37&38, B-Wing
54
(a) (b)
(c) (d)
Figure 3.18. Photographs showing leakage problems along with some distress in the RCC
members/Walls ,minor spalling of plaster concrete on roof slabs of the various rooms of the
Room No. 35&36 B-Wing
(a) (b)
55
(c) (d)
(e) (f)
Figure 3.19. Photographs showing leakage problems along with some distress in the Walls
Chajja, spalling of plaster concrete of walls of the various rooms of the Room No. 33&34 B-
Wing
56
(a) (b)
(c) (d)
Figure 3.20. Photographs showing leakage problems along with some distress in the Walls of
the various rooms of the Room No. 31&32 B-Wing
57
(a) (b)
(c) (d)
(e) (f)
Figure 3.21. Photographs showing leakage problems along with some distress in the Walls,
spalling of plastering concrete of walls of various rooms of the Room No. 29&30 B-Wing
58
(e) (f)
(a) (b)
Figure 3.22. Photographs showing leakage problems along with some distress in the Walls of
the various rooms of the Room No. 27&28 B-Wing
59
(a) (b)
(c) (d)
60
(e) (f)
Figure 3.23. Photographs showing leakage problems along with heavy distress in the RCC
members/Walls of the various rooms of the Room No. 23&24 B-Wing
(a) (b)
61
(c) (d)
Figure 3.24. Photographs showing leakage problems along with some distress in the Walls of
the various rooms of the Room No. 21&22 B-Wing
62
(a) (b)
Figure. 3.25. Photographs showing exterior views of C-Wing at DN Nagar
(a) (b)
63
(c) (d)
(e) (f)
64
(g) (h)
(i) (j)
65
(k) (l)
Figure. 3.26 Photographs showing heavily distressed and cracked Walls, Corrosion of reinforcement
of columns of B-Wing
(a) (b)
66
(c) (d)
(e) (f)
67
(g) (h)
(i) (j)
Figure 3.27. Photographs showing slight distress in the parapet wall, water tank and stair case
room slab, slight fungal growth on Parapet walls, slightly damaged terrace floor, water tank in C-
wing
68
(a) (b)
(c) (d)
69
(e ) (f)
(g) (h)
70
(i) (j)
(k) (l)
Figure 3.28. Photographs showing heavily distressed and cracked landings and stair case slabs and
beams, spalling of plaster concrete of slab and beams of staircase room of C-Wing
71
(a) (b)
(c) (d)
72
(e) (f)
(g) (h)
73
(i) (j)
Figure 3.29. Photographs showing leakage problems along with some distress in the Walls of
the various rooms of the Room No. 59&60, C Wing
(a) (b)
74
(c) (d)
(e)
Figure 3.30. Photographs showing leakage problems various rooms of the Room No. 49&50,
C Wing
75
(a) (b)
(c) (d)
76
(e) (f)
(g) (h)
Figure 3.31. Photographs showing leakage problems along with some distress in the walls,
spalling of plaster concrete on roof slab of the various rooms of the Room No. 45&46, C Wing
(a) (b)
77
(c) (d)
(e) (f)
78
(g) (h)
(i) (j)
Figure 3.32. Photographs showing leakage problems along with some distress in the RCC
members of the various rooms of the Room No. 43&44, C Wing
79
(a) (b)
(c) (d)
80
(e) (f)
(g) (h)
(i) (j)
81
(k) (l)
Figure 3.33. Photographs showing seepage/leakage problems along with some distress in the
RCC members, spalling of plaster concrete of walls of the various rooms of the Room No.
41&42, C Wing
(a) (b)
82
(c) (d)
(e) (f)
Figure 3.34. Photographs showing heavy distress in the Compound Wall
83
NDT PHOTOS
84
(a) (b)
(c) (d)
(e) (f)
Figure 3.35. Photographs showing Rebound Hammer Tests of external Columns of the A,B,C-
wings
85
(a) (b)
(c) (d)
(e) (f)
Figure 3.36. Photographs showing Ultrasonic Pulse Velocity Tests of external Columns of
A,B,C- wings
86
A-Wing
(a) (b)
(c)
Figure 3.37. Photographs showing Rebound Hammer Tests of internal Columns of the A-Wing
87
(a) (b)
(c) (d)
(e) (f)
Figure 3.38. Photographs showing Rebound Hammer Tests of internal Beams of A-Wing
88
(a) (b)
(c) (d)
(e)
Figure 3.39. Photographs showing Rebound Hammer Tests of internal Slabs of A Wing
89
(a) (b)
(c) (d)
Figure 3.40. Photographs showing Ultrasonic Pulse Velocity Tests of internal Columns of A-
Wing
90
(a) (b)
(c) (d)
(e)
91
Figure 3.41. Photographs showing Ultrasonic Pulse Velocity Tests of Beams of A-Wing
92
(a) (b)
(c) (d)
(e)
Figure 3.42. Photographs showing Ultrasonic Pulse Velocity Tests of Slabs of A-Wing
B-Wing
93
(a) (b)
(c)
Figure 3.43. Photographs showing Rebound Hammer Tests of internal Columns of B-Wing
(a) (b)
94
(c) (d)
(e)
Figure 3.44. Photographs showing Rebound Hammer Tests of internal Beams of B-Wing
(a) (b)
95
(c) (d)
Figure 3.45. Photographs showing Rebound Hammer Tests of internal Slabs of B-Wing
(a) (b)
96
(c)
Figure 3.46. Photographs showing Ultrasonic Pulse Velocity Tests of internal Columns of B
Wing
(a) (b)
(c) (d)
97
(e) (f)
Figure 3.47. Photographs showing Ultrasonic Pulse Velocity Tests of internal Beams of B-
Wing
98
(a) (b)
(c) (d)
Figure 3.48. Photographs showing Ultrasonic Pulse Velocity Tests of internal Slabs of B-Wing
C-Wing
99
(a) (b)
(c) (d)
Figure 3.49. Photographs showing Rebound Hammer Tests of internal Columns of C-Wing
(a) (b)
100
(c) (d)
Figure 3.50. Photographs showing Rebound Hammer Tests of internal Beams of C-Wing
101
(a) (b)
(c) (d)
Figure 3.51. Photographs showing Rebound Hammer Tests of internal Slabs of C-Wing
(a) (b)
102
(c) (d)
(e)
Figure 3.52. Photographs showing Ultrasonic Pulse Velocity Tests of internal Columns of C-
Wing
(a) (b)
103
(c) (d)
(e)
Figure 3.53. Photographs showing Ultrasonic Pulse Velocity Tests of internal Beams of C-
Wing
(a) (b)
104
(c) (d)
Figure 3.54. Photographs showing Ultrasonic Pulse Velocity Tests of internal Slabs of C-Wing
105
(a) (b)
(c) (d)
(e)
Figure 3.55. Photographs showing the external Carbonation Tests (common photos )
106
(a)
Figure 3.56. Photographs showing the internal Carbonation Tests of the B-Wing
(a) (b)
Figure 3.57. Photographs showing the internal Carbonation Tests of the C-Wing
107
(a) (b)
Figure 3.58. Photographs showing the external Half Cell Potentiometer Tests
(a)B-wing (b)C-wing
Figure 3.59. Photographs showing the internal Half Cell Potentiometer Tests
108
9. CONCLUDING REMARKS AND RECOMMENDATIONS
The ONGC buildings (A,B and C-Wing) located at DN Nagar were assessed
for its current structural condition based on visual observations and necessary NDT
tests. Based on the important observations and analysis, the following is concluded
and recommended:
2. Externally the RCC members., e.g extended beam and slabs, pardis/projections are
showing severe cracks/spalled concrete along the main reinforcement directions due to
corrosion.
3. Inside the building, mainly RCC slab has been distressed and have rebar exposed to
atmosphere. The internal rooms are also seen to have been affected primarily affected
reinforcement resulted from corrosion can be observed in some places. Typically, the
thinner RCC sections such as extended projections/pardis/ slabs as shown in the report
are being deteriorated. The original plastering work of the building (especially of the
slabs) appears to be of weak quality. However, no major distress was noticed in the
4. It shall be clearly noted that the repeated drying and wetting cycles caused by
excessive seepage and leakages, inadequate cover at places during construction and
reinforcements.
109
5. The primary source for the seepage and leakages are found to be deteriorated
plumbing lines around the toilet/canteen, additionally erected toilet adjacent to office
rooms, distressed/failed roof water proofing and projected areas from the windows
with inadequate slope/water proofing, worn out plasters/paintings, and structural and
non-structural cracks.
6. The NDT test results have indicated that the residual strength of concrete in
columns, beams and slabs is just adequate but have doubtful grading exhibiting some
aging and corrosion related events. The beam and slabs were found to be
comparatively weaker than columns. Moderate carbonation has taken place with about
7. The building will require major structural and non-structural repairs on extremely
urgent basis for structural safety and stability as per the general methodologies
provided below.
110
10. REFERENCES
Standards.
pulse velocity.
Structures.
111