USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 1 of 16
IN THE UNITED STATES COURT OF APPEALS
FOR THE DISTRICT OF COLUMBIA CIRCUIT
SIERRA CLUB, APPALACHIAN VOICES, )
INDIAN CREEK WATERSHED )
ASSOCIATION, PRESERVE CRAIG, )
SAVE MONROE, AND WILD VIRGINIA )
)
Petitioners, )
)
v. ) No. 21-1040
) (consolidated with 20-1512)
FEDERAL ENERGY REGULATORY )
COMMISSION, )
)
Respondent. )
_________________________________________)
MOTION OF PUBLIC SERVICE COMPANY OF NORTH CAROLINA
FOR LEAVE TO INTERVENE AS A PARTY RESPONDENT
Under Federal Rules of Appellate Procedure 15(d) and 27 and this Court’s
local rules, the Public Service Company of North Carolina, Incorporated, d/b/a
Dominion Energy North Carolina (“PSNC”), moves to intervene in the above-
captioned proceeding as a party respondent. 1
1
PSNC recognizes that the Court has issued a scheduling order regarding
Petitioners’ emergency motion for a stay pending judicial review and will abide by
that schedule if its motion is granted. It does not intend to seek permission to file a
separate brief from other Intervenors-Respondents.
1
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 2 of 16
I. Background
PSNC is a South Carolina corporation with its principal place of business in
Gastonia, North Carolina. It operates a natural gas pipeline system for the
transportation, distribution, and sale of gas within a service territory covering all or
part of 28 North Carolina counties. Regulated by the North Carolina Utilities
Commission, PSNC currently serves approximately 600,000 customers, including
residential, commercial, and industrial demand.
In Mountain Valley Pipeline, LLC, Order Partially Lifting Stop Work Orders
and Allowing Certain Construction to Resume, 173 FERC ¶ 61,252 (Dec. 17, 2020)
(“December Construction Order”), the Commission authorized Mountain Valley
Pipeline, LLC (“MVP”) to resume construction on parts of a 300-mile natural gas
pipeline originally approved by the Commission in Mountain Valley Pipeline, LLC,
161 FERC ¶ 61,043 (2017) (“Certificate Order”). The portions to be resumed are
parts of MVP’s Mainline System, which will connect with MVP’s Southgate Project.
Specifically, the Southgate Project would extend the Mainline with 75 miles of new
pipeline capable of carrying 375,000 dekatherms per day of natural gas to the local
distribution facilities of movant PSNC. Mountain Valley Pipeline, LLC, Order
Issuing Certificate (“Southgate Order”), 171 FERC ¶ 61,232 (2020).
To meet its customers’ growing demand for natural gas, and head off a
projected shortfall in its supply, PSNC has subscribed to 250,000 dekatherms per
2
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 3 of 16
day of transportation capacity on the Mainline. PSNC has also entered into a
precedent agreement with MVP for 300,000 dekatherms per day of firm
transportation service on the Southgate Project, or 80% of the project capacity. See
id. at 3. The agreement requires PSNC to make a 20-year commitment to pay for
such firm transportation service. Id. The Southgate Project will draw from, and
depends on, the Mainline System at issue in the December Construction Order.
When Petitioners sought rehearing of the December Construction Order, the
Commission issued a Notice of Denial of Rehearing by Operation of Law and
Providing for Further Consideration, 174 FERC ¶ 62,0366 (Jan. 19, 2021)
(“Rehearing Order”). Petitioners seek review of both the December Construction
Order and the Rehearing Order. PSNC now moves to intervene as of right.
II. Argument
Under Rule 15(d) of the Federal Rules of Appellate Procedure, a party moving
to intervene in a petition to review agency action must do so “within 30 days after
the petition for review is filed,” and its motion “must contain a concise statement of
[its] interest . . . and the grounds for intervention.” The “interest” test is not unduly
restrictive but rather “is primarily a practical guide to disposing of lawsuits by
involving as many apparently concerned persons as is compatible with efficiency
and due process.” Nuesse v. Camp, 385 F.2d 694, 700 (D.C. Cir. 1967).
3
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 4 of 16
A. PSNC Has Standing To Intervene.
This Court has at times required would-be intervenors to establish their own
Article III standing. Deutsche Bank Nat’l Trust Co. v. FDIC, 717 F.3d 189, 193
(D.C. Cir. 2013). But the Supreme Court has recently clarified that intervenors need
do so only when they seek relief “broader than or different from” the relief sought
by “the party invoking a court’s jurisdiction.” Little Sisters of the Poor Saints Peter
& Paul Home v. Pennsylvania, 140 S. Ct. 2367, 2379 n.6 (2020). Here PSNC will
seek nothing but what the Commission seeks and what Petitioners oppose: dismissal
or denial of the petition challenging the orders at issue.
In any case, PSNC’s showing on the criteria for intervention as of right,
discussed below, suffices to establish its Article III standing as well. “It is axiomatic
that Article III requires a showing of injury-in-fact, causation, and redressability.”
Deutsche Bank, 717 F.3d at 193. PSNC’s financial stake in maintenance of the
Commission’s orders—which gives it enough of a stake in the outcome to justify
intervention, as explained below, see infra Part II.B—also gives PSNC a legally
cognizable interest for standing purposes, see Fund for Animal, Inc. v. Nortons, 322
F.3d 728, 735 (D.C. Cir. 2003) (showing for Article III injury-in-fact is coextensive
with showing for legally protected interest for purpose of intervention as of right).
Likewise, since the relief that Petitioners seek would harm PSNC’s financial
interests, granting that relief would “cause [PSNC] injury,” and a “judgment
4
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 5 of 16
preventing” the relief would “redress” (or prevent) any injury. Lujan v. Defs. of
Wildlife, 504 U.S. 555, 561–62 (1992).
B. PSNC Satisfies the Criteria for Intervention.
Besides standing, PSNC has valid grounds for intervening. The Federal Rules
of Appellate Procedure establish no specific criteria for intervention, but this Court
has held that “intervention in the court of appeals is governed by the same standards
as in the district court” under Federal Rule of Civil Procedure 24. Massachusetts
Sch. of Law at Andover, Inc. v. United States, 118 F.3d 776, 779 (D.C. Cir. 1997)
(citation omitted). Under that Rule, parties may intervene as of right, “upon timely
application,” if they claim “an interest relating to the property or transaction” at stake
and if the outcome “may as a practical matter impair” their ability to protect that
interest, “unless the applicant’s interest is adequately represented by existing
parties.” Fed. R. Civ. P. 24(a)(2). This Court has thus identified four conditions for
intervention as of right: “(1) the application to intervene must be timely; (2) the
applicant must demonstrate a legally protected interest in the action; (3) the action
must threaten to impair that interest; and (4) no party to the action can be an adequate
representative of the applicant’s interests.” Karsner v. Lothian, 532 F.3d 876, 885
(D.C. Cir. 2008) (citation omitted). PSNC meets all four criteria.
5
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 6 of 16
1. Timeliness
PSNC satisfies the first factor because this motion to intervene is timely. It
has been filed within 30 days of the filing of the petition for review, as required by
Federal Rule of Appellate Procedure 15(d).
2. Possible Impairment to Legally Protected Interest
PSNC also satisfies the second and third factors: a legally protected interest
that would be impaired by an adverse decision. This Court will recognize a legally
protected interest and threat of impairment “where a party benefits from agency
action, the action is then challenged in court, and an unfavorable decision would
remove the party’s benefit.” Crossroads Grassroots Policy Strategies v. FEC, 788
F.3d 312, 317, 320 (D.C. Cir. 2015). In such cases, this Court has freely allowed
intervention. For example,
[i]n Fund For Animals, [Inc. v. Norton, 322 F.3d 728, 735
(2003)], the Natural Resources Department of the Ministry
of Nature and Environment of Mongolia (“NRD”) sought
to intervene as a defendant in a suit challenging action by
the Fish and Wildlife Service (“FWS”). 322 F.3d at 730.
The Fund for Animals challenged FWS’ failure to classify
argali sheep as an endangered species. NRD sought to
intervene as a defendant, alleging that, if the district court
overturned the Secretary’s order and argali sheep were
declared endangered species, Mongolia would lose tourist
dollars associated with sheep hunting and a consequent
reduction in funding for its conservation program. Id. at
733. We found NRD’s “threatened loss of tourist dollars”
and the “consequent reduction in funding for Mongolia’s
conservation program” constituted a “concrete and
imminent injury.” Id.
6
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 7 of 16
Crossroads, 788 F.3d at 317. In other words, because the EPA’s refusal to protect
a certain species enhanced a certain country’s appeal to hunters, the EPA’s
protection of the species would have deprived that country of tourism revenue,
which would have lowered its funding for conservation efforts. This attenuated
causal chain sufficed to give the country’s environmental ministry a concrete interest
in defending the EPA’s inaction for purposes of intervention.
Here the causal connection is far more direct: the completion of the Mainline
System is essential for PSNC to obtain needed natural gas to supply its customers.
PSNC has contracted to use 250,000 dekatherms per day of Mainline transportation
capacity itself. But PSNC also plans to meet customers’ needs through the Southgate
Project, which depends on the Mainline. Indeed, it has committed to use 80% of the
Southgate Project’s capacity for natural gas transportation—300,000 dekatherms per
day—for an initial term of 20 years. See Certificate Order at 9–10. The Southgate
Project also will benefit customers by giving PSNC additional options to select cost-
effective supply sources. See id. at 10. Thus, the fact that the Southgate Project
depends on the Mainline System (of which Southgate is an extension) only
reinforces PSNC’s direct interest in the Mainline. Both projects give PSNC a
financial stake concrete and particularized enough to establish a legally protected
interest, for intervention purposes, in the Mainline System’s completion—and thus
in the defense of the orders at issue here, without which the Mainline’s completion
7
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 8 of 16
would be legally impossible. For several reasons, then, PSNC has a legally protected
interest that could be impaired by the outcome of this review proceeding.
3. Lack of Assured Adequate Representation
Finally, the fourth factor, inadequacy of representation of the party’s interests,
is satisfied. While there may be no right to intervene if the movant’s interest is
“adequately represent[e]d” by existing parties, Fed. R. Civ. P. 24(a)(2), a movant
need only show “that representation of his interest” by the other parties “‘may be’
inadequate,” Trbovich v. United Mine Workers of America, 404 U.S. 528, 538 n.10
(1972) (emphasis added). And “the burden of making that showing should be treated
as minimal,” id., “not onerous,” Fund for Animals, 322 F.3d at 735 (internal citation
omitted). Mere “general agreement” between an existing party’s positions and those
of a would-be intervenor is not enough to ensure adequate representation. Id. at 737.
In particular, this Court “look[s] skeptically on government entities serving as
adequate advocates for private parties.” Crossroads, 788 F.3d at 321. Above all,
“this circuit recognize[s] the inadequacy of governmental representation of the
interests of private parties” where the private parties have a financial stake in an
outcome but the government does not. Dimond v. District of Columbia, 792 F.2d
179, 192 (D.C. Cir. 1986). For while governmental entities are “charged by law with
representing the public interest of [the] citizens,” private corporations are “seeking
to protect more narrow and ‘parochial’ financial interest not shared by the citizens.”
8
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 9 of 16
Id. at 192–93. Under such circumstances, “no presumption exists that the
[government] will adequately represent” the private party’s interests. Id. at 193.
That is the case here. As a private corporation that buys natural gas for sale
and distribution to consumers, PSNC stands to gain financially from the increased
capacity and efficiencies promised by the Mountain Valley Pipeline. The
Commission does not. This suffices to rebut any suggestion that the Commission
could adequately represent PSNC’s interests.
CONCLUSION
For the foregoing reasons, PSNC respectfully asks this Court to grant its
motion to intervene as party respondent in the above-captioned appeal.
Dated: February 3, 2021 Respectfully submitted,
/s/ Charlotte Taylor
Charlotte Taylor
Sherif Girgis
JONES DAY
51 Louisiana Ave. NW
Washington, DC 20001
Telephone: (202) 879-3939
[email protected] [email protected] James Olson
JONES DAY
717 Texas St. #3300
Houston, TX 77002
Telephone: (832) 239-3939
[email protected]
9
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 10 of 16
B. Craig Collins
Dominion Energy Services, Inc.
Mail Code C222
220 Operation Way
Cayce, South Carolina 29033-2701
Telephone: (803) 217-7513
[email protected]
Attorneys for Public Service Company of
North Carolina, Incorporated
10
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 11 of 16
IN THE UNITED STATES COURT OF APPEALS
FOR THE DISTRICT OF COLUMBIA CIRCUIT
SIERRA CLUB, APPALACHIAN VOICES, )
INDIAN CREEK WATERSHED )
ASSOCIATION, PRESERVE CRAIG, )
SAVE MONROE, AND WILD VIRGINIA )
)
Petitioners, )
)
v. ) No. 21-1040
) (consolidated with 20-1512)
FEDERAL ENERGY REGULATORY )
COMMISSION, )
)
Respondent. )
_________________________________________)
CERTIFICATE OF COMPLIANCE
This motion complies with the typeface requirements of Fed. R. App. P.
32(a)(5) and type-style requirements of Fed. R. App. P. 32(a)(6) because this motion
has been prepared in 14-point Times New Roman font using Microsoft Word.
This motion complies with the word-count limitation of Fed. R. App. P.
27(d)(2) because this motion contains 1,864 words.
Dated: February 3, 2021 Respectfully submitted,
s/ Charlotte Taylor
Charlotte Taylor
JONES DAY
51 Louisiana Ave. NW
Washington, DC 20001
1
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 12 of 16
Telephone: (202) 879-3939
[email protected] 2
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 13 of 16
IN THE UNITED STATES COURT OF APPEALS
FOR THE DISTRICT OF COLUMBIA CIRCUIT
SIERRA CLUB, APPALACHIAN VOICES, )
INDIAN CREEK WATERSHED )
ASSOCIATION, PRESERVE CRAIG, )
SAVE MONROE, AND WILD VIRGINIA )
)
Petitioners, )
)
v. ) No. 21-1040
) (consolidated with 20-1512)
FEDERAL ENERGY REGULATORY )
COMMISSION, )
)
Respondent. )
_________________________________________)
CORPORATE DISCLOSURE STATEMENT OF
PUBLIC SERVICE COMPANY OF NORTH CAROLINA
Pursuant to Federal Rule of Appellate Procedure 26.1 and D.C. Circuit Rule
26.1, Public Service Company of North Carolina, Incorporated, d/b/a Dominion
Energy North Carolina, makes the following disclosures:
Public Service Company of North Carolina, Incorporated, is an energy
company incorporated in South Carolina, with its principal place of business in
Gastonia, North Carolina. It operates a natural gas pipeline system for the
transportation, distribution, and sale of gas within a service territory covering parts
of North Carolina.
1
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 14 of 16
Public Service Company of North Carolina, Incorporated, is a wholly owned
subsidiary of SCANA Corporation, which is wholly owned by Dominion Energy,
Inc. No publicly held corporation owns more than 10% of the stock of Dominion
Energy, Inc.
Dated: February 3, 2021 Respectfully submitted,
s/ Charlotte Taylor
Charlotte Taylor
JONES DAY
51 Louisiana Ave. NW
Washington, DC 20001
Telephone: (832) 239-3866
[email protected]
2
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 15 of 16
IN THE UNITED STATES COURT OF APPEALS
FOR THE DISTRICT OF COLUMBIA CIRCUIT
SIERRA CLUB, APPALACHIAN VOICES, )
INDIAN CREEK WATERSHED )
ASSOCIATION, PRESERVE CRAIG, )
SAVE MONROE, AND WILD VIRGINIA )
)
Petitioners, )
)
v. ) No. 21-1040
) (consolidated with 20-1512)
FEDERAL ENERGY REGULATORY )
COMMISSION, )
)
Respondent. )
_________________________________________)
CERTIFICATE OF SERVICE
Pursuant to Rule 25 of the Federal Rules of Appellate Procedure, I hereby
certify that on February 3, 2021, I electronically filed the foregoing Motion of Public
Service Company of North Carolina, Incorporated For Leave to Intervene As Party
Respondent, and the Corporate Disclosure Statement, with the Clerk of the Court for
the U.S. Court of Appeals for the District of Columbia Circuit by using the appellate
CM/ECF system, and served copies of the foregoing via the Court’s CM/ECF system
on all ECF registered counsel.
Dated at Washington, DC, this 3rd day of February, 2021.
1
USCA Case #21-1040 Document #1883630 Filed: 02/03/2021 Page 16 of 16
/s/ Charlotte Taylor
Charlotte Taylor
Attorney for Public Service Company of
North Carolina, Incorporated