NSCR Project CP01 Schedule Overview

This document provides a schedule for the North South Commuter Rail Project Package CP01 from February 2021 to May 2021. It outlines the key activities and their timelines related to documents submittals, erection works, precast yard construction, segment fabrication, and casting cell assembly. The segment fabrication is scheduled to be completed by March 15, 2021 while the overall project is scheduled to be finished by May 24, 2021.

Uploaded by

Marky
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
240 views8 pages

NSCR Project CP01 Schedule Overview

This document provides a schedule for the North South Commuter Rail Project Package CP01 from February 2021 to May 2021. It outlines the key activities and their timelines related to documents submittals, erection works, precast yard construction, segment fabrication, and casting cell assembly. The segment fabrication is scheduled to be completed by March 15, 2021 while the overall project is scheduled to be finished by May 24, 2021.

Uploaded by

Marky
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

 

North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
1/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03

North South Commuter Rail Project - Package CP01_(01022021) 179.35 02-Oct-20 A 24-May-21

61.00 03-Feb-21 05-Apr-21 05-Apr-21, DOCUMENTS SUBMITTALS


DOCUMENTS SUBMITTALS
0.00 03-Feb-21 03-Feb-21 03-Feb-21, 3. Launching Gantry
3. Launching Gantry
3.1 Method Statements 0.00 03-Feb-21 03-Feb-21 03-Feb-21, 3.1 Method Statements
N-VSL-SMT-1080 Submit to TDJV - MS2 - Gantry Launching,Testing & Commissioning 0.00 03-Feb-21* Submit to TDJV - MS2 - Gantry Launching,Testing & Commissioning
58.00 06-Feb-21 05-Apr-21 05-Apr-21, 4. Erection
4. Erection
4.1 Method Statements 58.00 06-Feb-21 05-Apr-21 05-Apr-21, 4.1 Method Statements
N-VSL-SMT-1100 Submit to TDJV - MS1 - Span Erection Works 0.00 06-Feb-21* Submit to TDJV - MS1 - Span Erection Works
N-VSL-SMT-1150 Submit to TDJV - MS6 - Starting & Closure Span 0.00 12-Feb-21* Submit to TDJV - MS6 - Starting & Closure Span
N-VSL-SMT-1140 Submit to TDJV - MS5 - Permanent Post Tensioning Works 0.00 17-Feb-21* Submit to TDJV - MS5 - Permanent Post Tensioning Works
N-VSL-SMT-1180 Submit to TDJV - MS7 - Erection of Precast Segment on Scaffolding 0.00 16-Mar-21* Submit to TDJV - MS7 - Erection of Precast Segment on Scaffolding
N-VSL-SMT-1190 Submit to TDJV - MS8 - Launching Gantry Dis-assembly 0.00 05-Apr-21* Submit to TDJV - MS8 - Launching Gantry Dis-assembly

PRECAST YARD, CONSTRUCTION, PROCUREMENT, DELIVERY & 230.00 02-Oct-20 A 19-May-21


INSTALLATION
165.00 02-Oct-20 A 15-Mar-21 15-Mar-21, 1. Segment Fabrication
1. Segment Fabrication
1.1 Precasting Sheds 121.00 02-Oct-20 A 04-Feb-21 04-Feb-21, 1.1 Precasting Sheds

1.1.3 Shed #2 67.00 02-Oct-20 A 04-Feb-21 04-Feb-21, 1.1.3 Shed #2

1.1.3.2 Steel Structure 67.00 02-Oct-20 A 04-Feb-21 04-Feb-21, 1.1.3.2 Steel Structure
N-VSL-PCY-1070 Erection of steel structure and Install Panels [P2] 67.00 02-Oct-20 A 04-Feb-21 04-Feb-21, Erection of steel structure and Install Panels [P2]
1.1.4 Utility Network 109.00 14-Oct-20 A 02-Feb-21 02-Feb-21, 1.1.4 Utility Network
N-VSL-PCY-1500 Shed Electrical Connections 109.00 14-Oct-20 A 02-Feb-21 02-Feb-21, Shed Electrical Connections
1.2 Casting Cells 135.00 05-Oct-20 A 28-Feb-21 28-Feb-21, 1.2 Casting Cells

1.2.1 Field Segment Double Track - C1 81.00 28-Nov-20 A 28-Feb-21 28-Feb-21, 1.2.1 Field Segment Double Track - C1

1.2.1.7 Field Segment Double Track - C1 #7 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, 1.2.1.7 Field Segment Double Track - C1 #7
N-VSL-PCY-1100 Casting cells assembly 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, Casting cells assembly
1.2.1.8 Field Segment Double Track - C1 #8 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, 1.2.1.8 Field Segment Double Track - C1 #8
N-VSL-PCY-1350 Casting cells assembly 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, Casting cells assembly
1.2.1.9 Field Segment Double Track - C1 #9 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, 1.2.1.9 Field Segment Double Track - C1 #9
N-VSL-PCY-1360 Casting cells assembly 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, Casting cells assembly
1.2.1.10 Field Segment Double Track - C1 #10 30.00 04-Jan-21 A 10-Feb-21 10-Feb-21, 1.2.1.10 Field Segment Double Track - C1 #10
N-VSL-PCY-1110 Casting cells assembly 30.00 04-Jan-21 A 10-Feb-21 10-Feb-21, Casting cells assembly
1.2.1.11 Field Segment Double Track - C1 #11 30.00 04-Jan-21 A 28-Feb-21 28-Feb-21, 1.2.1.11 Field Segment Double Track - C1 #11
N-VSL-PCY-1370 Casting cells assembly 30.00 04-Jan-21 A 28-Feb-21 28-Feb-21, Casting cells assembly
1.2.1.11 Field Segment Double Track - C1 #12 30.00 04-Jan-21 A 28-Feb-21 28-Feb-21, 1.2.1.11 Field Segment Double Track - C1 #12
N-VSL-PCY-1380 Casting cells assembly 30.00 04-Jan-21 A 28-Feb-21 28-Feb-21, Casting cells assembly
1.2.2 Pier Segment Double Track - C2 36.00 01-Dec-20 A 28-Feb-21 28-Feb-21, 1.2.2 Pier Segment Double Track - C2

1.2.2.1 Pier Segment Double Track - C2 #1 30.00 01-Dec-20 A 03-Feb-21 03-Feb-21, 1.2.2.1 Pier Segment Double Track - C2 #1
N-VSL-PCY-1120 Casting cells assembly 30.00 01-Dec-20 A 03-Feb-21 03-Feb-21, Casting cells assembly
1.2.2.2 Pier Segment Double Track - C2 #2 30.00 01-Dec-20 A 03-Feb-21 03-Feb-21, 1.2.2.2 Pier Segment Double Track - C2 #2
N-VSL-PCY-1390 Casting cells assembly 30.00 01-Dec-20 A 03-Feb-21 03-Feb-21, Casting cells assembly
1.2.2.3 Pier Segment Double Track - C2 #3 30.00 07-Dec-20 A 28-Feb-21 28-Feb-21, 1.2.2.3 Pier Segment Double Track - C2 #3
N-VSL-PCY-1130 Casting cells assembly 30.00 07-Dec-20 A 28-Feb-21 28-Feb-21, Casting cells assembly
1.2.2.4 Pier Segment Double Track - C2 #4 30.00 07-Dec-20 A 28-Feb-21 28-Feb-21, 1.2.2.4 Pier Segment Double Track - C2 #4
N-VSL-PCY-1400 Casting cells assembly 30.00 07-Dec-20 A 28-Feb-21 28-Feb-21, Casting cells assembly
Date Revision Checked Approved
Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
                          
 
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
2/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
1.2.3 Field Segment Single Track - C3 88.00 05-Oct-20 A 12-Feb-21 12-Feb-21, 1.2.3 Field Segment Single Track - C3
1.2.3.1 Field Segment Single Track - C3 #1 88.00 05-Oct-20 A 11-Feb-21 11-Feb-21, 1.2.3.1 Field Segment Single Track - C3 #1
N-VSL-PCY-1140 Casting cells assembly 88.00 05-Oct-20 A 11-Feb-21 11-Feb-21, Casting cells assembly
1.2.3.2 Field Segment Single Track - C3 #2 46.00 26-Oct-20 A 11-Feb-21 11-Feb-21, 1.2.3.2 Field Segment Single Track - C3 #2
N-VSL-PCY-1410 Casting cells assembly 46.00 26-Oct-20 A 11-Feb-21 11-Feb-21, Casting cells assembly
1.2.3.3 Field Segment Single Track - C3 #3 85.00 08-Oct-20 A 12-Feb-21 12-Feb-21, 1.2.3.3 Field Segment Single Track - C3 #3
N-VSL-PCY-1150 Casting cells assembly 85.00 08-Oct-20 A 12-Feb-21 12-Feb-21, Casting cells assembly
1.2.3.4 Field Segment Single Track - C3 #4 46.00 26-Oct-20 A 12-Feb-21 12-Feb-21, 1.2.3.4 Field Segment Single Track - C3 #4
N-VSL-PCY-1420 Casting cells assembly 46.00 26-Oct-20 A 12-Feb-21 12-Feb-21, Casting cells assembly
1.2.3.5 Field Segment Single Track - C3 #5 46.00 26-Oct-20 A 12-Feb-21 12-Feb-21, 1.2.3.5 Field Segment Single Track - C3 #5
N-VSL-PCY-1430 Casting cells assembly 46.00 26-Oct-20 A 12-Feb-21 12-Feb-21, Casting cells assembly
1.2.4 Pier Segment Single Track - C4 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, 1.2.4 Pier Segment Single Track - C4
1.2.4.1 Pier Segment Single Track - C4 #2 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, 1.2.4.1 Pier Segment Single Track - C4 #2
N-VSL-PCY-1160 Casting cells assembly 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, Casting cells assembly
1.2.4.2 Pier Segment Single Track - C4 #2 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, 1.2.4.2 Pier Segment Single Track - C4 #2
N-VSL-PCY-1440 Casting cells assembly 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, Casting cells assembly
1.3 Overhead Crane - 10 Tons (9 Units) 30.00 04-Jan-21 A 25-Feb-21 25-Feb-21, 1.3 Overhead Crane - 10 Tons (9 Units)

1.3.3 3rd Batch (3 Units) 30.00 04-Jan-21 A 25-Feb-21 25-Feb-21, 1.3.3 3rd Batch (3 Units)
N-VSL-PCY-1190 Overhead Crane assembly 30.00 04-Jan-21 A 25-Feb-21 25-Feb-21, Overhead Crane assembly
1.4 Straddle Carrier (3 Units) 43.00 01-Feb-21 15-Mar-21 15-Mar-21, 1.4 Straddle Carrier (3 Units)

1.4.1 1st Unit 20.00 12-Feb-21 04-Mar-21 04-Mar-21, 1.4.1 1st Unit
N-VSL-PRC-1500 Delivery to site 0.00 12-Feb-21* Delivery to site
N-VSL-PCY-1200 Straddle Carrier assembly 20.00 13-Feb-21 04-Mar-21 04-Mar-21, Straddle Carrier assembly
1.4.2 2nd Unit 36.00 01-Feb-21 08-Mar-21 08-Mar-21, 1.4.2 2nd Unit

1.4.2.1 Structure & Walkways_China 15.00 01-Feb-21 15-Feb-21 15-Feb-21, 1.4.2.1 Structure & Walkways_China
N-VSL-PCY-1510 Straddle Carrier assembly 15.00 01-Feb-21 15-Feb-21 15-Feb-21, Straddle Carrier assembly
1.4.2.2 Other Parts_Italy 28.00 08-Feb-21 08-Mar-21 08-Mar-21, 1.4.2.2 Other Parts_Italy
N-VSL-PRC-1520 Arrival at Manila Port 0.00 08-Feb-21 Arrival at Manila Port
N-VSL-PRC-1530 Delivery to site 0.00 26-Feb-21* Delivery to site
N-VSL-PCY-1210 Straddle Carrier assembly 10.00 27-Feb-21 08-Mar-21 08-Mar-21, Straddle Carrier assembly
1.4.3 3rd Unit 43.00 01-Feb-21 15-Mar-21 15-Mar-21, 1.4.3 3rd Unit
1.4.3.1 Structure & Walkways_China 15.00 01-Feb-21 15-Feb-21 15-Feb-21, 1.4.3.1 Structure & Walkways_China
N-VSL-PCY-1520 Straddle Carrier assembly 15.00 01-Feb-21 15-Feb-21 15-Feb-21, Straddle Carrier assembly
1.4.3.2 Other Parts_Italy 32.00 11-Feb-21 15-Mar-21 15-Mar-21, 1.4.3.2 Other Parts_Italy
N-VSL-PRC-1550 Arrival at Manila Port 0.00 11-Feb-21* Arrival at Manila Port
N-VSL-PRC-1560 Delivery to site 0.00 05-Mar-21* Delivery to site
N-VSL-PCY-1220 Straddle Carrier assembly 10.00 06-Mar-21 15-Mar-21 15-Mar-21, Straddle Carrier assembly
129.00 16-Jan-21 A 19-May-21
2. Segment Erection
2.1 Launching Girder (4 Units) 129.00 16-Jan-21 A 19-May-21

2.1.1 Launching Girder #1 (Valenzuela Area) 84.00 02-Feb-21 27-Apr-21 27-Apr-21, 2.1.1 Launchin

2.1.1.1 Main Truss 58.00 01-Mar-21 27-Apr-21 27-Apr-21, 2.1.1.1 Main Tr


N-VSL-PRC-1570 Departure from Factory (Malaysia) 0.00 01-Mar-21* Departure from Factory (Malaysia)
N-VSL-PRC-1580 Arrival at Manila Port 0.00 15-Mar-21 Arrival at Manila Port
N-VSL-PRC-1590 Delivery to site 0.00 19-Mar-21 Delivery to site

Date Revision Checked Approved


Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
                          
 
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
3/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
N-VSL-PCY-1230 Main Truss Unloading, Pre-assembly & Assembly 40.00 19-Mar-21 27-Apr-21 27-Apr-21, Main Truss Unl
2.1.1.2 Equipment 49.00 02-Feb-21 23-Mar-21 23-Mar-21, 2.1.1.2 Equipment
N-VSL-PRC-1620 Delivery to site (from Malaysia) 0.00 02-Feb-21 Delivery to site (from Malaysia)
N-VSL-PRC-1640 Arrival at Manila Port (from China) 0.00 08-Feb-21 Arrival at Manila Port (from China)
N-VSL-PRC-1650 Delivery to site (from China) 0.00 12-Feb-21 Delivery to site (from China)
N-VSL-PCY-1240 Equipment Unloading, Pre-assembly & Assembly 40.00 12-Feb-21 23-Mar-21 23-Mar-21, Equipment Unloading, Pre-assembly & Assembly
2.1.2 Launching Girder #2 (Meycauayan -1st LG) 71.00 16-Jan-21 A 22-Mar-21 22-Mar-21, 2.1.2 Launching Girder #2 (Meycauayan -1st LG)
2.1.2.1 Main Truss 49.00 01-Feb-21 22-Mar-21 22-Mar-21, 2.1.2.1 Main Truss
N-VSL-PRC-1670 Arrival at Manila Port 0.00 01-Feb-21 Arrival at Manila Port
N-VSL-PRC-1680 Delivery to site 0.00 04-Feb-21 Delivery to site
N-VSL-PCY-1250 Main Truss Unloading, Pre-assembly & Assembly 46.00 05-Feb-21 22-Mar-21 22-Mar-21, Main Truss Unloading, Pre-assembly & Assembly
2.1.2.2 Equipment 46.00 16-Jan-21 A 09-Mar-21 09-Mar-21, 2.1.2.2 Equipment
N-VSL-PCY-1260 Equipment Unloading, Pre-assembly & Assembly 46.00 16-Jan-21 A 09-Mar-21 09-Mar-21, Equipment Unloading, Pre-assembly & Assembly
N-VSL-PRC-1700 Arrival at Manila Port (from Malaysia) 0.00 12-Feb-21 Arrival at Manila Port (from Malaysia)
N-VSL-PRC-1710 Delivery to site (from Malaysia) 0.00 16-Feb-21 Delivery to site (from Malaysia)
2.1.3 Launching Girder #3 (Bocaue Area) 73.00 01-Feb-21 14-Apr-21 14-Apr-21, 2.1.3 Launching Girder #3 (Bocaue Ar

2.1.3.1 Main Truss 58.00 16-Feb-21 14-Apr-21 14-Apr-21, 2.1.3.1 Main Truss
N-VSL-PRC-1750 Departure from Factory (Malaysia) 0.00 16-Feb-21* Departure from Factory (Malaysia)
N-VSL-PRC-1760 Arrival at Manila Port 0.00 02-Mar-21 Arrival at Manila Port
N-VSL-PRC-1770 Delivery to site 0.00 06-Mar-21 Delivery to site
N-VSL-PCY-1270 Main Truss Unloading, Pre-assembly & Assembly 40.00 06-Mar-21 14-Apr-21 14-Apr-21, Main Truss Unloading, Pre-assembly &
2.1.3.2 Equipment 55.00 01-Feb-21 27-Mar-21 27-Mar-21, 2.1.3.2 Equipment
N-VSL-PRC-1790 Arrival at Manila Port (from Malaysia) 0.00 01-Feb-21 Arrival at Manila Port (from Malaysia)
N-VSL-PRC-1820 Arrival at Manila Port (from China) 0.00 01-Feb-21 Arrival at Manila Port (from China)
N-VSL-PRC-1800 Delivery to site (from Malaysia) 0.00 04-Feb-21 Delivery to site (from Malaysia)
N-VSL-PCY-1280 Equipment Unloading, Pre-assembly & Assembly 40.00 16-Feb-21 27-Mar-21 27-Mar-21, Equipment Unloading, Pre-assembly & Assembly
2.1.4 Launching Girder #4 (after Bocaue Station) 105.00 04-Feb-21 19-May-21

2.1.4.1 Main Truss 59.00 22-Mar-21 19-May-21


N-VSL-PRC-1840 Departure from Factory (Malaysia) 0.00 22-Mar-21* Departure from Factory (Malaysia)
N-VSL-PRC-1850 Arrival at Manila Port 0.00 05-Apr-21 Arrival at Manila Port
N-VSL-PRC-1860 Delivery to site 0.00 09-Apr-21 Delivery to site
N-VSL-PCY-1290 Main Truss Unloading, Pre-assembly & Assembly 40.00 10-Apr-21 19-May-21
2.1.4.2 Equipment 73.00 04-Feb-21 18-Apr-21 18-Apr-21, 2.1.4.2 Equipment
N-VSL-PRC-1900 Departure from Factory (China) 0.00 04-Feb-21* Departure from Factory (China)
N-VSL-PRC-1910 Arrival at Manila Port 0.00 15-Feb-21 Arrival at Manila Port
N-VSL-PRC-1920 Delivery to site 0.00 19-Feb-21 Delivery to site
N-VSL-PCY-1300 Equipment Unloading, Pre-assembly & Assembly 40.00 19-Feb-21 30-Mar-21 30-Mar-21, Equipment Unloading, Pre-assembly & Assembly
N-VSL-PRC-1870 Departure from Factory (Malaysia) 0.00 31-Mar-21* Departure from Factory (Malaysia)
N-VSL-PRC-1880 Arrival at Manila Port 0.00 14-Apr-21 Arrival at Manila Port
N-VSL-PRC-1890 Delivery to site 0.00 18-Apr-21 Delivery to site
109.35 04-Jan-21 A 24-May-21
PRECAST PRODUCTION
93.05 04-Jan-21 A 04-May-21 04-May-21, 1.
1. Double Track Cells (10.3 meter Flange width)
1.5 Segment Activitity 93.05 04-Jan-21 A 04-May-21 04-May-21, 1.

1.5.1 Field Mould Double Track 93.05 04-Jan-21 A 04-May-21 04-May-21, 1.


1.5.1.1 Field Mould C1 #1 (T1 & T1M Segment Type) 92.05 04-Jan-21 A 03-May-21 03-May-21, 1.5.
Date Revision Checked Approved
Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
                          
 
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
4/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
N-VSL-FBC-4490-T1-02 VIA05-15M-T1M.01 3.00 04-Jan-21 A 03-Feb-21 03-Feb-21, VIA05-15M-T1M.01
N-VSL-FBC-4490-T1-03 VIA05-15M-T1.01 3.00 18-Jan-21 A 06-Feb-21 06-Feb-21, VIA05-15M-T1.01
N-VSL-FBC-4490-T1-04 VIA05-15M-T1.02 3.00 20-Jan-21 A 10-Feb-21 10-Feb-21, VIA05-15M-T1.02
N-VSL-FBC-4490-T1-05 VIA05-15M-T1.03 3.00 23-Jan-21 A 15-Feb-21 15-Feb-21, VIA05-15M-T1.03
N-VSL-FBC-4490-T1-06 VIA05-15M-T1.04 3.00 28-Jan-21 A 18-Feb-21 18-Feb-21, VIA05-15M-T1.04
N-VSL-FBC-4490-T1-07 VIA05-15M-T1.05 3.00 18-Feb-21 22-Feb-21 22-Feb-21, VIA05-15M-T1.05
N-VSL-FBC-4490-T1-08 VIA05-15M-T1.06 3.00 22-Feb-21 26-Feb-21 26-Feb-21, VIA05-15M-T1.06
N-VSL-FBC-4490-T1-09 VIA05-15M-T1.07 3.00 26-Feb-21 02-Mar-21 02-Mar-21, VIA05-15M-T1.07
N-VSL-FBC-2020-T1-02 VIA03-113M-T1M.01 2.00 27-Feb-21 02-Mar-21 02-Mar-21, VIA03-113M-T1M.01
N-VSL-FBC-4490-T1-10 VIA05-15M-T1.08 3.00 02-Mar-21 05-Mar-21 05-Mar-21, VIA05-15M-T1.08
N-VSL-FBC-2020-T1-03 VIA03-113M-T1.01 2.00 02-Mar-21 04-Mar-21 04-Mar-21, VIA03-113M-T1.01
N-VSL-FBC-2020-T1-04 VIA03-113M-T1.02 2.00 04-Mar-21 08-Mar-21 08-Mar-21, VIA03-113M-T1.02
N-VSL-FBC-4490-T1-11 VIA05-15M-T1M.02 3.00 05-Mar-21 10-Mar-21 10-Mar-21, VIA05-15M-T1M.02
N-VSL-FBC-2020-T1-05 VIA03-113M-T1.03 2.00 08-Mar-21 10-Mar-21 10-Mar-21, VIA03-113M-T1.03
N-VSL-FBC-2020-T1-06 VIA03-113M-T1.04 2.00 10-Mar-21 12-Mar-21 12-Mar-21, VIA03-113M-T1.04
N-VSL-FBC-2020-T1-07 VIA03-113M-T1.05 2.00 12-Mar-21 15-Mar-21 15-Mar-21, VIA03-113M-T1.05
N-VSL-FBC-2020-T1-08 VIA03-113M-T1.06 2.00 15-Mar-21 17-Mar-21 17-Mar-21, VIA03-113M-T1.06
N-VSL-FBC-2020-T1-09 VIA03-113M-T1.07 2.00 17-Mar-21 19-Mar-21 19-Mar-21, VIA03-113M-T1.07
N-VSL-FBC-2020-T1-10 VIA03-113M-T1M.02 2.00 19-Mar-21 22-Mar-21 22-Mar-21, VIA03-113M-T1M.02
N-VSL-FBC-2010-T1-02 VIA03-114M-T1M.01 2.00 22-Mar-21 24-Mar-21 24-Mar-21, VIA03-114M-T1M.01
N-VSL-FBC-2010-T1-03 VIA03-114M-T1.01 2.00 24-Mar-21 26-Mar-21 26-Mar-21, VIA03-114M-T1.01
N-VSL-FBC-2010-T1-04 VIA03-114M-T1.02 2.00 26-Mar-21 29-Mar-21 29-Mar-21, VIA03-114M-T1.02
N-VSL-FBC-2010-T1-05 VIA03-114M-T1.03 2.00 29-Mar-21 31-Mar-21 31-Mar-21, VIA03-114M-T1.03
N-VSL-FBC-2010-T1-06 VIA03-114M-T1.04 2.00 31-Mar-21 06-Apr-21 06-Apr-21, VIA03-114M-T1.04
N-VSL-FBC-2010-T1-07 VIA03-114M-T1.05 2.00 06-Apr-21 08-Apr-21 08-Apr-21, VIA03-114M-T1.05
N-VSL-FBC-2010-T1-08 VIA03-114M-T1.06 2.00 08-Apr-21 12-Apr-21 12-Apr-21, VIA03-114M-T1.06
N-VSL-FBC-2010-T1-09 VIA03-114M-T1.07 2.00 12-Apr-21 14-Apr-21 14-Apr-21, VIA03-114M-T1.07
N-VSL-FBC-2010-T1-10 VIA03-114M-T1M.02 2.00 14-Apr-21 16-Apr-21 16-Apr-21, VIA03-114M-T1M.02
N-VSL-FBC-2000-T1-02 VIA03-115M-T1M.01 1.00 16-Apr-21 17-Apr-21 17-Apr-21, VIA03-115M-T1M.01
N-VSL-FBC-2000-T1-03 VIA03-115M-T1.01 1.00 17-Apr-21 19-Apr-21 19-Apr-21, VIA03-115M-T1.01
N-VSL-FBC-2000-T1-04 VIA03-115M-T1.02 1.00 19-Apr-21 20-Apr-21 20-Apr-21, VIA03-115M-T1.02
N-VSL-FBC-2000-T1-05 VIA03-115M-T1.03 1.00 20-Apr-21 21-Apr-21 21-Apr-21, VIA03-115M-T1.03
N-VSL-FBC-2000-T1-06 VIA03-115M-T1.04 1.00 21-Apr-21 22-Apr-21 22-Apr-21, VIA03-115M-T1.04
N-VSL-FBC-2000-T1-07 VIA03-115M-T1.05 1.00 22-Apr-21 23-Apr-21 23-Apr-21, VIA03-115M-T1.05
N-VSL-FBC-2000-T1-08 VIA03-115M-T1.06 1.00 23-Apr-21 26-Apr-21 26-Apr-21, VIA03-115M-T1.0
N-VSL-FBC-2000-T1-09 VIA03-115M-T1.07 1.00 26-Apr-21 27-Apr-21 27-Apr-21, VIA03-115M-T1
N-VSL-FBC-2000-T1-10 VIA03-115M-T1.08 1.00 27-Apr-21 28-Apr-21 28-Apr-21, VIA03-115M-T
N-VSL-FBC-2000-T1-11 VIA03-115M-T1M.02 1.00 28-Apr-21 29-Apr-21 29-Apr-21, VIA03-115M
N-VSL-FBC-1980-T1-02 VIA03-117M-T1M.01 1.00 29-Apr-21 30-Apr-21 30-Apr-21, VIA03-117
N-VSL-FBC-1980-T1-03 VIA03-117M-T1.01 1.00 30-Apr-21 03-May-21 03-May-21, VIA
1.5.1.2 Field Mould C1 #2 (T1 & T1M Segment Type) 70.05 01-Feb-21 04-May-21 04-May-21, 1.
N-VSL-FBC-2030-T1-02 VIA03-112M-T1M.01 2.00 01-Feb-21 03-Feb-21 03-Feb-21, VIA03-112M-T1M.01
N-VSL-FBC-2030-T1-03 VIA03-112M-T1.01 2.00 03-Feb-21 05-Feb-21 05-Feb-21, VIA03-112M-T1.01
N-VSL-FBC-2030-T1-04 VIA03-112M-T1.02 2.00 05-Feb-21 08-Feb-21 08-Feb-21, VIA03-112M-T1.02
N-VSL-FBC-2030-T1-05 VIA03-112M-T1.03 2.00 08-Feb-21 10-Feb-21 10-Feb-21, VIA03-112M-T1.03
N-VSL-FBC-2030-T1-06 VIA03-112M-T1.04 2.00 10-Feb-21 13-Feb-21 13-Feb-21, VIA03-112M-T1.04

Date Revision Checked Approved


Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
                          
 
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
5/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
N-VSL-FBC-2030-T1-07 VIA03-112M-T1.05 2.00 13-Feb-21 16-Feb-21 16-Feb-21, VIA03-112M-T1.05
N-VSL-FBC-2030-T1-08 VIA03-112M-T1.06 2.00 16-Feb-21 18-Feb-21 18-Feb-21, VIA03-112M-T1.06
N-VSL-FBC-2030-T1-09 VIA03-112M-T1.07 2.00 18-Feb-21 20-Feb-21 20-Feb-21, VIA03-112M-T1.07
N-VSL-FBC-2030-T1-10 VIA03-112M-T1M.02 2.00 20-Feb-21 23-Feb-21 23-Feb-21, VIA03-112M-T1M.02
N-VSL-FBC-1990-T1-02 VIA03-116M-T1M.01 2.00 23-Feb-21 26-Feb-21 26-Feb-21, VIA03-116M-T1M.01
N-VSL-FBC-1990-T1-03 VIA03-116M-T1.01 2.00 26-Feb-21 01-Mar-21 01-Mar-21, VIA03-116M-T1.01
N-VSL-FBC-1990-T1-04 VIA03-116M-T1.02 2.00 01-Mar-21 03-Mar-21 03-Mar-21, VIA03-116M-T1.02
N-VSL-FBC-1990-T1-05 VIA03-116M-T1.03 2.00 03-Mar-21 05-Mar-21 05-Mar-21, VIA03-116M-T1.03
N-VSL-FBC-1990-T1-06 VIA03-116M-T1.04 2.00 05-Mar-21 09-Mar-21 09-Mar-21, VIA03-116M-T1.04
N-VSL-FBC-1990-T1-07 VIA03-116M-T1.05 2.00 09-Mar-21 11-Mar-21 11-Mar-21, VIA03-116M-T1.05
N-VSL-FBC-1990-T1-08 VIA03-116M-T1.06 2.00 11-Mar-21 13-Mar-21 13-Mar-21, VIA03-116M-T1.06
N-VSL-FBC-1990-T1-09 VIA03-116M-T1.07 2.00 13-Mar-21 16-Mar-21 16-Mar-21, VIA03-116M-T1.07
N-VSL-FBC-1990-T1-10 VIA03-116M-T1.08 2.00 16-Mar-21 18-Mar-21 18-Mar-21, VIA03-116M-T1.08
N-VSL-FBC-1990-T1-11 VIA03-116M-T1M.02 2.00 18-Mar-21 20-Mar-21 20-Mar-21, VIA03-116M-T1M.02
N-VSL-FBC-4160-T1-02 VIA05-26M-T1M.01 2.00 20-Mar-21 23-Mar-21 23-Mar-21, VIA05-26M-T1M.01
N-VSL-FBC-4160-T1-03 VIA05-26M-T1.01 2.00 23-Mar-21 25-Mar-21 25-Mar-21, VIA05-26M-T1.01
N-VSL-FBC-4160-T1-04 VIA05-26M-T1.02 2.00 25-Mar-21 27-Mar-21 27-Mar-21, VIA05-26M-T1.02
N-VSL-FBC-4160-T1-05 VIA05-26M-T1.03 2.00 27-Mar-21 30-Mar-21 30-Mar-21, VIA05-26M-T1.03
N-VSL-FBC-4160-T1-06 VIA05-26M-T1.04 2.00 30-Mar-21 05-Apr-21 05-Apr-21, VIA05-26M-T1.04
N-VSL-FBC-4160-T1-07 VIA05-26M-T1.05 2.00 05-Apr-21 07-Apr-21 07-Apr-21, VIA05-26M-T1.05
N-VSL-FBC-4160-T1-08 VIA05-26M-T1.06 2.00 07-Apr-21 10-Apr-21 10-Apr-21, VIA05-26M-T1.06
N-VSL-FBC-4160-T1-09 VIA05-26M-T1.07 2.00 10-Apr-21 13-Apr-21 13-Apr-21, VIA05-26M-T1.07
N-VSL-FBC-4160-T1-10 VIA05-26M-T1.08 2.00 13-Apr-21 15-Apr-21 15-Apr-21, VIA05-26M-T1.08
N-VSL-FBC-4160-T1-11 VIA05-26M-T1M.02 2.00 15-Apr-21 17-Apr-21 17-Apr-21, VIA05-26M-T1M.02
N-VSL-FBC-4090-T1-02 VIA05-19M-T1M.01 1.00 17-Apr-21 19-Apr-21 19-Apr-21, VIA05-19M-T1M.01
N-VSL-FBC-4090-T1-03 VIA05-19M-T1.01 1.00 19-Apr-21 20-Apr-21 20-Apr-21, VIA05-19M-T1.01
N-VSL-FBC-4090-T1-04 VIA05-19M-T1.02 1.00 20-Apr-21 21-Apr-21 21-Apr-21, VIA05-19M-T1.02
N-VSL-FBC-4090-T1-05 VIA05-19M-T1.03 1.00 21-Apr-21 22-Apr-21 22-Apr-21, VIA05-19M-T1.03
N-VSL-FBC-4090-T1-06 VIA05-19M-T1.04 1.00 22-Apr-21 23-Apr-21 23-Apr-21, VIA05-19M-T1.04
N-VSL-FBC-4090-T1-07 VIA05-19M-T1.05 1.00 23-Apr-21 26-Apr-21 26-Apr-21, VIA05-19M-T1.05
N-VSL-FBC-4090-T1-08 VIA05-19M-T1.06 1.00 26-Apr-21 27-Apr-21 27-Apr-21, VIA05-19M-T1.
N-VSL-FBC-4090-T1-09 VIA05-19M-T1.07 1.00 27-Apr-21 28-Apr-21 28-Apr-21, VIA05-19M-T
N-VSL-FBC-4090-T1-10 VIA05-19M-T1.08 1.00 28-Apr-21 29-Apr-21 29-Apr-21, VIA05-19M-
N-VSL-FBC-4090-T1-11 VIA05-19M-T1M.02 1.00 29-Apr-21 30-Apr-21 30-Apr-21, VIA05-19M
N-VSL-FBC-1940-T1-02 VIA03-121M-T1M.01 2.00 30-Apr-21 04-May-21 04-May-21, VI
1.5.1.3 Field Mould C1 #3 (T1 & T1M Segment Type) 50.00 26-Feb-21 03-May-21 03-May-21, 1.5
N-VSL-FBC-4060-T1-02 VIA05-16M-T1M.01 2.00 26-Feb-21 27-Feb-21 27-Feb-21, VIA05-16M-T1M.01
N-VSL-FBC-4060-T1-03 VIA05-16M-T1.01 2.00 01-Mar-21 02-Mar-21 02-Mar-21, VIA05-16M-T1.01
N-VSL-FBC-4060-T1-04 VIA05-16M-T1.02 2.00 03-Mar-21 04-Mar-21 04-Mar-21, VIA05-16M-T1.02
N-VSL-FBC-4060-T1-05 VIA05-16M-T1.03 2.00 05-Mar-21 08-Mar-21 08-Mar-21, VIA05-16M-T1.03
N-VSL-FBC-4060-T1-06 VIA05-16M-T1.04 2.00 09-Mar-21 10-Mar-21 10-Mar-21, VIA05-16M-T1.04
N-VSL-FBC-4060-T1-07 VIA05-16M-T1.05 2.00 11-Mar-21 12-Mar-21 12-Mar-21, VIA05-16M-T1.05
N-VSL-FBC-4060-T1-08 VIA05-16M-T1.06 2.00 13-Mar-21 15-Mar-21 15-Mar-21, VIA05-16M-T1.06
N-VSL-FBC-4060-T1-09 VIA05-16M-T1.07 2.00 16-Mar-21 17-Mar-21 17-Mar-21, VIA05-16M-T1.07
N-VSL-FBC-4060-T1-10 VIA05-16M-T1.08 2.00 18-Mar-21 19-Mar-21 19-Mar-21, VIA05-16M-T1.08
N-VSL-FBC-4060-T1-11 VIA05-16M-T1M.02 2.00 20-Mar-21 22-Mar-21 22-Mar-21, VIA05-16M-T1M.02

Date Revision Checked Approved


Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
                          
 
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
6/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
N-VSL-FBC-4070-T1-02 VIA05-17M-T1M.01 2.00 23-Mar-21 24-Mar-21 24-Mar-21, VIA05-17M-T1M.01
N-VSL-FBC-4070-T1-03 VIA05-17M-T1.01 2.00 25-Mar-21 26-Mar-21 26-Mar-21, VIA05-17M-T1.01
N-VSL-FBC-4070-T1-04 VIA05-17M-T1.02 2.00 27-Mar-21 29-Mar-21 29-Mar-21, VIA05-17M-T1.02
N-VSL-FBC-4070-T1-05 VIA05-17M-T1.03 2.00 30-Mar-21 31-Mar-21 31-Mar-21, VIA05-17M-T1.03
N-VSL-FBC-4070-T1-06 VIA05-17M-T1.04 2.00 05-Apr-21 06-Apr-21 06-Apr-21, VIA05-17M-T1.04
N-VSL-FBC-4070-T1-07 VIA05-17M-T1.05 2.00 07-Apr-21 08-Apr-21 08-Apr-21, VIA05-17M-T1.05
N-VSL-FBC-4070-T1-08 VIA05-17M-T1.06 2.00 10-Apr-21 12-Apr-21 12-Apr-21, VIA05-17M-T1.06
N-VSL-FBC-4070-T1-09 VIA05-17M-T1.07 2.00 13-Apr-21 14-Apr-21 14-Apr-21, VIA05-17M-T1.07
N-VSL-FBC-4070-T1-10 VIA05-17M-T1.08 2.00 15-Apr-21 16-Apr-21 16-Apr-21, VIA05-17M-T1.08
N-VSL-FBC-4070-T1-11 VIA05-17M-T1M.02 2.00 17-Apr-21 19-Apr-21 19-Apr-21, VIA05-17M-T1M.02
N-VSL-FBC-4080-T1-02 VIA05-18M-T1M.01 2.00 20-Apr-21 21-Apr-21 21-Apr-21, VIA05-18M-T1M.01
N-VSL-FBC-4080-T1-03 VIA05-18M-T1.01 2.00 22-Apr-21 23-Apr-21 23-Apr-21, VIA05-18M-T1.01
N-VSL-FBC-4080-T1-04 VIA05-18M-T1.02 2.00 26-Apr-21 27-Apr-21 27-Apr-21, VIA05-18M-T1
N-VSL-FBC-4080-T1-05 VIA05-18M-T1.03 2.00 28-Apr-21 29-Apr-21 29-Apr-21, VIA05-18M
N-VSL-FBC-4080-T1-06 VIA05-18M-T1.04 2.00 30-Apr-21 03-May-21 03-May-21, VIA
1.5.1.4 Field Mould C1 #4 (T1 & T1M Segment Type) 24.00 30-Mar-21 03-May-21 03-May-21, 1.5
N-VSL-FBC-4100-T1-02 VIA05-20M-T1M.01 2.00 30-Mar-21 31-Mar-21 31-Mar-21, VIA05-20M-T1M.01
N-VSL-FBC-4100-T1-03 VIA05-20M-T1.01 2.00 05-Apr-21 06-Apr-21 06-Apr-21, VIA05-20M-T1.01
N-VSL-FBC-4100-T1-04 VIA05-20M-T1.02 2.00 07-Apr-21 08-Apr-21 08-Apr-21, VIA05-20M-T1.02
N-VSL-FBC-4100-T1-05 VIA05-20M-T1.03 2.00 10-Apr-21 12-Apr-21 12-Apr-21, VIA05-20M-T1.03
N-VSL-FBC-4100-T1-06 VIA05-20M-T1.04 2.00 13-Apr-21 14-Apr-21 14-Apr-21, VIA05-20M-T1.04
N-VSL-FBC-4100-T1-07 VIA05-20M-T1.05 2.00 15-Apr-21 16-Apr-21 16-Apr-21, VIA05-20M-T1.05
N-VSL-FBC-4100-T1-08 VIA05-20M-T1.06 2.00 17-Apr-21 19-Apr-21 19-Apr-21, VIA05-20M-T1.06
N-VSL-FBC-4100-T1-09 VIA05-20M-T1.07 2.00 20-Apr-21 21-Apr-21 21-Apr-21, VIA05-20M-T1.07
N-VSL-FBC-4100-T1-10 VIA05-20M-T1.08 2.00 22-Apr-21 23-Apr-21 23-Apr-21, VIA05-20M-T1.08
N-VSL-FBC-4100-T1-11 VIA05-20M-T1M.02 2.00 26-Apr-21 27-Apr-21 27-Apr-21, VIA05-20M-T1
N-VSL-FBC-4180-T1-02 VIA05-28M-T1M.01 2.00 28-Apr-21 29-Apr-21 29-Apr-21, VIA05-28M
N-VSL-FBC-4180-T1-03 VIA05-28M-T1.01 2.00 30-Apr-21 03-May-21 03-May-21, VIA
1.5.1.5 Field Mould C1 #5 (T1 & T1M Segment Type) 24.00 30-Mar-21 03-May-21 03-May-21, 1.5
N-VSL-FBC-4170-T1-02 VIA05-27M-T1M.01 2.00 30-Mar-21 31-Mar-21 31-Mar-21, VIA05-27M-T1M.01
N-VSL-FBC-4170-T1-03 VIA05-27M-T1.01 2.00 05-Apr-21 06-Apr-21 06-Apr-21, VIA05-27M-T1.01
N-VSL-FBC-4170-T1-04 VIA05-27M-T1.02 2.00 07-Apr-21 08-Apr-21 08-Apr-21, VIA05-27M-T1.02
N-VSL-FBC-4170-T1-05 VIA05-27M-T1.03 2.00 10-Apr-21 12-Apr-21 12-Apr-21, VIA05-27M-T1.03
N-VSL-FBC-4170-T1-06 VIA05-27M-T1.04 2.00 13-Apr-21 14-Apr-21 14-Apr-21, VIA05-27M-T1.04
N-VSL-FBC-4170-T1-07 VIA05-27M-T1.05 2.00 15-Apr-21 16-Apr-21 16-Apr-21, VIA05-27M-T1.05
N-VSL-FBC-4170-T1-08 VIA05-27M-T1.06 2.00 17-Apr-21 19-Apr-21 19-Apr-21, VIA05-27M-T1.06
N-VSL-FBC-4170-T1-09 VIA05-27M-T1.07 2.00 20-Apr-21 21-Apr-21 21-Apr-21, VIA05-27M-T1.07
N-VSL-FBC-4170-T1-10 VIA05-27M-T1.08 2.00 22-Apr-21 23-Apr-21 23-Apr-21, VIA05-27M-T1.08
N-VSL-FBC-4170-T1-11 VIA05-27M-T1M.02 2.00 26-Apr-21 27-Apr-21 27-Apr-21, VIA05-27M-T1
N-VSL-FBC-4130-T1-02 VIA05-23M-T1M.01 2.00 28-Apr-21 29-Apr-21 29-Apr-21, VIA05-23M
N-VSL-FBC-4130-T1-03 VIA05-23M-T1.01 2.00 30-Apr-21 03-May-21 03-May-21, VIA
1.5.1.6 Field Mould C1 #6 (T1 & T1M Segment Type) 24.00 30-Mar-21 03-May-21 03-May-21, 1.5
N-VSL-FBC-1950-T1-02 VIA03-120M-T1M.01 2.00 30-Mar-21 31-Mar-21 31-Mar-21, VIA03-120M-T1M.01
N-VSL-FBC-1950-T1-03 VIA03-120M-T1.01 2.00 05-Apr-21 06-Apr-21 06-Apr-21, VIA03-120M-T1.01
N-VSL-FBC-1950-T1-04 VIA03-120M-T1.02 2.00 07-Apr-21 08-Apr-21 08-Apr-21, VIA03-120M-T1.02
N-VSL-FBC-1950-T1-05 VIA03-120M-T1.03 2.00 10-Apr-21 12-Apr-21 12-Apr-21, VIA03-120M-T1.03

Date Revision Checked Approved


Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
                          
 
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
7/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
N-VSL-FBC-1950-T1-06 VIA03-120M-T1.04 2.00 13-Apr-21 14-Apr-21 14-Apr-21, VIA03-120M-T1.04
N-VSL-FBC-1950-T1-07 VIA03-120M-T1.05 2.00 15-Apr-21 16-Apr-21 16-Apr-21, VIA03-120M-T1.05
N-VSL-FBC-1950-T1-08 VIA03-120M-T1.06 2.00 17-Apr-21 19-Apr-21 19-Apr-21, VIA03-120M-T1.06
N-VSL-FBC-1950-T1-09 VIA03-120M-T1.07 2.00 20-Apr-21 21-Apr-21 21-Apr-21, VIA03-120M-T1.07
N-VSL-FBC-1950-T1-10 VIA03-120M-T1M.02 2.00 22-Apr-21 23-Apr-21 23-Apr-21, VIA03-120M-T1M.02
N-VSL-FBC-1930-T1-02 VIA03-122M-T1M.01 2.00 26-Apr-21 27-Apr-21 27-Apr-21, VIA03-122M-T
N-VSL-FBC-1930-T1-03 VIA03-122M-T1.01 2.00 28-Apr-21 29-Apr-21 29-Apr-21, VIA03-122
N-VSL-FBC-1930-T1-04 VIA03-122M-T1.02 2.00 30-Apr-21 03-May-21 03-May-21, VIA
1.5.2 Pier Mould Double Track 61.70 10-Feb-21 03-May-21 03-May-21, 1.5
1.5.2.1 Pier Mould C2 #1 (A1 Segment Type) 61.00 10-Feb-21 03-May-21 03-May-21, 1.5.
N-VSL-FBC-5420-A1-01 VIA05-15M-A1.01 6.00 10-Feb-21 18-Feb-21 18-Feb-21, VIA05-15M-A1.01
N-VSL-FBC-7700-A1-01 VIA03-112M-A1.01 6.00 18-Feb-21 26-Feb-21 26-Feb-21, VIA03-112M-A1.01
N-VSL-FBC-5420-A1-12 VIA05-15M-A1.02 6.00 10-Mar-21 17-Mar-21 17-Mar-21, VIA05-15M-A1.02
N-VSL-FBC-7700-A1-12 VIA03-112M-A1.02 6.00 17-Mar-21 24-Mar-21 24-Mar-21, VIA03-112M-A1.02
N-VSL-FBC-5140-A1-01 VIA05-16M-A1.01 4.00 24-Mar-21 29-Mar-21 29-Mar-21, VIA05-16M-A1.01
N-VSL-FBC-6040-A1-01 VIA03-113M-A1.01 4.00 29-Mar-21 06-Apr-21 06-Apr-21, VIA03-113M-A1.01
N-VSL-FBC-5170-A1-01 VIA03-116M-A1.01 4.00 06-Apr-21 12-Apr-21 12-Apr-21, VIA03-116M-A1.01
N-VSL-FBC-6040-A1-12 VIA03-113M-A1.02 4.00 12-Apr-21 16-Apr-21 16-Apr-21, VIA03-113M-A1.02
N-VSL-FBC-5140-A1-12 VIA05-16M-A1.02 2.00 16-Apr-21 19-Apr-21 19-Apr-21, VIA05-16M-A1.02
N-VSL-FBC-5170-A1-12 VIA03-116M-A1.02 2.00 19-Apr-21 21-Apr-21 21-Apr-21, VIA03-116M-A1.02
N-VSL-FBC-7690-A1-01 VIA03-114M-A1.01 2.00 21-Apr-21 23-Apr-21 23-Apr-21, VIA03-114M-A1.01
N-VSL-FBC-5150-A1-01 VIA05-17M-A1.01 2.00 23-Apr-21 27-Apr-21 27-Apr-21, VIA05-17M-A1.
N-VSL-FBC-6890-A1-01 VIA05-26M-A1.01 2.00 27-Apr-21 29-Apr-21 29-Apr-21, VIA05-26M-
N-VSL-FBC-7690-A1-12 VIA03-114M-A1.02 2.00 29-Apr-21 03-May-21 03-May-21, VIA
1.5.2.2 Pier Mould C2 #2 (A1 Segment Type) 18.00 10-Apr-21 03-May-21 03-May-21, 1.5
N-VSL-FBC-5210-A1-01 VIA05-27M-A1.01 6.00 10-Apr-21 16-Apr-21 16-Apr-21, VIA05-27M-A1.01
N-VSL-FBC-6000-A1-01 VIA03-120M-A1.01 6.00 17-Apr-21 23-Apr-21 23-Apr-21, VIA03-120M-A1.01
N-VSL-FBC-6860-A1-01 VIA05-20M-A1.01 6.00 26-Apr-21 03-May-21 03-May-21, VIA
77.00 11-Feb-21 24-May-21
2. Single Track (6.3 & 5.1 meter Flange width)
2.2 Field Mould Single Track 77.00 11-Feb-21 24-May-21

2.2.1 Field Mould C3 #1 (T2 & T3 Segment Type) 60.00 13-Feb-21 03-May-21 03-May-21, 2.2
N-VSL-FBC-8560 Precast SP3-49SB - T2 [10 units] 20.00 13-Feb-21 10-Mar-21 10-Mar-21, Precast SP3-49SB - T2 [10 units]
N-VSL-FBC-8730 Precast SP3-46SB (Valenzuela Station) - T3 [10 units] 20.00 11-Mar-21 06-Apr-21 06-Apr-21, Precast SP3-46SB (Valenzuela Station) - T3 [10 unit
N-VSL-FBC-8700 Precast SP3-43SB (Valenzuela Station) - T3 [10 units] 20.00 07-Apr-21 03-May-21 03-May-21, Pre
2.2.2 Field Mould C3 #2 (T2 & T3 Segment Type) 60.00 11-Feb-21 03-May-21 03-May-21, 2.2
N-VSL-FBC-8550 Precast SP3-48SB - T2 [10 units] 20.00 11-Feb-21 10-Mar-21 10-Mar-21, Precast SP3-48SB - T2 [10 units]
N-VSL-FBC-8720 Precast SP3-45SB (Valenzuela Station) - T3 [10 units] 20.00 10-Mar-21 06-Apr-21 06-Apr-21, Precast SP3-45SB (Valenzuela Station) - T3 [10 units
N-VSL-FBC-8690 Precast SP3-42SB (Valenzuela Station) - T3 [10 units] 20.00 06-Apr-21 03-May-21 03-May-21, Pre
2.2.3 Field Mould C3 #3 (T2 & T3 Segment Type) 60.00 13-Feb-21 03-May-21 03-May-21, 2.2
N-VSL-FBC-8740 Precast SP3-47SB (Valenzuela Station) - T3 [10 units] 20.00 13-Feb-21 10-Mar-21 10-Mar-21, Precast SP3-47SB (Valenzuela Station) - T3 [10 units]
N-VSL-FBC-8710 Precast SP3-44SB (Valenzuela Station) - T3 [10 units] 20.00 11-Mar-21 06-Apr-21 06-Apr-21, Precast SP3-44SB (Valenzuela Station) - T3 [10 unit
N-VSL-FBC-8540 Precast SP3-41SB - T2 [10 units] 20.00 07-Apr-21 03-May-21 03-May-21, Pre
2.2.4 Field Mould C3 #4 (T2 & T3 Segment Type) 20.00 28-Apr-21 24-May-21
N-VSL-FBC-8630 Precast SP3-49NB - T2 [10 units] 20.00 28-Apr-21 24-May-21
2.2.5 Field Mould C3 #5 (T2 & T3 Segment Type) 20.00 28-Apr-21 24-May-21

Date Revision Checked Approved


Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
                          
 
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
8/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
N-VSL-FBC-8640 Precast SP3-48NB - T2 [10 units] 20.00 28-Apr-21 24-May-21
2.5 Segment Activity 50.00 20-Feb-21 27-Apr-21 27-Apr-21, 2.5 Segment A

2.5.2 Pier Mould Single Track 50.00 20-Feb-21 27-Apr-21 27-Apr-21, 2.5.2 Pier Mou
2.5.2.1 Pier Mould C4 #1 (A2 & A3 Segment Type) 50.00 20-Feb-21 27-Apr-21 27-Apr-21, 2.5.2.1 Pier M
N-VSL-FBC-8970-A2-01 VIA03-49S-A2.01 2.00 20-Feb-21 22-Feb-21 22-Feb-21, VIA03-49S-A2.01
N-VSL-FBC-8610-A2-01 VIA03-48S-A2.01 2.00 23-Feb-21 24-Feb-21 24-Feb-21, VIA03-48S-A2.01
N-VSL-FBC-8960-A3-01 VIA03-47S-A3.01 2.00 26-Feb-21 27-Feb-21 27-Feb-21, VIA03-47S-A3.01
N-VSL-FBC-8970-A2-12 VIA03-49S-A2.02 2.00 11-Mar-21 12-Mar-21 12-Mar-21, VIA03-49S-A2.02
N-VSL-FBC-8600-A3-01 VIA03-46S-A3.01 2.00 18-Mar-21 19-Mar-21 19-Mar-21, VIA03-46S-A3.01
N-VSL-FBC-8610-A2-12 VIA03-48S-A2.02 2.00 20-Mar-21 22-Mar-21 22-Mar-21, VIA03-48S-A2.02
N-VSL-FBC-8960-A3-12 VIA03-47S-A3.02 2.00 23-Mar-21 24-Mar-21 24-Mar-21, VIA03-47S-A3.02
N-VSL-FBC-8590-A3-01 VIA03-44S-A3.01 2.00 25-Mar-21 26-Mar-21 26-Mar-21, VIA03-44S-A3.01
N-VSL-FBC-8950-A3-01 VIA03-45S-A3.01 2.00 27-Mar-21 29-Mar-21 29-Mar-21, VIA03-45S-A3.01
N-VSL-FBC-8600-A3-12 VIA03-46S-A3.02 2.00 07-Apr-21 08-Apr-21 08-Apr-21, VIA03-46S-A3.02
N-VSL-FBC-8940-A3-01 VIA03-43S-A3.01 2.00 15-Apr-21 16-Apr-21 16-Apr-21, VIA03-43S-A3.01
N-VSL-FBC-8590-A3-12 VIA03-44S-A3.02 2.00 17-Apr-21 19-Apr-21 19-Apr-21, VIA03-44S-A3.02
N-VSL-FBC-8950-A3-12 VIA03-45S-A3.02 2.00 20-Apr-21 21-Apr-21 21-Apr-21, VIA03-45S-A3.02
N-VSL-FBC-8580-A3-01 VIA03-42S-A3.01 2.00 22-Apr-21 23-Apr-21 23-Apr-21, VIA03-42S-A3.01
N-VSL-FBC-8920-A2-01 VIA03-41S-A2.01 2.00 26-Apr-21 27-Apr-21 27-Apr-21, VIA03-41S-A2
27.00 05-Apr-21 08-May-21
VIADUCT CONSTRUCTION
27.00 05-Apr-21 08-May-21
2. SPAN ERECTION WORKS
2.1 SECTION 2 27.00 05-Apr-21 08-May-21

2.1.2 Launching Girder #2 - Total 84 Spans 27.00 05-Apr-21 08-May-21


2.1.2.1 PR3-112 ---> PR4-18 All Northbound (45 Spans) 27.00 05-Apr-21 08-May-21
N-VSL-ECC-2210 Erect SP3-112M [11 units] 11.00 05-Apr-21 17-Apr-21 17-Apr-21, Erect SP3-112M [11 units]
N-VSL-ECC-2200 Erect SP3-113M [11 units] 9.00 19-Apr-21 29-Apr-21 29-Apr-21, Erect SP3-
N-VSL-ECC-2190 Erect SP3-114M [11 units] 7.00 30-Apr-21 08-May-21
2.2 SECTION 3 11.00 19-Apr-21 03-May-21 03-May-21, 2.2

2.2.1 Launching Girder #3 - Total 135 Spans 11.00 19-Apr-21 03-May-21 03-May-21, 2.2

2.2.1.1 PR5-16 ---> PR5-27 All Northbound (11 spans) 11.00 19-Apr-21 03-May-21 03-May-21, 2.2
N-VSL-ECC-5030 Erect SP5-15M [12 units] 11.00 19-Apr-21 03-May-21

Date Revision Checked Approved


Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
                          