NSCR Project CP01 Schedule Overview
NSCR Project CP01 Schedule Overview
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
1/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
North South Commuter Rail Project - Package CP01_(01022021) 179.35 02-Oct-20 A 24-May-21
1.1.3.2 Steel Structure 67.00 02-Oct-20 A 04-Feb-21 04-Feb-21, 1.1.3.2 Steel Structure
N-VSL-PCY-1070 Erection of steel structure and Install Panels [P2] 67.00 02-Oct-20 A 04-Feb-21 04-Feb-21, Erection of steel structure and Install Panels [P2]
1.1.4 Utility Network 109.00 14-Oct-20 A 02-Feb-21 02-Feb-21, 1.1.4 Utility Network
N-VSL-PCY-1500 Shed Electrical Connections 109.00 14-Oct-20 A 02-Feb-21 02-Feb-21, Shed Electrical Connections
1.2 Casting Cells 135.00 05-Oct-20 A 28-Feb-21 28-Feb-21, 1.2 Casting Cells
1.2.1 Field Segment Double Track - C1 81.00 28-Nov-20 A 28-Feb-21 28-Feb-21, 1.2.1 Field Segment Double Track - C1
1.2.1.7 Field Segment Double Track - C1 #7 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, 1.2.1.7 Field Segment Double Track - C1 #7
N-VSL-PCY-1100 Casting cells assembly 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, Casting cells assembly
1.2.1.8 Field Segment Double Track - C1 #8 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, 1.2.1.8 Field Segment Double Track - C1 #8
N-VSL-PCY-1350 Casting cells assembly 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, Casting cells assembly
1.2.1.9 Field Segment Double Track - C1 #9 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, 1.2.1.9 Field Segment Double Track - C1 #9
N-VSL-PCY-1360 Casting cells assembly 30.00 28-Nov-20 A 10-Feb-21 10-Feb-21, Casting cells assembly
1.2.1.10 Field Segment Double Track - C1 #10 30.00 04-Jan-21 A 10-Feb-21 10-Feb-21, 1.2.1.10 Field Segment Double Track - C1 #10
N-VSL-PCY-1110 Casting cells assembly 30.00 04-Jan-21 A 10-Feb-21 10-Feb-21, Casting cells assembly
1.2.1.11 Field Segment Double Track - C1 #11 30.00 04-Jan-21 A 28-Feb-21 28-Feb-21, 1.2.1.11 Field Segment Double Track - C1 #11
N-VSL-PCY-1370 Casting cells assembly 30.00 04-Jan-21 A 28-Feb-21 28-Feb-21, Casting cells assembly
1.2.1.11 Field Segment Double Track - C1 #12 30.00 04-Jan-21 A 28-Feb-21 28-Feb-21, 1.2.1.11 Field Segment Double Track - C1 #12
N-VSL-PCY-1380 Casting cells assembly 30.00 04-Jan-21 A 28-Feb-21 28-Feb-21, Casting cells assembly
1.2.2 Pier Segment Double Track - C2 36.00 01-Dec-20 A 28-Feb-21 28-Feb-21, 1.2.2 Pier Segment Double Track - C2
1.2.2.1 Pier Segment Double Track - C2 #1 30.00 01-Dec-20 A 03-Feb-21 03-Feb-21, 1.2.2.1 Pier Segment Double Track - C2 #1
N-VSL-PCY-1120 Casting cells assembly 30.00 01-Dec-20 A 03-Feb-21 03-Feb-21, Casting cells assembly
1.2.2.2 Pier Segment Double Track - C2 #2 30.00 01-Dec-20 A 03-Feb-21 03-Feb-21, 1.2.2.2 Pier Segment Double Track - C2 #2
N-VSL-PCY-1390 Casting cells assembly 30.00 01-Dec-20 A 03-Feb-21 03-Feb-21, Casting cells assembly
1.2.2.3 Pier Segment Double Track - C2 #3 30.00 07-Dec-20 A 28-Feb-21 28-Feb-21, 1.2.2.3 Pier Segment Double Track - C2 #3
N-VSL-PCY-1130 Casting cells assembly 30.00 07-Dec-20 A 28-Feb-21 28-Feb-21, Casting cells assembly
1.2.2.4 Pier Segment Double Track - C2 #4 30.00 07-Dec-20 A 28-Feb-21 28-Feb-21, 1.2.2.4 Pier Segment Double Track - C2 #4
N-VSL-PCY-1400 Casting cells assembly 30.00 07-Dec-20 A 28-Feb-21 28-Feb-21, Casting cells assembly
Date Revision Checked Approved
Actual Work summary NSCR1-VSL-V00-PMT-PRG-0036-A
31-Jan-21 North South Commuter Rail Project Schedule
Remaining Work North South Commuter Rail Project - CP01
Critical Remaining Work 3 Months Rolling Programme (January 31, 2021)
Milestone
North South Commuter Rail (NSCR) Project - Package CP01 : Section 2 & 3
2/8
Activity ID Activity Name Original Start Finish February March April May
14 15 16 17
Duration 01 08 15 22 01 08 15 22 29 05 12 19 26 03
1.2.3 Field Segment Single Track - C3 88.00 05-Oct-20 A 12-Feb-21 12-Feb-21, 1.2.3 Field Segment Single Track - C3
1.2.3.1 Field Segment Single Track - C3 #1 88.00 05-Oct-20 A 11-Feb-21 11-Feb-21, 1.2.3.1 Field Segment Single Track - C3 #1
N-VSL-PCY-1140 Casting cells assembly 88.00 05-Oct-20 A 11-Feb-21 11-Feb-21, Casting cells assembly
1.2.3.2 Field Segment Single Track - C3 #2 46.00 26-Oct-20 A 11-Feb-21 11-Feb-21, 1.2.3.2 Field Segment Single Track - C3 #2
N-VSL-PCY-1410 Casting cells assembly 46.00 26-Oct-20 A 11-Feb-21 11-Feb-21, Casting cells assembly
1.2.3.3 Field Segment Single Track - C3 #3 85.00 08-Oct-20 A 12-Feb-21 12-Feb-21, 1.2.3.3 Field Segment Single Track - C3 #3
N-VSL-PCY-1150 Casting cells assembly 85.00 08-Oct-20 A 12-Feb-21 12-Feb-21, Casting cells assembly
1.2.3.4 Field Segment Single Track - C3 #4 46.00 26-Oct-20 A 12-Feb-21 12-Feb-21, 1.2.3.4 Field Segment Single Track - C3 #4
N-VSL-PCY-1420 Casting cells assembly 46.00 26-Oct-20 A 12-Feb-21 12-Feb-21, Casting cells assembly
1.2.3.5 Field Segment Single Track - C3 #5 46.00 26-Oct-20 A 12-Feb-21 12-Feb-21, 1.2.3.5 Field Segment Single Track - C3 #5
N-VSL-PCY-1430 Casting cells assembly 46.00 26-Oct-20 A 12-Feb-21 12-Feb-21, Casting cells assembly
1.2.4 Pier Segment Single Track - C4 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, 1.2.4 Pier Segment Single Track - C4
1.2.4.1 Pier Segment Single Track - C4 #2 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, 1.2.4.1 Pier Segment Single Track - C4 #2
N-VSL-PCY-1160 Casting cells assembly 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, Casting cells assembly
1.2.4.2 Pier Segment Single Track - C4 #2 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, 1.2.4.2 Pier Segment Single Track - C4 #2
N-VSL-PCY-1440 Casting cells assembly 60.00 23-Nov-20 A 09-Feb-21 09-Feb-21, Casting cells assembly
1.3 Overhead Crane - 10 Tons (9 Units) 30.00 04-Jan-21 A 25-Feb-21 25-Feb-21, 1.3 Overhead Crane - 10 Tons (9 Units)
1.3.3 3rd Batch (3 Units) 30.00 04-Jan-21 A 25-Feb-21 25-Feb-21, 1.3.3 3rd Batch (3 Units)
N-VSL-PCY-1190 Overhead Crane assembly 30.00 04-Jan-21 A 25-Feb-21 25-Feb-21, Overhead Crane assembly
1.4 Straddle Carrier (3 Units) 43.00 01-Feb-21 15-Mar-21 15-Mar-21, 1.4 Straddle Carrier (3 Units)
1.4.1 1st Unit 20.00 12-Feb-21 04-Mar-21 04-Mar-21, 1.4.1 1st Unit
N-VSL-PRC-1500 Delivery to site 0.00 12-Feb-21* Delivery to site
N-VSL-PCY-1200 Straddle Carrier assembly 20.00 13-Feb-21 04-Mar-21 04-Mar-21, Straddle Carrier assembly
1.4.2 2nd Unit 36.00 01-Feb-21 08-Mar-21 08-Mar-21, 1.4.2 2nd Unit
1.4.2.1 Structure & Walkways_China 15.00 01-Feb-21 15-Feb-21 15-Feb-21, 1.4.2.1 Structure & Walkways_China
N-VSL-PCY-1510 Straddle Carrier assembly 15.00 01-Feb-21 15-Feb-21 15-Feb-21, Straddle Carrier assembly
1.4.2.2 Other Parts_Italy 28.00 08-Feb-21 08-Mar-21 08-Mar-21, 1.4.2.2 Other Parts_Italy
N-VSL-PRC-1520 Arrival at Manila Port 0.00 08-Feb-21 Arrival at Manila Port
N-VSL-PRC-1530 Delivery to site 0.00 26-Feb-21* Delivery to site
N-VSL-PCY-1210 Straddle Carrier assembly 10.00 27-Feb-21 08-Mar-21 08-Mar-21, Straddle Carrier assembly
1.4.3 3rd Unit 43.00 01-Feb-21 15-Mar-21 15-Mar-21, 1.4.3 3rd Unit
1.4.3.1 Structure & Walkways_China 15.00 01-Feb-21 15-Feb-21 15-Feb-21, 1.4.3.1 Structure & Walkways_China
N-VSL-PCY-1520 Straddle Carrier assembly 15.00 01-Feb-21 15-Feb-21 15-Feb-21, Straddle Carrier assembly
1.4.3.2 Other Parts_Italy 32.00 11-Feb-21 15-Mar-21 15-Mar-21, 1.4.3.2 Other Parts_Italy
N-VSL-PRC-1550 Arrival at Manila Port 0.00 11-Feb-21* Arrival at Manila Port
N-VSL-PRC-1560 Delivery to site 0.00 05-Mar-21* Delivery to site
N-VSL-PCY-1220 Straddle Carrier assembly 10.00 06-Mar-21 15-Mar-21 15-Mar-21, Straddle Carrier assembly
129.00 16-Jan-21 A 19-May-21
2. Segment Erection
2.1 Launching Girder (4 Units) 129.00 16-Jan-21 A 19-May-21
2.1.1 Launching Girder #1 (Valenzuela Area) 84.00 02-Feb-21 27-Apr-21 27-Apr-21, 2.1.1 Launchin
2.1.3.1 Main Truss 58.00 16-Feb-21 14-Apr-21 14-Apr-21, 2.1.3.1 Main Truss
N-VSL-PRC-1750 Departure from Factory (Malaysia) 0.00 16-Feb-21* Departure from Factory (Malaysia)
N-VSL-PRC-1760 Arrival at Manila Port 0.00 02-Mar-21 Arrival at Manila Port
N-VSL-PRC-1770 Delivery to site 0.00 06-Mar-21 Delivery to site
N-VSL-PCY-1270 Main Truss Unloading, Pre-assembly & Assembly 40.00 06-Mar-21 14-Apr-21 14-Apr-21, Main Truss Unloading, Pre-assembly &
2.1.3.2 Equipment 55.00 01-Feb-21 27-Mar-21 27-Mar-21, 2.1.3.2 Equipment
N-VSL-PRC-1790 Arrival at Manila Port (from Malaysia) 0.00 01-Feb-21 Arrival at Manila Port (from Malaysia)
N-VSL-PRC-1820 Arrival at Manila Port (from China) 0.00 01-Feb-21 Arrival at Manila Port (from China)
N-VSL-PRC-1800 Delivery to site (from Malaysia) 0.00 04-Feb-21 Delivery to site (from Malaysia)
N-VSL-PCY-1280 Equipment Unloading, Pre-assembly & Assembly 40.00 16-Feb-21 27-Mar-21 27-Mar-21, Equipment Unloading, Pre-assembly & Assembly
2.1.4 Launching Girder #4 (after Bocaue Station) 105.00 04-Feb-21 19-May-21
2.2.1 Field Mould C3 #1 (T2 & T3 Segment Type) 60.00 13-Feb-21 03-May-21 03-May-21, 2.2
N-VSL-FBC-8560 Precast SP3-49SB - T2 [10 units] 20.00 13-Feb-21 10-Mar-21 10-Mar-21, Precast SP3-49SB - T2 [10 units]
N-VSL-FBC-8730 Precast SP3-46SB (Valenzuela Station) - T3 [10 units] 20.00 11-Mar-21 06-Apr-21 06-Apr-21, Precast SP3-46SB (Valenzuela Station) - T3 [10 unit
N-VSL-FBC-8700 Precast SP3-43SB (Valenzuela Station) - T3 [10 units] 20.00 07-Apr-21 03-May-21 03-May-21, Pre
2.2.2 Field Mould C3 #2 (T2 & T3 Segment Type) 60.00 11-Feb-21 03-May-21 03-May-21, 2.2
N-VSL-FBC-8550 Precast SP3-48SB - T2 [10 units] 20.00 11-Feb-21 10-Mar-21 10-Mar-21, Precast SP3-48SB - T2 [10 units]
N-VSL-FBC-8720 Precast SP3-45SB (Valenzuela Station) - T3 [10 units] 20.00 10-Mar-21 06-Apr-21 06-Apr-21, Precast SP3-45SB (Valenzuela Station) - T3 [10 units
N-VSL-FBC-8690 Precast SP3-42SB (Valenzuela Station) - T3 [10 units] 20.00 06-Apr-21 03-May-21 03-May-21, Pre
2.2.3 Field Mould C3 #3 (T2 & T3 Segment Type) 60.00 13-Feb-21 03-May-21 03-May-21, 2.2
N-VSL-FBC-8740 Precast SP3-47SB (Valenzuela Station) - T3 [10 units] 20.00 13-Feb-21 10-Mar-21 10-Mar-21, Precast SP3-47SB (Valenzuela Station) - T3 [10 units]
N-VSL-FBC-8710 Precast SP3-44SB (Valenzuela Station) - T3 [10 units] 20.00 11-Mar-21 06-Apr-21 06-Apr-21, Precast SP3-44SB (Valenzuela Station) - T3 [10 unit
N-VSL-FBC-8540 Precast SP3-41SB - T2 [10 units] 20.00 07-Apr-21 03-May-21 03-May-21, Pre
2.2.4 Field Mould C3 #4 (T2 & T3 Segment Type) 20.00 28-Apr-21 24-May-21
N-VSL-FBC-8630 Precast SP3-49NB - T2 [10 units] 20.00 28-Apr-21 24-May-21
2.2.5 Field Mould C3 #5 (T2 & T3 Segment Type) 20.00 28-Apr-21 24-May-21
2.5.2 Pier Mould Single Track 50.00 20-Feb-21 27-Apr-21 27-Apr-21, 2.5.2 Pier Mou
2.5.2.1 Pier Mould C4 #1 (A2 & A3 Segment Type) 50.00 20-Feb-21 27-Apr-21 27-Apr-21, 2.5.2.1 Pier M
N-VSL-FBC-8970-A2-01 VIA03-49S-A2.01 2.00 20-Feb-21 22-Feb-21 22-Feb-21, VIA03-49S-A2.01
N-VSL-FBC-8610-A2-01 VIA03-48S-A2.01 2.00 23-Feb-21 24-Feb-21 24-Feb-21, VIA03-48S-A2.01
N-VSL-FBC-8960-A3-01 VIA03-47S-A3.01 2.00 26-Feb-21 27-Feb-21 27-Feb-21, VIA03-47S-A3.01
N-VSL-FBC-8970-A2-12 VIA03-49S-A2.02 2.00 11-Mar-21 12-Mar-21 12-Mar-21, VIA03-49S-A2.02
N-VSL-FBC-8600-A3-01 VIA03-46S-A3.01 2.00 18-Mar-21 19-Mar-21 19-Mar-21, VIA03-46S-A3.01
N-VSL-FBC-8610-A2-12 VIA03-48S-A2.02 2.00 20-Mar-21 22-Mar-21 22-Mar-21, VIA03-48S-A2.02
N-VSL-FBC-8960-A3-12 VIA03-47S-A3.02 2.00 23-Mar-21 24-Mar-21 24-Mar-21, VIA03-47S-A3.02
N-VSL-FBC-8590-A3-01 VIA03-44S-A3.01 2.00 25-Mar-21 26-Mar-21 26-Mar-21, VIA03-44S-A3.01
N-VSL-FBC-8950-A3-01 VIA03-45S-A3.01 2.00 27-Mar-21 29-Mar-21 29-Mar-21, VIA03-45S-A3.01
N-VSL-FBC-8600-A3-12 VIA03-46S-A3.02 2.00 07-Apr-21 08-Apr-21 08-Apr-21, VIA03-46S-A3.02
N-VSL-FBC-8940-A3-01 VIA03-43S-A3.01 2.00 15-Apr-21 16-Apr-21 16-Apr-21, VIA03-43S-A3.01
N-VSL-FBC-8590-A3-12 VIA03-44S-A3.02 2.00 17-Apr-21 19-Apr-21 19-Apr-21, VIA03-44S-A3.02
N-VSL-FBC-8950-A3-12 VIA03-45S-A3.02 2.00 20-Apr-21 21-Apr-21 21-Apr-21, VIA03-45S-A3.02
N-VSL-FBC-8580-A3-01 VIA03-42S-A3.01 2.00 22-Apr-21 23-Apr-21 23-Apr-21, VIA03-42S-A3.01
N-VSL-FBC-8920-A2-01 VIA03-41S-A2.01 2.00 26-Apr-21 27-Apr-21 27-Apr-21, VIA03-41S-A2
27.00 05-Apr-21 08-May-21
VIADUCT CONSTRUCTION
27.00 05-Apr-21 08-May-21
2. SPAN ERECTION WORKS
2.1 SECTION 2 27.00 05-Apr-21 08-May-21
2.2.1 Launching Girder #3 - Total 135 Spans 11.00 19-Apr-21 03-May-21 03-May-21, 2.2
2.2.1.1 PR5-16 ---> PR5-27 All Northbound (11 spans) 11.00 19-Apr-21 03-May-21 03-May-21, 2.2
N-VSL-ECC-5030 Erect SP5-15M [12 units] 11.00 19-Apr-21 03-May-21