Bar Chart Time Schedule SPAM Kampar Project Rev.0.0

The document outlines a schedule for two shipments of SPAM KAMPAR over 80 and 85 day periods from August 2021 to September 2021. Shipment 1 involves purchasing materials, producing and finishing 776 metric tons of bare pipe, applying protective coatings, inspection and testing, and delivery to site between August and May. Shipment 2 follows a similar process between June and September. Key steps include material purchasing, pipe production, finishing, coating application, testing, and delivery for both shipments.

Uploaded by

Alfian Imaduddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
122 views1 page

Bar Chart Time Schedule SPAM Kampar Project Rev.0.0

The document outlines a schedule for two shipments of SPAM KAMPAR over 80 and 85 day periods from August 2021 to September 2021. Shipment 1 involves purchasing materials, producing and finishing 776 metric tons of bare pipe, applying protective coatings, inspection and testing, and delivery to site between August and May. Shipment 2 follows a similar process between June and September. Key steps include material purchasing, pipe production, finishing, coating application, testing, and delivery for both shipments.

Uploaded by

Alfian Imaduddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Bar Chart Time Schedule Issued Date : Fri 05/02/21

Revision : 00
SPAM KAMPAR
ID Task Name Quantity Output Duration Start Finish
W-6 W1 W7 W13 W19 W25 W31
1 SPAM KAMPAR SHIPMENT 1 1553 Mton 80 days Mon 08/02/21 Fri 28/05/21
2 PO 1 day Mon 08/02/21 Mon 08/02/21
3 Purchasing Hot Rolled Coil 20 days Mon 08/02/21 Fri 05/03/21
4 1016 mm x 10 mm x 12 m L = 265 pcs 776 Mton 60 days Mon 08/03/21 Fri 28/05/21
5 - Production Bare Pipe 80 ton/day 10 days Mon 08/03/21 Fri 19/03/21
6 - Finishing Bare Pipe 20 pcs/day 14 days Tue 09/03/21 Fri 26/03/21
7 - Aplikasi 3LPE 50 pcs/day 6 days Fri 19/03/21 Fri 26/03/21
8 - Inspection & Test 3LPE 50 pcs/day 6 days Mon 22/03/21 Mon 29/03/21
9 - Aplikasi Cement Lining 15 pcs/day 18 days Tue 23/03/21 Thu 15/04/21
10 - Inspection & Test Cement Lining 15 pcs/day 12 days Wed 21/04/21 Thu 06/05/21
11 - Cargo readiness 1 day Fri 07/05/21 Fri 07/05/21
12 - Delivery to Site 15 days Mon 10/05/21 Fri 28/05/21
13 SPAM KAMPAR SHIPMENT 2 1553 Mton 85 days Tue 01/06/21 Mon 27/09/21
14 PO 1 day Tue 01/06/21 Tue 01/06/21
15 Purchasing Hot Rolled Coil 20 days Tue 01/06/21 Mon 28/06/21
16 1016 mm x 10 mm x 12 m L = 265 pcs 776 Mton 63 days Thu 01/07/21 Mon 27/09/21
17 - Production Bare Pipe 80 ton/day 10 days Thu 01/07/21 Wed 14/07/21
18 - Finishing Bare Pipe 20 pcs/day 14 days Fri 02/07/21 Wed 21/07/21
19 - Aplikasi 3LPE 50 pcs/day 6 days Mon 19/07/21 Mon 26/07/21
20 - Inspection & Test 3LPE 50 pcs/day 6 days Tue 20/07/21 Tue 27/07/21
21 - Aplikasi Cement Lining 15 pcs/day 18 days Wed 21/07/21 Fri 13/08/21
22 - Inspection & Test Cement Lining 15 pcs/day 15 days Mon 16/08/21 Fri 03/09/21
23 - Cargo readiness 1 day Mon 06/09/21 Mon 06/09/21
24 - Delivery to Site 15 days Tue 07/09/21 Mon 27/09/21

Task Project Summary Inactive Summary Manual Summary External Milestone


Split External Tasks Manual Task Start-only Progress
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks

Page 1