Bar Chart Time Schedule Issued Date : Fri 05/02/21
Revision : 00
SPAM KAMPAR
ID Task Name Quantity Output Duration Start Finish
W-6 W1 W7 W13 W19 W25 W31
1 SPAM KAMPAR SHIPMENT 1 1553 Mton 80 days Mon 08/02/21 Fri 28/05/21
2 PO 1 day Mon 08/02/21 Mon 08/02/21
3 Purchasing Hot Rolled Coil 20 days Mon 08/02/21 Fri 05/03/21
4 1016 mm x 10 mm x 12 m L = 265 pcs 776 Mton 60 days Mon 08/03/21 Fri 28/05/21
5 - Production Bare Pipe 80 ton/day 10 days Mon 08/03/21 Fri 19/03/21
6 - Finishing Bare Pipe 20 pcs/day 14 days Tue 09/03/21 Fri 26/03/21
7 - Aplikasi 3LPE 50 pcs/day 6 days Fri 19/03/21 Fri 26/03/21
8 - Inspection & Test 3LPE 50 pcs/day 6 days Mon 22/03/21 Mon 29/03/21
9 - Aplikasi Cement Lining 15 pcs/day 18 days Tue 23/03/21 Thu 15/04/21
10 - Inspection & Test Cement Lining 15 pcs/day 12 days Wed 21/04/21 Thu 06/05/21
11 - Cargo readiness 1 day Fri 07/05/21 Fri 07/05/21
12 - Delivery to Site 15 days Mon 10/05/21 Fri 28/05/21
13 SPAM KAMPAR SHIPMENT 2 1553 Mton 85 days Tue 01/06/21 Mon 27/09/21
14 PO 1 day Tue 01/06/21 Tue 01/06/21
15 Purchasing Hot Rolled Coil 20 days Tue 01/06/21 Mon 28/06/21
16 1016 mm x 10 mm x 12 m L = 265 pcs 776 Mton 63 days Thu 01/07/21 Mon 27/09/21
17 - Production Bare Pipe 80 ton/day 10 days Thu 01/07/21 Wed 14/07/21
18 - Finishing Bare Pipe 20 pcs/day 14 days Fri 02/07/21 Wed 21/07/21
19 - Aplikasi 3LPE 50 pcs/day 6 days Mon 19/07/21 Mon 26/07/21
20 - Inspection & Test 3LPE 50 pcs/day 6 days Tue 20/07/21 Tue 27/07/21
21 - Aplikasi Cement Lining 15 pcs/day 18 days Wed 21/07/21 Fri 13/08/21
22 - Inspection & Test Cement Lining 15 pcs/day 15 days Mon 16/08/21 Fri 03/09/21
23 - Cargo readiness 1 day Mon 06/09/21 Mon 06/09/21
24 - Delivery to Site 15 days Tue 07/09/21 Mon 27/09/21
Task Project Summary Inactive Summary Manual Summary External Milestone
Split External Tasks Manual Task Start-only Progress
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks