Sample Hospital Project Report in PDF
Sample Hospital Project Report in PDF
Medium Term
Plan Ref:
Page 1 of 5
UNIVERSITY HOSPITALS BIRMINGHAM NHS FOUNDATION TRUST
BOARD OF GOVERNORS
MONDAY 19 SEPTEMBER 2011
1. Summary of Progress
Progress continues on the completion of the new building and all moves have
been managed and completed in line with the master programme.
The servery area for the main staff dining room is complete and
the unit was opened on 13 June 2011 as planned. Works to the
Outpatients Pharmacy have completed on time to allow the
robot installation and for a “go live” date of 4 July 2011. The
Technical Team is progressing a variation enquiry for the final fit
out of the automated laboratories in preparation for the
installation works to commence following handover in August.
Page 2 of 5
2.2 Technical Commissioning and Validation
3. Operational Commissioning
Moves 5 and 6
Detailed planning for the remaining Outpatient services and Clinical moves
continues.
The lessons learned from previous moves have been incorporated into these
plans. Regular briefing sessions are being held with key Trust staff, including
those that will act as the Team Leaders for each transferring department
Detailed plans for both the equipping and physical transfer of all services
continue for Outpatients and other departments transferring in Move 5.
4. Finance
The latest payment to the PFI Operator relating to the new hospital is
set out below:
Page 3 of 5
• £3,389,692 excluding VAT) monthly service payment for June
2011. This includes the Unitary Payment for construction and
financing the new building as well as payment for services received
(e.g. car parking, estates, ICT and security). This amount is also
net of £270k deductions in relation to service failures that occurred
during the contract month of March 2011.
The following variations have been completed since the last Board of
Governors meeting:
5. Communications
5.1 The new edition of the staff handbook was made available via the
intranet and handed out to all staff involved in the Outpatients Area 4
move.
5.2 Following on from the Lessons Learned from the first Outpatients
walkthrough, the Trust’s Communications Department organised
further temporary signage and handled recruitment for a second
walkthrough of Area 4 to test improvements made to assist patient
flow.
5.3 Detailed maps of the new Outpatients areas on Level 0 have been
created and distributed to staff in all areas of the new QEHB and new
Level 0 maps created for the public.
5.4 Updated telephone lists have been distributed to all areas of the Trust.
The Prince’s Regeneration Trust have been engaged to assist with the plans
in relation to the locally listed original workhouse buildings.
8. Recommendations
Accept the progress reported in the New Hospitals Project Director’s report.
Morag Jackson
New Hospitals Project Director
1 September 2011
Page 5 of 5