Commercial Circular No.322
Commercial Circular No.322
,
Office of the Chief Engineer (Commercial).
Maharashtra State Electricity Distribution Co. Ltd
"Prakashgad", 5th Floor, Station Road, Bandra (E), Mumbai - 400 051.
Tel.: (P) 26474753, (0) 26474211, Fax: (022) 26472366
(A Govt. of Maharashtra Undertaking) Email: [email protected], Website: www.mahadiscom.com
CIN: U40109MH20055GC153645
SUB: Connectivity to the Distribution network of MSEDCL for eligible consumers installing
Roof top Renewable Energy Generating Systems in his premises under MERC (Grid
Interactive Roof top Renewable Energy Generating Systems) Regulations, 2019-------
Procedure for Application, methodology for Metering & Billing, etc.
REF.: (1) The Electricity Act, 2003 & all other enabling provisions.
(2) MERC (Grid Interactive Rooftop Renewable Energy Generating Systems) Regulations,
2019
(3) CEA (Technical Standard for Connectivity of the Distributed Generation
Resources) Regulations, 2013
(4) CEA (Measures relating to Safety and Electric Supply), Regulations, 2010.
(5) Maharashtra Electricity Regulatory Commission (State Grid Code) Regulations,
2006.
1. Preamble
1.2 MERC has notified MERC (Grid Interactive Roof top Renewable Energy Generating
Systems) Regulations, 2019 and accordingly this circular is being issued for
providing guidelines on implementation for installation of Renewable Energy
Generating System on Roof top or any mounting structure by existing/new
consumers of MSEDCL in their premises.
2. Definitions:
Page 2 of 11
Provided that a separate Renewable Energy Generation Meter shall be installed
for each source of Renewable Energy in case of hybrid or combination of such
sources;
The general guidelines for implementation of MERC (Grid Interactive Roof top
Renewable Energy Generating Systems) Regulations, 2019 are as under:
4.1 The Eligible Consumer of all categories may set up the Renewable Energy
Generating System under the Net Metering Arrangement or Net Billing
Arrangement.
5.1 The minimum size of the Renewable Energy Generating System that can be set
up under Net Metering Arrangement and Net Billing Arrangement would be 1
kW.
5.2 The capacity of the Renewable Energy Generating System to be connected at the
Eligible Consumer's premises under any of the three arrangements shall not
exceed the Sanctioned load (in kW) or the Contract Demand (in kVA) of the
Consumer, as applicable.
Page 3 of 11
5.3 The maximum Renewable Energy Generating System capacity to be installed at
an Eligible Consumer's premises shall be subject to the cumulative capacity of all
Renewable Energy Generating Systems under Net Metering Arrangements
and/or Net Billing Arrangements connected to a particular Distribution
Transformer/feeder of the Licensee shall not exceed 70% of its rated capacity.
Provided that the variation in the rated capacity of the System within a range of
five percent shall be allowed.
5.4 HT (11 kV and above) Consumers may install and connect Renewable Energy
Generating System at their LT Bus Bar System:
Provided that, in such cases, the Net Meter shall be installed on the HT side of
the Consumer's Transformer.
5.5 An Eligible Consumer may install or enhance the capacity of, or upgrade the
Renewable Energy Generating Systems at different locations within the same
premises:
Provided that the total capacity of such Systems within the same premises shall
not exceed the capacity limits specified as above.
5.6 Consumers with pending arrears with the MSEDCL shall not be eligible for Net
Metering Arrangement or Net Billing Arrangement under these Regulations.
7.2 The Eligible Consumer may install a Renewable Energy Generating System with
or without storage.
7.3 If an Eligible Consumer opts for connectivity with storage, the inverter shall have
appropriate arrangement to prevent the power from flowing into the grid in the
Page 4 of 11
absence of grid supply, and that an automatic as well as manual isolation switch
shall also be provided.
7.4 The Eligible Consumer shall be responsible for the safe operation, maintenance
and rectification of any defect in the Renewable Energy Generating System up to
the point of Net Meter or Renewable Energy Generation Meter.
7.5 The Renewable Energy Generating System must have appropriate protection for
islanding the RE generating system from the network of MSEDCL to prevent any
feeding into the grid in case of failure of supply or grid and the same shall be
verified / certified by concern MSEDCL Testing division in consultation with
concerned subdivision/Circle as per applicable IEC/IEEE Technical Standards.
7.6 MSEDCL shall have the right to disconnect the Renewable Energy Generating
System from its network at any time in the event of any threat of accident or
damage from such System to its distribution system so as to avoid any accident
or damage to it: Provided that MSEDCL, considering the criticality, may call upon
the Consumer to rectify the defect within a reasonable time.
7.7 Every Renewable Energy Generating System shall be equipped with an automatic
synchronization device: Provided that the Renewable Energy Generating System
using inverter shall not be required to have separate synchronizing device, if it is
inherently built into the inverter.
7.8 The Total Voltage Harmonic Distortion (THD) shall be within the limits specified
in the Indian Electricity Grid Code (IEGC)/IEEE technical standards.
7.9 Grid Connected Renewable Energy Generating Systems connected behind the
Consumer's meter, and not opting for either Net Metering Arrangement or Net
Billing Arrangement, shall be allowed only after prior intimation as per
Annexure-5 of Regulations: Provided that the Consumer shall be responsible for
ensuring that all necessary safeguarding measures as specified by Central
Electricity Authority (CEA) are taken.
8. Metering
8.1 The Net Metering Arrangement shall include a single-phase or a three-phase Net
Meter, as may be required, located at the point of inter-connection as
ascertained by the MSEDCL.
8.2 All meters installed at the Renewable Energy Generating System shall comply
with the CEA (Installation and Operation of Meters) Regulations, 2006.
8.3 All meters shall have Advanced Metering Infrastructure (AMI) facility with RS485
(or higher) communication port.
8.4 Existing Meter in the premises of the Eligible Consumer shall be replaced by the
Net Meter at the cost of the Consumer.
8.5 If the Eligible Consumer is within the ambit of Time-of-Day ('ToO') Tariff, the Net
Meter installed shall be capable of recording ToO consumption and generation.
Page 5 of 11
8.6 MSEDCL shall be responsible for the testing, installation, and maintenance of the
metering equipment, and its adherence to the applicable standards and
specifications.
8.8 The Net Meter and the Renewable Energy Generation Meter shall be installed at
such locations in the premises of the Eligible Consumer as would enable easy
access to the MSEDCL for meter reading.
8.9 Check Meter of appropriate class to be installed by the MSEDCL for the
Renewable Energy Generation Meter for RE systems with capacity above 20 kW.
8.10 In case of Renewable Energy Generating System set up under Net Billing
Arrangement, an additional Check Meter for the Renewable Energy Generation
Meter of appropriate class shall be installed by the MSEDCL.
9.3 MSEDCL shall register the Application on first come first served basis and
acknowledge its receipt within three working days; or intimate the Applicant
within that period of any deficiency or incompleteness.
9.5 The time limits for sanctioning the RE generating system is given in the
Procedure of Application in Annexure-I which shall be followed scrupulously.
Page 6 of 11
9.6 All applications and payment of fees shall be compulsorily allowed through web-
based processing system by electronic means only.
9.7 All correspondence by the MSEDCL with the Consumer shall be through email
and mobile only.
HT Rs 5,OOO/-
Consumer
9.8 The approval for connectivity from the MSEDCL shall indicate the maximum
permissible capacity of the System, and shall be valid for a period of 6 months
from the date of approval, or such extended period as may be agreed to by the
MSEDCl. If the Consumer fails to set up the Renewable Energy Generating
System within the above stated period, then the approval shall be deemed to be
cancelled, and the Consumer shall have to apply afresh.
9.10 If the application is rejected due to defects in the ambit of consumer, a notice to
rectify the same shall be served to the consumer to rectify the defects within 15
days or such longer period as may be necessary, the deficiencies.
9.11 The Executive Engineer (O&M) Division and Sub Divisional Officer (O&M) shall be
the nodal officer for implementation from application to billing. SE (O&M),
MSEDCL to take monthly review and to co-ordinate the implementation of
connectivity of Roof top Solar PV systems issued by the concerned authorities as
above.
10.1 The eligible consumer after the approval of the RE generating system, shall have
to execute the connection agreement under Net-Metering or Net-Billing as the
case may be in the format Annexure-3 or Annexure-4 respectively.
10.2 The Connection Agreement shall remain in force for twenty years.
10.3 Eligible Consumer may terminate the Agreement at any time by giving 90 days'
notice to the MSEDCL: Provided further that the MSEDCL may terminate the
Page 7 of 11
Agreement by giving 30 days' notice, if the Eligible Consumer breaches any term
of the Agreement and does not remedy such breach within 30 days, or such
other longer period as may be provided, of receiving notice from the MSEDCL of
such breach, or for any other valid reason to be communicated in writing:
Provided also that the MSEDCL may terminate the Agreement by giving 15 days'
notice in case the consumer fails to pay his dues in a timely manner or indulges
in any malpractices: Provided also that the Agreement may be terminated at any
time by mutual consent.
11.1 The energy accounting and billing shall be carried out by the Nodal Officer/Billing
In charge.
11.2 The accounting of electricity exported and imported by the Eligible Consumer
shall become effective from the date of connectivity of the Renewable Energy
Generating System with the distribution network.
11.3 For each Billing Period the following information shall be made available on its
bill to the Eligible Consumer-
11.4 The energy generated by the Renewable Energy Generating Station shall be
offset against the energy consumption of the consumer from the MSEDCL in the
following manner:
Page 8 of 11
approved by the Commission for that year, within the first month of the
following year: Provided that, at the beginning of each Settlement Period,
the cumulative quantum of injected electricity carried forward will be re-
set to zero.
d) In case the Eligible Consumer is within the ambit of Time of Day (ToD)
tariff, the electricity consumption in any time block, i.e. peak hours, off-
peak hours, etc., shall be first compensated with the quantum of
electricity injected in the same time block; any excess injection over and
above the consumption in any other time block in a Billing Cycle shall be
accounted as if the excess injection had occurred during off peak hours;
e) MSEDCL shall compute the amount payable to the Eligible Consumer for
the excess Renewable Energy purchased by it as specified in Regulation
11.4 (c), and shall provide credit equivalent to the amount payable in the
immediately succeeding Billing Cycle.
11.5 Grid support charges shall be levied on the generated energy under Net-
Metering system: Provided that the consumers of all Categories having
Sanctioned Load up to 10 kW shall be exempted from payment of Grid Support
Charges for Net Metering systems.
11.6 If the Eligible Consumer leaves the system or changes the Supply Licensee, the
excess electricity shall be:
12.1 Net billing is the arrangement where the Renewable Energy Generating Station is: a)
Installed to serve a specific consumer, b) Connected on MSEDCL side or consumer
side of the consumer meter, c) Selling entire power generated to MSEDCL under
Power Purchase Agreement: Provided that if the Renewable Energy Generating
Station is connected on the consumer side of the consumer meter, then the
consumer shall have to replace the consumer meter with a Net Meter.
12.2 The accounting of electricity exported and imported by the Eligible Consumer shall
become effective from the date of connectivity of the Renewable Energy Generating
System with the distribution network.
12.3 For each Billing Period, MSEDCL shall make the following information available on its
bill to the Eligible Consumer:
Page 9 of 11
b) Quantum of electricity units consumed by the Consumer in the billing
period, including opening and closing balance;
12.4 MSEDCL shall enter into Power Purchase Agreement at the APPC approved for
the respective period by the Commission: Provided that the APPC stipulated in
the Power Purchase Agreement shall be constant for the entire duration of the
Agreement.
Energy Bill of consumer = Fixed Charges + other applicable charges and levies +
(EDLx TRST)- (ERE* TpPA) - Billing Credit;
[ Where EOLmeans the energy units supplied (i.e., Gross Electricity Consumption
by the Consumer) by MSEDCL as recorded by the consumer meter for the billing
period. TRSTmeans the applicable retail supply tariff of the concerned consumer
category as per the applicable retail supply Tariff Order of the Commission. ERE
means the energy units recorded for the billing period by the Renewable Energy
Generation Meter. TpPA means the energy charges as per the Power Purchase
Agreement signed between the Consumer and MSEDCL].
12.6 In case the Consumer installs Renewable Energy Generating Systems behind the
Consumer's meter without prior intimation to MSEDCL, then the total additional
liabilities in terms of additional Fixed Charges or Demand Charges and any other
Charges for such systems, shall be levied at twice the determined rate for such
period of default.
13.2 The electricity generated by the Renewable Energy Generating System during
the period in which the meter is defective shall be determined based on the
readings of the Check Meter: Provided that if the Check Meter is not installed,
then the electricity generated shall be considered equal to the average monthly
generation in the last one year or such shorter period as available.
14.1 Eligible consumer under these Regulations shall be eligible for incentives, which
may be applicable as per MERC Tariff Order for MSEDCL consumer; only to the
extent it uses MSEDCL supply.
Page 10 of 11
14.2 The Eligible consumer shall be liable to pay the penalty charges which may be
applicable as per MERC tariff order, amended from time to time, if the power
factor / THD is not maintained at required level as per State Grid Code.
All the field officers are requested to take necessary action accordingly.
~" ~\''1.9'l9
Chief En~~~ercial)
Copy to:
As per mailing list
Page 11 of 11
. ~-. - . -----