SPAR OVERVIEW
April 2003
THE PORI DELIVERY MODEL
Euronext
13170
TECHNIP-COFLEXIP FINLAND 2
WELCOME
MW YARD
TECHNIP-COFLEXIP FINLAND 3
MÄNTYLUOTO WORKS – FINLAND
TECHNIP-COFLEXIP FINLAND 4
MÄNTYLUOTO WORKS – FINLAND
n Covered fabrication area 48000 square meters
n Total yard area 11 hectares
n Steel fabrication capacity 18000 tonnes per annum
n Heavy Lift Capacity 2400 tonnes
n Multiwheeler transportation capacity 2300 tonnes
n The yard layout&loading facilities fits well for Spar Fabrication
n Competitive Advantages
l Reliability and Flexibility
l Short delivery times; successful concurrent engineering&fabrication
l Proven infrastructure management
l Cost effective and innovative construction methods
l Schedule according to contract, but not compromising QA/HSE
l Reference list
TECHNIP-COFLEXIP FINLAND 5
REFERENCE LIST
Project Delivery Date Project Delivery Date
Contract Actual Contract Actual
Gullfaks C, Gravity Base Sleipner Vest M12 Mod
GBS/MMO May 18, 88 May 1, 88 Deck Sections Nov 7, 94 Nov 6, 94
Snorre TLP Topsides Neptune Oryx
M1 Deck Part Apr 7, 90 Apr 12, 90 Spar Hull Jun 26, 96 Jun 19, 96
Sleipner Condensate Genesis
Modules Apr 27, 92 Apr 27, 92 Spar Hull Feb 15, 98 Feb 14, 98
Brage M10 Modules Gemini
Deck Sections Apr 3, 92 Apr 15, 92 Spar Hull Feb 2, 98 Jan 20, 98
Troll Phase 1 M2 Part Diana
Troll Deck May 20, 93 May 20, 93 DDCV Hull Jun 2, 99 May 26, 99
Troll Olje Nansen
Box Girders Oct 7, 93 Sep 20, 93 Truss Spar Hull Jul 27, 01 Jul 27, 01
Deepsea Bergen Boomvang
Sponsons Mar 1, 94 Feb 26, 94 Truss Spar Hull Sep 23, 01 Oct 12, 01
Heidrun M30 Module BP Horn Mountain
Grillage Apr 5, 94 Apr 6, 94 Truss Spar Hull Apr 12, 02 Apr 18, 02
Troll Olje MO Gunnison
Corbel Rings Jul 2, 94 Jul 2, 94 Truss Spar Hull Jun 1, 03
Holstein
Hard Tank & Mooring Sep 13, 03
Mad Dog
Truss Spar Hull Dec 16, 03
TECHNIP-COFLEXIP FINLAND 6
TECHNIP RAUMA OFFSHORE
Three Businesses:
•Staff 2000 - 100 people
•Staff 2001 - 120 people
•Staff 2002 - 130 people Project Management
MÄNTYLUOTO WORKS
•Staff 2000 - 580 people
•Staff 2001 - 650 people
•Staff 2002 - 800 people Fabrication
PI-RAUMA
•Staff 2000 - 180 people
•Staff 2001 - 200 people Engineering
•Staff 2002 - 200 people
SPAR CAPABILITIES 7
n Water depth 1,000 to 10,000 ft
n Well slots up to 40
n Oil throughout to 400 Mbod
n Gas throughout to 750 MMscfd
n Topside payloads 1,500 to 45,000 s. tons
n Hull diameters 20 to 200 ft
n Hull drafts 280 to 800 ft
n Storage 5 to 10 days production
SPAR ADVANTAGES 8
è Proven Concept
è Proven Delivery Record
è Flexible to Late Changes
è CAPEX Competitive
l T-C Delivers on Time
l T-C Delivers on Budget
è OPEX Superior
l More Drilling/Workover Up-Time due to Seafloor Riser Angle
l Smaller Marine Crew
è Safest Floater on the Market
è Concept for the Future Deep Water Activities World Wide
SPAR STABILITY 9
è Unconditional Stability
è Center of Gravity always below Center of Buoyancy
è Derives No Stability from Mooring System
è Failsafe Ballast System
l Filling all Ballast Tanks does not Sink the Spar
è No Licensed Marine Crew Required
è High Reserve Buoyancy
l Spar remains Afloat with 3 Buoyancy Compartments
è Good Tolerance for Topside Eccentricity
è Good Tolerance for Change in Topside Weight
è Stable in all Phases of Installation
è Can be Towed Vertically with Topside Installed
SPAR OPERATIONS 10
n Drilling/Workover
è Can start Well Deviation at Seafloor
è Pre-Drill with MODU
l Complete with MODU
l Complete with Spar WO Rig
è Drill and Complete with Spar
l Drilling Rig
è Phased Drilling with MODU
l Pre-Drill Phase 1 Wells with MODU
l Complete and Produce Phase 1 with Spar
l Offset Spar with Mooring System
l Drill Phase 2 Wells with MODU while Spar is Offset and Producing Phase 1 Wells
l Complete and Produce Phase 2 Wells with Spar
n Ballasting
è Unconditional Stability
è Failsafe System
è No Licensed Marine Crew Required
è Operators Option
l Trim for Rig Offset
l Trim for Load Changes
è Adjust Variable Ballast if Significant Weight Changes in the Future
l Neptune increased Topside Weight 17% after installation
SUCCESSFUL PROJECT EXECUTION 11
è Design
l Robust Concept
l Can adopt Changes at late Stage
§ Increase hard Tank Depth
§ Utilize Variable Ballast Margin
è Hull Fabrication
l Mantyluoto Works Experienced Yard Dedicated to Spar Hull Fabrication
l Proven Track Record
è Moorings
l Simple and Rugged
è Topside Fabrication
l Gulf Marine Experienced Yard
l Proven Track Record
è Risers
l TOI Design and Delivery Capability
l Proven Track Record
è Marine Operations
l Heavy Lift Vessel Required
l Topside Lift Critical
TECHNIP-COFLEXIP FINLAND 12
SUCCESSFUL PROJECT EXECUTION
ationship
m er Rel
RESULTS Custo ement
g
Mana
DELIVERY ject
Project Pro
e m ent
g
Mana
CAPACITY C hain
Infrast ly
ructure Supp gement
Mana 9001
PROCESS Quality ISO
Standa
rd
TECHNIP-COFLEXIP FINLAND 13
SUCCESSFUL PROJECT EXECUTION
PROJECT MANAGEMENT PLAN
Project Specific Plans
Standard
Project Management
Substance
Procedures
Project
Management
Company Plan - PMP
Procedures
TECHNIP-COFLEXIP FINLAND 14
SUCCESSFUL PROJECT EXECUTION
PROPOSAL
BASIS
Delivery
Commitment
Pricing
Project
Management
Plan
Technical Proposal
Specification
TECHNIP-COFLEXIP FINLAND 15
SUCCESSFUL PROJECT EXECUTION
CUSTOMER
RISK COST
Ownership
Structure
Management Contingency
Systems
Track Record
Execution
Price
Plan
CONTRACTOR
• •Commitment • •Innovation
Innovation
Commitment
• •Communication • •Productivity
Productivity
Communication
• •Profit
ProfitExpectations
Expectations
• •Currency
CurrencyRate
Rate
• •Labor cost
PROJECT COST DRIVERS Labor cost
TECHNIP-COFLEXIP FINLAND 16
SUCCESSFUL PROJECT EXECUTION
FABRICATION ORIENTED
ALL PROJECTS ARE
SCHEDULE DRIVEN • Clear goals
• Clear responsibilities
• Meaningful work
ENGINEERING SERVES
FABRICATION
THE ONE WHO DOES THE WORK
IS THE BEST EXPERT
OF HIS WORK
TECHNIP-COFLEXIP FINLAND 17
KEY SUCCESS FACTOR
SEQUENTIAL
Engineering
• Information
Transfer
Fabrication
CONCURRENT
Engineering
• Knowledge Sharing
• Controlled Risk Decisions
Fabrication
CAISSON SPAR VS. TRUSS SPAR 18
SPAR DRILLING OPTIONS 19
TECHNIP-COFLEXIP FINLAND 20
RING SECTION ASSEMBLY
TECHNIP-COFLEXIP FINLAND 21
MATING TRUSS TO HULL
TECHNIP-COFLEXIP FINLAND 22
DRY TRANSPORT
PRE-UPEND 23
TOPSIDE LIFT 24
TECHNIP-COFLEXIP FINLAND 25
NEPTUNE ROC-32 GENESIS ARO-33 DIANA ARO-45
Main dimensions: Main dimensions: Main dimensions:
Hull diameter 21,95 m Hull diameter 37,19 m Hull diameter 37,19 m
Hull height 214,88 m Hull height 214,88 m Hull height 214,89 m
Hull light weight 11 699 tons Hull light weight 25 923 tons Hull light weight 31 224 tons
Delivery year 1996 Delivery year 1998 Delivery year 1999
Client Oryx Client Chevron Client Exxon
TECHNIP-COFLEXIP FINLAND 26
NANSEN ARO-55 BOOMVANG ARO-56 HORN MOUNTAIN ARO-58
Main dimensions: Main dimensions: Main dimensions:
Hull diameter 27,43 m Hull diameter 27,43 m Hull diameter 32,21 m
Hull height 165,51 m Hull height 165,51 m Hull height 169,16 m
Hull light weight 10 521 tons Hull light weight 10 540 tons Hull light weight 13 278 tons
Delivery year 2001 Delivery year 2001 Delivery year 2002
Client SII Client SII Client AMI
BP HOLSTEIN SPAR 27
n Water depth: 4,344 ft. (1,324 m)
n Topsides payload: 28,000 ST (25,400 metric tons)
n Diameter: 146 ft. (44.5 m)
n Length: 780 ft. (HT: 256 ft., T: 493 ft., ST: 22 ft.)
n (237.7 / 78.0 / 150.3 / 6.7 m)
n Center-well: 75 ft. x 75 ft. (22.9 m)
n Top tensioned risers: 16
n Hard tank weight: 20,700 ST (21,500 metric tons)
n Truss and soft tank weight: 9,000 ST (8,200 metric tons)
n Mooring: 16 lines with suction anchors
TECHNIP-COFLEXIP FINLAND 28
Status of projects
Project Section Half section Hull erection Outfitting Delivery
fabrication assembling
Gunnison 100 % 100 % 100 % 80 % June 1.
2003
Holstein 100 % 70 % 30 % 20 % Sep 9.
2003
Mad Dog 60 % 40 % 10 % 10 % Dec 16.
2003
TECHNIP-COFLEXIP FINLAND 29
SPAR PROGRESSION
30
For more information,
please contact:
INVESTOR RELATIONS
G. Christopher Welton
Tel. +33 (0) 1 55 91 88 27
e-mail: [email protected]
David-Alexandre Guez
Tel. +33 (0) 1 47 78 27 85
e-mail: [email protected]