PMP Manual
PMP Manual
Page i
Notices
Disclaimer: While Looking Glass Development takes care to ensure the accuracy and quality of these materials, we
cannot guarantee their accuracy, and all materials are provided without any warranty whatsoever, including, but not
limited to, the implied warranties of merchantability or fitness for a particular purpose. The names used in the exercises
are fictitious. Any resemblance to current people or organizations is purely coincidental. LGd is an independent provider
of integrated training and consulting solutions for individuals, businesses, educational institutions, and government
agencies.
Use of screenshots, photographs, or other representations of another entity’s product or service in this book is for
editorial purposes only. No such use should be construed to imply sponsorship or endorsement of the book by, nor any
affiliation of such entity with Looking Glass Development. This courseware may contain links to sites on the Internet that
are owned and operated by third parties (the “External Sites”). Looking Glass Development is not responsible for the
availability of, or the content located on or through, any External Site.
Trademark Notices: Looking Glass Development, LGd and the LGd logo are trademarks of Looking Glass
Development.
Copyright © 2016 Looking Glass Development, LLC. All rights reserved. Screenshots, photographs and other
representations used for illustrative purposes are the property of the software proprietor. This publication, or any part
thereof, may not be reproduced or transmitted in any form or by any means, electronic or mechanical, including
photocopying, recording, storage in an information retrieval system, or otherwise, without express written permission of
Looking Glass Development, LLC PO Box 630516 Littleton, CO 80136-0516 (303) 883-3917. Looking Glass
Development LLC’s World Wide Web site is located at http://www.lookingglassdev.com.
This book conveys no rights in the software or other products about which it was written; all use or licensing of such
software or other products is the responsibility of the use according to terms and conditions of the owner. Do not make
illegal copies of books or software. If you believe that this book, related materials, or any other Looking Glass
Development materials are being reproduced or transmitted without permission, please call
1-303-883-3917.
“PMI” is a federally registered trade and service mark; “PMP” and the PMP logo are federally registered certification
marks; and the PMI logo, “PMBOK” and “Building professionalism in project management” are trademarks of the
Project Management Institute.
PMI did not participate in the development of this course and has not reviewed the content for accuracy or content. PMI
does not endorse or otherwise sponsor this course, and makes no warrantee, guarantee, or representation, express or
implied, as to its accuracy or content.
Contact Information:
Looking Glass Development, LLC
PO Box 630516
Littleton, CO 80163-0516
(303) 883-3917
Fax: (303) 600-0985
E-Mail: [email protected]
Internet: http://www.lookingglassdev.com
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Table of Contents
Page ii
Table of Contents
Chapter 1 — PMP® Application & Exam ……………………….…………………….…1
Student Guide Overview ………………………………………………..………….1
Course Expectations …………………………………………………..……………2
PMI’s Assumptions ………………………………………………..……………….3
The Certification Process ………………………………………..…………………5
PMP® Candidate Requirements ………………………………..……………..…….6
The PMP® Exam …………………………………………………..…….………….8
Domain Tasks ……………………………………………………………………..10
The Required Score ……………………………………………………………….17
What Makes the PMP® Exam So Difficult? ………………….……………...……18
Test Taking Strategies …………………………………………………………….19
Final Comments Before Starting ……………………………………..…….……..21
Exercise 1 — Application & Exam ...………….………………………….…...….23
Exercise 1 — Application & Exam Answers ……………………………..………25
Chapter 2 — Types of Exam Questions ……………………………………………..…...26
Chapter Overview ………………………………………….…………..………….26
Questions With Two Right Answers ………………….……………..……………26
Situational Questions …………………………………………...…………………27
Math or Modeling Questions ………………………………………………...……28
Long winded questions & questions with extraneous information ……………….29
Understanding Versus Memorization ………………………………………...…...30
Questions With Invented Terms ……………………………………………...…...31
Answers With More than One Component ………………………………..……...31
PMIisms ………………………………………………………………..…………32
Why People Fail The Exam ……………………………………..………………..34
Exercise 2 — Types of Questions …………………………………..…………….36
Exercise 2 — Types of Questions Answers …………………………………..…..37
Chapter 3 — The Basics of Project Management — Part 1 ……………………….…...38
What is the Perfect Structure? ………………………………………………...…..38
Organic or Simple Organizations …………………………………………………39
Functional Organizations ……………………………………………………..…..39
Projectized Organizations ………………………………………………..………..42
Matrix Organizations …………………………………………………..……….…45
A Weak Matrix Organization …………………………………………………..…45
A Balanced Matrix Organization ……………………………………………..…..46
A Strong Matrix Organization ……………………………………………..……..46
Advantages of a Matrix Organization ………………………………………..…...47
Potential Issues With a Matrix Organization …………………………………..…48
Virtual / Hybrid / PMOs …………………………………………………………..49
Exercise 3 — Organizations and Project Management ………….…………..……51
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Table of Contents
Page iii
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Table of Contents
Page iv
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Table of Contents
Page v
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Table of Contents
Page vi
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 1
Course Introduction
Student Guide Overview
This student guide is designed to be the primary resource for your PMI Project
Management Professional or PMP® Certification Exam Prep course. The course
itself is an online course which includes video lecture, exercises, and practice
quizzes. It is specifically designed for the PMP® Exam released in March, 2018.
However, if you have not purchased the online course you will still find this book
extremely useful in preparing for the exam. Regardless of whether you have
purchased the online course or not, it is highly recommended that you obtain a copy
of the PMBOK® Guide from the PMI® online bookstore.
Throughout the guide major points are called out in the sidebar to improve
learning. These comments appear with one of several indicators to highlight the
type of information provided. These indicators include:
TIPS — Key tips to help ensure that you pass your test.
WARNINGS — Major pitfalls that often cause people to fail the test.
PRACTICE EXAMS — Practice exams to help you prepare for the exam.
Page 2
Not all chapters have the same level of difficulty. When studying, you should
therefore allot your time based upon the suggested level of difficulty. Most
candidates find the information/knowledge areas fall on a spectrum from most
difficult to least difficult that looks like this:
Learning the 49 PMI processes, inputs, outputs, tools and techniques Focus your
Learning the 42 processes defined by the Role Delineation Study studies
Integration Management based on the
level of difficulty
Risk Management
Cost and Schedule Management (most of the tools and techniques are
the same in both knowledge areas)
Procurement Management
Quality Management
Scope Management
Resource Management
Communication Management
Stakeholder Management
This manual provides some additional resources to assist your learning. The first is
a copy of the PowerPoint material used to develop the online course. Additionally,
there are three documents that will help you prepare for the exam. These include
the PMP Handbook, the Current PMP Exam Content Outline, and the PMP Sample
Questions. Each of these items are PDFs that you may download and print and are
found at:
Download the
https://www.pmi.org/certifications/types/project-management-pmp/exam-prep PMP®
Credential
Course Expectations Handbook
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 3
First skim the entire work taking not more than 90 minutes to two hours for the Use the three
entire book focusing on the headings, graphics and captions. Don’t worry that read
you can’t remember anything. You are just getting the big ideas at this point. technique to
quickly learn the
Secondly, read for understanding and highlight important information. PMBOK® Guide.
However, be careful. The PMBOK® Guide is incredibly information dense and
there is a tendency to highlight too much.
Finally, review your highlighted content to ensure your learning.
At first blush it might not seem like the three read technique is a time saver,
however using this technique will save significant time and dramatically increase
your understanding and retention—both of which will increase your likelihood of
passing the exam on the first try.
Despite the fact that the PMBOK® Guide is very important for the exam, it is a
misconception to think that the PMI-PMP® Exam is based on the PMBOK® Guide.
This is not the case. The exam is actually based on a document called the Role
Delineation Study, or RDS, which is conducted every three to five years as part of
PMI’s standards development process. The RDS is a available on Amazon or
PMI’s bookstore. However, be forewarned it is not your typical read. The RDS is
a social science survey report showing what skills, tools, and techniques real-world
project managers are using to deliver business results. Unfortunately, the
information is not presented in a way that provides much help. Outside of the
PMBOK® Guide there are twelve books are considered foundational for the exam.
The PMBOK® Guide is merely one of the 12 although it provides the framework
for project management. The other books used as a foundation for the exam
include:
Project and Program Risk Management, R. Max Wideman, Editor
Quality Management for Projects and Programs, Lewis R. Ireland Slide 4
Doing Business Internationally, Walker, Walker and Shmitz
The Cultural Dimensions of International Business, Gary P. Ferraro
Global Literacies, Robert Rosen
How to Lead Work Teams, Fran Rees
Principles of Project Management, PMI®
Project Management A Systems Approach, Harold Kerzner
Human Resource Skills for the Project Manager, Vijay K. Verma
Earned Value Practice Standard, PMI®
The Scrum Guide™ , Jeff Sutherland and Ken Schwaber
These books provide significant information used by the people who write the
exam questions. However, it is NOT recommended that you read all of these
books to prepare for the test unless you are really struggling with a topic and wish
to have all the source information.
PMI’s Assumptions
As you prepare for the PMP® exam, it is important that you understand some basic
assumptions made by the exam item writers. These tidbits can be thought of as
free points of wisdom for the exam. They provide much needed context for
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 4
specific questions. One of the basic assumptions PMI® makes with the exam is that
you have real-world experience managing projects. You prove this assumption
through the answers you provide on your application concerning your post
positions.
The next assumption PMI® makes concerns the type of project you are leading. In
the real-world, we are all leading very different sized projects across a wide range
of industries. Unfortunately, it is impossible to test across that range. Therefore,
PMI® standardizes the basic project used as the baseline for the exam. This is
typically a large project in a matrixed organization. Examples of large projects
include:
Deploying a new accounting, ERP, or CRM system for any organization of
more than 500 people.
Building a new building, road, light-rail system, or other large traditional
engineering endeavor.
Developing a new commercial product.
Creating a new manufacturing process for medium to heavy industry or
hardware for a high technology firm.
Developing a new support operation for an organization of more than 500
people, such as a new accounting operation, call center, or help desk.
The best way to succeed on the exam is to keep one point of focus. Unless the
question provides a different scenario, the following circumstances apply as you go
through the exam. You work as a project manager for a large multinational called
Slide 5
the Acme Widget Factory. You are leading a project to develop a new product that
is critical to the organization’s success. You are managing 100 resources located in
five different time zones on two different continents. You work in a matrixed
organization and none of the resources are dedicated to only your project or report
directly to you. It is not enough to simply have worked on projects like these. To
be successful with the exam, it is also important that you assume nothing goes
perfectly. You are expected to have confronted the following challenges:
Significant issues with scope change.
Significant schedule and cost overruns.
Problems managing resource constraints.
Problems managing product quality.
Significant resource burnout.
A sense of fighting your processes to complete the real work.
The first “free” question is about what the acronym PMP® represents. PMP®
stands for Project Management Professional® when formally spelled out. The Slide 6
second “free” question is “When was PMI® founded?” PMI® was founded in
1969. The third set of “free” questions deals with understanding why PMI®
believes it is important that project managers become certified. PMI® offers three
main reasons for certification from the project manager’s perspective:
It gives you higher income potential
It proves you know international standards
It’s required by a growing number of employers
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 5
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 6
Do not be tempted to exaggerate your experience in any way. PMI® is very good
at weeding out embellished applications and you will likely be caught.
Additionally, such efforts are clear violations of the PMI® Code of Conduct.
PMI® targets an audit rate between 12% and 18% of all applications received.
Therefore, it is also possible to be selected for an audit without having a problem
on your application. Should you be selected for an audit, PMI® will contact each
of your former employers to confirm the information provided, and you will be
asked to provide formal proof of your degree and educational status. PMI®
commits to completing their portion of the audit process in five to seven days but
you are allowed up to 90-days to collect all the information. Should you be audited
you can reasonably expect the process to add 30-days to your timeline.
Once you have completed the Experience Verification Form you must submit it to
PMI®. You are not required to submit payment at the time of application but you
must pay the test fees prior to being able to schedule your exam. PMI® provides a
significant enough discount to PMI® members that it actually costs less to join
PMI® and pay for the test than to pay for the exam as a non-member. The fees for
the exam are:
®
PMI members pay $405 (retaking the test costs $275)
Non-members pay $555 (retaking the test costs $375)
Once you have received your acceptance notification from PMI® and have paid
your exam fee you can schedule the test. With limited exceptions, the test is
delivered as a computer-based exam and is not based on a set schedule. The exam
is administered by Prometric Testing Centers. In most locations it can be taken
Monday through Friday during normal business hours as well as on Saturday. This
does not necessarily mean, however, that you can take the exam whenever you
like. Prometric provides support for most standardized exams so there is often
significant competition to get a seat. Therefore, you should schedule your exam at
least two weeks prior to your target date and have a little flexibility around your
date and time. To schedule your exam or to find the nearest testing center visit
Prometric’s website at:
http://prometric.com/PMI
PMP® Candidate Requirements
Many candidates are confused by PMI’s requirements for entry to the exam. There
are two major components of the requirements: your professional experience and
your education that is specific to project management.
PMI® breaks a candidate’s experience into two categories, referred to as Category I
and Category II. The defining criteria for which category you are placed in is
whether or not you hold a four year bachelor’s degree or global equivalent.
Candidates do not receive additional consideration for advanced degrees. Those
holding a four year degree are considered Category I candidates and those without
a four year degree or equivalent are considered Category II candidates. The
category determines the number of hours of professional experience required to
qualify for the exam.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 7
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 8
Should you have questions about certification or any other PMI® specific Slide 8
information you should contact PMI® Customer Care at:
Project Management Institute
Certification Dept.
14 Campus Boulevard
Newtown Square, PA 19073-3299 USA
Tel: +1-610-356-4600
Fax: +1-610-356-4647
E-mail: [email protected]
If you do not have access you the internet, it is possible to complete the application
using the application found in the PMP® Certification Handbook. Once you have
completed the application simply mail it in to the address listed above. Using the
paper application will significantly slow down the review process, however. PMI®
says they will review paper applications within 10-days of receipt for an individual
and within 20-days for a group. The standard for online applications is five days.
You should not hold these as guarantees as it has been known to take longer based
on the volume of applications PMI® has at any point in time.
The PMP® Exam
The standard format for the exam is a four hour, 200 question, computer-based test
(CBT) administered in English. PMI® does allow for paper-based testing in limited
circumstances. Those circumstances include:
Candidates who live at least 186.5 miles/300 km from a Prometric CBT site.
®
Employers (Corporate Sponsors) who wish to administer a PMI examination
to their employees. In this case, there is no restriction on distance. Only
employees of that one organization may test at the event. PMI® also reserves
the right to cancel a corporate session if less than 10 participants are scheduled
to take the exam.
®
PMI maintains additional restrictions for paper-based testing. To learn more
about paper-based testing contact PMI® directly at [email protected].
Although the test is only provided in English,
PMI® does provide additional language support Arabic Hebrew
in several additional languages. In such Brazilian Portuguese Italian
situations the exam question is given in English
on one half of the screen and the question and Chinese (Simplified) Japanese
possible answers are on the other half of the Chinese (Traditional) Korean
screen translated into a second language. The
available languages are shown in the Image 2. French Russian
German Spanish
Upon entering the testing center you must
provide two forms of identification. One of Image 2: Additional Languages Supported
these must be a government issued photo ID.
Many of the testing centers provide storage for personal items. However, it is
strongly recommended that you do not take anything other than your two forms of
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 9
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 10
Domain Tasks
An issue that many PMP students struggle with is understanding the difference
between the processes found in the PMBOK® Guide and those defined by PMI’s
Role Delineation Study. The two are actually very close but they are not in a one-to
-one relationship. There are 49 processes defined in the PMBOK® Guide and 42
tasks found in the Role Delineation Study. It is important that you understand both
sets of processes. For the purposes of this manual we will refer to the items found
in the PMBOK® Guide as “Processes” and the items found in the Role Delineation
Study as “Tasks.” Both are grouped into the five process groups shown in Image 3
(Initiating, Planning, Executing, Monitoring and Controlling, and Closing). Much
of this course focuses on the Processes found in the PMBOK® Guide. We will start
however, with the Tasks and then relate them to the Processes as we go.
The Tasks are often an easier place to start because they are designed to represent a
specific task done by the project manager and/or the team in the execution of a
project. There is absolutely nothing that says that you must do all of the tasks or
processes on any given project. Remember, these simply represent the most
common or generally accepted practices PMI® has seen based on their Role
Delineation Study (RDS). These tasks did NOT change with the release of the 6th
edition of the PMBOK Guide, and will only change when the RDS is updated. It is
fully expected, and even encouraged, that every project manager and their team
must define the “right” processes and tasks on each specific project. This includes
the selection of the specific methodology the team wishes to use.
The June, 2015 version of the Exam Content Outline defines the following tasks:
Initiating Domain — 13% of the Exam
Slides 10-11
1. Perform a project assessment based on the available information, the
lessons learned from previous projects, and the meetings held with
relevant stakeholders. This provides the information necessary to
evaluate the feasibility of new products or services within the given
assumptions and/or constraints. This task is a mouthful, but it simply
means that someone must look at what the organization and others have
done in the past to determine if the project can really be done in the
current situation. This task is all about determining whether or not the
project will provide the desired business value given the specific
conditions that currently exist.
2. Identify the key deliverables based on the business requirements in order
to manage customer expectations and direct the achievement of project
goals. This task was new for the 2016 exam, and brought an agile
perspective to the PMP®. It pushes project leaders to prioritize the
project’s requirements from most important to least. It also demands
that a project focuses on business needs rather than simply project
deliverables.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 11
Page 12
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 13
Page 14
Page 15
Measure project performance using appropriate tools and techniques in Slide 16
order to identify and quantify any variances and corrective actions.
Quantitative measurement is a key aspect of attaining project success.
Only by using objective measures can the team determine variances and
define appropriate corrective action.
Manage changes to the project by following the change management
plan in order to ensure that project goals remain aligned with business
needs. Throughout the project, the team will face a variety of changes.
Therefore, it is critical that they follow the approved change
management plan and constantly reconfirm that the project fits with the
organizational strategy.
Verify that project deliverables conform to the quality standards
established in the quality management plan by using the appropriate
tools and techniques to meet project requirements and business needs.
This task is simply about following through on the practices that were
established when quality was defined.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 16
Monitor and assess risk by determining whether exposure has changed
and evaluating the effectiveness of the response strategies in order to
manage the impact of the risks and opportunities on the project. There
are a variety of techniques that may be used to respond to different
project risks. The key is alignment, or making sure the team uses the
best response strategy to achieve the desired end. This means that the
team must constantly judge how well each response is working.
Review the issue log, update if necessary, and determine corrective
actions by using appropriate tools and techniques in order to minimize
the impact on the project. An ISSUE is a current condition or situation
that may have an impact on the project objective (PMBOK® Guide 2017
p.709). Issues may have positive or negative outcomes and are
documented in the issue log.
Capture, analyze, and manage the lessons learned, using lessons learned
management techniques in order to enable continuous improvement.
Successful teams know they cannot keep making the same mistakes
over and over again. It is critical that teams review what has happened
on projects in the past.
Monitor procurement activities according to the procurement plan in
order to verify compliance with project objectives. Lessons learned
provide an opportunity to focus on continuous improvement. This is a
task often foreign to PMP® students. Make sure you understand PMI’s
perspective on procurement to avoid missing points on questions that
are easy otherwise.
Closing Domain — 7% of the Exam
Page 17
Prepare and share the final project report according to the
communications management plan in order to document and convey the
project performance and assist in project evaluation. As has already
been stated, lessons learned and continuous improvement are key topics
for test takers. You must focus on these two ideas and understand the
importance that PMI® places on them.
Collate lessons learned that were documented throughout the project
and conduct a comprehensive project review in order to update the
organization’s knowledge base. This is yet another task dealing with
lessons learned and continuous improvement. Hopefully, you already
see the trend.
Archive project documents and materials using generally accepted
practices in order to comply with statutory requirements and for use in
future projects and audits. This was a new task with the 2016 exam and
represents a continuation of the efforts seen in the last couple of items.
There has always been an idea that project managers should look at
what the organization has previously done to understand how to avoid
common pitfalls. This task formalizes that process.
Obtain feedback from relevant stakeholders using appropriate tools and
techniques and based on the stakeholder management plan in order to
evaluate their satisfaction. This task was also new for the 2016 exam.
It provides the opportunity for the team to check in with the key
stakeholders to ensure that their needs have been met. It focuses the
attention of the team on meeting the needs of the business. It is the very
reason projects are undertaken in the first place.
Required Score
Once you begin the actual exam make sure to answer every question because there
is no penalty for incorrect answers, but questions left blank are considered wrong. Slides 19
As you progress through the exam, mark any question you are unsure of for review.
At the end of the exam you can check all the questions or only those questions that
you have marked for review. Upon completing the exam, and your review, the
system will ask if you are ready to have the exam scored. Once you confirm you
are ready for the exam to be scored it will take less than ten seconds for the results
to be presented. It is important to remember that the PMP® Exam is a pass/fail
exam. The passing score is 61% or 106 of the 175 graded questions.
Unfortunately, only 68% of the exams taken are actually passed! Stop for a
moment and think about those two numbers. What they suggest is that this exam is
so difficult that only about two-thirds of those who take the test can answer enough
questions correctly to obtain a D– or better. Simply put, the PMP® Exam is likely
the most difficult standardized test you will ever take. Do not underestimate how
hard it will be!
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 18
Page 19
answer the questions from the perspective of the standard meaning you must
assume the “typical” project PMI® uses for test design.
Some questions might be a series. This means the first question in the series
asks you to solve a math problem or model and then anywhere from one to four
additional questions asks what the resultant value tells you about the situation.
If you get the first question wrong you will likely get all the associated
questions incorrect as well. Missing a series of questions like this is a quick
way to fail the exam.
Some of the questions are based on the inputs, outputs, tools and techniques
found in the 49 processes described in the PMBOK® Guide. This creates a list
of several hundred items that must be learned correctly. That’s a lot of
information and it takes time. It is not required to memorize each input, output,
tool and technique, but you do need to have a strong sense about them and
when one is called out where it fits in a specific process. Manage your time
accordingly!
A number of key formulas will likely be on the exam. These formulas include:
Earned Value, Critical Chain or CCPM, PERT, EMV, and CPM. Studying
these formulas is a lot like purchasing insurance. The formula you are most
likely to see on the exam is the one you have studied the least or with which
you are least comfortable. In fact, if you really study hard and master all the
formulas, it’s even possible to not get any questions requiring their use. On the
other hand, if you don’t study them you will be the one person that seems to get
an exam of nothing but math. Which one of these scenarios sounds better to
you?
Another 10%-15% of the exam will require the use of other formulas such as
the formulas for Didactic communication, standard deviation, depreciation, or
net present value (NPV). The same rules apply here as above.
Test-Taking Strategies
The PMP® exam is similar to a lot of other standardized exams, and as such you Slide 22
can apply a number of commonly used test-taking strategies to improve your
results. These strategies will not replace knowing the subject matter, but they can
provide a significant lift to your score when you are nervous or struggle with
specific questions. These strategies include:
Predict the answer: If you have studied hard and truly know the material, a
great technique is to predict the correct answer to a question before you read the
choices. This technique is especially effective on questions that test your
factual knowledge or ask you to fill in the blank or complete a sentence. By
first predicting the answer you can avoid being distracted by choices that don’t
agree with your knowledge. Once you make your prediction make sure to read
all of the choices so you can be sure to select the answer that most closely
meets your expectations.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 20
Your first instinct: Often, test-takers struggle because they overthink the
questions. If you have done your homework, you will know the information
and must have confidence in that knowledge. It is critical that you trust your
first instinct. That little voice you hear is right more often than not. Research
has shown that your intuition often works faster than your reasoned mind. If
you have studied, your subconscious will often retrieve information before you
have a chance to work out the associations that support it.
Read the whole question: Predicting the right answer and trusting your
instincts does NOT justify failing to read the entire question. Adding or
deleting one word can significantly alter the meaning of a question. Far too
often, test takers scan a multiple-choice question and recognize a few familiar
words. They then quickly progress to the answers where they find exactly what
they believe to be the correct choice. Unfortunately for them, test designers
also know about this tendency and regularly design questions taking it into
account. The only way you can avoid this pitfall is to read each question
carefully and then read it again before continuing to the potential answers.
PMI® allows up to four hours for the exam. This is more than enough time to
complete the exam. There is absolutely no reason to rush through the exam.
Take the time to carefully read each question and all the potential answers
before attempting to select the appropriate answer.
Look for wrong answers: Once you have read the question carefully twice it is
time to examine the potential answers. One of the best way to simplify a
multiple-choice exam is to limit the number of potential choices. Focus on
removing the obviously wrong answers from the list before you consider the
potential right ones. Sometimes identifying an incorrect answer can help you
find the correct one as often the right answer is the exact opposite of one of the
wrong answers. This is not always the case, but it is a quick enough tactic to
help in many cases.
Don’t overanalyze: It is very common for test takers to be nervous. When you
are nervous the brain often runs wild with a hundred different thoughts and
scenarios for each question. To succeed, you must take a deep breath and
SLOW DOWN! You have plenty of time to complete the exam. Focus on the
actual words in front of you. Do NOT create complex interpretations or try to
get into the mind of the test designers. Answer the question in front of you and
limit your thoughts to the information presented.
Key words: Do you struggle with poor reading comprehension skills? If so,
you are like 60% of the people who take the PMP® exam. You can
dramatically improve your understanding by using the provided scratch paper
to jot down a few key words or phrases. This practice helps you to concentrate
on the process of reading by forcing the mind to weight the relative importance
of the question parts. This process will help you think more deeply and
carefully about the question.
®
Confusing answer choices: The PMP exam is full of long winded questions
and answers. Many candidates are confused by such wordy content. As a
result, they tend to focus on the answers that are shorter and often easier to
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 21
understand. Don’t make this mistake. The length of an answer or its confusing
diction has nothing to do with its validity. When you see a long winded
question or answer pay extra attention and try rephrasing it to ensure your
understanding.
®
True statements: Often PMI uses information within the four potential
answers that is completely factual. That’s right, the information is true, but just
because the information provided in the answer is true it does NOT make the
answer necessarily correct. It is critical that you learn to tell the difference
between a factual answer and a correct one.
No pattern: Many students believe they can decipher a pattern in the answers
on the test, or that they should always select a specific letter like “C”. This is
one of the worst ideas you can possibly take into the testing room. Remember,
your exam is generated from thousands of potential questions. The criteria for
being included in your test is whether or not the question gives us the correct
number of questions for a specific area. Additionally, the system randomizes
the answers so that two candidates could be sitting next to each other and get
the same question, but find the correct answer is a different letter.
Final Comments Before Starting
It is very important that you plan on taking your exam within 45-days of
completing this course. Although according to PMI® you have up to one year to
complete the exam from the date of your application acceptance, our experience
has been that students who do not complete the exam within 45-days have a high
probability of never taking the exam at all. It all starts by making the commitment.
You WILL complete the process within 45-days from the end of this class. The
clock is ticking so it’s time to get serious.
You must have a plan for studying for the exam. There are a few techniques we
recommend. First, become part of a study group. Studying with others can really
help. Each time your group meets it is a great practice to have each member of the
group present a different PMBOK® Guide knowledge area until each person
presents each area. The single best thing you can do to prepare for the exam is
teach the material to someone else. Studies have shown you will retain more than
90% of what you teach to others.
Should it be required, you may take the PMP® exam up to three times in one 12-
month period. If you fail the exam three times in that period PMI® requires you to
wait a full 12-months before you can test again. We have never had a candidate
who needed to take the exam three times. In fact, 99% of our candidates pass on the
first attempt. Do not become the exception. We know the test and have a proven
method to get you ready. This process and the knowledge you need has absolutely
nothing to do with the way your organization manages projects. As much as you
might want to argue with some of the processes, most—if not all of them—have
their basis in common sense, have been designed to work across a wide range of
industries, and are on the test. Arguing about questions or answers will not
accomplish anything but waste your time and create confusion.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 22
The rest of this course is designed to follow the basic structure of the PMBOK®
Guide with practice exams designed to facilitate learning at the end of each section.
The first two chapters are the exceptions as they simply introduce information
about the test and learning process. Chapter three in the Student Guide represents
chapters one through three of the PMBOK® Guide. Chapters four and onward
align with the same chapter number found in the PMBOK® Guide.
There are two types of questions in this guide:
Questions designed to facilitate your learning of the processes, formulas,
inputs, outputs, tools and techniques. These are memorization questions and do
not reflect the questions you will see on the real exam. However, they are a
powerful tool to help you learn the information that will allow you to answer
the real exam questions.
Questions designed to simulate what you will see on the real test.
It is important that you do not write in the course book when taking your practice
exams because you will want to retake the practice tests multiple times. Finally,
you will know that you are ready for the real exam when you regularly score 90%
or better on the practice tests.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 23
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 24
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 1 — PMP® Application and Exam
Page 25
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 26
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 27
During your daily standup, a teammate reports that they are struggling with a Slide 25
critical task that is causing the project backlog item to be delayed. What should
you do?
A. Immediately inform the sponsor and key stakeholders.
B. Evaluate alternatives with the team.
C. Trust the team to handle it.
D. Keep pushing ahead as there is nothing you can do.
Most people are able to immediately eliminate D because it means ignoring the
problem. The other three options might be a bit tougher. Immediately informing
the sponsor and key stakeholders might seem like a good idea if you are a
proponent of transparency, but it is a terrible idea. Most senior leaders do not
respond well to project managers who come in with problems and no potential
solutions. Project leaders are hired to lead. Option B provides a reasonable
solution in evaluating alternatives based what was just suggested. Option C also
appears reasonable given that this question suggests yours is an agile project. Agile
development places a strong emphasis on trusting the team. However, agile
development does NOT suggest that the scrum master or project leader should just
assume the team will handle problems. The correct answer is B — Evaluate
alternatives with the team. It is always the first step in the process.
Situational Questions
The most important questions to prepare for on the exam are the situational
questions. These questions attempt to place you in a real-world situation and
require you to determine the best answer. In most cases the textbook answer is not
one of the four choices. As a result, you must pick the best from four sub-optimal
answers where you probably don’t really like any of the choices. Isn’t that often
the way things work in the real world?
Let’s examine a sample question.
Molly works for a large multi-national organization that manufactures steel as a Slide 26
project coordinator. He organization is matrixed. She is responsible for three
different projects, each with teams of ten to 20 team members who are also
assigned to multiple projects. Yesterday she received an email from the vice
president of stamped products complaining that one of her three projects was
failing to meet the customer’s expectations, and they had sent notification of their
intent to cancel the contract. What is the most likely cause of this problem?
A. The customers in question were not involved early enough in the
process.
B. Molly failed to get the customer to sign the scope statement.
C. Scope definition happened after the backlog definition.
D. The customer did not read their e-mail.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 28
This question requires two skills. First you needed to eliminate the answer or Stakeholders
answers you know to be false. In this case, most students are able to eliminate must be
option D. Rarely is PMI® ever flippant and “the customer did not read their e- engaged
mail” definitely qualifies as a flippant answer. The other options all look at least early and often for
the project to
possible. Most experienced project managers have struggled with scope and succeed.
requirements issues so the question has a ring of truth to it. PMI’s perspective on
scope and requirements issues is that they often occur because stakeholders become
involved way too late in the process to actually impact the results. The team is then
forced to deal with significant changes to meet the true stakeholder needs. The
way PMI® phrases this problem is to say that stakeholders are usually not involved
earlier enough in the process. When you know this basic PMIism and have real
world experience to back it up, this question becomes very easy. Based on the
information provided, you cannot tell whether or not Molly failed to get the
customer to sign the scope statement. Nor can you tell if scope definition happened
after the backlog definition. Both of these answers describe specific scenarios that
require additional information to confirm. Option A, “the customers in question
were not involved early enough in the process” is the correct answer because it
follows the PMI® mindset and matches the information provided.
Math or Modeling Questions
Most exam takers fall into one of two camps. Camp one struggles with the
situational and ambiguous questions. Camp two struggles with questions requiring
a strong working knowledge of the math and modeling in project management.
Fortunately—or unfortunately, depending on who you are—the PMP® exam has a
lot more of the former than the latter. However, this does not mean you do not
need to know the formulas and modeling. There are many different ways PMI® can
test your knowledge of these equations beyond just making you solve a math
problem. As we’ve said, it’s a lot like insurance. The one time you are not
prepared will be the time you need the information. The good news is that these
often represent the easiest questions on the exam because they have absolute right
and wrong answers. The difficulty with these questions comes from two aspects.
First, you must actually know the equations and models and also know how to
use them. This is simple memorization, but it must be done. This course will
examine all of these equations.
The second aspect making these questions difficult is that they often are used as
part of a series that requires you to build the model first and then answer two or
three questions about the results. If you do not build the model or complete the
equation correctly in the first question you will not get the rest of the questions
correct either. It is almost impossible to pass the exam if you get these series
questions wrong.
Let’s look at a sample.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 29
Jot down any key words or phases you notice in the question.
Ask yourself what is the question really asking? Then, go through the question
and eliminate information that does not help address that issue.
Finally, carefully examine the last sentence. Often this last sentence includes Read every
the real question. In many cases, the last sentence will even have everything question and
necessary to answer the question. However, do not assume this to be true. answer twice
Make sure to carefully read the entire question twice. before answering.
Page 30
This question has a lot of information from a discipline called earned value
management (EVMS) with which you might or might not yet be familiar.
Answering this question correctly requires that you to know about earned value.
Knowing earned value allows you to know that it has nothing to do with the
question being asked. Only the last sentence is pertinent. The last sentence asks
what would you do if the person paying for the project asks for a significant shift in
scope. The answer to this question is found in the most important PMIism. The
first thing you must always do is analyze the situation and develop alternatives. You MUST
Simply getting the sponsor to change their mind is rarely a valid option without first read the
doing some analysis. Similarly, you should never agree to implement changes PMBOK®
without completing the requisite analysis. You also rarely have time to just stop the Guide to pass the
project until you can solve the problem. In analyzing alternatives two key areas of exam!
examination are cost and schedule. Once you remember those factors the question
is easy. Only option C, “evaluate the changes for impacts to the cost and schedule”
takes this concept into account.
Understanding Versus Memorization
Many people who attempt the PMP® exam try to pass by memorizing the PMBOK®
Guide. More often than not, they fail. The importance of the PMBOK® Guide
creates a major point of confusion for the exam. Many exam preparation books and
publications suggest you do not need to read the PMBOK® Guide. If you didn’t get
this point earlier, let’s make it again. Although the PMP® exam is based on the
Role Delineation Study, and although there are twelve other resources used for the
exam, the PMBOK® Guide is the most important resource for the exam. YOU
MUST READ THE PMBOK® GUIDE TO SUCCESSFULLY PASS THE
EXAM. However, you will not pass the exam just by memorizing the 49 different
processes and the inputs, tools and techniques, and outputs found in the ten
knowledge areas of the PMBOK® Guide. To pass the exam you must be able to
take that knowledge and apply it to real situations.
So what kind of questions can PMI® ask that require memorization as a baseline
and at the same time require knowledge of practical application? Examine the
following sample question:
At lunch you are sitting with a new employee within the organization. They are an Slide 28
experienced scrum master and commenting about how frustrated they are with the
organizational requirement to use a Work Breakdown Structures for their projects
especially early in the process when requirements are so poorly defined. You
comment that a properly done WBS is similar to an FBS and an important tool for
project success even early in the project. Which of the following statements best
justifies this statement?
A. The WBS is a great communication tool.
B. A well formed WBS provides a strong visualization of the product of the
project across its phases.
C. A well formed WBS is similar to a FBS allowing for task assignments.
D. The WBS allows for progressive elaboration using placeholder work
packages.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 31
To answer this question correctly you must know what a WBS really is. A Work
Breakdown Structure is a graphical representation of the deliverables of the project
that is then further extended to include the tasks and activities needed to produce
the desired project results. It has nothing to do with time or resources and is only
organized based upon things that belong together. There is a lot of debate within
the agile community around the differences and similarities between a feature
breakdown structure and a work breakdown structure, but most experts agree that
well formed WBSs and FBSs are largely the same. Although PMI® considers the
WBS an excellent communication tool, it is vague and not the best answer. A well
formed WBS has nothing to do with time so B is not a correct choice. A WBS also
has nothing to do with resources so C is excluded. Option D mentions the use of
progressive elaboration using placeholder work packages and is a true statement.
Therefore, both A and D are true statements, but option D is the best answer
because it is both true and specific. For the 2016 exam the WBS was de-
emphasized, but it is still worth knowing.
Questions With Invented Terms
Making up terms is a very old test designer’s trick to weed out candidates who
really don’t know the material. A few well placed highly technical sounding terms
can quickly throw off the unprepared. PMI® rarely attempts to trick test takers by
requiring you to remember complicated acronyms and most terms are completely
spelled out. However, the only real solution is to actually know the subject matter.
Again, this takes you back to the need to study the PMBOK® Guide and this book.
If you truly put in your time you will quickly be able to pick out questions with
made up terms like the one shown here:
Your boss wants to know what cost performance measures your team must achieve Slide 29
to complete the project within the original budget. Which of the following do you
provide to her?
A. The Cost Performance Index
B. The To-Complete Performance Index
C. The Remaining Budget Ratio
D. The Estimate For Completion
In this question two of the answers are fabricated terms and two are real. Only one
of the real terms is correct. The Remaining Budget Ratio and Estimate For
Completion are both fake project management terms that sound like real terms.
Although the Cost Performance Index is real, it also is not correct. The correct
answer is the To-Complete Performance Index or TCPI.
Answers With More than One Component
Questions with more than one component in the answer require you to carefully
examine the component pairings within each option in order to find the correct
answer. Many students struggle with these questions and are frustrated because
they feel the questions are a gimmick or trick. They are not. In fact, with a little
practice these can be some of the easiest questions on the exam. So what is the best
way to deal with these questions? The answer is the same as with several other
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 32
sections. First, you need to know the processes of project management. Knowing
the basic processes of project management will often allow you to determine the
correct answer because the options will often include sets of made up processes.
Begin by eliminating the incorrect choices. Second, like all questions, ask yourself
what is the test really asking.
Let’s examine a potential question:
According to the PMBOK® Guide, how stringently must a project manager ensure Slides 30
that all the defined process interactions occur?
A. Interactions within the planning process are dependent on the nature of
the project, and so there is a great deal of flexibility.
B. Interactions within the planning process are not dependent on the nature
of the project and are only depend on the PMBOK® Guide, so there is
not significant flexibility.
C. Interactions within the planning process group are not dependent on the
nature of the project but there is significant flexibility based on the
definitions in the PMBOK® Guide.
D. None of the above is true.
There is a lot of text to get through with these answers. And most of them have
more than one piece of information. However, this question is actually very easy.
If you have read the PMBOK® Guide you know that PMI® presents a framework
and not a formal methodology. Because it’s a framework, the only answer that is
possibly correct is one that allows for flexibility and not rigid structure. Therefore
option A is the correct answer.
These questions are very similar to the longwinded questions. The only difference
is that in these questions it’s the answers that are long and not the questions. Note
that it’s also possible to see questions where both the question and the answer are
long. Make sure to take your time and read both the questions and answers
carefully.
PMIisms
What is a PMIism? A PMIism is a heuristic and represents our interpretation of the
PMP® exam authors’ perspective on an issues. Because test preparation book Slides 31-32
authors are not allowed into the test writing sessions, we cannot say for sure if
these beliefs are true—and they are not endorsed by PMI®. However, we believe
they accurately reflect the exam itself. We have had great success preparing
candidates for the exam based on these assumptions and recommend that you take
them to heart. Each of these assumptions can be used on almost every question.
There is a basic assumption that you keep historical records for all your
projects. These records are important for the organization to continue to make
improvements. Remember, continuous improvements and lessons learned are
very important to PMI®.
You must understand the process of project management (what to do first,
second, third, etc.). This process is found in the PMBOK® Guide. The Guide
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 33
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 34
PMI does not support gold plating. Simply put, gold plating is evil! Gold
plating is adding extra functionality or features into a product that have not
been agreed to by the sponsor. This is bad because the project manager is held
accountable to deliver the triple constraints of a schedule, a budget and a list of
agreed upon features, requirements or scope. Adding something without
approval often causes one leg of this triangle to change without balancing the
others—and that is a major problem.
The preferred estimating techniques are almost always consulting experts and
using bottoms up methods. In most of the processes that require that some sort
of estimate be developed, there are several choices. Expert judgment and
bottoms up estimating are always options on the list. From PMI’s perspective,
these represent the best choice and using them together gets your most
knowledgeable people to provide estimates at a level where they will be the
most accurate.
Environmental factors always influence a project. Projects are never done in a
vacuum. They are done in the real world. And in the real world our
surroundings and our situation have a major impact on every project.
Why People Fail The Exam
A lot of people take the PMP® exam. In fact, the number of people is quickly Slide 33
approaching 150,000 each year. When considering all the ways to design a test
most people would agree that one of the easier designs is where every question
offers four potential multiple choice answers. However, the numbers tell a
different story. Each year only approximately 68% of all exams taken achieve the
requisite 61% passing score. That means nearly one-third of all exams are failed
on a test where simply guessing provides a one in four chance of a correct answer!
Simply put, this exam is hard. To increase your odds of success it is very
important that you understand the most common causes of failure. These include:
Many people fail because they believe they can pass the test by relying only on
their professional experience. Probably 60% of all failed exams fall into this
category. Every exam prep instructor has had at least one student who believed
because they were a practicing project manager for a long time they did not
need a prep class. These people represent the hardest group to help. If the
exam was about how their particular organization managed projects they would
be correct. Unfortunately, it is not. The exam covers how PMI® believes
projects are to be managed — and that can be a very different thing. Sadly,
most of these grizzled old veterans will not believe in the need to study until
they have failed a few practice tests. Don’t let your ego get in the way of your
success!
At the other extreme are those people who fail the exam because they lack real-
world project management experience. As has already been stated, it is
impossible to pass the PMP® exam by memorizing the PMBOK® Guide or any
other book. A significant number of questions on the test are situational in
nature. If you have never experienced similar situations, you will lack the
appropriate context to answer the question correctly.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 35
Candidates often miss a large number of questions because they fail to read the
questions carefully. The questions can be wordy. PMI® often uses language
that is difficult to understand. One reason for this is that some of the questions
are designed by people who have english as their second language.
Additionally, many questions can be confusing because they include words like
EXCEPT or NOT. Make sure to take your time and read every question twice
before you answer it.
Many people also get questions wrong because they fail to read all of the
potential answers. This issue arises when test takers read an early answer and it
sounds pretty good. However, if they would have read all the options, they
would have found a better answer. Remember that you are always trying to
find the BEST answer and not the perfect answer. The only way you can do
that is if you read every potential answer!
Another common mistake test takers make is simply not trusting their own
knowledge. This often happens when you change an answer. 90% of the time
your first instincts are correct. Do not change an answer unless you are
absolutely positive about the change. If you have doubts, the odds are you are
changing a correct answer to an incorrect response.
®
The final thing that causes candidates to fail the PMP exam is nervousness.
No matter how hard you prepare you will be nervous when taking the exam.
Depending on who you are, nervousness can have a major impact on your
score. Do not be surprised if your actual score is 10%-15% points lower than
your average practice score. To allow for this drop we recommend that you
study until you score 90% or better on all your practice exams before you
attempt the real test.
If you avoid these common pitfalls and follow the instruction laid out in this
manual you can successfully navigate the PMP® exam.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 36
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 2 — Types of Questions
Page 37
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 38
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 39
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 40
Slide 37
Page 41
Page 42
Slide 40
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 43
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 44
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 45
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 46
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 47
responsibility. What makes this structure unique is the fact that a single
department owns process, methodology definition, and practice maintenance. It
also allows for a single executive to own the entire portfolio of new initiatives
within the organization. Image 8 shows a strong matrix organization.
Slide 46
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 48
Remember, project managers provide a single point of focus for the project.
Project end is not a traumatic event — This advantage addresses one of
the major concerns of a projectized organization. In projectized
organizations the staff has no job when the project ends. This does not
happen in functional organizations because the resources are part of their
functional teams. Matrix organizations gain the advantage found in
functional organizations through the hybrid model while also improving on
project focus.
Strong technical base — This is another advantage shared with functional
organizations. Because the functional organizations still exist in matrix
structures, projects gain access to the strong technical knowledge provided
by the hierarchical, skill-based functional organizations.
More effective dissemination of information — This advantage is also the
subject of much debate. The theory is that because matrix organizations have
both the vertical communication found in functional organizations and the
horizontal communication found in projectized organizations the staff should
have a lot more accurate information and should have a greater ability to
quickly communicate with other project stakeholders. However, there is also
a chance that all this communication will cause confusion.
Matrix organizations have a number of challenges as well. These challenges
include:
Potential Issues With a Matrix Organization
Project personnel report to more than one boss — This issue is often Slide 48
referred to as a “dotted line relationship.” In many cases, resources are
forced to choose between conflicting instructions given to them by the
project manager and the resource manager. In these situations the resource
rarely wins.
Complex to monitor and control — As organizations become more
complex with bidirectional leadership (both functional and project) the
metrics used to monitor real performance become more complicated. As
they become more complicated the probability of providing false indications
of performance become greater.
Conflicts with resource allocation and project priorities — What should
the resources be working on at any given moment? Functional managers
often have responsibilities for operational efforts as well as project work.
Their priorities are often very different from those of each project manager.
This can lead to project work not getting done.
Potential for duplication of effort with “independent” projects — As the
organization moves closer to the projectized structure, the tendency is to
examine the team’s efforts based on the totality of the project. While this is
good from a project management standpoint, it can create a blind spot by not
comparing all projects. The result can be a portfolio with several similar
products or services when only one was needed.
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 49
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 50
Slide 49
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 51
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 52
6. Sally is a frustrated project coordinator. All of her resources split their time
between operational responsibility and project work. It seems she can only
get about 10% to 15% of their time. She also has very limited authority, and
has very little administrative support. In what kind of organization does
Sally work?
A. Functional
B. Weak matrix
C. Balanced matrix
D. Strong matrix
7. Kevin is a full-time project manager within his organization. He gets some
administrative support, but really has to fight to get time from his resources
because of his low level of authority. In what type of organization does
Kevin work?
A. Weak matrix
B. Balanced matrix
C. Strong matrix
D. Projectized
8. Ann is new to her company, the XYZ Widget Co. She really likes her job
because although she has to interface with functional managers, she has a
high degree of authority within the company, can quickly get the resources
she needs, and gets a lot of administrative support. In what kind of
organization does Ann work?
A. Functional
B. Balanced matrix
C. Strong matrix
D. Projectized
9. Jim is a project manager within the ABC Company. Within his organization
there are departments but these groups provide support services to the
various projects. In what kind of organization does Jim work?
A. Functional
B. Balanced matrix
C. Strong matrix
D. Projectized
10. The project manager’s role in a weak matrix organization is most like what?
A. A true project manager
B. A project sponsor
C. A coordinator
D. A functional manager
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 53
11. The term used to describe most modern organizations that use multiple
organizational structures is what?
A. Composite organization
B. Balanced Matrix
C. Projectized
D. Functional
12. In which of the following organization types can a PMO not exist?
A. Functional
B. Balanced matrix
C. Composite
D. A PMO may exist in any organization type
13. A project manager takes a job with a new firm. He has little experience and will be
working in a matrix organization. Based upon his situation he should expect
communication with his stakeholders to be:
A. Complex
B. Formal and written
C. Formal and verbal
D. Informal and written
14. A very seasoned project manager leaves a position in an organization that was
highly projectized for a job in an organization that is a balanced matrix. His new
manager is very senior in the organization. Based on this information, he can expect
communication to be:
A. Complex
B. Less structured
C. More structured
D. Easy
15. A project coordinator takes a new position and she is concerned about the amount of
work it will take to communicate with all the stakeholders. The organization
employs more than 30,000 people in 12 different locations. Her project team is a
strong matrix organization. In her previous job her resources were projectized. As
a general rule, what can she expect the communication to be?
A. Complex
B. Simple
C. More structured
D. Hard to automate
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 54
16. Two project managers in a weak matrix organization argue over which of
them is more senior. Eventually they determine that one of them is actually a
project manager and the other is a project expeditor. How is the expeditor
different from the project manager?
A. The manager cannot spend money
B. The expeditor cannot make decisions
C. The manager reports to a higher level authority
D. The expeditor can spend money
17. A project manager comments to their spouse about how frustrated they are at
work. Everyone is telling their resources what to do. In a functionally
organized firm who can formally direct project resources?
A. The functional manager
B. The project sponsor
C. The senior manager
D. All of the above
18. Two project managers are discussing how frustrated they are with their
projects because of the number of people who provide direction to their
project resources. In a matrix organization, who can direct project
resources?
A. The project manager
B. The functional manager
C. The project sponsor
D. All of the above
19. Sam is talking to Sally about his new job. As he describes his position he
concludes that although he is called a project manager he is actually a project
coordinator. Sally comments that he’s doing better than her because she’s a
project expeditor. Which of the following most accurately describes the
difference between a project expeditor and a project coordinator?
The project coordinator cannot make more decisions
The project coordinator can make more decisions
C. The project expeditor reports to a higher level manager
D. The project expeditor has more authority
20. A project manager is trying to complete a complicated COTS software
project but is struggling to get enough attention to complete the required
work. Most of the resources needed are focused on completing operational
work and the project manager doesn’t have authority to shift their focus or
assign other resources. In which type of organization must the project
manager be working?
A. A functional organization
B. A technical matrix organization
C. An operational matrix organization
D. A weak matrix organization
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 55
21. Cathy is a new project manager with very little real experience. She’s been
assigned to lead a project for which her boss feels she’s perfectly suited. Her
organization is a matrix organization. Based on these characteristics she
should expect communications to be:
A. Simple
B. Mostly verbal
C. Mostly automated and written
D. Complex
22. Ralph is currently leading a project in the planning phase when two key
stakeholders come to him and ask for an explanation of the development
methodology being used on the project. They are specifically interested in
where it came from and how it differs from the methodology being used on
most of the projects being done within the organization. As Ralph explains
the methodology, the stakeholders become nervous about a number of new
terms he uses (which they are unfamiliar with) and how this new
methodology will impact the organization. They stakeholders are long-time
associates of Ralph’s. What should he do?
A. Ask the stakeholders to trust him as they are long-time associates
B. Supply the stakeholders with a glossary of terms for the new
methodology
C. Notify the PMO of the stakeholders’ concerns
D. Advise the stakeholders that he will keep them informed regularly on
the project
23. A young project manager has just been assigned to his second project even
though he has yet to complete his first project. The first project is relatively
small and both the project manager and his boss believe the project manager
has the capacity to manage both efforts at the same time. However, as time
passes the second project begins to grow significantly in scope and the
project manager quickly comes to believe he needs help. In talking about the
situation with his peers, the project manager learns a similar project was
completed 18 months prior. What should the project manager do?
A. Wait to see if the second project continues to grow in scope
B. Make sure the scope is agreed to by all stakeholders
C. Obtain the historical records and guidance from the project
management office (PMO)
D. Contact the project manager from the previous project for guidance
24. A project manager gets assigned to a manufacturing effort for a new product
and gathers their team to begin work. Although the team has worked
together on previous efforts they struggle to create the project charter.
Which of the following best describes the real problem?
A. Constraints and assumptions have not been defined
B. The project deadline has not been set
C. They have not identified the project objectives
D. They are working on an operation and not a project
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 56
25. The previous project manager for your project did her work without much
formal organization. There is little management control and there are no
clearly defined deliverables. Which of the following would be the best
choice for getting the project better organized?
A. Define the project methodology
B. Adopt a lifecycle approach to the project
C. Develop specific work plans for each work package
D. Develop a description of the product of the project
26. The project cycle differs from the product life cycle in that the project life
cycle:
A. Does not incorporate a methodology
B. Is different for each industry
C. Can spawn many projects.
D. Describes project management activities
27. You are a Project Manager leading a large project within a manufacturing
organization that is matrixed. One day one of your resources approaches
you and states that she does not know which of her several assignments for
different projects is most important. Who should determine the priorities
between projects in the organization?
A. The project management office (PMO)
B. The project manager
C. The project team
D. The project management team
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 57
Page 58
12. Answer D. PMBOK® Guide – A PMO can exist in any of the organizational
structures—including a functional organization. However, the more the
organization moves towards a projectized organization, the more likely a
PMO becomes.
13. Answer A. PMBOK® Guide p.28 – This is a tricky question because much
of the information is unnecessary to correctly answer it. The only piece of
information necessary to answer this question is the fact that the organization
is a matrix. In matrix organizations communication is complex because of
the importance placed on communicating with the many power structures.
14. Answer A. PMBOK® Guide p.28 – This is a tricky question because much
of the information is unnecessary to correctly answer it. The only piece of
information necessary to answer this question is the fact that the new
organization is a balanced matrix. In matrix organizations communication is
complex because of the importance placed on communicating with the many
power structures.
15. Answer A. PMBOK® Guide p.28 – This is a tricky question because much
of the information is unnecessary to correctly answer it. The only piece of
information necessary to answer this question is the fact that the new
organization is a strong matrix. In matrix organizations communication is
complex because of the importance placed on communicating with the many
power structures.
16. Answer B. PMBOK® Guide p.28 – A project expeditor has no authority to
make decisions or spend money. Typically a true project manager can make
decisions and often reports to a higher-level authority, but this is not
guaranteed.
17. Answer A. PMBOK® Guide p.28 – In a functional organization, the
functional manager has the power to direct resources. The project manager
must use influence to get the functional manager to direct the resources
necessary to achieve project tasks.
18. Answer D. PMBOK® Guide p.28 – In a matrix organization, either the
functional manager, project manager or a sponsor could have the power to
direct resources.
19. Answer B. The project coordinator can typically make more decisions than
an expeditor. They also usually have more authority and report to a higher
level manager than the expeditor.
20. Answer A. This is an example of a functional organization because the
project manager does not have any power to shift resources that are focused
on operational activities.
21. Answer D. Matrix organizations increase the complexity of
communications. This question has little to do with the amount of
experience the project manager has. Additionally, it is not possible to tell if
the communication would be written or verbal with the information given.
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 59
PMP Exam Preparation Student Guide v. 10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 60
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 61
results. Projects focus on the new things being created. While operations focus on Slide 52
consistency, stability and repeatability, projects focus on change. Operations focus
on removing the waves from processes. Projects, on the other hand, create the next
product, service or result — and these naturally create waves. Operations and
projects do, however, have several characteristics in common. The obvious thing
they have in common is that both operations and projects are accomplished by
people. Also, people are a kind of resource that is often limited in both operations
and projects. Finally, in both projects and operations there are efforts are made to
plan and control the people and processes involved.
For the PMP® exam, it is important that you can compare and contrast projects and
operations. Here are the common characteristics held by projects:
Have unique charter and goals — Projects are created to generate a very
specific and defined set of results. To help ensure that this actually happens,
projects have charters that define the boundaries, the success criteria and the
specified goals.
Might have unique organization — The organizational structure defines
whether or not the project will have a unique organization assigned to produce
it. Projectized organizations will have a unique organization defined, while
functional or matrix organizations will not.
Develops a unique product or service — Projects produce a unique product
or service — in contrast to operations which manufacture the same product,
such as a car or a widget. Projects are not used to create repetitive products or
services.
Defined start and end dates — Projects are not continuous. In addition to
having specified scope with defined success criteria projects also have defined
start and end dates. These factors create what is commonly referred to as the
triple constraints of project management (time, costs, scope and quality).
Mostly heterogeneous teams — Projects require teams with varying and often
dissimilar skills. This makeup is also determined by the organizational
structure. The closer an organization is to being projectized, the more
heterogeneous the team will be.
A better understanding of the difference between projects and operations can be
had by comparing the common characteristics of each. Here are the common
characteristics of operations:
Usually has semi-permanent charter — Operations can exist for a significant
period of time — often significantly longer than projects. The agreement to do
the operation and the rules under which it exists form the basic operational
charter.
Semi-permanent organization — Operations require teams that are long-term
and stable to deal with the repetitive nature of the operation. Therefore, semi-
permanent structures often make the most sense.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 62
Slide 54
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 63
visibility and control purposes. Often, portfolios are created based upon budgetary
authority, but they can be formed for many reasons. An example of a simple
portfolio is everything for which an executive has budgetary responsibility. To
better understand the relationship between projects, programs and portfolios
examine how each address the issues of scope, change, planning, management
success, and monitoring.
Projects
Scope — Projects have defined objectives. Scope is progressively elaborated
on throughout the project’s life cycle.
Change — Project managers expect change and therefore implement processes
to keep change managed and controlled.
Planning — Project managers elaborate on high-level information, turning it
into detailed plans throughout the project cycle.
Management — Project managers manage the project team in order to meet
the project’s objectives.
Success — Success is measured by the product and project quality, timeliness,
budget compliance, and degree of customer satisfaction.
Monitoring — Project managers monitor and control the work of producing
the products, the services or the results that the project was undertaken to
produce.
Programs
Scope — Programs have a larger scope and provide more significant benefits.
Change — The program manager must expect change from both inside and
outside the program and must be prepared to manage it.
Planning — Program managers develop the overall program plan and create
other high-level plans to guide detailed planning at the component level.
Management — Program managers manage the program staff and the project
managers. They provide vision and overall leadership.
Success — Success is measured by the degree to which the program satisfies
the needs and benefits for which it was undertaken.
Monitoring — Program managers monitor the progress of program
components to ensure the overall goals, schedules, budget, and benefits of the
program are met.
Portfolios
Scope — Portfolios have a business scope that changes with the strategic goals
of the organization.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 64
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 65
PMI® describes three types of PMOs that each have varying degrees of control and Slide 55
influence over the project. These include:
Supportive — These PMOs act as a consultative role. Their primary function
is to provide things like templates, best practices, training, access to pertinent
information, and most importantly lessons learned from previous projects. You
should think of this type of PMO as a repository. This type PMO has very little
power or control over the projects in the organization.
Controlling — Controlling PMOs do NOT directly manage projects.
However, this type of PMO mandates compliance to varying degrees. The
PMO maintains this control by establishing project management frameworks
and methodologies that must be adopted. It also requires the use of specific
templates, forms, and tools.
Directive — Directive PMOs take the most direct and overt control of projects.
Directive PMOs include the organization’s project managers who are assigned
by and report to the PMO. In this form of a PMO a high degree of control is
maintained.
When discussing a PMO realize that they can have oversight over the entire
organization or a single area.
Other Terms
Management by Objectives (MBO) — MBO is a management technique that Slide 56
requires all processes, initiatives and operations to be tracked against specific,
defined objectives. If the project does not support or follow a defined objective it
is likely to lose it’s resources and sponsor support and will therefore fail. MBO
only works if management strongly supports it. MBO has three basic steps:
Establish unambiguous and realistic objectives.
Work Performance Data — These are the raw observations and measurements Slide 57
that are identified during the activities performed in the project work: % of work
that has been physically completed, start and finish dates & technical measures.
Work Performance Information — This is the performance data that has been
collected from the controlling processes. It includes the status of deliverables,
status of change requests, etc.
Work Performance Reports — These are the physical or electronic records of
work performance.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 66
Project Life Cycle — These are a series of phases that a project passes through Slide 58-60
from its initiation to its closure. They provide the basic framework for managing
the project.
Project Phases — These are logically related project activities that culminate in
the completion of one or more of the deliverables.
Predictive — These are also known as fully plan driven. They are ones where the
scope, time and cost are determined as early as possible. They arise in the Waterfall
method of management.
Iterative and Incremental — These are project phases that intentionally repeat
one or more project activities as the team’s understanding increases.
Adaptive — Change driven, adaptive, or Agile methods of management are
intended to respond to high levels of change and stakeholder involvement with
fixed time and fixed cost.
Constraints — Constraints are factors that limit the options of the project manager
and the project team. Common constraints — such as time, budget, requirements,
resources or risks — can dramatically impact the results, like the customer
satisfaction. It’s the management’s responsibility to set the priority of each
constraint within a project. It is the project manager’s and project team’s
responsibility to analyze the impacts that any changes will have according to the
project constraints.
OPM3™ — OPM3™ stands for Organizational Project Management Maturity
Model. It is PMI’s model to help organizations determine their level of project
management maturity. PMI® publishes a separate standard for OPM3™.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 67
Quality — Quality is the degree to which the product, service or result meets
the stated requirements.
Schedule — The project schedule is the committed delivery date for the
project.
Budget — The budget is the forecasted expenditure for the project.
Resources — The resources are the people and/or materials needed to complete
the desired product, service, or result.
Risk — Unknown events happen on every project. Being able to manage the
unknowns is perhaps the most important skill of a true professional project
manager.
Deming’s PDCA Cycle and the PMI® Process Model
One of the key elements to passing the Slide 62
PMP® exam is understanding the
process model for project management
as defined by PMI®. Like most of the
process models widely used in the
world today, PMI’s model finds its
roots in Edward Deming’s famous
PDCA cycle. The PDCA cycle
represents a well formed process
where the work is first planned, then
the work is executed according to the
plan, the results are checked against
the expected outcomes, and finally
any variances are acted upon. PMI®
builds on this basic model to explain
the process every well-managed
project goes through regardless of Image 11: The PDCA Cycle
size, cost or scale.
To understand the PMI® model, it is important to know a number of key concepts
(PMBOK® Guide 6th Ed. p.18):
Project life cycle — The series of phases that a project passes through from its
start to its completion.
Project phase — A collection of logically related project activities that
culminates in the completion of one or more deliverables.
Phase gate — A review at the end of a phase in which a decision is made to
continue to the next phase, to continue with modification, or to end a program
or project.
Project management processes — A systematic series of activities directed
toward causing an end result where one or more inputs will be acted upon to
create one or more outputs.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 68
Image 12: Interrelationship of PMBOK Guide Key Components in Projects PMBOK Guide 6th Ed.
p.18
In the 6th edition of the PMBOK® Guide changed how PMI® represented this model
in hopes of reducing confusion between the defined framework and various
methodologies or life cycles (See Image 12). The new representation begins at the
top with the project life cycle which represents the actual process used for your
specific project. In general terms, each life cycle goes through a similar series of
steps where the project is first started. Once the organization recognizes it has a
project on its hands and decides to manage it as such, the effort must be organized
and preparatory work completed. The team then uses its defined processes to
complete the project work, and eventually the project ends.
Beneath the project’s specific life cycle sits the five PMI® process groups:
initiating; planning; executing; monitoring and controlling; and closing. These five
containers represent placeholders for the 49 specific processes defined in the ten
knowledge areas of the PMBOK® Guide. It is at this point that examining PMI’s
previous model holds value for understanding the project management framework.
The model (Image 13) begins with a project sponsor or initiator defining a business
or organizational need. The need is further defined until someone recognizes that it
should be a project. At that point the initiating process group begins.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 69
Slide 64
Image 13: The PMI® Process Framework PMBOK® Guide 2013 p.54
The initiating process group has two key goals: to develop a project charter and to
identify stakeholders. The charter authorizes the project and is discussed further in
the next chapter. Identifying the stakeholders is discussed in the stakeholder
management chapter. Once the charter is created and stakeholders have been
identified, the project progresses into the planning process group.
The planning process group is the largest of the five project management process
groups. It also has the potential for a looping relationship with the executing
process group. This relationship is the point of the confusion with students of
project management. If both the planning process group and executing process
Group are done just once it creates a linear life cycle such as in a waterfall or
SDLC. But the model also allows for the planning and executing process groups to
be completed many, many times in a back-and-forth relationship.
Deciding when planning is complete, and when it is time to execute the project is
the monitoring and controlling process group. This process group acts as the
project’s eyes and ears. The monitoring and controlling process group might also
decide that a project requires more planning after execution has begun, or that all
the project work is complete.
Lastly, there is the closing process group. Whereas the executing process group
produces deliverables, only the closing process group produces the final product,
service, or result. Additionally, the closing process group produces project records
which then become assets to the organization because they allow it to engage in
continuous process improvement, which is very important to PMI®.
Development Methodologies /Life Cycles
Development methodologies and life cycles are critical to project success.
However, a development methodology should not be confused with project
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 70
The horizontal axis in the model measures the amount of formality or a structured
process the methodology uses. A key representation of this formality is found in
the volume of required documentation. Methodologies with low formality typically
require little documentation, while methodologies with highly structured processes
usually require significantly more documentation. However, do not equate the
amount of process and formality with the quality of the management or likelihood
of success.
The vertical axis in Image 14 represents the number of loops or iterations a project
goes through. A methodology that only cycles once through its steps is said to be
highly linear or sequential. If the methodology is highly linear it often appears to
be rigid. Methodologies that are highly linear tend not to loop back on themselves
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 71
or repeat steps. If the methodology is not highly linear then it is iterative. This
means that the methodology allows the project to repeat steps as more information
is learned about the project. Recognize that it is not required that only pure
methodologies be used. Experienced project managers regularly combine
methodologies to best meet specific business needs as is represented by a hybrid
life cycle. This is a key ability for project success. However, the project leader
must understand the basics of the major methodologies to build that custom
methodology. Image 15 shows the “Big 3” types of life cycles together to give you
a visual reference.
Slide 66
We have already offered a basic definition of the core methodology or life cycle
classes, but we have not really dove into them in any detail. That discussion begins
with a better understanding of the predictive model.
Understanding the various life cycles that fit into this model is a very important
aspect of your studies. PMI® describes life cycles as generally either being
adaptive or predictive. In the simplest terms, these two concepts represent
constantly evolving planning where the project is broken into small components
over a less determined timeline versus project planning that is done in a linear
fashion with a specific development plan structured specific scope, schedule and
cost estimates. However, all of these life cycles are broken into phases specifically
associated with the development of products, services and results. The discussion
of lifecycles or methodologies has a variety of options beyond the basic predictive
and adaptive. These include:
Predictive life cycles — In a predictive life cycle the team spends significant
time in the early phases of the project determining project schedule, scope, and
cost estimates, often referred to as the project’s triple constraints. Throughout
the rest of the project, the team then works to tightly manage any scope
changes. A predictive life cycles include the Software Development Life Cycle
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 72
and the Waterfall Methodology. This model works well when it is reasonable
to expect that all the requirements are knowable at the beginning of the project
and it is critical to maintain stable scope, schedule and cost targets. However,
this model does not typically respond well to missed or changing requirements.
Iterative life cycles — Iterative development generates a cyclical process that
often has a single general roadmap. However, it uses a series of steps where
each step learns from the previous ones to produce the overall product, service
or result. An iterative process embraces the fact that many projects struggle
with knowing at the beginning what the final product should look like and
responds by building in as many learning opportunities as possible. An often
used tool in iterative development is prototyping.
Incremental life cycles — In incremental life cycles the product, service, or
result of the project is produced using a series of chunks. The most common
implementation of incremental delivery has the team delivering business value
in a series of releases rather than one large chunk. The big difference between
this model and an iterative cycle is that those using an incremental life cycle
will work to maintain the original road map, and few opportunities exist for
feedback from the customer until the final product, service or result is released.
Adaptive life cycles — Adaptive life cycles may be iterative, incremental, or
agile. In an adaptive model, project scope is defined at the beginning of each
iteration and only generally at the beginning. These life cycles are also called
agile or change-driven. Agile methodologies are all the current rage. Scrum,
Extreme Programming, DSDM, Feature Driven Development, and Crystal are
all examples. These models typically have smaller collocated teams and offer
critical advantages when the team is dealing with poorly defined or changing
requirements.
Hybrid life cycles — A hybrid life cycle is a combination of the adaptive and
predictive life cycles. In this model, the team uses a predictive model for those
requirements that are either well known or fixed and uses an adaptive model for
requirements that are unknown, incomplete, or evolving. This is not an
undefined process where the team is allowed to do whatever it wants. In most
cases, the team follows a process defined by the larger organization to ensure
consistency of process.
It is up to the team to decide the best life cycle for the particular project in their
specific organization. However, the information provided above, which largely
aligns with the limited information found in the PMBOK® Guide, is definitely not
enough to make a real-world decision on the best methodology to use. It also isn’t
enough to get you through the exam. To help you better understand methodologies
review the following:
The Predictive Model
The use of the term “waterfall model” comes from its linear series of steps that
proceed downward like a waterfall. Work is completed in a sequential manner with
one deliverable being completed and approved prior to moving to the next
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 73
deliverable. These gates are commonly referred to as phase gates, stage gates, Slide 67
milestones or go-no-go decision points. Some common names for these gates
include:
Stakeholder Review
Requirements Review
Use Case Review
Critical Design Review
The waterfall model uses an extremely linear process. This process begins with the
definition of the business need. This is referred to as conceptualization or analysis.
It then continues through all the steps in the waterfall until ending in the
deployment of the product or service of the project. The Software Development
Lifecycle or SDLC is one of the best known waterfall models. Like many waterfall
models it has five steps or phases.
Analysis — The business need is defined and the top level scope is defined for Slide 68
the product or service that will best meet the need.
Design — The specific requirements that are necessary to complete the product
or service are defined.
Development — The product or service is built in accordance with the
previously defined requirements.
Testing — The product is tested to ensure that all the features and functionality
are working in accordance with the requirement. In addition, integration testing
is completed to ensure the product or service will function correctly within the
global environment.
Deployment — The product or service is completed and moves into the
operations phase.
Waterfall Advantages
A waterfall model offers the easiest departmentalization and managerial Slide 69
control.
A waterfall model forces the team to completely define all requirements before
proceeding to the next phase. This is also its biggest disadvantage.
The waterfall model has strong emphasis on documentation and the
development of source code.
The waterfall model provides a very structured and disciplined approach to
development. This high degree of structure may also be seen as a disadvantage
by many.
Waterfall Challenges
Real world projects rarely follow a purely sequential process. In practice steps Slide 70
are often repeated multiple times or the project must go backwards to continue
progressing.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 74
The waterfall model requires the project team to know and define all the
requirements at the beginning of the project. This can be extremely unrealistic.
Waterfall models often cause a large time gap between requirements definition
and when stakeholders actually see the product or service of the project. This
gap can cause the stakeholders to become uncomfortable with the progress or to
change requirements. There is also a risk the product or service may no longer
meet stakeholder needs.
Selecting a waterfall methodology is often warranted if any of the following are
true:
The project has requirements that are extremely well known and unlikely to
change.
The project involves a high volume, transactional system where errors or
incomplete requirements could damage existing capabilities.
The project team is made up of new and inexperienced resources or resources
that have never worked together before.
The project would benefit the organization was not allowed to alter
requirements.
To better understand how these decisions should be made, examine the following
situations:
Imagine a credit card processing system. Several million times a day merchants
send credit card transactions into your system. If your team was to deploy
inaccurate or incomplete components the entire system might fail. This would both
significantly and negatively impact the business. This situation would provide a
timely opportunity to use a waterfall methodology.
Now imagine a new website. What would be the impact on the site if one or two of
the pages were not completed when the site is deployed? You would not be able to
see those pages, but all the other pages would work correctly. This may lead the
project manager to select a different methodology, such as one where the project
manager could deliver some type of actual product so the stakeholders could
determine what they really want prior to the end of the project.
Iterative Life Cycles
The most common form of an iterative life cycle is the Spiral methodology. A
spiral methodology is one of the only formal methodologies that uses prototyping Slide 71
to prove capabilities or investigate requirements and functionality. This
methodology is often referred to as “chunking” because it makes use of discrete
phases to produce parts of the overall product, service, or result of the project.
These chunks are not considered “production ready until they are combined with
the other components at the end of the timeline.
Iterative development is a rework scheduling strategy in which time is set aside to
revise and improve parts of the system. The concepts of iterative development
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 75
creates loops in the process of executing a project that allow the team to change
their process to improve execution and delivery. In a single looped linear process,
the team is stuck with the process with which they start the project. This is a key
advantage to seasoned, experienced teams. Those teams have completed multiple
projects together and hopefully those experiences provide insights on the current
effort. Agile projects get lots and lots of chances to deliver because they use lots of
short iterations. Each one requires a short cycle of reflection to determine the best
way to improve the process and deliver better results.
Iterative development allows for segregated teams based on their functional areas.
For example, a project might have a group of stakeholders and team members
solely focused on the definition of requirements. These individuals would begin
immediately on the project defining the requirements by chunk. They would begin
by defining the first chunk, then the second, the third, and so on.
As soon as the first chunk is defined a second team or individual begins defining
the design specifications for the first chunk before moving on to the second, third,
and so on. There would also be sub-teams assigned to development and testing that
each would begin work as soon as the first iteration was ready.
Within each of these chunks, the team often produces one or more prototype to
prove technology, designs, methods or other key aspects. In each chunk the project
goes through four stages:
Determine objectives, alternatives and constraints.
Evaluate alternatives, identify and resolve risks (prototype).
Develop and verify the next level of the product.
Plan the next phase of the project.
The spiral model also demands the project manager make a strong effort to
determine how many phases or chunks the project will take before beginning the
looping process since a failure to effectively make this determination will often
lead to a significant problem with schedule and cost control. Remember, iterative
development still tries to fix the schedule and budget in the broad sense.
In the spiral model, a prototype is built during the “evaluate alternatives” phase.
After gathering feedback about the prototype, the project team determines the next
level of the project. The next level of effort and deliverables are planned and then a
new phase begins. This process continues in a looping fashion with more and more
iterations until the final product is ready for evaluation and testing.
Spiral Advantages
The spiral model is evolutionary in nature allowing the features and functions Slide 72
to evolve over time thereby creating a better final product.
The spiral model provides a strong focus on the project risks. The iterative
process mitigates risk by using prototypes to ensure the team can actually
deliver the desired results before too much time or money is invested.
Prototypes allow for rapid evaluation of the solution provided by the project
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 76
team. It allows the team to make adjustments to the solution based on the
changing business environment.
Other models can be incorporated into the spiral model to assist the developers
or to address special needs of the project team.
The project team and sponsor can more quickly see the results of the project
and alter requirements as needed.
Spiral Challenges
The project teams must have strong risk assessment expertise. The primary Slide 73
advantage of the spiral methodology is that it provides for better risk
management. If the project team lacks skills in this area the advantage doesn’t
exist.
The model has a greater potential to overrun costs and schedules because a
spiral methodology uses looping iterations. Even though the project manager is
supposed to define the number of these loops, often additional loops are added
to allow for new requirements or new information. This can cause the schedule
and/or costs to slip.
Prototyping
When prototyping, the project team builds a smaller version of the product or a Slide 74-75
core piece of the product’s functionality. This process allows the project team to
test theories, evaluate alternative solutions, or prove they are capable of delivering
specific features. The prototyping process also allows the team to make
refinements to the product requirements as new information is learned. Prototyping
assumes that it is difficult to know all the project requirements at the inception of
the project. To be able to discover and refine the requirements, the developer must
build a simplified version of the system and present it to the customer for
evaluation and feedback.
The most important thing to remember about prototyping is that it is only used to
solicit feedback, prove capabilities, and gather and refine requirements. It should
never be released as a finished product. Deploying prototypes is a common error.
Preventing this from happening requires the project manager to consistently and
carefully manage stakeholder expectations. There are three issues that must be
carefully managed with your stakeholders when prototyping:
Slide 76
The prototype should never be deployed as a product. This often happens and
causes significant frustration as the prototype is rarely designed to handle the
load of real world use.
Creation of the prototype will cost additional money without providing an
immediate product. However, it is expected that this will save money in the
long run.
The use of prototypes can dramatically increase the likelihood of a problem
called architectural compression. This problem occurs when organizations
build one system either on top of or beside another repeatedly without
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 77
Page 78
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 79
the maximum amount of water is constantly available to the end users when they
turn on their faucets. Contrary to what you might think, the best way to ensure
high water pressure is to ensure the mains are less than 100% full. Remember, the
mission is to get each drop to the customer as quickly as possible. If you ask your
friendly neighborhood civil engineer, they will confirm that the water will travel
the fastest when the pipe is less that 100% full. We do the same thing with our
project tasks when using WIP. We need to have all hands focus on getting one
deliverable through the process, then another, and another, and so on until the
project is complete. The team’s focus is on throughput and not just starting as
many things as possible.
Now let’s go back to our time/cost limitation. Remember, we still only have six
time/cost units to spend on our project. In Option 2, both Resources A and C start
out working on Deliverable X. At the same time Resource B begins working on
Deliverable Y. Once Deliverable X is complete Resource C shifts over and helps
Resource B complete Deliverable Y. At the end of the same six time/cost units
both Deliverables X and Y are complete. Immediately you might have just
thought, “Yeah, but you have nothing done with Deliverable Z.” And, you would
be correct. However, advocates of WIP would argue this is a positive not a
negative. In addition to maximizing throughput (remember we now have two
deliverables completed), the team has eliminated all waste. Waste in this case is
defined as any partially completed work product when the team runs out of time or
money. In this case, we are talking about Deliverable Z. Nothing was done on it
so there is no waste. This puts our Project Sponsor in a powerful position because
now they truly have a choice. Should they spend the extra 50% time/cost to
complete Deliverable Z or not? If the team has correctly applied another common
Agile principle of completing the most important work first than Deliverables X
and Y were the two most important and Z is less important. The key question for
our Sponsor centers on whether or not Z is worth the added 50%. If she walks
away now, she has gotten her two most important deliverables and stayed within
budget. WIP gives the power back to business and removes the common complaint
that they were forced to complete a project because they had already invested so
much. Good money no longer needs to follow bad.
Agile Methodologies
Today there are more than 16 different methodologies that are considered part of
the agile family. Some of these like to refer to themselves as “frameworks”, but
the PMBOK® Guide refers to them as methodologies or life cycles because they
each have specific rules and processes that must be followed. The most common
of these methodologies include Scrum, Extreme Programming (XP), Feature-
Driven Development (FDD), Dynamic Systems Development Method (DSDM),
and the many forms of Crystal. Two less common, but no less important closely
related methodologies include Lean Software Development and Kanban. For the
purposes of the PMP® we will focus on Scrum only.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 80
Scrum
Scrum is far and away the most popular agile methodology globally. It was first
defined as “a flexible, holistic product development strategy where a development
team works as a unit to reach a common goal” as opposed to a “traditional
approach” (read a linear approach such as Waterfall) in January,1986 by Hitotaka
Takeuchi and Ikujiro Nonaka in the New Product Development Game published in
the Harvard Business Review. This article described a new approach to
commercial product development that they argued would increase both speed and
flexibility based upon their examination of numerous case studies in
manufacturing, photocopier, and printer industries. They called this the holistic or
rugby approach. The idea was to create a single, small cross functional team that
possessed all, or at least most, of the skills required to complete the project and this
team would work singularly on the project across multiple overlapping phases
constantly passing work back and forth until complete.
In the early 1990s Ken Schwaber used a version of this approach at Advanced
Development Methods while Jeff Sutherland with others developed a similar
approach at Easel Corporation. Sutherland is believed to be the first to refer this
approach as, “Scrum.” In 1995, Sutherland and Schwaber jointly presented a paper
describing the “Scrum Methodology” at the Business Object Design and
Implementation Workshop held as part of the Object-Oriented Programming,
Systems, Languages, and applications 1995 in Austin, Texas. The two continued
to work together for several years bringing together their ideas on Scrum until in
2001, Schwaber published Agile Software Development with Scrum coauthored by
Mike Beedle.
Scrum is based on two aspects of industrial process theory: self-organization; and
emergence.
Self-organization is the idea that the development team will decide what work Slide 78
needs to be accomplished and who will do the work to deliver the desired
business results.
Emergence is the idea that information, requirements and facts will emerge as
the project progresses. The key is that the team uses processes, tools, and
techniques capable of harnessing this new information for the betterment of the
organization.
The creators of Scrum argue that traditional linear approaches for projects such as
Waterfall are based on the concepts of defined processes. Defined processes are
repeatable processes such as in manufacturing. Imagine working at the Acme
Widget factory. In order to produce widgets of a consistent level of quality it is
imperative that our machines stamp and assemble each widget the same way. The
more consistently we can stamp the widgets the less variance we see in the finished
product. As we move forward we also try to increase the rate of production. With
smaller and smaller variances and greater and greater production we are able to
take our widget production to a point where we commoditize the production of
widgets. Commoditization is defined as the process in which goods that have
economic value and are indistinguishable in terms of attributes (uniqueness or
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 81
Page 82
The first role is the product owner or PO. The PO is the individual responsible for Slide 80
representing the interests of all stakeholders, obtaining funding, defining the initial
requirements, defining the return on investment or ROI, and the project objectives.
They are the primary owner of the product backload, a document where the user
stories, features or requirements of the project are listed in rank order from most
important to least important from the perspective of the business. The closest term
in the PMBOK Guide® to the product owner is the project sponsor, but there are
some differences. Theoretically, a sponsor exists as the all powerful leader. They
give the project manager and their team the authority they need to execute the
project. The rule when discussing a project sponsor is that you want the most
powerful one you can find because the project manager is only as powerful as their
Sponsor. This concept creates a hierarchical structure and a direct reporting
relationship from the sponsor to the project manager, and then to the team. In
Scrum, it is not assumed that the PO is this all powerful entity. Instead, we simply
say that the product owner is responsible for certain areas. This means that the PO
either has the direct authority to provide the funding and other items or the must go
into the greater organization and obtain those things. Scrum doesn’t care which.
When the development team needs more information about a user story, they rely
on the product owner to either know that information or ensure that the correct
people are in the room to provide that information.
The second role is the development team. In earlier Scrum writings, this role was
referred to as simply the team. This is the small group of people who actually do
the work to deliver the product, service, or result of the project. The development
team is self-managing, self-organizing, and cross functional. The team does not
have a project manager or functional leader who directs the team’s efforts. The
development team is also small. According to the rules of Scrum, the team size is
six plus or minus three. This puts the optimal team size somewhere between three
and nine individuals. This is an important aspect of agile development. Research
has repeatedly shown that smaller teams are much more successful than larger
ones. Scrum also defines the development team as being multi-functional meaning
it contains all the skills the team needs to complete the work of the project.
Furthermore, the team is 100% dedicated to one and only one project. This notion
of a team is often difficult for people new to agile development, especially the idea
of a team being dedicated to one and only one project. “How is that even possible
in the real world?” They ask. It works because the typical Agile team is much
smaller than teams in traditional projects. It is still the same total number of total
people in the organization, but by breaking the whole into smaller independent
teams the organization is able to divide and conquer.
The third and final role is the scrum master. The scrum master is responsible for
the scrum process, teaching scrum to everyone, implementing scrum so it fits with
culture, and ensuring that everyone follows scrum’s rules and practices. The
closest approximation to in a linear project is the project manager, but there are
some key differences, at least from the perspective of the Agilist. Most Agilists
believe that traditional project managers are only part of hierarchical organizations
with the project manager at the top. All the resources report to the PM.
Additionally, this person serves as an administrator directing the team, but having
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 83
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 84
solve it. Projects exist in a competitive landscape. The business must be able to
explain why doing this project is the best expenditure of the available resources.
Success Criteria — This is where the rubber hits the road. It answers the question,
how will we know when we are successful? It is where the business defines the
attributes that are critical to satisfying their needs, and the overall success of the
product. The measures must be quantifiable and objective to prevent different
people from interpreting the project’s results differently.
Prioritization — This area is all about determining how the project fits into the
landscape of all the other projects going on within the organization. This is critical
information for the Team to know. Understanding where a project rates versus all
the other work the organization is trying to accomplish informs the team about the
likely level of support they are likely to receive. It is also a good idea to
understand how the product owner values three legs of the triple constraints. This
will also provide guidance about how much support the project is likely to receive.
Constraints and Assumptions — This last area provides critical information for
the development team because it allows the business to define limitation with
which the team must live. This includes issues like budget limitations, time
constraints, technology or resource limitations.
A common way to validate your vision is to answer the elevator test. Can you
explain the product, service or result of the project in the time it takes to ride up in
an elevator? (Moore 2006 p. 152). No project can begin without a vision. It is how
the organization recognizes a potential project exists. Regardless of methodology
every project should have a vision.
The second document in the list of four is a ranked product backlog. More often
than not the literature talks about just the product backlog. A product backlog is a Slide 83
listing of the user stories, features or requirements. These items are often referred
to as product backlog items or PBIs. The key is the “ranked” portion. It is a key
aspect of using the product backlog. Ranking the backlog requires the business to
prioritize the items in the backlog from most important to the business to the least
important. Sometimes the backlog is further defined into groups of user stories that
belong together. The development team uses the backlog to define which features
to deliver when. Each of the items on the backlog items relatively independent of
each other. Additionally, the items on the backlog may be reprioritized at any time.
Before moving to Scrum process, there are a few additional terms pertinent terms
which must be introduced.
User Stories — A story is a self-contained unit of work agreed upon by the
developers and the stakeholders. Stories are the heart of Scrum, and the building
blocks of the sprint. Each user story must be producible in a single sprint. Often,
this requires the development team to break stories down until they fit into a single
sprint. Additionally, each story must provide functionality that has real value to the
business. A user story is different from a feature however as a feature represents a
distinct element of functionality that provides capability to the business while a
user story is a small aspect of a feature that is used to get feedback from
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 85
stakeholders and find out if you are doing anything wrong. In the real world of
implementing agile the two terms are often used synonymously.
Themes — Themes may be thought of as groups of related stories. Often the
stories all contribute to a common goal or are related in some obvious way, such as
focusing on a single customer. Sometimes stories within a theme may be
dependent on each other, and then do not necessarily encapsulate a specific work
flow or be delivered together.
Epics — Epics resemble themes in the sense that they are made up of multiple
stories. Sometimes they also resemble stories in the sense that may appear as a big
story. Unlike themes, epics often comprise a complete workflow for a user and
they typically cut across all or some of the three business dimensions (time, scope
and organizations). Another important difference is while the stories that comprise
an epic may be completed independently, their business value isn’t realized until
the entire epic is complete. This means that it rarely makes sense to deliver an epic
until all of the underlying stories are complete. In contrast, while stories
comprising a theme are related, each is independent enough to be delivered
separately and still provide some measurable sense of business value. A related
rule of thumb is to automatically further break down any story that is estimated
above a certain threshold. A good starting point for this threshold may be where
your team has historically tended to become inaccurate with their estimates. Epics
are most often seen when teams are implementing SAFe as they are often used to
enhance business value of the FULL solution set or bring a range of technologies
together. They are often key economic drivers for the portfolio,
Rocks — Rocks are pieces of functionality used as placeholders when there is an
absence of information. The rock acts as a signpost signifying the team does have
information about a feature or requirement.
Sprint — A short iteration of fixed time where features are produced that have
tangible value to the customer. The original Rules of Scrum stated that each sprint
was 30 days in length. However, over the years Scrum has adopted the practices
from other agile methodologies and the common practice is to see sprints of
between two and six weeks in length. The key is that each sprint must be the exact
same fixed length, and each MUST produce fully tested functionality that has real
value to the customer.
Release — A release is a group of related sprints. Releases become necessary for a
variety of reasons. The Rules of Scrum require every sprint to provide fully tested,
production ready features. However, there are many situations where it is either
impractical or ill advised to put the features completed from a single sprint into
production. Imagine an organization that has set release windows where new code
can be put into the production system. In these situations, the Development Team
simply places the results from sprints “on the shelf” until all the releases that are
part of the release are complete and then the entire group of features is place into
production together.
The next artifact included in the set of four is the team or scrum board. The team
board is the primary tool used by a Scrum team to manage the sprint. The team
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 86
The far left most column contains the product backlog items or user stories
assigned to the current sprint. Each of the other columns represents the tasks
required to deliver that story. The next column moving from left to right is To Do.
This column is for the tasks that have not started and still need to be completed.
The In Progress column represents tasks on which the team is currently working.
The number beneath the column represents the maximum number of tasks that are
allowed within the column. These numbers are part of using Kanban to managing
work in progress or WIP. The values for each column are defined by the team at
the beginning of the project. For the In Progress column, this number is 5 meaning
there can be up to five tasks in progress at the same time. The next column is
validate. This column contains the tasks that are complete and ready for testing. In
this example, only three tasks can be present at a time. The next column is
Impeded. This column is for tasks that are currently blocked. The team needs to
focus on these items to resolve whatever the issue is. Only two items are allowed
to be impeded at a time. The final column is Done. This column is where the team
places it complete, fully tested tasks. At the end of the sprint all the tasks which
begin in the To Do column end in the Done column.
At the bottom of the team board is a single row dedicated to something called
technical debt. Ward Cunningham, one of the authors of the Agile Manifesto, said
that “so problems with code are like financial debt. It’s OK to borrow against the
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 87
future, as long as you pay it off.” The notion here, is that sometimes teams push
products and services into production quickly to get some experience. In many
cases this is both a necessary evil and/or a good idea. Eventually, however the
team has to go back to that completed item and incorporate that learning into the
product. This process is called refactoring. Therefore, technical debt represents is
the process of taking short cuts and delivering product, service or result that is not
quite right for the task currently being done. Doing so reduces the team’s
productivity, and eventually the team must go back a correct these imperfections.
The fourth artifact used in Scrum is a burndown chart. A burndown chart is
another information radiator used by the team to show stakeholders how the team is
doing on the current sprint. Each day of the sprint is represented by a vertical bar
showing the number of story points remaining in the sprint. A story point is an
arbitrary estimate of the work required to complete the task. The rate at which the
team produces story points is called its velocity. The team begins the sprint with a
forecasted rate of productivity with the end of the sprint fixed. As the sprint
progresses, the team constantly must evaluate how it is doing against that forecast.
If it finds the velocity is falling beneath the forecast they must adjust the number of
stories being produced because the team is not allowed to change the end date of
the sprint.
A fifth artifact that is occasionally included, but does not nicely fit into the memory
jogger is the sprint backlog. Let’s now take a look at the basic Scrum process.
This process is relatively simple, but it is critical that it be exactly followed for one
to gain the benefits of Scrum. The most commonly cited source for what
specifically these rules or guidelines are is the Scrum Guide available from the
Scrum Alliance or Scrum.org.
Slide 85
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 88
Every project begins the same way. Someone creates a vision and a ranked product
backlog and the team enters a release planning meeting. The release planning
meeting serves several purposes. The development team first uses the meeting to
examine the backlog items to determine how they need to be grouped together to
produce releases. Additionally, the team must determine how long each sprint
needs to be. Remember, each user story must fit into a single sprint. So the team is
tasked with getting a sprint length that is as short as possible, but long enough to
deliver fully tested, production ready results that have real value to the business.
To do this, the team must somehow determine estimates for each PBI. There are a
number of techniques commonly used for this purpose that are discussed later in
this book. The estimates are used by the development team to ensure each sprint is
approximately the same size. Once the development team has determined how
long the sprints will be and how the sprints will be grouped into releases, then team
is done with the release planning meeting. Approximately once a quarter the team
must revisit the release planning meeting.
The next step in the process is the sprint planning meeting represents the first step Slide 86
of the process that gets repeated with each sprint. The purpose of the sprint
planning meeting is to plan the work of the current sprint, and it officially kicks off
the sprint. The meeting is broken into two parts.
To begin the meeting the team sits and examines the ranked product backlog. The
goal of the development Team is to produce the most important features to the
business first. That means they take the maximum number of items they can
produce in a single sprint starting at the top of the list and work down until they
have all they can reasonably complete. There are a number of factors that can limit
this production, but let’s keep it simple for now. Sometimes, as the team examines
the backlog they discover there are User Stories that appear lower down the
backlog, but that it makes sense to pull those items up into the current sprint
because they relate to the current work in some way, make it easier to produce
future items, or are just easier to produce right then. It is perfectly acceptable to
occasionally pull those items up so long as it is an exception and not the rule. In
addition to selecting the user stories to be produced in the current sprint, the team
must also get a lot more detail about those items.
The process of gaining more detail about a feature or backlog item is called
backlog grooming. This is process where the product backlog items are defined in
enough detail that the development team can build the feature. This is a
requirements definition process, and is expected to take half the meeting. The
second half of the meeting is used to break apart those now well defined PBIs into
the tasks needed to complete the user stories, defining the task order, any
dependencies, and any specific resource requirements. Earlier we established the
rule that no user story could be larger than a single sprint. Now we establish a
similar rule concerning the size of the tasks used to deliver the PBIs. The rule is
that not task can be larger than a single day. Some sources say no task can be
larger than two days. The problem I have with this two-day alternative is that it
fails to align with Scrum’s measurement system, the daily scrum. In addition, each
task must either be a whole day or half day. No other options are allowed. This
means exacting estimates of “X” number of hours are completely unnecessary.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 89
The first half of the meeting requires heavy involvement by the PO. However, the
second half does not. Remember, the development team is self-governing so there
is no need for a project manager or product owner to tell the team members what
tasks they should do. Each sprint then becomes a small project with a fixed
duration. The development team’s plan must include all the resource requirements,
dependencies, task order, and any other necessary information to complete the
work. This plan is documented using a visual posted in a war room called a team
or scrum board. The scrum board is recreated for each sprint. In the original rules
of scrum the sprint planning meeting was expected to take a full work day.
However, in the real world where sprints average between two and three weeks the
sprint planning meeting rarely takes longer than four hours. Once the development
team has created their scrum board they end the sprint planning meeting and begin
executing what they just planned.
The goal of the execution phase in Scrum is to produce the just defined User
Stories or features by the end of the sprint. These features must be fully tested and
truly ready for production. Remember, part of the release planning meeting
process was to determine how long the sprints needed to be so the development
team had enough time to produce working product, service or project result that
was fully tested and ready for production. This means we test and test in every
sprint. This process often limits the number of features we can produce in each
sprint, but it also tends to produce a better finished product.
To reach the goal, the team uses a standard process every single day to complete
the desired work. This is where Scrum really adds value to organizational
performance. The early leaders of Scrum learned an obvious lesson often missed
by their linear project management cousins. In more linear projects, the team often
struggles to determine they are in trouble and react. This happens because of the
basic mechanisms use to report progress. In most project, reporting is done on a
weekly or alternating week basis. The team comes together either via a conference
all or physically and is asked report where they are with their tasks. The most
common answer is, “right on track.” If a numeric value is required, the most
common value is 90%. Yet, somehow it always takes twice as long to do the last
10% as it did the first 90%. Furthermore, no one reports they are behind until it is
the last possible second when they suddenly discover they can’t meet the deadline.
This all happens because of the reporting model. It is not because of bad people. It
is a problem with the project measuring increments. If the team is working on a
project expected to take several years to complete it is likely OK to have every
other week or weekly reporting. However, when the project is a year or less that is
likely not frequent enough. Scrum long ago figured out a lesson most of us
consider common sense. Smaller things are much easier to manage than larger
ones. One of the reasons Scrum works is that it aligns its measurement with
reporting frequency.
Every day in a Scrum project the team uses the same process. This is part of what Slide 87
creates its cadence. Each day begins the same way with a meeting called the Daily
Scrum. This is a ten to fifteen minute meeting that provides the Team with basic
project status and communication. Each day the Development Team stands around
the Scrum or Team Board and answers three questions:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 90
The focus is supposed to be on the second and third questions as the first is
historical and there is no chance to impact it. Each member of the Development
Team reports their results to the other members of the Development Team and
NOT to the Scrum Master or Product Owner who are also present. The Scrum
Master is tasked to act as a facilitator and the PO is only an observer. As each
Team member reports their answers to the three questions at the same time they
move physical representations of the tasks on the Team Board. The team is
allowed to spend a quick moment or two solving simple problems, but cannot get
sidetracked as the meeting is only allowed to take 10 to 15 minutes. Once each
member of the Development Team has answered the three questions the meeting
disbands and everyone begins working on the tasks for that day. While the
Development Team works to produce the days results, the Product Owner works on
grooming yet undefined User Stories for future sprints while also working with the
Scrum Master to remove impediments. No one from the business may add a
feature to a sprint once work has commenced, but may add, delete or change items
on the Product Backlog at their discretion. The Development Team occasionally
has to take User Stories out of the current sprint as new information is learned and
may at their discretion pull up a new item if the situation warrants.
On the last day of each sprint two meetings are conducted. First, the Team
conducts a Sprint Review. This one hour to 90 minute meeting allows the Product Slide 88
Owner to present the results of the sprint to the customers. This is all about
showing working product to the people who will really use it. The Development
Team wants the product owner to take this responsibility because it both provides a
connection from them to the users and helps to ensure their engagement throughout
the sprint. The Team is allowed a few hours to prepare for this meeting.
Once the Sprint Review is complete, the Development Team conducts a Sprint
Retrospective. If the Sprint Review is all about the product of the project, the
Sprint Retrospective is all about the process. The Product Owner is not allowed to Slide 89
attend the Retrospective and the Scrum Master is only present as a facilitator. This
meeting provides the Development Team the opportunity to review the process and
find the best way to improve the process. The team uses a wide range of games
and tools to answer the question, “If tomorrow we were 1,000% more efficient
what we do to get there?” It is singularly focused on the process the Development
Team is using to achieve their results.
The next day the process begins again with a new sprint and the Sprint Planning
Meeting until either the Development Team delivers all the promised functionality
or is out of time and money at which point the Product Owner must decides to
close the project or obtain more. That is all there is to the basic Scrum process.
However, before we completely leave Scrum I want to spend a minute and add a
few connected ideas that are often added to Scrum as a team becomes more
advanced.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 91
The first if these ideas is a revisit of a previous topic. If you remember back
several pages we discussed Work In Progress or WIP. Managing WIP requires the
Team to limit the number of tasks being worked a single moment based on priority.
However, none of the Scrum tools we have so far discussed force this to occur.
One tool that is often added to Scrum to achieve this desired result is Kanban. We
are not going to introduce Kanban here, just describe its implementation with
Scrum.
Within the Team’s Scrum Board, there are a series of columns that each represent a
separate state in the work’s progress. When using Kanban, the only alteration the
Team makes to the Board is adding numeric values for each column. These values
represent the maximum number of items that can be present in that column. The
effect of these limiters is to force the Team to focus on getting tasks all the way
through the process rather than allowing them to stagnate in one particular state
(usually the Impeded State).
Another practice sometimes used by Scrum teams is Iteration 0. This is NOT part
of Scrum found in the Scrum Guide. Remember the basic rule we established for
Scrum that said every single sprint would be the same length of time and must
produce functionality that has real value to the business? Iteration 0 violates both
those rules. The goal of Iteration 0 is to produce two items that do not initially
have value to the business. These are the core architecture and feature list. It is not
unusual for this work to take significantly longer than a single sprint, and as such it
violates the Rules of Scrum requiring and out. If a team has decided to use
Iteration 0 because they believe the project needs a more formal architectural plan
and/or work on its feature list it is important that the team also provides an iteration
or milestone plan to ensure the team quickly moves into more standard Scrum
sprints.
Hybrid Life Cycles
A hybrid life cycle is one that combines one or more of the other life cycles. It
offers the highest degree of variability and complexity. For the exam, it is unlikely
you will see many if any questions on it as it is almost impossible to establish any
standards for them.
Agile Development and the PMBOK® Guide
Over the last decade an unnecessary battle has waged between proponents of agile
development and the world of professional project management. According to
many Agilists, the practices expressed in the PMBOK® Guide are old, and dated
representing a linear way of executing projects using only predictive life cycles.
PMPs often argued that agile development was costly, unpredictable, and a
dangerous way to manage business critical initiatives. Sadly, neither of these
views is true. While there are many projects led by PMPs using predictive life
cycles, there has never been anything in the PMBOK® Guide that mandated it be
done that way. The Guide also has never suggested agile development offered any
less chance of success than any other methodology. In fact, PMI® has funded a
significant amount of research looking at methodologies and success. That
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 92
research has consistently found there are great advantages to applying agile
concepts. Yet, the battle raged. With the 6th edition of the PMBOK® Guide finally
addressed this disagreement head-on by making a significant effort to specifically
call out applications of agile development throughout the Guide. Simply put, as a
professional project manager and a PMP candidate you have an obligation to know
and understand the basics of agile development. The PMP® exam for which you
are preparing will give you ample opportunity to prove that knowledge.
The Ten Knowledge Areas
PMI® takes these six elements and adds four more factors that are elaborated on in
chapters four through 13 of the PMBOK® Guide. These chapters are referred to as
the ten knowledge areas of the PMBOK® Guide. Appearing in order, these
knowledge areas are:
Integration Management Resource Management Slide 92
Scope Management Communications Management
Schedule Management Risk Management
Cost Management Procurement Management
Quality Management Stakeholder Management
Within these knowledge areas, the 49 defined processes of project management are
found. It is necessary for you to memorize each of the individual processes to pass
the exam. However, simply memorizing the processes, their makeup, and how
they relate to one and other is not enough. To successfully pass the PMP® exam,
you must clearly understand why each process is important and how it relates to
successfully completing a project. Remember, you cannot read into this
requirement an attempt by PMI® to suggest that on every project you must
complete every one of the processes.
Slide 95
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 93
Conclusions
The process groups are highly interconnected and often flow in non-sequential
patterns to produce successful projects. The simplest way of saying this is that you
do not know for sure what is going to happen on any given project so you must be
prepared to deal with change. Change might require you to enter or make use of
another process group. This happens when you run into problems that require
additional planning, when you start a new project because the scope warrants a
second effort, or when you are simply unable to complete the project so it is
cancelled.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 94
Exercise 4 —
Exercise 4 — The Basics of Project Management The Basics
Some of these questions are not designed to replicate or reflect actual exam
questions. They are designed to ensure you clearly understand the topics discussed
in this chapter, which will help you study for the PMP® Exam.
1. Which of the following is not an output of a project?
A. A product or artifact that is quantifiable
B. A capability to perform a service
C. A manufactured product
D. All of the above
2. Which of the following is not a characteristic shared by both projects and
operations?
A. Performed by people
B. Generates repetitive outputs
C. Are constrained by limited resources
D. Are planned, executed, and controlled
3. Which of the following is an example of an operation?
A. The development of a new product
B. Constructing a building
C. Producing a new car
D. Developing a new marketing campaign
4. Which of the following is a key element of defining an operation?
A. Operations maintain an existing set of practices
B. Operations have unique charters and goals
C. Operations have defined start and end dates
D. None of the above
5. Which of the following is an that is organization likely to be project-based?
A. Organizations who derive most of their revenue from performing
projects
B. Organizations that have adopted management by projects
C. Both A & B
D. None of the above
6. Which of the following is not a factor in the development of organizational
culture and style?
A. Shared values, norms or beliefs
B. Technical certifications
C. Policies and procedures
D. View of authority relationships
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 95
7. Who is responsible for determining what the “appropriate practice” for the
project is?
A. The project sponsor
B. The project manager
C. The key stakeholders
D. The project management team
8. Which of the following is the best description of the primary purpose of the
PMBOK® Guide?
A. To define the proper methodology for managing project
B. To identify the PM knowledge considered good practice
C. To establish the international PM standards
D. To define proper PM practices
9. Which of the following is not a common characteristic of a project?
A. A project is temporary
B. A project produces a unique product or service
C. A project has repetitive tasks
D. A project uses progressive elaboration
10. Which of the following is part of the temporary nature of projects?
A. The project team seldom outlives the project
B. The project team existed prior to the project being created
C. The market window is not usually temporary
D. The project team is always broken up at the end of the project
11. Which of the following represents the best definition for progressive
elaboration?
A. Developed in steps and continuing in increments
B. Developed with a continuous process
C. Developed with explicit steps
D. Developed in accordance with the defined project phases
12. Which of the following is a reason to authorize a project?
A. A market demand
B. A specified organizational need
C. A regulatory requirement
D. All of the above
13. Which of the following correctly identifies the project management process
groups?
A. Initiating, planning, developing, testing, and deployment
B. Initiating, planning, executing, monitoring and controlling, and closing
C. Envisioning, planning, developing, deployment, and closing
D. Envisioning, planning, executing, monitoring and controlling, and
closing.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 96
14. Which of the following is not one of project management’s triple constraints?
A. Time
B. Costs
C. Scope
D. Requirements
15. Which of the following is not one of the PMBOK® Guide’s nine (9) knowledge
areas?
A. Cost management
B. Human resources management
C. Requirements management
D. Quality management
16. Which of the following is not one of the PMBOK® Guide’s nine (9) knowledge
areas?
A. Time Management
B. Risk management
C. Communications management
D. Contract management
17. Which of the following is not a key element to understanding the project
environment?
A. Understanding specific government regulations
B. Understanding the cultural and social environments
C. Understanding the international and political environments
D. Understanding the physical environment
18. Which of the following is not a term used to define application areas?
A. Technical elements, such as a specific kind of engineering
B. Financial elements, such as a knowledge of reading financial statements
C. A management specialization, such as government contracting
D. Industry groups or verticals, such as telecommunications, automotive,
or financial
19. Which of the following is the best definition of a standard?
A. A government requirement, which specifies product, process or service
characteristics
B. A document established by consensus and approved by a recognized
body that provides for common and repeated use
C. A guideline that describes a preferred approach
D. Mandated compliance by some governmental organization
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 97
20. Which of the following is not a key common element of understanding the
project environment?
A. The cultural and social environment
B. The international and political environment
C. The outside environment
D. The physical environment
21. Which of the following best represents the definition of a program?
A. A temporary endeavor undertaken to create a unique product or service
B. A group of related efforts managed in a coordinated way to obtain
benefits and control not available from managing them separately
C. A collection of efforts or groups of efforts and other work that are
grouped together to facilitate effective management of that work to
meet strategic business objectives
D. None of the above
22. Which of the following statements is a key element of a subproject?
A. They are based on the project processes
B. They often involve specialized technology
C. The subproject can consist of a series of even smaller subprojects
D. All of the above
23. Which of the following is not true about a project management office?
A. A PMO should always have direct control over all project activities in
the organization.
B. A PMO is an organizational unit to centralize and coordinate the
management of projects.
C. A PMO oversees the management of a project, programs or a
combination of both.
D. PMOs can operate on a continuum from providing project management
support functions to software, policies, and actual direct management of
projects.
24. What does a project life cycle define?
A. What technical work to do in each phase
B. What the deliverable dependencies are
C. Who will complete each deliverable
D. How each deliverable is approved
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 98
25. Which of the following is a characteristic that most project life cycles share in
common?
A. Projects might or might not have phases, but are defined by deliverable
handoffs.
B. Phases are usually sequential and are usually defined by some sort of
technical information transfer or component handoff.
C. Projects are defined by iterative phases that continue for a predefined
period.
D. Projects do not have phases and are usually defined by the need to have
requirements defined at the beginning of the project.
26. Which of the following is not common for a project’s life cycle?
A. Cost and staffing levels tend to be low at the start, peak during the
intermediate phases and drop rapidly as the project concludes
B. The level of uncertainty and risk of failure is highest at the beginning
and improves throughout the project
C. The cost of project changes and correcting errors gets progressively
lower as the project continues
D. The ability of stakeholders to influence the project’s characteristics is
highest at the beginning and gets progressively lower
27. When are project phases generally considered to be completed?
A. When a review of the accomplished work and the deliverables has taken
place, and they have been accepted
B. When a managerial decision to continue to the next phase has been
made
C. When the deliverables have been accepted
D. A & B
28. Two characteristics of a deliverable are:
A. They are quantified and usable
B. They are part of the process and are tangible
C. They are measurable and verifiable
D. None of the above
29. Bob is a project manager whose project has been closed at the end of the third
phase of the five phases that were initially planned. What should Bob’s next
course of action be in terms of the current project?
A. Seek a review with the key stakeholders
B. Seek a review with the project sponsor
C. Complete a review with the project team
D. Nothing, this is a legitimate decision
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 99
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 100
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 101
44. A project manager comments to a coworker that she is having a lot of trouble
with a large number of scope changes in her project. Which of the following is
a likely cause of the large number of changes?
A. Not involving stakeholder early enough in the project
B. Having too many project stakeholders
C. Not having a senior enough sponsor
D. All of the above
45. Management by Objectives works only if:
A. The process is well documented
B. The processes do not impact the objectives
C. It is supported by the management team
D. The processes are defined in the project charter
46. In which of the following process groups are stakeholders not identified?
A. Initiating
B. Closing
C. Executing
D. Stakeholders can be identified in any process group
47. Jane is a project expediter working at a manufacturing company. Her main
project is currently in the planning process. Her project sponsor comes to her
and asks for information about the project management methodology the
company has decided to deploy. He asks her why they are using it and where it
came from. What should Jane do?
A. Provide the information to the project sponsor
B. Advise the owners of the new methodology of the request
C. Provide the sponsor with the appropriate templates
D. All of the above
48. Sam is a project manager working for a consulting company. He is currently
responsible for a large multi-million dollar effort with resources in seven
locations. One day three stakeholders come into his office and are very upset
because they just realized that requirements they see as critical are not included
in the project scope. What is the most likely cause of the absence of these
requirements?
A. The sponsor decided against including their requirements
B. The stakeholders in question were not involved early enough in the
process
C. The stakeholders are new to the organization
D. All of the above
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 102
49. Linda is a project manager for a major engineering project. She is in her third
year on the project and has been in charge since project’s inception. Her boss,
the Vice President of Engineering, walks into Linda’s office one day to inform
Linda that it is likely that her project is going to be postponed because several
of the project’s major stakeholders are unhappy with the project. Which of the
following is likely the cause of Linda’s problems?
A. Linda has been late with deliverables
B. Linda’s project is over budget
C. Changes in the triangle have caused a reduction in project scope
D. Any of the above
50. Iain is a program manager at a small engineering firm. He is currently leading
a project with 14 resources that provides a new design for a major urban hub.
He is almost through with the execution phase. Iain just learned that several
environmental interest groups intend to protest his design at an upcoming
public hearing. What is the most likely cause of their issues?
A. They are extremist groups
B. The interest groups were not included early in the project process
C. Key elements of project scope have been dropped
D. All of the above
51. Regina is a project manager for a major engineering project. She is in her third
year on the project and has been in charge since project’s inception. Her boss,
the Vice President of Engineering, walks into Regina’s office one day to inform
Regina that it is likely that her project is going to be postponed because several
of the project’s major stakeholders are unhappy with the project. What should
Regina do?
A. Revisit the scope statement
B. Ask to freeze the project
C. Try to convince her boss that the project can be saved
D. Open a dialogue with unsatisfied stakeholders
52. What is the relationship between the project manager and the stakeholders?
A. The project manager is a stakeholder
B. The project manager supervises the stakeholders
C. The project manager reports to the stakeholders
D. The project manager communicates with the stakeholders
53. In Scrum, the team activity is monitored and coordinated on the following
basis:
A. Hourly
B. Daily
C. Weekly
D. Monthly
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 103
54. The Product Owner of your project is absent due to a planned vacation. Who
should assume the Product Owner’s responsibilities at a sprint planning
meeting?
A. The ScrumMaster
B. The Team
C. A person selected by the Team
D. The CEO
55. You are new on an internal Agile project for a company with well developed
processes. You need to find the list of prioritized project requirements. Where
will you most likely find this list?
A. Sprint Backlog
B. Product Backlog
C. Iteration Backlog
D. The Release Plan
56. In a Scrum Project, the typical length of an iteration is:
A. Between 2-6 weeks
B. 30 days
C. 45 days
D. 90 days
57. Which of the following statements BEST describes the relationship between
Agile Development and the PMBOK Guide?
A. The PMBOK Guide represents PMI's methodology for executing
projects. While Agile Development represents a software development
framework.
B. Agile Development represents the newest way to execute a project
while the PMBOK Guide represents the old way of executing a project.
C. The PMBOK Guide represents the overall framework for executing
projects and Agile Development represents a set of specific
methodologies used in project execution.
D. Agile Development represents the overall framework for executing
projects and the PMBOK Guide represents a set of specific practices
used in large scale projects.
58. Which of the following terms refers to a staging and scheduling strategy in
which the various parts of the system are developed at different times or rated
and integrated as they are completed?
A. Iterative development
B. Incremental development
C. Staged development
D. Agile development
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 104
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 105
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 106
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 107
25. Answer C. PMBOK® Guide – The cost of project changes and the correction
of errors gets progressively higher on most projects because of the amount
already invested and because of the fact that changes or errors often force the
rework of already-produced deliverables. It is this fact that often justifies the
significant amount of work done at the beginning of the project to define
requirements.
26. Answer A. PMBOK® Guide – A project phase is generally considered
concluded when the key project stakeholders have actually accepted the
deliverables from that phase. This might also include an overt decision to
continue to the next phase. However, this does not preclude multiple phases
from occurring at the same time.
®
Answer C. PMBOK Guide – A deliverable is a measurable, verifiable work
product such as a specification, feasibility report, detailed design document, or
working prototype. Some deliverables can correspond to the project
management process, whereas others are the end products or components of the
end products for which the project was conceived.
®
Answer D. PMBOK Guide – The answer is nothing because according to the
®
PMBOK Guide a phase can be legitimately closed without the decision to
initiate any other phases for a wide variety of reasons.
30. Answer D. PMBOK® Guide – Formal phase completion does not include
authorizing the subsequent phase. For effective control, each phase is formally
initiated to produce a phase-dependent output of the Initiating Process Group,
specifying what is allowed and expected for that phase.
31. Answer A. PMBOK® Guide p. 23 – Phase-end reviews can be called phase
exits, phase gates, or kill points. Milestones are significant points or events in
the project such as when the phase-end review has been completed, but they are
not the review itself.
32. Answer B. PMBOK® Guide – Many projects are linked to operational work of
the organization while other organizations only formally approve projects after
the completion of a feasibility study, or manage the preliminary planning phase
as a separate project. Some projects can initially be informal for a limited
amount of time before formal approval has been secured.
33. Answer D. PMBOK® Guide – The driving forces that creates the stimuli for a
project are typically referred to as problems, opportunities, or business
requirements.
34. Answer C. LGd PMP® Exam Prep course. While it is true that operations
often require key resources, projects do also. Projects and operations also both
have limited budgets. However, whereas operations are ongoing and repetitive,
projects are fixed to a set time.
35. Answer A. LGd PMP® Exam Prep Course. The project lifecycle defines what
resources will be involved in each phase and what work is to be done in each
phase.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 108
36. Answer A. PMBOK® Guide p.24 – This is an example of the kind of question
on the exam where multiple answers look right. According to the PMBOK
Guide, responsibility and authority is the correct answer—even though project
managers must watch the stakeholders’ influence and their level of support
throughout the project.
37. Answer C. PMBOK® Guide p. 23 – Negative stakeholders are often
overlooked by the project team and because of this they risk failing to bring
their projects to a successful end.
38. Answer D PMBOK® Guide p. 25 - This is one of the many questions where
your ability to select the best answer—as seen by PMI®—becomes critical.
Many select the PMO because not every company has a Project or Program
Management Office. However, this is not the best answer. The PMO is listed
in the PMBOK® Guide as a key stakeholder, but the general public is not.
39. Answer A. PMBOK® Guide p. 23 – All of these items are important. But
because stakeholders often have very different or conflicting objectives, it is
most important that the project manager manage the stakeholder expectations.
40. Answer A. In the project management process the approved budget and the
quantitative risk assessment both come after the project schedule. Only the
WBS is required from this list.
41. Answer B. In the project management process, the project manager should be
named as early as possible and should take charge of the project upon their
assignment. It is considered a poor choice to allow a stakeholder to take charge
of the project.
42. Answer A. Exceeding stakeholder expectations is the same as gold plating.
Gold plating is a key evil according to PMI® that should never be done.
43. Answer D. Stakeholder management is an ongoing part of the project
management process. The identification of stakeholders is a key element of
this and must be done in all of the process groups.
44. Answer A. Many projects involve a significant number of stakeholders or
suffer from not having a senior enough sponsor. These issues do not
necessarily have any impact on scope change. However, not having
stakeholders involved at an early enough stage can dramatically increase the
amount of scope change.
45. Answer C. Any management methodology requires the management team to
support it in order to be effective.
46. Answer D. Stakeholders can be identified at any point in the PM process.
47. Answer B. This question is another example of a question requiring you to
determine what you would do first. In this situation it would be best if you
immediately notified the owners of this request. In many cases this is going to
be a PMO.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 109
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 3 — The Basics of Project Management
Page 110
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 111
Integration Management
Overview
The Integration Management Knowledge Area is found in the fourth chapter of
the PMBOK® Guide. For many PMP® candidates it is one of the most difficult
knowledge areas to learn. Students struggle with Integration Management
because the topic comes up very early in the course but it is about bringing other
processes together — processes with which they are not yet very familiar. This
creates a problem. When should we discuss Integration Management? At the
very beginning of the course when students are not yet familiar with the other
processes? Or at the end after they have learned about everything else that must
be brought together? For the sake of consistency, we have chosen to handle the
Integration Management Knowledge Area in the same order as the PMBOK®
Guide.
What is Integration Management anyway? Integration Management is where all
the other processes are brought together and reconciled. The PMBOK® Guide
says this a little bit differently. The PMBOK® Guide (p.63) defines Integration
Management as “the processes and activities needed to identify, define, combine,
unify and coordinate the various processes and project management activities
within the project management process groups.” According to PMI®, Integration
management is the ONLY knowledge area that CANNOT have its
accountability transferred to a specialist. It must be managed by the project
leader. It is the project leader that is ultimately responsible for the project as a
whole. As you go through this chapter, it is important that you remember these
processes can be iterative.
The Integration Management Knowledge Area is comprised of six individual
processes. There is one process found in the initiating, planning, executing and
closing process groups and there are two processes found in the monitoring and
controlling process group. The seven processes involved with integration
management include:
4.1 — Develop project charter Slide 97
4.2 — Develop project management plan
4.3 — Direct and manage project work
4.4 — Manage project knowledge
4.5 — Monitor and control project work
4.6 — Perform integrated change control
4.7 — Close project or phase
4.1 Develop Project Charter
All
The first process found in the integration management knowledge area is the PMBOK®
develop project charter process. Notice how the process title appears. It is in Guide
verb/noun format. Every one of the 49 processes are titled the same way. They processes
are always verb/noun format. This can help you with the memorization process. are in verb/noun
Developing a well formed project charter is critical to the overall success of the format
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 112
project. However, in the real world project charters are often not done well — or
even done at all. To understand why they are often not done correctly we have to
begin with an understanding of the purpose of the project charter.
The primary purpose of the project charter is to authorize work to begin on the
project. However, the charter also provides some other basic information. In Slide 98
addition to authorizing work to begin, the charter does the following:
Names the project manager and project sponsor
Defines any constraints and assumptions that exist (this includes any deadlines,
budget limitations, resource limitations, any known risks, and scope must-
haves)
Defines the project success criteria (it is always recommended that success
criteria be quantitative in nature as subjective success criteria usually leads to
project failure)
The charter does NOT include detailed requirements, the project schedule, the
project budget or other detailed information. Remember, from PMI’s perspective
the project has not started yet. The charter is the document that authorizes the
project manager to begin the planning process and to determine what it is going to
take to successfully complete the project. Once the plan is submitted, the sponsors
maintain the right to cancel the project if they deems the plan not what they desire.
The inputs to the develop project charter process include:
Slide 99
®
.1 Business documents — When discussing business documents the PMBOK
Guide is primarily referring to the business case and benefits management plan.
The business case is a document written from the perspective of the business
that explain how the expected project outcomes justify the necessary
investment. The second document referred to in the PMBOK® Guide is the
benefits management plan. This is a documented explanation defining the
processes for creating, maximizing, and sustaining the benefits provided by a
project or program.
.2 Agreements — Agreements are used to define the initial intentions for a
project. They may take many different forms such as memorandums of
understanding (MOUs), service level agreements (SLAs), contracts, etc.
.3 Enterprise environmental factors — Enterprise environmental factors
represent the first of a number of items we like to call freebes. Freebes
represent items that almost always appear in the listing of inputs, tools and
techniques, or outputs. Enterprise environmental factors represent the things
going on around the project that could impact it. They are almost always an
input to a defined process. It is far easier to memorize the few times they do
not appear than it is to try and learn all the times they do appear. Examples of
enterprise environmental factors include things like governmental or industry
standards, organizational infrastructure, and marketplace conditions.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 113
Page 114
Net Present Value (NPV) — The Net Present Value is almost identical to the Slide 102
present value. In the Present Value calculation you discount the value—
typically representing a revenue stream—to account for inflation or some other
similar rate. Net Present Value does the same thing, but it also takes into
consideration the money that must be spent to complete the project over time.
To do so it costs the Present Value from the net costs to obtain the NPV.
Internal Rate of Return (IRR) — If you have followed these equations
carefully, you might have noticed the variables in each are largely the same. In
addition, each equation assumes that the term and interest rates are provided.
In an Internal Rate of Return equation, it is the interest rate that must be
determined. Unfortunately, there is no simple equation to calculate the internal
rate of return. To solve for the IRR you must use the NPV calculation and
select the middle-most interest rate of the four potential answers. You are
looking for an interest rate which produces an NPV of zero. Based upon the
result from the first calculation you can determine if you need a larger or
smaller value. You should not have to calculate the NPV more than twice to
determine the correct IRR.
Benefit / Cost Ratio (BCR or BCI) — Most people are used to talking about a
cost / benefit ratio and this is the same thing. The only difference is that the
benefits are always placed in the numerator and the costs in the denominator.
This is done so that any value greater than one is good.
Depreciation — These are calculations used to reduce the value of a large asset
primarily for tax purposes. This takes into account the wearing out of
equipment. Although possible, it is unusual to select a project based upon
depreciation. The four most common methods of depreciation are discussed
later in this course.
Opportunity Cost — Opportunity cost is the value of the next highest
alternative—assuming the alternatives are mutually exclusive. It defines what
you are giving up by making the choice.
Sunk Costs — Sunk costs refer to the money that has already been spent on the
project. It cannot be recovered. You should never make a project decision
based upon sunk costs because it could be good money following bad.
Economic Value Added (EVA) — This concept rarely appears on the exam,
but references whether the project returns more value to the organization than it
costs to produce.
Working Capital — Working Capital is an accounting term defined as the
current assets minus the current liabilities. It shows how much money the
organization has available to invest on projects.
Law of Diminishing Returns — The Law of Diminishing Returns argues that
with every process you reach a point where adding one more dollar of cost will
not add an equal return of value. If you discover that increasing the costs by a
dollar does not provide at least a dollar return, you should not invest any more.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 115
The most common type of questions seen on the PMP® exam that deals with these
equations doesn’t actually require you to calculate anything. The most common
type of test question simply asks you to compare several projects where no two
projects have the same kind of data. One project might provide an NPV while
another revenue, a third the Future Value, and the last one has a BCR. At first
glance this might be impossible to solve. However, it is actually very simple. You
need to first look for any BCR data. Remember that any value greater than one is
good. There is no set value with FV, PV, NPV or IRR that is guaranteed to be
good. When taking the test you should never assume information that is not
provided. This means you cannot assume a positive value just because of the size
of the value unless you are given the Benefit / Cost Ratio.
Although these determination methods appear in the business case, they are also
tools and techniques that are available to develop the project charter. The tools and
techniques used in the develop project charter include:
.1 Expert judgment — Expert judgment is simply relying on your subject
matter experts (SMEs). It is PMI’s preferred tool and technique in many
situations — in fact, it is the most common tool and technique. It is always a
good guess if you have no idea. Almost every process has expert judgment as a
tool and technique.
.2 Data gathering — These include a diverse set of tools such as
brainstorming, focus groups and interviews. Brainstorming represents a group
creativity technique where the team attempts to find a conclusion by gathering
information through a spontaneous discussion by the members. Typically, a
dry erase board or other tool is used to capture the information for both
historical purposes and to help the team maintain focus.
A focus group is often used for specific product research. In a focus group a
demographically diverse group of people is brought together for a guided, open
discussion about a product, service or project result. The goal is to use the
information collected from the small group to represent expected results from a
larger populations. The keys are that the discussion is led by a facilitator and
that the members of the group are free to talk with other group members.
Throughout the process researchers observe the group taking notes for future
analysis.
Interviews require the team to meet with stakeholders to elicit information
about the product, service or results of the project.
.3 Interpersonal and team kkills — Techniques such as conflict management,
facilitation, and basic meeting management are commonly cited here. We will
discuss these concepts in the communications and resource management
knowledge areas.
.4 Meetings —Meetings are perhaps the easiest tool or technique used in this
are. The important thing to remember about them for the purposes of the test is
that they are held with key stakeholders to define the key project drivers such as
success criteria, requirements, milestones, etc.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 116
The easiest part of the develop project charter process is the output. This process
only has two outputs. As you have probably already guessed, the first output to the
develop project charter process is the project charter. Upon receiving the signed
charter the project manager begins the real work on the project. Above all else
remember that no project ever begins without a charter. Charters empower the
project manager and provide the team with their success criteria. They also MAY
provide other information necessary to get the project off the ground.
The second output from the develop project charter process is the assumption log.
This document is used to track all assumptions and constraints throughout the
project life cycle.
4.2 Develop Project Management Plan
The second process in the integration management knowledge area appears in the
planning process group and is the develop project management plan. The develop
project management plan process is one of the most important processes found
anywhere. It is the process that aggregates the outputs from the other processes
found in the planning process group. It also Slide 103
defines which project management processes will
be used in the project, as well as how the project
will be executed, monitored, controlled, and
closed. Remember that the project management
plan is a living, breathing document that must be
updated throughout the project’s life. The develop
project management plan process is made up of
four inputs that include:
.1 Project charter — The project charter was
Image 20: Develop PM Plan
just completed as one of the very first Slide 104
processes done in the project. It set a marker notifying everyone that there was
a project and you were its leader. It also defined the project success criteria and
a number of other critical elements you need to move forward regardless of
methodology. If your organization uses an agile methodology like scrum, this
document was called a project vision.
.2 Outputs from planning processes — As soon as the team enters the
planning stage, something PMI® calls the planning process group a lot begins to
happen. If you have already scanned the PMBOK® Guide, you likely already
noticed the fact that virtually every knowledge area has a process that calls out
the creation of some form of a plan. These documents define the rules used to
manage that particular area and therefore become part of the overall project
management plan. The processes used to create these subsidiary plans are often
occurring at the same time the team is developing their overall project
management plan. Be careful and do not let this confuse you.
.3 Enterprise environmental factors — As was stated in the develop project
charter process, enterprise environmental factors are almost always at play. As
the team begins to develop the guidelines and plans they intend to use many so
called environmental factors can influence their work. The most important
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 117
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 118
groups hear the same information. It is often conducted using a variety of games or
brainstorming techniques to capture the stakeholders’ initial input while the team
listens without providing solutions. For the exam, remember that a kickoff can be
done to initiate either the project or a new project phase.
The only output for the develop project management plan process is the project
management plan. As has been stated, the project management plan is the
aggregation of the outputs from the other processes found in the planning process
group. But what does that really mean? For many practicing project managers this
is a point of much confusion. Many believe a project plan is a Microsoft Project®
file and/or a schedule. Neither of these is a true project plan. A real project plan
potentially includes a lot of different components. In addition, there are even more
items that are considered project documents, but not part of the project
management plan. The documents are important even if they are not part of the
official plan document. The table below shows the items that form the basis of a
project management plan and those basic items that are considered project
documents. As you examine the list notice that almost all of the knowledge areas
found in the PMBOK® Guide produces a plan document. Don’t be overwhelmed
by the size of the list. Remember, not every document is used on every project. It
is up to the team to decide which apply to every specific project.
Below is a sampling of the various plans that give you a flavor of their purpose.
Notice how each one establishes a set of basic rules for the management of that
particular area.
Slide 105
Image 21: The Project Management Plan and Project Documents, PMBOK® Guide 6th ed. p. 89
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 119
The scope management plan — The scope management plan describes how
the team plans to define, develop, monitor control and validate scope.
The requirements management plan — The requirements management plan
describes how requirements will be identified, collected, managed and
controlled. It is part of the scope management process.
The change management plan — The change management plan deals with all
potential variances to baselines. This includes scope and requirements
variances as well as variances to schedule, costs, quality, and any other area of
the project. The goal is to prevent negative changes and to enhance positive
changes. No matter what, the key is to follow the change management plan.
The configuration management plan — What version of your plan are you
on? Doesn’t it make sense to ensure that everyone has the correct version of
any document? That’s what the configuration management plan is all about. It
defines how any changes to documents are made and how people are notified of
those changes.
The process improvement plan — A key element of project management for
PMI® is the idea of continuous process improvement. Every project needs a
plan for how you will continue to get better.
For the exam, it a good idea to assume you have all these plans included as part of
your project management plan. To give you a sense of the other project documents
potentially involved with managing a project we define some of those documents
as well. The key is not that you memorize the list, but instead focus on the trends
you see. Notice the number of items that represent baselines, logs, and registers.
Scope baseline — The scope baseline includes the scope statement, work Slide 106
breakdown structure (WBS), and WBS dictionary.
Milestone list — The milestone list is a listing of the major, defined milestones
for the project.
Resource calendars — A good project manager knows when their resources
will be available to complete project work and does not assume they will
simply be there when the schedule says they will.
Schedule baseline — The schedule baseline represents a snapshot or picture of
the schedule as promised to the sponsor. It is critical that the project manager is
always comparing the actual delivered results to the scheduled results found in
the schedule baseline.
Cost baseline — The cost baseline is the same as the Schedule Baseline, except
it is focused on the project budget instead of the schedule.
Risk register — The risk register is a critical document for project success.
The risk register documents all the known potential risks, their triggers,
categories, owners, and the response strategies. The risk register is discussed
extensively in the risk management knowledge area.
The scope, schedule and cost baselines combine to form the performance
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 120
management baseline. Image 22 shows the documents that make up a true project
management plan.
Slide 107
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 121
.2 Project documents — For the direction and management of project work Slide 106
several project documents that are important including the change log, lessons
learned register, milestone list, project communications, the project schedule,
requirements traceability matrix, risk register, and the risk report.
Approved change requests — Notice that the input here is not “change
requests,” but “approved change requests.” Only approved change requests
should ever alter the actions of the project team. Approved change requests in
this context also includes corrective action, preventive action and defect repair.
.3 Enterprise environmental factors — Here is our old friend again. Like
most processes, the directing and managing project execution process can be
influenced by enterprise environmental factors.
.4 Organizational process assets — Organizational process assets often
influence the directing and managing of project execution. They area also one
of the constants.
There are three tools and techniques used in the direct and manage project
execution process. They include the following:
.1 Expert judgment — As always, expert judgment is a tool and technique
used in this process.
.2 Project Management Information System — The PMIS is used to contain
the information about the project. Therefore it is critical to the direct and
manage project work process.
Meetings — Meetings come primarily in three types: informational exchange,
decision making, or brainstorming, option evaluation or design.
The outputs to the direct and manage project work process create problems for
some candidates. Take some time to study them carefully. They include the
following:
.1 Deliverables — Be careful with the deliverables. Recognize that they are not
the same thing as the final product, service or result of the project. They are
components which make up that final output.
.2 Work performance data — This refers to the information from project
activities that is specifically related to the results. It includes deliverable status,
schedule progress, and any costs incurred. They are raw observations at the
lowest level of detail.
.3 Issue log — An issue log is a document used to track conditions or situations
that may have an impact on one or more project objective.
.4 Change requests — Some students find it confusing that “approved change
requests” is an input to a process whereas “change requests” is an output.
Don’t let it confuse you. This is a looping, ongoing process. As approved
changes occur they can cause other changes to be requested.
.5 Project management plan updates — As the changes are approved and
made the project documentation must be updated to reflect the changes. This
might include any of the documents in the plan.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 122
.6 Project document updates — There are some project documents that are
not considered part of the project management plan. As execution occurs and
changes happen these documents must be updated. These documents include:
Requirements documents
Project logs (such as issue or assumption)
Stakeholder register
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 123
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 124
Page 125
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 126
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 127
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 128
process ensures that all the required project work has been completed correctly and
that the project has met its objectives. It also establishes the procedures to follow if
a project is terminated before completion, i.e., how to investigate and document the
reasons for the actions taken. Do not underestimate the importance of this section.
According to PMI®, proper project closeout is an often overlooked process.
The inputs to the Close Project or Phase Process include the following: Slide 117
.1 Project charter — The project charter defines the project success criteria,
and is necessary to close any phase or the project as a whole.
.2 Project management plan — It is impossible to determine whether or not
you have completed all that you are supposed to unless you have a Project
Management Plan that makes it possible for you to comparison what happened
with what was supposed to happen.
.3 Project documents — The huge list of potential documents are all inputs to
the process of closing a project
.4 Accepted deliverables — Good project managers are those who manage
deliverables not tasks. It is the aggregation of deliverables that creates the final
product, service or result.
.5 Business documents — Both the business case and the benefit management
plan are inputs to closing the project or just a phase because they provide a
detailed explanation of why the organization needed the project completed. It
is more information than provided in the charter.
.6 Agreements — Those contracts used to obtain components and work from
those outside the organization are critical to closing the project.
.7 Procurement documentation — Agreements are the actual contracts
necessary to complete the project. Procurement documentation represents all
the other documents such as payment records, manuals, or inspection results.
.8 Organizational process assets — Many organizations have processes,
templates and/or practices that are used throughout the organization to
complete a project.
The tools and techniques used in the close project or phase include the following:
.1 Expert judgment — This applies almost everywhere. Closing a project or a
phase requires it as well.
.2 Data analysis — This is also a previously discussed tool. Don’t lose sight
of the simple ideas—they have great power.
.3 Meetings — This is another common sense tool that appears in the
standards.
There are only two outputs to the close project or phase process. If you look back
at the basic PMI® process model you can easily see what they are.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 129
.1 Project documents updates — Most are a little surprised to see that project
document updates appear before the final product, service or result. These
updates appear first in the lessons learned register.
.2 Final product, service or result — This is it. It’s the reason for doing the
project. This is the only spot where the final product, service or result is an
output.
.3 Final report — The project’s final report provides a summary of how the
team did throughout the project. It addresses issues like the scope objectives
and all the other objectives. It also provides a summary of the validation
information for the final product, service or result.
.4 Organizational process assets updates — As has been mentioned earlier,
continuous process improvement is a key concept for the exam. This means
looking at the processes you currently have and improving them based upon
lessons learned.
Integration Management Summary
As you conclude your studies of the Integration Management Knowledge Area Slide 118
focus in on these points:
The role and components of the charter
The project management plan is a collection of other plans, and the level of
detail depends on the project
Change control must happen throughout the project
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 130
Exam 5 —
Exercise 5—Integration Management Integration
Management
Which of the following is the first process in the integration management
knowledge area?
A. Develop project charter
B. Develop project scope statement
C. Develop project management plan
D. Distribute Information
2. Which of the following is not part of the integration management knowledge
area?
A. Direct and manage project work
B. Develop project management plan
C. Distribute information
D. Monitor and control project work
3. Which of the following information is not captured in the project charter?
A. Initial constraints and assumptions
B. The name of the project manager
C. The project management plan
D. All of the above are captured
4. When should the organization’s business needs be documented?
A. Throughout the entire project process
B. In the planning process
C. In the initiation process
D. Before beginning the initiation process
5. When is a project officially authorized?
A. When the required information has been captured
B. When the project charter is approved
C. When the initial assumptions and constraints have been reviewed
D. When the Project Manager has been selected
6. Which of the following is not a reason to repeat the initiating process group at
the start of each project phase?
A. To keep the project focused on the business need that the project was
undertaken to address
B. It allows the project team to evaluate whether or not the business need
no longer exists
C. It allows the project team to evaluate whether or not the project will be
able to satisfy the business need
D. It ensures project success
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 131
12. The development of the project charter is primarily concerned with which of
the following?
A. Assigning the project team
B. Authorizing the project
C. Providing constraints and assumptions
D. Providing the limits of the project manager’s authority
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 132
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 133
18. What typically happens to the project management processes when the project
is divided into phases?
A. Nothing. The project management processes are designed to work with
many methodologies.
B. The process groups are normally repeated within each phase.
C. The process groups must be altered because they are not designed for a
phased-based methodology.
D. None of the above
19. Which of the following statements is true about processes?
A. Not all of the project management processes are needed on every project
B. All of the processes are required on every project
C. All of the process interactions are required
D. None of the above
20. Which of the following statements is not true about projects?
A. Not all of the project management processes are needed on every project
B. Not all of the interactions apply to all project phases
C. Projects dependent on unique resources might skip the definition of
roles and responsibilities as they are already defined
D. None of the above
21. Can process inputs be predefined on a project as constraints?
A. Rarely
B. Never
C. Often
D. Occasionally
22. Which of the following is not a process from the integration management
knowledge area?
A. Create WBS
B. Develop project charter
C. Close project or phase
D. Develop project management plan
23. In which of the following processes would you develop a high-level narrative
of the project?
A. Develop project charter
B. Develop preliminary project scope statement
C. Develop project management plan
D. All of the above
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 134
24. Which of the following statements about the project charter is true?
A. Chartering a project links the project to the ongoing work of the
organization
B. The project charter helps define the organizational strategy
C. A project is not informally recognized until it is chartered
D. All of the above
25. Which of the following is an acceptable reason to need to re-baseline your
$25,000,000 project?
A. The IT department deploys a new project management control system
B. Your primary vendor requests the use of a new Earned Value reporting
methodology
C. Your sponsor approves a $1,500,000 change in scope.
D. The most expensive deliverable on the project comes in 20% under
budget.
26. What kind of project justification would it be if a chemical manufacturer
authorized a project as a result of new national guidelines for handling of toxic
materials?
A. A business need
B. A legal requirement
C. A market demand
D. A social need
27. Which of the following either directly or indirectly should be addressed by the
project charter?
A. Requirements that satisfy stakeholder needs, wants and expectations
B. Summary milestone schedule
C. Functional organizations and their participants
D. All of the above
28. Which of the following describes whether the expected outcomes of the project
justify the investment?
A. Contract
B. Business case
C. Business needs analysis
D. Project justification
29. What kind of project estimate is typically included in the preliminary project
charter?
A. Rough order of magnitude estimate
B. Detailed budget estimate
C. Budget estimate
D. None of the above
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 135
30. Who is responsible to ensure that the knowledge, skills, and processes of
project management are applied as needed by the project?
A. The project team
B. The project sponsor
C. The project manager
D. All of the above
31. Which of the following is usually a core area of emphasis for effective project
integration?
A. The technical expertise of the team
B. Effective use of the change management process
C. Efficient and effective communication throughout the key interfaces
D. Efficient and effective product control
32. Which of the following is a key driving force for communication on a project?
A. Performance
B. Differentiation
C. Optimization
D. Integration
33. You are a project manager meeting with a coworker over lunch. You explain
that you spend a lot of time reviewing historical records from previous, similar
projects to prepare for your current project. Which of the following describes
the best use of those records?
A. Project planning, creating lessons learned, and risk management
B. Life cycle costing, estimating and lessons learned
C. Estimating, risk management and project planning
D. Life cycle costing, lessons learned and project planning
34. You are a relatively new project manager in your organization and have been
given a mentor to help you succeed. While meeting with your mentor she
suggests that when it comes to change, your attention should be given to:
A. Following your change management process
B. Making the changes
C. Tracking and recording the changes
D. Preventing unnecessary changes
35. When designing an effective change management plan it should include all of
the following except:
A. Lessons learned
B. Policies
C. Procedures
D. Meetings
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 136
36. You have just been hired by a company and are a new project manager. You
receive your first project and are preparing to begin your role. To improve your
chances of success, it would be best in this situation to rely on what during the
planning stage?
A. Lessons learned repository
B. Stakeholder input
C. Certification training
D. Scope verification
37. When attempting to lead a project, you struggle because your project is
experiencing a significant number of changes to the project charter. As you
work through these changes, who has the primary responsibility to decide if the
changes are necessary?
A. Project manager
B. Project team
C. Project sponsor
D. Project stakeholders
38. You are a project manager at ABC Corp. Which of the following explanations
would most accurately describe your project management plan to a coworker?
A. A Gantt chart showing the project schedule and resources
B. The project scope document
C. A scope management plan, risk management plan combined with six
other management plans
D. The project management plan is the document that describes how the
project will be executed, monitored and controlled, and closed.
39. As a project manager your boss instructs you to develop a realistic plan. Which
of the following is the best method for achieving a realistic plan?
A. You create the plan with input from the sponsor
B. You create the plan with input from the project team
C. You create the plan with input from the stakeholders
D. The team creates the plan with your input
40. As a new project manager, you discover that you will be required to have 11
stakeholders sign off on your charter. Which of the following is your greatest
concern?
A. The amount of time spent on configuration management
B. Defining your change management process
C. Managing the sponsors
D. Defining your reporting structure
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 137
41. As a professional project manager you know that many of the processes are
ongoing efforts that potentially overlap. In the real world, which of these
processes are you most likely to combine?
A. Collect requirements and create WBS
B. Create WBS and define activities
C. Plan communications and develop human resources plan
D. None of the above—you should not combine these processes in the real
world
42. All of the following are part of performing integrated change control except
which one:
A. Project management plan
B. Change management plan
C. Project management information system
D. Work performance reports
43. You are an information technology project manager and have been asked to
lead a traditional engineering project. You delegate the various processes to the
project resources who are subject matter experts and you serve as the
coordinator of activities and an arbiter for disagreements. What results do you
expect based upon this approach?
A. A team that functions as a cohesive unit with both commitment and
collaboration
B. A team that might start out slow with a large amount of confusion, but
eventually gets organized and performs well
C. A team with strong technical focus and performance, but little interest in
the overall goal
D. A team with poor performance, low morale, significant conflicts and a
significant amount of turnover
44. As a project manager you build your project plan and schedule based upon a
commitment from the senior management that you will have several senior
level resources completely dedicated to your project. When it actually comes
time to do the work you are provided with much less skilled resources. The
best thing to do is which of the following:
A. Remind management that you were promised senior level resources
B. Show management the impact of having the less experienced resources
assigned to your project
C. Rework the project schedule with the new, less experienced resources
D. Crash the project
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 138
45. You are six months into an 18-month project when you receive a change
request from the customer that will not affect the project schedule and is easy to
complete. What should you do first?
A. Evaluate the change’s impacts on the other constraints
B. Get the sponsor’s approval before making the change
C. Get the change completed as soon as possible
D. Go to the CRB
46. You are a project manager within a large PMO. Currently, the PMO is at about
75% capacity when your company wins a new, very large contract that will
require significant organizational resources to execute. What is the first thing
you should do once you hear about the new project?
A. Ask management if you can lead the new effort
B. Ask management how the new project will use organizational resources
C. Fast track your project
D. Ask management how the new project will affect your project
47. You are a project manager and get asked to take over for a retiring coworker.
You meet with the current project manager as part of your transition and
discover that the project is currently on schedule. The current project manager
tells you that the project is only on schedule because he has constantly pushed
the project team to perform. What is the first thing you should do?
A. Determine your management strategy
B. Determine the exact SPI
C. Determine the current cost performance
D. Meet with your new team to outline your objectives
48. During the project you determine that additional material needs to be
purchased. You call your team together to plan exactly how to make the
required change. This is an example of what?
A. Management by consensus
B. Lack of a change management plan
C. Good team relations
D. Management by objectives
49. Linear programming is an example of what type of project selection criteria?
A. Regression analysis
B. Benefit cost measurement
C. Quantitative scoring
D. Constrained optimization
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 139
50. Your company is evaluating three different projects, but can do only one.
Project A has an NPV of $120,000 and will take 6 years to complete. Project B
will take 3 years and has an NPV of $91,500 and Project C has an NPV of
$83,000. Based on this information, which project would you pick?
A. Project A
B. Project B
C. Project C
D. Not enough information to determine
51. A project manager is interested in obtaining a position within his organization’s
project management office. As part of the hiring process the PMO reviews the
project manager’s past performance on projects within the organization. The
project manager has four projects that are reviewed. One project finished ahead
of schedule and had a CPI of 1.04. That project sponsor provided a
recommendation for the project manager. The second project had an SPI of
0.92 and a less than 10% cost variance. In discussions with the sponsor the
PMO team discovers that these results were achieved due to fast tracking the
schedule, that some rework was required after project completion, and that the
product of the project has never been used. The third project was a large
project for the organization with significant visibility throughout the firm. This
project experienced three restarts due to changes that were 30% greater than
other projects within the organization and was completed with 17 items
remaining on the issue log. The final project was relatively low in the
organizational priority system and had an SPI of 0.76, had struggled with
several unexpected items on the risk register, and had to rework their project
charter twice.
The PMO decides not to hire this project manager based on the past
performance. Which of the following statements best justifies this decision?
A. The project manager had consistently missed schedule and cost targets
showing he does not have the skill to work in the PMO.
B. The project manager consistently failed to involve stakeholders showing
he does not have they skills to work in the PMO.
C. The project manager failed to properly use a risk register showing he
does not have the skills to work in the PMO
D. The project manager consistently showed problems managing change
showing he does not have the skills to work in the PMO.
52. Your project has changed significantly and requires changes be made to the
project charter. Who has primary responsibility to decide if these changes are
necessary?
A. The project manager
B. Key stakeholders
C. The project team
D. The sponsor
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 140
53. Which of the following best describes the project manager’s role as an
integrator?
A. The project manager puts all the pieces of a project into a cohesive
whole
B. The project manager puts all the pieces of the project into program
C. The project manager helps the team become familiar with the pieces of
the project
D. The project manager gets the project team together into a cohesive unit
54. As a new project manager you are tasked with delivering an important project
in a short time window. In this situation what would it be best to rely on in
order to improve your chances of success?
A. The organization’s configuration management system
B. Your PMP training
C. Historical information
D. Stakeholder input
55. Which of the following is NOT one of the four fundamental categories acting
upon organizations illustrating the context of a project?
A. Meet regulatory, legal or social requirements.
B. Satisfy senior leadership’s vision of the future.
C. Implement or change business or technological strategies.
D. Create, improve, or fix products, processes, or services.
56. In what kind of life cycle is the project scope, time and cost determined in the
early phases and then any changes are carefully managed?
A. Predictive
B. Iterative
C. Incremental
D. Adaptive
57. What kind of life cycle is agile, iterative, or incremental with the detailed scope
being defined and approved at the start of an iteration?
A. Iterative
B. Incremental
C. Adaptive
D. Hybrid
58. Which of the following is represents the raw observations and measurements
identified during activities performed to carry out the project work?
A. Work performance reports
B. Work performance information
C. Work performance data
D. Work results
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 141
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 142
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 143
10. Answer A. PMBOK® Guide p. 25 – The only two processes within the
Initiating Process Group are the Develop Project Charter Process and the
Identify Stakeholders Process. All other choices are part of the Planning
Process Group.
11. Answer C. PMBOK® Guide p. 18 – Because the Initiating Process Group is
supposed to be done at the beginning of each project phase, there is a need to
communicate with each of the other process groups (except the Closing Process
Group) when the project has ended.
12. Answer B. PMBOK® Guide p. 75-77 – The development of the Project
Charter (4.1) is primarily concerned with authorizing the project. It also names
the project manager and will often include any constraints or assumptions.
However, its core function is project authorization.
13. Answer C. PMBOK® Guide p. 160, 185 – Significant changes occurring
throughout the project cycle often trigger a need to revisit one or more of the
project management processes. Although the frequency might vary, this
progressive detailing of the project management plan is the very definition of a
rolling wave plan.
14. Answer A. PMBOK® Guide p. 34-35 – It is critical that the project team gets
as many of the stakeholders involved in the project as early as possible and
keeps them involved throughout the project. To do this, the project manager
and team must create an environment that is conducive to stakeholder
participation. A wide range of stakeholders can have information that can help
the project succeed.
15. Answer D. PMBOK® Guide p. 21-23 – Because the feedback and refinement
process can continue indefinitely if left unchecked, procedures set by the
organization identify when the planning effort ends.
16. Answer A. PMBOK® Guide p. 19-23 – Interactions among the processes
within the planning process group are dependent on the nature of the project.
This makes significant refinement and iterations possible—as well as
reordering of some of the relationships due to the fact that in many projects
information is simply not available until later in the process.
17. Answer D. PMBOK® Guide p. 22-23 – The results of the iterations within the
planning process are documented as updates to the project management plan.
18. Answer B. PMBOK® Guide p.19-21 – When a project is broken into phases
the project management process groups usually repeats it an iterative manner
because they are designed to work in either an iterative or linear manner.
19. Answer A. PMBOK® Guide p. 22 – Not all of the processes are needed in all
projects. This is because flexibility is a key concept for project management.
20. Answer D. PMBOK® Guide p.21-23 – A key concept with the project
management process groups is flexibility. This requirement means that not all
processes are needed on every project and not all of the interactions apply to
every project phase. Unique resources are often predefined.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 144
21. Answer C. PMBOK® Guide p. 28,39 – It is not at all unusual for process
inputs to be locked into place as a constraint. This usually happens when they
are predefined.
22. Answer A. PMBOK® Guide p. 25 – Creating the WBS is part of Scope
Management. All others are part of Integration Management.
23. Answer A. PMBOK® Guide p. 75-77 – The high level narrative is part of the
project charter.
24. Answer A. PMBOK® Guide p. 75-77 – According to the PMBOK Guide,
chartering a project links the project to the ongoing work of the organization.
The charter does not define the organizational strategy. Additionally, the
charter formally recognizes the project.
25. Answer C. PMBOK® Guide p. 87 – The integrated change control process is
performed throughout the project. This is because no project runs perfectly.
As part of this process, it is critical to maintain only changes that have been
approved . Significant changes in scope may require re-baselining the project.
26. Answer B. PMBOK® Guide p. 7 – Projects can be justified for a number of
reasons that include:
A market demand
A business need
A customer request
A technology advance
A legal requirement
A social need
In this case, the situation describes doing a project because of a legal need. The
key indicator is the national guideline, law or regulation.
27. Answer D. PMBOK® Guide p.75-77 – The project charter is one of the most
important project documents. It is created prior to beginning the project. The
charter should address the following information either by reference or directly:
Requirements that satisfy stakeholder needs
Business needs
The project purpose or justification
Assigned project manager and their authority level
Summary milestone schedule
Stakeholder influences
Functional organizations and their participations
Organizational, environmental and external assumptions
Organizational, environmental and external constraints
Business case justifying the project including ROI
Summary budget
28. Answer B. PMBOK® Guide p. 77 – The project statement of work (SOW) is a
narrative description of products or services to be supplied by the project.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 145
29. Answer A. PMBOK® Guide p. 706 – The Rough Order of Magnitude Estimate
has a variance of -50% to +50% and is the first estimate completed in the
project process.
30. Answer C. PMBOK® Guide p. 51-52 – The project manager—in collaboration
with the project team—is always responsible for determining what processes
are appropriate, as well as the appropriate degree of rigor for any given process.
31. Answer C. PMBOK® Guide p. 72 – This point cannot be emphasized enough.
Communication is key to managing projects successfully. It is the starting
point for all other efforts.
32. Answer D. PMBOK® Guide p. 72 – This question goes back to the constant
battle between the need for differentiation (or subject matter expertise) and the
need for integration (or team members working together). The need for
integration is the key reason to focus on communication.
33. Answer C. PMBOK® Guide p. 104 – Historical records are not typically used
for lessons learned, life cycle costing, or status reports.
34. Answer D. A key component of project management is ALWAYS being
proactive. In this question only one choice is proactive and that is preventing
unnecessary changes.
35. Answer A. PMBOK® Guide p. 104 – Lessons learned are reviews of the
policies and procedures and are not part of the process itself.
36. Answer A. PMBOK® Guide p. 104 – In this case, it would be best to rely on
historical information about the results from past projects within the
organization. Although stakeholder input might help it also might not be
trusted. The only other possible answer is certification training, which taught
that these things are situational.
37. Answer C. PMBOK® Guide p. 75-77 – The project sponsor is supposed to
approve the charter. They are also responsible for approving any changes to
that charter.
38. Answer D. PMBOK® Guide p. 86 – A true project management plan is made
up of plans from each of the knowledge areas except Integration Management.
39. Answer B. PMBOK® Guide p. 82-83 – The project manager is responsible for
creating the plan with the input from their subject matter experts and the team.
40. Answer A. Two key issues are likely to impact this project. This first is
communication. This is the same on every project, but here the number of
signoffs will make communication even more important. The second is
configuration management. Since communication is not one of the choices,
configuration management is the best choice.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 146
41. Answer B. PMBOK® Guide p. 156-161 – In the real world, many of these
processes are ongoing and overlap. Additionally, not every process is required
on every project. It is up to the project manager to decide when these processes
are appropriate. In this case, the most commonly combined processes (yes, it is
allowed) are to create the WBS and to define the activities—because the
activities are often simply extensions of the work packages.
42. Answer C. PMBOK® Guide p. 113 – The project management information
system is part of Direct and Manage Project Execution but not Performing
Integrated Change Control.
43. Answer D. To be successful, the project manager must actually manage the
project. When he or she acts as a simple coordinator the project will most
likely fail and the resources will become frustrated.
44. Answer B. Remember that a project manager must always be proactive. This
means the PM must get in front of the situation. In this case, the project
manager needs to bring alternatives and recommendations to management. The
answer that most reflects this concept is showing management the impact of
having the less experienced resources assigned to the team.
45. Answer A. The first thing the project manager should do is evaluate the
change for impacts against the major constraints.
46. Answer D. The first thing you should do is obtain or complete an evaluation of
how the new project will impact your project. Only then can you make an
informed choice about what to do next.
47. Answer A. Successful project management has a lot to do with aligning
strategy with project management. This is just such a case. The first thing you
should do is determine your own management strategy and then move forward.
48. Answer B. This is a clear example of the absence of a change management
plan—or at the very least a failure to follow the plan. It should be unnecessary
to bring the team together in this case.
49. Answer D. Linear programming is a form of constrained optimization that
uses advanced mathematics to evaluate choices.
50. Answer A. The years are irrelevant to this question as the whole point of NPV
is to convert the project value into today’s dollars. In this case, project A is the
correct choice with an NPV of $120,000 because it has the highest value.
51. Answer B. This is one of the longest questions you might see. Be careful.
Much of the information in the question is there to misdirect you. This
question takes you back to a core PMIsm. One of the most common problems
is a failure to engage stakeholders early and often enough. This problem is
evidenced in the question by the significant scope changes, the remaining issue
log items and the fact of having to redo the charter.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 4 — Integration Management
Page 147
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 148
Scope Management
Overview
Scope management is chapter five in the PMBOK® Guide. Slide 120
For most PMP® exam takers scope is one of the easiest
knowledge areas on the exam. But that does not mean you
can ignore it! Make sure to take some time to study this
section like all the others and watch your test scores.
Remember that you goal is to score 90% or better on all
exams before you take the real test.
Scope management is the process of defining what work is
required and then making sure all that work — and only
that work— is done [PMBOK® Guide p.129].
Remembering a few simple concepts will dramatically
improve your performance on the exam in this area.
You must always plan your work and
then work your plan. No project is ever
conducted without a plan.
A work breakdown structure must be
created for all projects.
You must involve all the project
stakeholders in the gathering of Image 23: The Processes of Scope Mgmt.
requirements and not just the project
sponsor.
You must obtain approval of the project scope before execution ever begins.
Do not ever gold plate the project. Complete only the agreed upon work and
nothing else.
Scope changes are allowed so long as they follow the change management
process and have been agreed to by the sponsor and/or key stakeholders. As
part of following the approved change control process, make sure to analyze
any potential changes for the way they will impact time, cost, resource needs,
risks, etc.
One of the few areas of confusion when discussing scope is the fact that there are
two types of scope involved in the scope management knowledge area. These
are:
Project Scope — The work that must be performed to deliver a product, Slide 121
service or result with the specified features and functions [PMBOK® Guide
2017 p. 131].
Product Scope — The features and functions that characterize a product
service or result [PMBOK® Guide 2017 p. 131].
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 149
Notice that product scope is all about the characteristics of the product, service or
result of the project. Project scope, on the other hand, is concerned with the work
that must be completed to deliver that product, service or result. As the project
manager, you are responsible for both. An easy way to make a mistake on the
exam is by not reading the question carefully and neglecting to notice the type of
scope being discussed. Be careful and read each question twice to ensure you do
not make this simple mistake.
Another common exam mistake is to assume that you must determine the
requirements of the project as part of your project management processes. A
requirement is not the same as scope. A requirement is a condition or a capability
that must be met or possessed by a system, product, service or component in order
to satisfy a contract, standard, specification, or other formally imposed document.
Requirements include the quantified, and documented needs, wants, and
expectations of the sponsor, customer and other stakeholders. In short,
Requirements are what the customer needs. Product scope refers to all the
requirements that must be met for the specific result to be created. Project scope
refers to all the work that must be done to deliver those requirements/product
scope.
In the integration management chapter you learned that every one of the knowledge
areas produces some type of management plan. Usually they are simply named
after the knowledge area. That’s the case when dealing with scope. The
management plan is the scope management plan. However, unlike integration
management and the project management plan, the scope management plan does
not have a specific process where the plan is called out as an output. Instead, you
must recognize that the scope management plan is one of the many plans produced
by the develop project management plan process. As with all the management
plans, the scope management plan defines how you will manage that particular area
of the project. The scope management plan answers questions such as the
following:
How will you determine the product scope for the project? This includes the
Slide 122
specific requirements of the product, service, or result.
How will you balance the needs of all your stakeholders?
What tools and techniques will the project team specifically use?
How will you measure scope performance and adjust to variances as needed?
In addition to these questions, the PMBOK® Guide outlines a five step process for
scope management. You must be familiar with this process and keep the steps in
order. The steps are as follows:
Determine the product, service, or result requirements. Make sure all the Slide 123
requirements tie back to the business need described in the charter.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 150
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 151
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 152
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 153
use several of them to ensure all the requirements are captured. The possible tools
and techniques include the following:
.1 Expert judgement — Many of the requirements come from your subject
matter experts. It is critical that the project leader listens to them.
®
.2 Data gathering — The PMBOK Guide suggests a number data gathering
techniques including:
Slide 129
Brainstorming — Brainstorming is a group participation activity where
members of a group verbally collect information about a topic typically
in a free form fashion. Often, a facilitator acts as a note taker writing
ideas on a white board or poster paper. We will talk repeatedly about
brainstorming.
Interviews — Interviews represent either a formal or informal process
of obtaining information from stakeholders by asking both prepared and
spontaneous questions of participants, usually in a one-on-one
environment. Interviews are important to project leaders because they
often allow the discovery of key information unavailable through any
other manner.
Focus groups — Focus groups are small groups of individuals brought
together for the purpose of discussing a specific topic. The focus group
is typically led by a trained facilitator who asks pointed questions to its
members and leads it through a discussion that is either video taped or
watched by others. Focus groups are typically designed to create a
more informal discussion amongst a small group about a topic.
Questionnaires and surveys — Imagine having an organization with
hundreds or thousands of stakeholders. It would be unreasonable to
expect the team to speak to all of them. Questionnaires and surveys
provide a solution. They represent written sets of questions that can be
compiled and responses quantified for more robust analysis.
Benchmarking — Benchmarking is tool used to compare best
practices, products or services, and practices from both inside and
outside the organization. It allows the team to compare themselves
against the performance of others.
Nominal group techniques — This is similar to brainstorming but it
requires the group to vote to establish a prioritized listing of the defined
topic items.
The Delphi technique — This is a three step survey process that makes
Make sure to
use of surveys and subject matter experts. It has three steps: know the
1. Survey the selected subject matter experts. Delphi
2. Aggregate their responses. Technique
3. Feed the aggregated results back to the subject matter experts for
agreement.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 154
.3 Data analysis — In this case, much of the data analysis involves examining
documents. The list of documents includes agreements, business plans,
business processes, marketing literature, policies and procedures and a lot of
others.
.4 Decision Making — Groups make decisions using a lot of different
techniques. PMI® calls out three specific ways that groups make decisions
including voting, autocratic decision making, multicriteria decision analysis.
Voting — This is exactly what it sounds like. Decisions are made Slide 130
based upon the opinions of a group. There are a number of ways this
can be done:
Unanimity — This is where everyone agrees on a course of
action.
Majority — This is a process where the majority of members in
the group decide direction. Anything over 50% wins.
Plurality — This is used when a simple majority is not possible.
In these cases, whichever group has the largest number wins—
even though it is not a majority.
Autocratic decision making— This is a fancy way of dictatorship. In
this method, one person makes the decision for the group.
Multicriteria decision analysis — Multicriteria decision analysis
represents the process of examining situations where teams are dealing
competing decision criteria. Sometimes referred to as MCDA, it was
made popular by Stanley Zionts in 1979. It establishes a basic
framework for making a decision when the team is looking at important
aspects in conflict with each other. A common example is the
relationship between cost and quality.
.5 Data representation — Data representation addresses the question of how
does the team display information. Two examples of data representation
include affinity diagrams and mind mapping.
Affinity Diagrams — Affinity diagrams represent a technique used to
sort through a large number of ideas and place them into groups for
review and analysis based upon their natural relationships. They were
originally created in the 1960s by Jiro Kawakita. Teams use affinity
diagrams when they are dealing with a lot of facts that appear in chaos
or when the team is deal with issues seem too large or complex to grasp.
Affinity diagrams are also a good tool when group consensus is
necessary. Affinity diagrams are also known as affinity charts, K-J
method or thematic analysis.
The process for actually doing affinity diagrams is simple. Typically,
affinity diagrams are used after a brainstorming exercise or after
analyzing verbal. The affinity diagramming process begins with sticky
notes and markers. The team begins by writing all their ideas on
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 155
stickies. The stickies are then spread around a table for everyone to see.
In the second step, the team silently moves the stickies into groups. It is
OK if the items are moved multiple times until everyone agrees with the
groupings. The team then discusses the groupings that may lead to
some other changes, The team finally comes up with titles for the
groups.
Idea/mind mapping — Mind, or idea mapping is a diagramming Slide 131
technique used to visually organize information, and is considered a
type of spider diagram. There are a number of different ways to build
mind maps. Typically, these visual tools are hierarchical and show the
relationship of a component or idea to the whole. Mind maps were
made popular by Tony Buzan who suggested ten guidelines for creating
them:
1. Start in the center with an image of the topic, using at least 3
colors.
2. Use images, symbols, codes, and dimensions throughout your
mind map.
3. Select key words and print using upper or lower case letters.
4. Each word/image is best alone and sitting on its own line.
5. The lines should be connected, starting from the central image.
The lines become thinner as they radiate out from the center.
6. Make the lines the same length as the word/image they support.
7. Use multiple colors throughout the mind map, for visual
stimulation and also for encoding or grouping.
8. Develop your own personal style of mind mapping.
9. Use emphasis and show associations in your mind map.
10. Keep the mind map clear by using radial hierarchy or outlines to
embrace your branches.
.6 Interpersonal and team skills — This primarily refers to brainstorming for
Slide 132
which there actually is a defined process. It has four steps:
1. A question or problem is posed to the group and each member silently
generates and writes down their ideas.
2. The moderator writes down the ideas on a flip chart until all the ideas
are recorded.
3. Each recorded idea is discussed until all group members have a clear
understanding.
4. Individual vote privately to prioritize the ideas, using a scale of 1 to 5,
with 1 being the lowest and 5 being the highest. After each vote the
ballots are counted and the team revote until the highest option is
selected.
Observations/conversation — In this process the project team simply
observes stakeholders doing activities that would involve the product,
service or result of the project in order to better understand the user
community’s needs. The team also needs to have conversations with
the stakeholders.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 156
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 157
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 158
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 159
A project charter initiates the project. It defines the project success, empowers
the project leader, defines any constraints and assumptions and prioritizes the
project. The scope statement gives description of the project scope and names
the project deliverables along with the things the team will not deliver.
.2 Project document updates — As with most of the 49 defined processes, the
define scope process can cause updates to the documents outside the project
plan. However, it should not cause alterations to the project management plan
itself.
5.4 Create WBS
The work breakdown structure, or WBS is one of the Slide 136
most important and most under utilized documents in
the project management world. Much of the under
utilization stems from a lack of understanding of
exactly what a WBS is and how it should be used. A
WBS is a deliverable-oriented, hierarchical
decomposition of the work to be executed by the
project team. It enables them to accomplish the
project objectives and create the required product,
service, or result. This is a fancy way of saying that
the WBS is a picture that resembles an organization
chart, but for deliverables. Although it has
absolutely nothing to do with resources, it does have
boxes organized into a tree like an organization
chart. Each box is a deliverable. Being deliverable-
focused is a very important aspect of a well formed
WBS. It is not supposed to be a listing of the tasks
or activities that are to be accomplished.
In the real world, project managers work very hard to Image 28: 5.4 Create WBS
avoid creating a WBS based upon project phases.
However, when taking the exam you should remember that such time-based
structures are not technically wrong. If you have spent any time in project
management you already know a number of documents that help you understand
when work is to be done. It wouldn’t make any sense to simply have another time-
based tool!
When preparing for the exam, it is critical that you spend a significant amount of
time studying work breakdown structures. They are very important to PMI®. You
must understand the WBS and how to use it. Let’s begin with a number of key
terms for a WBS:
Work packages — Each individual box in the WBS structure is a unique Slide 137
deliverable or work package. The two terms are synonymous.
Decomposition — Decomposition is the process of breaking deliverables down
into smaller and smaller deliverables until they can be easily understood and
managed. It is the process used to create the WBS.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 160
Page 161
Slide 139
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 162
.1 Scope baseline — As soon as the WBS and WBS Dictionary are complete
the project has its scope baseline. From this point forward the project will be
reporting on what was originally promised in terms of scope, versus what was
really produced.
.2 Project documents updates — The information collected in the steps taken
to generate the WBS may necessitate updates to some of the non-plan project
documents.
To understand the process of decomposition that is used to Create the WBS
Process, you must know the four questions that allow the user to determine if they
have broken the structure down far enough. These questions are as follows:
Can you accurately estimate the resources required to do the work?
Can you accurately estimate the time it will take those resources to complete
the deliverables?
If you had to assign the deliverable to someone else are you confident they
would know what to do?
If you complete the deliverables listed in the WBS — and only those
deliverables — will you successfully complete the project?
5.5 Validate Scope
Once the WBS has been created it is time to validate scope. This process moves us
out of the planning process group and into the monitoring and controlling process Slide 141
group. Validate scope is the process where
the project manager and the team review the
completed deliverables with the sponsor
and key stakeholders in order to ensure they
have been completed satisfactorily.
Validating scope requires holding regular
meetings — that are part of the plan — with
the major stakeholders and sponsor in order
to gain formal acceptance of the Image 31: 5.5 Validate Scope
deliverables. This process is not the same
as control quality. In the control quality process the project manager and team are
concerned with the correctness of the deliverables. In the validate scope process
the only concern is if the deliverable was accepted. But this is not the acceptance
of the final product, service or result of the project. It is only the acceptance of the
particular deliverables. The inputs to the validate scope process include the
following:
.1 Project management plan — Three specific parts of the project Slide 142
management plan are important here. They include the project scope statement,
the WBS and the WBS dictionary. A good rule of thumb to remember for the
exam is that any time the WBS is used the WBS dictionary is used as well. It
also includes the scope baseline.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 163
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 164
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 165
That both project and product scope are revised throughout project.
The WBS is critical. You must understand it completely. You must understand
why it is important and that it is used in many other processes. Also, remember
that the WBS is deliverable based.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 166
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 167
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 168
14. All of the following statements concerning the project scope management plan
are true except:
A. The project scope management plan defines the project scope.
B. Process that enables the creation of the WBS from the detailed project
scope statement.
C. Process that establishes how the scope baseline will be approved and
maintained.
D. Process that specifies how formal acceptance of the completed project
deliverables will be obtained.
15. The project scope statement includes all of the following except:
A. Acceptance criteria
B. Requirements
C. Deliverables
D. Project exclusions
16. All of the following statements are true about decomposition except:
A. Decomposition rarely is done too much or in too much detail.
B. Decomposition is the subdividing of project deliverables into smaller,
more manageable components.
C. Decomposition may not be possible for a deliverable or subproject that
is to be done far in the future.
D. Different deliverables can have different levels of decomposition.
17. All of the following are activities involved in the process of decomposition
except:
A. Identifying the deliverables and related work.
B. Ensuring that each work package has the appropriate activities assigned
to it.
C. Developing and assigning identification codes to WBS components.
D. Structuring and organizing the WBS.
18. You walk into your office on Monday morning to find an approved change
request sitting on your desk that impacts the project scope. This is best defined
as which of the following:
A. Any modification to the agreed upon project scope baseline including
the scope statement, the WBS or the WBS dictionary
B. Any change to a technical requirement
C. Any change to the project management processes
D. Any change to project staffing
19. The project scope change control system includes all of the following except:
A. Necessary documentation
B. An assessment process
C. Required approval levels
D. A tracking and monitoring system
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 169
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 170
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 171
31. You have just been given the assignment to be the project manager on a very
high profile, high value project within your organization. As you leave your
boss’s office, they hand you the completed Project Charter and Scope
Statement. The first thing you should do is what?
A. Begin work on the project management plan
B. Ensure the key stakeholders agree with the project charter
C. Create a WBS
D. Define the project scope statement
32. You are the project manager for a very important public works project in your
community. The project is nearing completion and will enter the final phase in
the next week. What should you be focused on most before moving on to the
final phase?
A. Project safety
B. Validating the scope
C. Losing project resource to other projects
D. Variance analysis
33. You are the project manager for a software development project that is using
the SDLC and are about to begin integration testing. With what should you be
primarily concerned?
A. Project testing procedures
B. Project resources multi-tasking
C. Validating the scope
D. Variance analysis
34. You are the project manager for a project that is entering the Closing Process
Group. As you attempt to close the project your sponsor informs you that they
have been approached by several stakeholders who are not happy with the
project deliverables. Which of the following processes could have prevented
this problem?
A. Validating scope
B. Define scope
C. Scope monitoring
D. Integrated change control
35. All of the following are part of the scope baseline except:
A. Project scope management plan
B. The WBS
C. The project scope statement
D. The WBS dictionary
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 172
36. You are the project coordinator for a small project within your organization.
One of the primary stakeholders approaches you with a properly completed
scope change request form. What should you do next?
A. Ask the stakeholder to justify the change request
B. Complete integrated change control
C. Determine how the request was missed during the initial scope
definition
D. None of the above
37. During which part of the project management process is the project scope
statement created?
A. Prior to beginning the project
B. Initiating
C. Planning
D. Monitoring and controlling
38. Halfway through a project that has a SPI of 0.89 and an CPI of 0.93 the project
manager is approached by a senior stakeholder requesting a minor addition to
scope. The project sponsor already rejected the same request prior to the
approval of the performance management baseline. What is the best thing for
the project manager to do?
A. Tell the stakeholder the scope cannot be added
B. Determine the root cause of the request
C. Evaluate the impact of adding the scope
D. Let the sponsor know of the stakeholders’ request
39. When should the Validating Scope Process be done?
A. At the beginning of the project
B. At the end of the project
C. Throughout the project
D. At the end of each project phase
40. You have just started a job as a project manager for a large manufacturing
company. On your first day you are given the completed and signed charter for
a new project. What is the first thing you should do?
A. Begin developing the project management plan
B. Create the project scope statement
C. Begin creating the WBS
D. Confirm all stakeholders had input into the scope
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 173
41. You are the project manager for a multi-year project and are approximately
80% through the project. You are on schedule and budget, but your sponsor is
not happy with the deliverables produced. Which of the following processes
could have best prevented this problem?
A. Define scope
B. Control scope
C. Close project or phase
D. Monitor and control risks
42. You are leading a large multinational manufacturing project. During the
process of collecting the percent complete of project work for your monthly
status reports, one of your resources asks, “percent complete of what?” You
have had issues with this resource on other projects in the past. Instead of
reporting the resource to his boss, you attempt to work through the issue with
him. Which of the following is most likely the real issue?
A. You do not have an issue with the resource’s boss
B. You should have taken the issue to the resource’s manager some time
ago
C. The project lacks an adequate rewards system
D. You failed to assign work packages
43. You are currently leading a project which has an SPI of 1.06 and a ETC of
$276,500. The BCR of the project is 1.45 and you are more than 70% through
the project. Requirements have consistently been changing over the last several
weeks no matter what you have tried. Which of the following are you most
likely to face in the future?
A. Not being able to measure completion of the product of the project
B. Needing to make sure the customer approves project scope
C. Needing to add resources to complete the project
D. Needing to cut costs to successfully complete the project
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 174
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 175
13. Answer B. PMBOK® Guide p. 150 – The tools and techniques used in the
define scope process includes expert judgment, data analysis (alternatives
analysis) decision making (multicriteria decision making), interpersonal and
team skills and product analysis.
14. Answer A. PMBOK® Guide p. 137 – The scope management plan may be
formal or informal. The project scope statement defines the project scope.
15. Answer B. PMBOK® Guide p. 154 – The project scope statement describes
the project’s deliverables and the work required to complete those deliverables.
It includes, either directly or by reference to other documents: the project
objectives, the product scope description, the project boundaries, the project
deliverables, the product acceptance criteria, the project constraints, the project
assumptions, the initial project organization, any initially defined risks, any
schedule milestones, any funding limitations, a cost estimate, the project
configuration management requirements, the project specifications, and any
approval requirements.
16. Answer A. PMBOK® Guide p.158 – In the decomposition process, beware of
the desire to break down the deliverables until they are too small or the team
spends too much time on the process. This requires the project manager to
maintain a careful balance between too little and too much WBS detail.
17. Answer B. PMBOK® Guide p. 158-161 – Decomposition of the total project
work generally involves the following activities: identifying the deliverables
and related work, structuring and organizing the WBS, decomposing the upper
WBS levels into lower level detailed components. Developing and assigning
identification codes to the WBS components, and verifying that the degree of
decomposition of the work is necessary and sufficient.
18. Answer A. PMBOK® Guide – When dealing with project scope, an approved
change request is any change or modification to the agreed upon project scope
that includes the project scope baseline, the project scope statement, the WBS
or the WBS Dictionary.
19. Answer B. PMBOK® Guide p. 137 – A project scope change control system—
as documented in the project scope management plan—defines the procedures
by which the project scope and the product scope can be changed. It includes
the documentation, tracking systems, and approval levels necessary for
authorizing changes.
20. Answer D. PMBOK® Guide – Constraints are things that specifically limit
your options. They are usually outside the project team’s control, and can
dictate specific actions that must be performed. Additionally, earned value isn’t
a constraint but a performance measurement technique.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 176
21. Answer C. PMBOK® Guide p. 158-161 – The code of accounts is the formal
name for the numbering system found in the WBS. It serves two primary
functions: First, it allows the project manager to link the work packages to
specific accounting codes used for tracking project costs, thereby enabling
work package costing. Second, it allows the project manager to identify the
level at which the work package is found.
22. Answer A. PMBOK® Guide p. 156-157 – The WBS is one of the most
powerful communication tools available to the project manager. It should be
used with every stakeholder to envision what the project is all about.
23. Answer B. PMBOK® Guide p. 160-161 – The detailed content of the
components contained in a WBS, including work packages, their complete
descriptions and control accounts is called the WBS dictionary. It is the best
tool for seeing how the project fits together.
24. Answer C. This is a complicated way of asking who creates the Project
Management Plan. The answer is always the project manager with input from
the project team. Input from the project team is necessary to ensure their
commitment to the objectives.
25. Answer B. PMBOK® Guide p. 129 – Project scope management is primarily
concerned with defining and controlling what is and is not included in the
project. You might debate whether or not the project manager was doing the
right thing, but that is not what this question asked. This is an example of
scope management.
26. Answer C. PMBOK® Guide p. 129 – Validate scope is the process of
obtaining the stakeholders’ formal acceptance of the completed project scope
and associated deliverables, e.g. making sure all deliverables have been
completed satisfactorily. This should be done at the end of each phase of the
project.
27. Answer C. This is an example of a PMIism. According to PMI®, your first
responsibility is to listen to the stakeholder without committing to anything
before you choose a course of action. Only when you understand the desired
change can you select the correct path.
28. Answer B. PMBOK® Guide p. 156-162 – This is another example of a
PMIism. In this case it is important to remember that PMI views the WBS as
very important to the project’s success because it helps identify all the
deliverables of the project. Therefore we always do them. Furthermore, you
do not have enough information in the question to accept the other answers.
29. Answer D. PMBOK® Guide p. 156-162 – For many students this is a tough
question because several of the answers are in fact true. But remember that the
question was asking for the best response. D is correct because the WBS helps
ensure team commitment.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 177
30. Answer C. PMBOK® Guide p. 156-162 – The WBS dictionary provides the
detailed description of each of the project work packages and is therefore the
best thing to provide in this situation.
31. Answer A. PMBOK® Guide p. 82-83 – This is the kind of question where you
must simply remember the order of the steps to get the proper answer. After the
Charter and Scope Statement have been created your next step is to develop the
Project Management Plan.
32. Answer B. PMBOK® Guide p. 163-164 – Validating the scope is done at the
end of each project phase to ensure that the project deliverables meet with the
customers’ satisfaction. It is done at the end of each phase before going to the
next.
33. Answer C. PMBOK® Guide p. 163-164 – Validating the scope is done at the
end of each project phase to ensure the project deliverables meet with the
customers’ satisfaction. It is done at the end of each phase before going to the
next.
34. Answer B. PMBOK® Guide p. 150-152 – Three of the answers to this question
are easy to discount. Scope monitoring, verification and integrated change
control are all part of the monitoring and controlling process group and
therefore are only helpful if the question deals with fixing the problem. Scope
planning is part of the planning process group and is the only one capable of
preventing the problem.
35. Answer A. PMBOK® Guide p. 150-152 – The project scope management plan
is the document that defines how you will manage project scope. The Scope
Baseline is an initial snapshot of what is in scope at a specific moment in time.
36. Answer B. Although several of these answers are good, this is an example of
the need to look for the best answer. In this case the best answer would be to
complete integrated change control. This is the step where the scope change is
evaluated against the impacts on time, cost and other project variables.
37. Answer C. PMBOK® Guide p. 150-152 – The scope statement is the primary
output from the define scope process which is part of the planning process
group.
38. Answer B. You might be tempted to blindly follow your process and determine
the impacts of the choice. Or you might want to just say no. But the question
asked what was the best choice. In this situation the best thing to do is figure
out why the stakeholder keeps asking for something the sponsor has already
rejected.
39. Answer D. PMBOK® Guide p. 163-166 – On any project the scope should be
validated at the end of each phase to ensure that you are still attaining the
desired results.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 5 — Scope Management
Page 178
40. Answer D. PMBOK® Guide p. 131-132 – You have to be careful with this
question. It is easy to memorize the PMI® process but forget the basics. A
basic PMIism is that most projects have scope problems because of a failure to
engage stakeholders early or often enough.
41. Answer A. PMBOK® Guide p. 150-155 – You have to be careful with this
question. The question asks which process could have prevented the problem.
Two of the answers are from the controlling process group which means they
could have helped manage the problem but not prevent it. One answer is in the
closing process group and therefore would not add much value. Only the
define scope process offers a change to prevent the problem.
42. Answer D. PMBOK® Guide p. 156-161 – A good project manager always
manages deliverables and not tasks. One of the main reasons for this statement
is that it is almost impossible to get a quantitative evaluation of status on a task.
43. Answer A. PMBOK® Guide p. 138-149 – This question has lots of
information, most of which doesn’t matter. The core issue is that requirements
are necessary to measure the completion of the project. Without the
requirements, measurement is impossible. Remember, good project managers
measure deliverables.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 179
Schedule Management
Overview
For many PMP® candidates, their past experience with project management has Project
largely involved developing a schedule using tools such as Excel® or Project® by Management
Microsoft. Many of these candidates have never learned the tools and is NOT a
techniques necessary to manage a schedule without such tools. While software software tool!
does make the job easier, not having the skills necessary to manage time without
the technology is dangerous. Real project management is a very different animal
from what is provided in any software application. For the exam do not assume
they are the same thing. The schedule management knowledge area is where
PMI® aggregates the information about managing a schedule. If you have
always used a software tool to manage your Planning Process Group
schedules it could be a very difficult section Slide 147
for you. The best advice is to take your time
and learn all the models, math and processes
described here. Not only will they help you
on the test, but they will also make a
significant difference in the real world!
PMI® considers the schedule management
knowledge area to include the processes
required to manage the timely completion of
the project. The knowledge area is broken
into seven individual processes which include
the following:
6.1 Plan schedule management
Monitoring & Controlling Process Group
6.2 Define activities
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 180
Be careful here because many PMP® candidates do not do this level of schedule
management on their real projects for a variety of reasons. When preparing for
the exam it is important to remember that you are managing a relatively large
project that requires more documentation and planning than you might be used
to. The schedule management plan includes a number of components:
The scheduling methodology and any scheduling tools such as software to be
used.
The schedule baseline against which all progress is measured.
A listing of the key performance indicators and metrics to be used on the
project to identify variances and how often those metrics are produced.
Variance thresholds requiring action.
Rules for how the schedule variances will be managed.
A defined schedule change control process with all its procedures.
The inputs to the plan schedule management process include the following: Slide 149
.1 Project charter — Used to provide the limits of authority, business need,
justification, constraints and assumptions.
.2 Project management plan — Specifically the scope baseline and other
information such as cost, risk and communication information.
.3 Enterprise environmental factors — Items here might include the
organizational culture and structure, the resource availability and skills and
commercial information.
.4 Organizational process assets — This is an old favorite that you should
just assume.
The three tools and techniques used in the plan schedule management process
include the following:
.1 Expert judgment — This the single most powerful tool that project
managers have at their disposal.
.2 Data analysis — This can involve selecting various scheduling
methodologies, estimating approaches, formats or may detail ways to fast
track or crash the project.
.3 Meetings — The team may hold meetings to develop the schedule
management plan.
There is only the one output for the plan schedule management process and it is
the schedule management plan.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 181
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 182
Slide 151
Even still, the team must work towards complete information which only occurs
at the very end when all the lines come together in the lower right-hand corner.
Both progressive elaboration and rolling wave planning are key concepts for the
exam.
There are three inputs to the define activities process. As you examine the list of
inputs, it is important that you notice the WBS and WBS dictionary are not
among them even though the defined activities are an extension of the
deliverables defined in the WBS. This is because the project management Plan
is inclusive of the WBS and WBS dictionary. If you are unsure of this point,
look back to the scope management knowledge area, process 5.4 create WBS
and examine the outputs and the explanation. The inputs to the define activities
process are as follows:
.1 Project management plan —The project management plan is the master
Slide 152
planning document for every project so it is naturally the starting point for
most processes. In defining activities, the project management plan is
bringing the schedule management plan and the scope baseline to the party.
.2 Enterprise environmental factors — There are many enterprise
environmental factors that can impact the process of defining activities, but
the most important is the project management Information system.
.3 Organizational process assets — Like almost all the processes, the
define activities process may have organizational process assets which must
be addressed. It is key to remember a number of things such as existing
policies, procedures, guidelines and methodologies used in scheduling and
any lessons learned from previous projects regarding scheduling.
The define activities process has four tools and techniques used to produce its
outputs. These tools and techniques include the following:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 183
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 184
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 185
The use of rectangles in diagramming created the graphic technique that almost
every scheduling software application uses today, called precedence
diagramming. You must be capable of using this technique for the PMP® exam.
Precedence diagrams have four types of relationships. Notice that in each of
these relationships the left side of each rectangle always represents the start of
the task, activity or deliverable and the right side of the rectangle always
represents the finish of the task, Slide 155
activity, or deliverable.
The first of the four possible
relationships is a finish-to-start
relationship. This relationship
represents tasks, activities or
deliverables that must be
completely finished before the
next one can begin. In this
relationship the arrow comes out
of the right side of the first task,
activity or deliverable and into the
Image 37: A Finish-to-Start relationship
left side of the second task, activity or
deliverable. This is the most common
type of relationship. Image 37 shows
a finish-to-start relationship.
The second type of relationship is a
start-to-start relationship. In a start-
to-start relationship the second task,
activity or deliverable can begin
anytime after the first task, activity or
deliverable has begun. Image 38
shows a start-to-start relationship.
Notice that the arrow comes out of
Image 38: A Start-to-Start relationship the left side of the first task, activity
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 186
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 187
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 188
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 189
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 190
2.
3.
4.
5.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 191
6.
7.
8.
9.
10.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 192
Precedence diagramming is not the only type of network diagram that can be Slide 156
done. However, it is the only type of diagramming you must do well to pass the
exam. It is important that you are aware of an alternative technique and know a
few key points about it. That technique is called conditional diagramming.
Conditional diagramming affords the project manager the ability to account for
probability and create conditional
loops. Image 42 shows a network
diagram with conditional looping
and probability. In the diagram
there is an 80% chance of moving
from B to C and there is a 20% Image 42: A Conditional Diagram
chance that you would have to
redo task, activity or deliverable A. Another common way of representing
conditional diagrams is with the eyeball diagram shown in Image 43. The
eyeball diagram is used to represent a single situation (the open circle on the left
of the image) with two possibilities (shown with the right facing arrows).
Readers can tell it is a single situation because the two arrows are connected
with the ellipse. It is called an eyeball diagram
because it resembles an eyeball from the side.
The PMP® exam will not require you to create
these diagrams, but you will need to recognize
them and remember the acronym GERT which
stands for graphical evaluation and review
technique. GERT is the most common form of
conditional diagramming. Also remember the
advantage of conditional diagramming is that it
allows for both probability and looping. Image 43: An Eyeball Diagram
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 193
relationship allows the successor task to start prior to the completion of the
predecessor. Lag time represents a relationship that requires a delay between
the two tasks. Both leads and lags can impact a schedule. Lead time will
generally shorten a schedule while lag time will increase it. Make sure you
understand the difference.
The inputs to the sequence activities process include the following:
.1 Project management plan — The project management plan contains a lot
of different components, but the two that are important for sequencing
project activities are the schedule management plan and the scope baseline.
These two documents establish how the schedule will be managed
throughout the project and what has to be completed (e.g. the project’s
current scope).
.2 Project documents — There are four documents specifically called out
by PMI® to properly sequence the project activities. The first is the activity
list. The list defines the activities that need to be accomplished. The second
are the activity attributes which provide the details about the defined
activities. The team also need to know about any assumptions that have been
made during the planning process so they need the assumption log and they
need to know about any established milestones so they must examine the
milestone list.
.3 Enterprise environmental factors — The factors that might influence the
Sequence Activities process include things such as governmental regulations
or industry standards, specific tools the team or organization uses, and the
work authorization system.
.4 Organizational process assets — Many organizations have predefined
tools, templates and processes designed to aid in the creation of a sequence
diagram.
The tools and techniques used in the sequence activities process include the
following:
Slide 158
.1 Precedence Diagramming
Method (PDM) — Precedence
Diagramming is the preferred and
most common method used to
develop Network Diagrams. It is
absolutely critical that you are
capable of correctly producing a
PDM Diagram to pass the exam.
.2 Dependency determination and
integration — Dependency
determination is simply the process
of determining what must come first,
second, third, etc. It also defines
exactly how each activity is Image 44: Dependency Determination
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 194
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 195
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 196
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 197
Several key factors define the shape seen in a bell curve. The first is the unusual
looking U symbol that appears in the exact middle of the curve. It is
accompanied by a vertical line that splits the curve into two equal halves. This is
the mean of the distribution and may also be represented by an X with a line
over it. The mean is defined as the sum of the values divided by the number of
cases. Next, notice how the image is divided into equal segments that are
marked at the bottom of the image with positive or negative values followed by a
small symbol. This symbol represents the standard deviation or sigma. The
shape of the bell curve is defined by the fact that within one sigma, or one
standard deviation, away from the mean 68% of the cases can be found. Within
two standard deviations 95% of the cases can be found, and within three
standard deviations 99% of the cases can be found.
Most project managers have neither the time nor the inclination to do a project
activity 100 different times. This is where PERT comes into play. PERT
provides a technique that allows the project manager to simulate completing the
project many times over to get more accurate estimates. The key to using PERT
is the use of a three point estimate combined with a Gaussian distribution. PERT
requires three estimates: an optimistic estimate, a pessimistic, and a most likely
estimate. These three estimates are then used in three different calculations to
determine durations.
The first calculation created is the PERT weighted average. The weighted Slide 164
average serves as the mid-point, or mean, of the bell curve that is artificially
created by the following formula:
(4 * The PERT
PERT Weighted Average = Pessimistic + Most Likely) + Optimistic Weighted
6 Average
The most common question concerning this calculation is why does it use four
times the most likely case? The answer is that by using four times the most
likely case, the formula creates the hump required to produce the bell curve
shape. It creates a bell curve with six cases even though there are only three real
values. Once the mid-point of the curve is determined, the PERT standard
deviation is next.
The PERT standard deviation defines the range and shape of the curve. It is
necessary to provide the confidence interval of the estimates. Within one PERT
standard deviation on either side of the PERT weighted average, 68% of the
cases will occur. Within two PERT standard deviations of the PERT weighted
average 95% of the cases will occur. And, within three PERT standard
deviations of the PERT weighted average 99% of the cases will occur. The
formula to calculate the PERT standard deviation is:
Pessimistic - Optimistic The PERT
PERT Standard Deviation = 6 Standard
Deviation
The last calculation used in PERT is the PERT variance. Although this
calculation is not seen as much on the PMP® exam as the PERT weighted
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 198
average or PERT standard deviation, it is still a good idea to be familiar with it.
The formula for the PERT variance is:
The PERT
PERT Variance = PERT Standard Deviation2 Variance
To better understand these three calculations let’s take a look at a simple
example. Imagine you’re leading a small project that has the following duration
estimates:
Best Case = 5 Weeks
Most Likely Case = 7 Weeks
Worst Case = 11 Weeks
Notice the change in terminology from pessimistic and optimistic cases to worst
and best cases. Do not be confused. They mean the same thing. The first step
in the process is to calculate the PERT Weighted Average. In this case the
formula would be:
44
PERT Weighted Average = 11 + (4 * 7) + 5 or or 7.33
6 6
The next step is to determine the PERT Standard Deviation which is:
11 - 5 6
PERT Standard Deviation = 6 or 6 or 1
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 199
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 200
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 201
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 202
A binomial distribution is used whenever there are only two possible outcomes. Slide 165
A perfect example is flipping a coin. Although there is an infinitesimally small
change of the coin landing on its side, most people would agree that with each
flip the outcome is either heads or tails. Typically, a binomial distribution is
graphed using two vertical bars displaying the likelihood of each outcome.
Binomial distributions are used in project management as a descriptor in Monte
Carlo simulations.
A uniform distribution represents a scenario where each value of a random
variable has an equal probability of occurrence. The values in a uniform
distribution can be continuous, meaning without limit, or they can be discrete
meaning they have a set range. A simple example of a uniform distribution is the
value shown on a dice when rolled. The values are either 1, 2, 3, 4, 5, or a 6.
Each value has a 1/6th probability of being rolled therefore the distribution is flat
and is described as a discrete uniform distribution. A uniform distribution is
used in project management to obtain a rough order of magnitude estimate where
very little information is available or in risk management when the team is
dealing with several risks that each have an equal probability of occurrence.
A triangular distribution is a continuous probability distribution that begins
with a minimum value, ends with a maximum value, and makes use of a mode,
or most likely value somewhere along the continuum. A triangular distribution is
different from a uniform distribution in that the probability of the random values
are not all the same. Remember, in the uniform distribution each of the potential
values had the same likelihood of occurring. In a triangular distribution, the
minimum and maximum values have a zero probability of happening. The mode
is the value most likely to be seen and so is shown as a spike in the graph which
creates the triangle when combined with the minimum and maximum. In project
management, the triangular distribution is used when an approximation is needed
for a beta distribution to estimate activity duration. It is not uncommon to use a
triangular distribution as an approximation for a beta distribution which is much
more difficult to calculate and graph.
A beta distribution represents a distribution of probabilities when we don’t
know what the probability is. Fortunately, the only time a project manager ever
deals with beta distributions is in some advanced software applications and never
of the PMP® exam.
The final statistical concept we will add to the conversation here is the central
limit theorem or CLT. This theorem simply states that the mean of a large
population of independent and random variables, each having a finite mean and
variance will be normally distributed. Although this theorem might sound
complex it impacts project management in a very practical way. Imagine you
have a project with more than 100 activities or deliverable. The team has
defined three estimates for each one. Is it OK if you use the sum PERT weighted
averages to estimate the overall project duration? The answer is yes, because of
the CTL we assume the project duration follows a normal distribution and the
variance can be calculated by summing the variances of the project activities on
the critical path.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 203
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 204
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 205
Critical path method (CPM) is one of the two major techniques that is used to
determine a project’s schedule. It is both the oldest and the most widely used
technique. The critical path of a project is defined as the longest chain of
dependent tasks, activities or deliverables with zero slack or float. It is the chain
of items through the precedence diagram that defines the overall project
duration. The tasks, activities or deliverables in the critical path do not
necessarily have the greatest risk or the most importance—but they do define the
earliest finish date of the project. There are six key variables used in the critical
path methodology: Slide 170
The Early Start (ES) — The early start is the
soonest day that the project task, activity or
deliverable can begin.
Duration (DUR) — The duration is the amount Image 51: The CPM Legend
of calendar time the project task, activity or
deliverable will take. It was defined for each item in the last process.
Early Finish (EF) — The early finish represents the soonest day that the
project task, activity or deliverable may be completed based on the
dependencies defined in the precedence diagram.
Late Start (LS) — The late start is the latest day that the task, activity or
deliverable can begin on without impacting the earliest overall delivery date
of the project.
Float — The slip, slack, total float, or float is the amount of time the task,
activity or deliverable can slip or extend without impacting the earliest
overall delivery date of the project.
Late Finish (LF) — The late finish is the latest day that the task, activity or
deliverable can end on without impacting the earliest overall delivery date of
the project.
With the definitions in hand let’s examine the steps involved in developing a
critical path model. Begin by examining the precedence diagram shown in
Image 52. Notice how the diagram shows the duration estimates for each
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 206
deliverable, task or activity. Also notice that the very first task, activity or
deliverable has an early start value in the upper left hand corner, and it is the
only early start value defined at this point.
The first rule that must be memorized is that the very first task, activity or
deliverable always begins on day zero. This is your anchor point or the
beginning of the project. Unfortunately, you cannot go back in time and start
your projects two weeks prior to today. To calculate the critical path you will
make two passes completely through the network diagram by first going left to
right and then going right to left. As you make these passes it is very important
that you always work in columns and do not skip ahead.
The first pass through the network is referred to as the forward pass because it Slide 171
goes the same way we read, from left to right. The formula you will use in each
box is: The
EF = ES + DUR Forward
Pass
In this case deliverable A is 0 + 2 = 2. A two can now be placed in the upper
right hand value (the early finish) of deliverable A. Because deliverables B, C,
and D all have logical dependencies on deliverable A we also can now place a
two in the early start position of deliverables B, C and D. Working in columns
as our earlier rule stated, we can now determine the early finish values for B, C,
and D.
Deliverable B: 2+4=6
Deliverable C: 2+2=4
Deliverable D: 2+3=5
Those values are then placed into the upper right hand position for each box
before continuing to the next column and deliverable E. Deliverable E is
dependent on deliverable B, and since deliverable B has an early finish value of
six, that becomes the early start value for deliverable E. The forward pass
calculation for deliverable E is now 6 + 2 = 8.
We have now reached a critical point in the forward pass. Deliverables C, D,
and E all feed into deliverable F. This is referred to as a converging (or a
convergence point) and occurs whenever two or more tasks, activities or
deliverables feed into a single item. The rule for a convergence point on the
forward pass is to always take the largest value. In this case we have values of
four, five and eight. The eight is selected and placed into the early start position
of deliverable F.
The forward pass has now been completed and we have determined that the early
finish for the project is 10. The next step is to take the early finish from the last
task, activity or deliverable (deliverable F) and make it the late finish as well.
deliverable F now has a value of 10 placed in both far right position. Now
complete the backward pass. Image 53 shows the CPM model once all passes
are complete. The backward pass begins with deliverable F and progresses from
right to left following the logical dependencies in reverse order. The objective of
the backward pass is to calculate the late start that appears in the lower left
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 207
Slide 171
corner of each box. The formula that will be used for the backward pass is:
The
LS = LF – DUR Backward
Using this formula the calculation for deliverable F is 10 - 2 = 8. An eight is Pass
placed in the lower left corner of deliverable F. The next step is to also place an
eight in the lower right position of any deliverable that is a precedent to
deliverable F. In this case, deliverables C, D, and E are all required to complete
deliverable F so an eight is placed in the lower right position of each of these
boxes as well.
Just as with the forward pass, we always work in columns when completing the
backward pass. That means deliverable E is the next value to be calculated. The
late start value for deliverable E is 8 - 2 = 6. The six is placed in the lower left
position for deliverable E and also in the lower right position of deliverable B.
The column of deliverables B, C, and D can all have their late start calculated.
Deliverable B = 6 – 4 = 2
Deliverable C = 8 – 2 = 6
Deliverable D = 8 – 3 = 5
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 208
The slack or float appears as the middle value on the bottom of each deliverable.
The values for the sample model are therefore as follows:
Deliverable A = 0 – 0 = 0
Deliverable B = 2 – 2 = 0
Deliverable C = 6 – 2 = 4
Deliverable D = 5 – 2 = 3
Deliverable E = 6 – 6 = 0
Deliverable F = 8 – 8 = 0
The critical path is where the slack or float is zero for every task, activity or
deliverable. Therefore the critical path for this project is ABEF. So what does
this really mean? If any of the tasks, activities or deliverables that are on the
critical path slip, the overall delivery of the project will slip by an equal amount.
When this happens, the first place the project manager should look to take
resources away from is any simultaneous non-critical item. Another way of
thinking about this is to ask yourself would you care if deliverables C or D
slipped two weeks? The answer is no. In both cases you have at least three
weeks slack or float, so such an occurrence would not impact the overall
delivery of the project.
There are three additional terms which might appear on the exam, although
rarely. These are as follows:
Near-Critical Path — This represents a project path that is close in duration
to the critical path. A significant delay to the near-critical path could cause it
to become critical. The closer these two paths are, the more risk the project
has.
Free Float — This is the amount of time an activity can be delayed without
delaying the early start of the successor activity.
Project Float — This is the amount of time an entire project can be delayed
without delaying an externally imposed project completion date.
It is absolutely critical that you can successfully calculate CPM models because
they often produce series questions on the exam. Because of that, a single model
could potentially represent five different questions on the PMP® exam! Exam
questions often ask you what the critical path is for a series of items, what the
overall project duration is, or how much slack or float any particular item has.
To ensure that you are prepared for these types of questions complete Exercise 9.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 209
2. Using the included table what is the project duration using CPM?
A. 35
B. 38
C. 34
D. 37
3. Using CPM to evaluate the project represented by the included table, which
of the following tasks are not on the critical path?
A. A
B. B
C. D
D. F
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 210
5. Using CPM and the included table, what is the project duration?
A. 44
B. 42
C. 45
D. 51
6. Based upon the included table and CPM, which of the following tasks is not
critical?
A. 1
B. 2
C. 4
D. 10
7. Based upon the included table and CPM, which of the following tasks is not
critical?
A. 4
B. 9
C. 6
D. 10
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 211
9. Using the included table what is the project duration using CPM?
A. 59
B. 63
C. 67
D. 61
10. Using CPM to evaluate the project represented by the included table, which
of the following tasks are not on the critical path?
A. A
B. B
C. C
D. J
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 212
11. Using CPM to evaluate the project represented by the included table, which
of the following tasks are not on the critical path?
A. F
B. E
C. I
D. J
12. Using the included table what is the critical path for the project?
A. 1, 3, 6, 7, 9, 10
B. 1, 3, 6, 7, 8, 10
C. 1, 2, 5, 7, 8, 10
D. 1, 2, 5, 7, 9, 10
13. Using the included table what is the project duration using CPM?
A. 66
B. 51
C. 48
D. 62
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 213
14. Using CPM to evaluate the project represented by the included table, which
of the following tasks are not on the critical path?
A. 2
B. 5
C. 3
D. 9
15. Using the included table what is the critical path for the project?
A. A, B, C, F, G, H
B. A, B, D, F, G, H
C. A, B, C, D, E, H
D. A, B, D, E, H
16. Using the included table what is the project duration using CPM?
A. 38
B. 36
C. 42
D. 40
17. Using the included table what is the critical path for the project?
A. 2, 4, 8, 9
B. 1, 3, 5, 6, 9
C. 2, 4, 8, 7, 9
D. 1, 3, 5, 7, 9
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 214
18. Using the included table what is the project duration using CPM?
A. 45
B. 43
C. 44
D. 46
19. Using the included table what is the critical path for the project?
A. A, B, D, G, J, L, M
B. A, C, E, H, I, L, M
C. A, C, E, G, J, L, M
D. A, B, F, G, K, L, M
20. Using the included table what is the project duration using CPM?
A. 52
B. 49
C. 50
D. 54
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 215
2. Answer B. Calculating the duration of the critical path is done by first building the
Precedence Diagram. Once that is done enter the task durations and complete the forward
and backward pass by evaluating the differences between the late and early start or the late
and early finish. The longest chain of dependent tasks with zero slack or float is the critical
path. The project duration for this model is 38.
3. Answer A. Task A has slack or float of 3. By definition, any task or deliverable with float
greater than zero is not on the critical path.
4. Answer D. Calculating the critical path is done by first building the Precedence Diagram.
Once that is done enter the task durations and complete the forward and backward pass by
evaluating the differences between the late and early start or the late and early finish. The
longest chain of dependent tasks with zero slack or float is the critical path. In this case the
Critical Path is 1, 4, 9, 10, 11.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 216
5. Answer C. Calculating the duration of the critical path is done by first building the
Precedence Diagram. Once that is done, enter the task durations and complete the forward
and backward pass by evaluating the differences between the late and early start or the late
and early finish. The longest chain of dependent tasks with zero slack or float is the critical
path. Summing this time provides the project duration. The correct project duration is 45.
6. Answer B. Task 2 has slack or float of 1. By definition, any task or deliverable with float
greater than zero is not on the critical path.
7. Answer C. Task 6 has slack or float of 1. By definition, any task or deliverable with float
greater than zero is not on the critical path.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 217
8. Answer D. Determining the critical path is done by first building the Precedence Diagram.
Once that is done, enter the task durations and complete the forward and backward pass. By
evaluating the differences between the late and early start or the late and early finish. The
longest chain of dependent tasks with zero slack or float is the critical path. The Critical
Path in this case is A, B, E, I, J, M.
9. Answer B. Calculating the duration of the critical path is done by first building the
Precedence Diagram. Once that is done, enter the task durations and complete the forward
and backward pass by evaluating the differences between the late and early start or the late
and early finish. The longest chain of dependent tasks with zero slack or float is the critical
path. This project duration is 63.
10. Answer C. Task C has slack or float of 1. By definition, any task or deliverable with float
greater than zero is not on the critical path.
11. Answer A. Task F has slack or float of 1. By definition, any task or deliverable with float
greater than zero is not on the critical path.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 218
12. Answer D. Calculating the critical path is done by first building the Precedence Diagram.
Once that is done, enter the task durations and complete the forward and backward pass by
evaluating the differences between the late and early start or the late and early finish. The
longest chain of dependent tasks with zero slack or float is the critical path. In this case the
Critical Path is 1, 2, 5, 7, 9, 10.
13. Answer A. Calculating the duration of the critical path is done by first building the
Precedence Diagram. Once that is done, enter the task durations and complete the forward
and backward pass by evaluating the differences between the late and early start or the late
and early finish. The longest chain of dependent tasks with zero slack or float is the critical
path. This project’s duration is 66.
14. Answer C. Task 3 has slack or float of 4. By definition, any task or deliverable with float
greater than zero is not on the critical path.
15. Answer D. Calculating the critical path is done by first building the Precedence Diagram.
Once that is done, enter the task durations and complete the forward and backward pass by
evaluating the differences between the late and early start or the late and early finish. The
longest chain of dependent tasks with zero slack or float is the critical path. The Critical
Path for this project is A, B, D, E, H.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 219
16. Answer A. Calculating the duration of the critical path is done by first building the
Precedence Diagram. Once that is done, enter the task durations and complete the forward
and backward pass by evaluating the differences between the late and early start or the late
and early finish. The longest chain of dependent tasks with zero slack or float is the critical
path. This project’s duration is 38.
17. Answer B. Calculating the critical path is done by first building the Precedence Diagram.
Once that is done, enter the task durations and complete the forward and backward pass by
evaluating the differences between the late and early start or the late and early finish. The
longest chain of dependent tasks with zero slack or float is the critical path. This project’s
Critical Path is 1, 3, 5, 6, 9.
18. Answer C. Calculating the duration of the critical path is done by first building the
Precedence Diagram. Once that is done, enter the task durations and complete the forward
and backward pass by evaluating the differences between the late and early start or the late
and early finish. The longest chain of dependent tasks with zero slack or float is the critical
path. This project’s duration is 44.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 220
19. Answer C. Calculating the critical path is done by first building the Precedence Diagram.
Once that is done, enter the task durations and complete the forward and backward pass by
evaluating the differences between the late and early start or the late and early finish. The
longest chain of dependent tasks with zero slack or float is the critical path. The diagram
shows the Critical Path for this model is A, C, E, G, J, L, M.
20. Answer A. Calculating the duration of the critical path is done by first building the
Precedence Diagram. Once that is done, enter the task durations and complete the forward
and backward pass by evaluating the differences between the late and early start or the late
and early finish. The longest chain of dependent tasks with zero slack or float is the critical
path. In this case the project duration is 52.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 221
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 222
Goldratt argues that you must first understand what is preventing success. It is
here that Goldratt introduces his Theory of Constraints.
Goldratt contends that in any system there is only one constraint at a time. It is
the one thing that acts as a bottleneck. To resolve this bottleneck you must
follow a simple process:
Identify the system constraint
Exploit the constraint
Subordinate everything to the constraint
Elevate the systems’ constraints
Repeat the process
When this process is applied to project management, the constraining factor
(according to Goldratt) is resources—specifically the tendency to have a single
resource assigned to multiple tasks, activities or deliverables at the same time.
This problem becomes compounded as the resource pool is shared across
projects. However, simply leveling the resources on a project largely fails to
resolve the issue of resource constraints because there are a number of other
issues tied to the problem. These issues include the following:
Probability and not precision — Most people assume project estimates are
precise, but they are actually exercises in probability and not precision.
Misplaced safety — In most cases, 50% of every existing duration estimate
is safety—yet we struggle to hit targets. One of the major causes for this is
that resources generally use the safety at the beginning of tasks, activities or
deliverables, instead of at the end when it might do some good.
Delays accumulate and advances get wasted — The intent of project
management is to deliver the overall project within the schedule baseline. To
accomplish this, most people manage each task, activity or deliverable to its
deadline, assuming that perfection in the parts will result in the desired
whole. Unfortunately, it doesn’t work like that. In the real world, sometimes
people are early and sometimes they are late. To achieve success we have to
be able to pass safety between tasks, activities or deliverables—and that
can’t be done easily.
There are several other factors that Goldratt discusses, but what we have
discussed so far provides you with a general background to the CCPM. The
basic goal is to produce a scheduling system that takes these factors into
consideration and puts the project manager—rather than the individual
resources—in charge of the safety.
The critical chain is defined as the longest chain of dependent tasks, activities or
deliverables with zero slack or float (sound familiar?) that takes into Slide 173
consideration the resource constraints. Here are the steps to complete a critical
chain model:
Complete the critical path model as discussed in the last section.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 223
Cut all duration estimates in half, thereby leaving the project finish date as
defined in CPM. There will then be a large gap to the left of the project,
closer to the beginning.
Level the resources so that no resource is ever doing more than one thing at a
time. In selecting which tasks, activities, or deliverables to move, always
select the ones which have the smallest impact on the schedule.
Determine the critical chain by following the logical dependencies and by
only moving off of the logical path when a single resource is asked to do two
or more things in succession.
Add the project buffer to the end of the critical chain using 30%, 25%, or the
sum of the squares methods. Allow the project to be pushed to the left
towards the start date.
Add up the lengths of the non-critical chains and add feed buffers wherever
the non-critical chains feed into the critical chain. As before, allow items to
be pushed to the left.
Add resource buffers in front of the first task, activity, or deliverable
whenever a single resource is asked to do a series of items in succession.
To measure progress on a project using critical chain project management
measure the percent of the project complete versus the burn rate of the project
buffer. They should be close to equal. Image 50 shows a critical chain diagram
with all its buffers.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 224
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 225
11. Using the table below, what is the length of the project's critical chain
excluding feed buffers and assuming 30% for all other buffers?
A. 73
B. 62
C. 95
D. 52
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 226
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 227
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 228
The Agile world does not typically use either the critical path or critical chain
method. Instead, Agilists use tools such as a story map to represent the timing of
a project. A story map is a two dimensional graphic. It arranges the project
features or user stories first on the horizontal axis to represent the item’s rough
priority with the highest priority items at the left and lowest on the right. The
vertical axis represents increasing sophistication of the implementation. What
this creates is a diagram where the first horizontal row represents what is called a
“walking skeleton”, or a barebones but usable version of the project’s product.
As the team works through successive rows they add features to the product with
additional functionality. Often distinct columns are used in the story map to
represent iterations or releases. Image 56 shows a sample story map.
Slide 174
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 229
the schedule. As you go through this effort you must also learn from
previous projects through the lessons learned register and make sure you are
aware of any milestones that exist as they can significantly alter the schedule.
Knowing the correct sequence of activities comes from the schedule network
diagram. Understanding when that work can be completed requires the
resource requirements, the team assignments, and the resource calendars.
Finally, the team must always look at the risk register to understand any
potential risks on the project.
.3 Agreements — Any contracts or agreements the organization has that may
impact how the work is done require careful examination.
.4 Organizational process assets — Any time the project manager has
organizational process assets which could make their job easier or faster they
should be used.
.5 Enterprise environmental factors — Like most of the processes,
enterprise environmental factors are at play in scheduling.
The tools and techniques for the develop schedule process include the following:
.1 Schedule network analysis— Precedence diagramming is the primary
technique used to produce network diagrams. You must be very familiar
with PDM. However, you might also see questions requiring you to
recognize Conditional Diagramming and GERT. You must examine those
diagrams to determine the best way to get the project done.
®
.2 Critical path method — CPM is the primary method used by PMI to
develop project schedules. You must be very good at working through CPM
models to pass the exam because there can be several questions that refer
back to one CPM model.
.3 Resource optimization — Resource optimization is done in order to
ensure that no resource is ever assigned to more work than can reasonably be
done. There are two aspects of resource optimization: resource leveling and
resource smoothing. Be careful as these terms do NOT mean the same thing
and they are NOT interchangeable.
Linear methodologies use one of two types of scheduling, resource
constrained scheduling or RCS and time constrained scheduling or TCS.
In resource constrained scheduling the team is limited to a defined set of
resources. This means the project is limited by the number of hours those
resources can work in a day, and while they can work overtime, research has
shown that the more overtime a resource works the less efficient they
become. Often the initial project schedule shows the same resource working
on multiple activities at the same time even though common sense says this
is impossible. The assignment of a resource to more work than they have
available time is called over allocation. This over allocation can happen
because of the total amount of work assigned to a resource or because of a
calendar constraint (e.g. the resource is assigned too much work but only for
a short period of time).
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 230
Resource leveling involves adjusting the start and finish dates of tasks to Slide176
prevent resources from becoming over allocated. Leveling often causes the
projects critical path to change, but the process begins by examining all
available float. Work is then moved until no resource has more work
assigned than they can handle. This process will often extend the project
completion date.
Resource smoothing adjust the project activities so they do not exceed
predefined resource limits. This is different from leveling in that smoothing
does not allow the project’s critical path to change and the project’s
completion date cannot be delayed. The goal in resource smoothing is to
maximize the utilization of all the resources on the team, but not at the
expense of the delivery date. Therefore, it is entirely possible that one or
more resources cannot be optimized because doing so would cause delays in
the project delivery date. The tables below compares and contrasts resource
smoothing with leveling.
Similarities
Resource Leveling Resource Smoothing
Slide 177
A schedule network analysis technique. A schedule network analysis technique.
Image 57: Taken from Satya Narayan Dash Nov.3 2015 MPUG
Differences
Resource Leveling Resource Smoothing Slide 178
Aim is to adjust start and end dates of a project Aim is to achieve optimal resource usage by
with resource constraints while balancing re- avoiding peaks and valleys in the resource
source requirements and resource availability usage profile. Hence the name smoothing.
Used in resource-constrained scheduling. Used in time-constrained scheduling.
Critical path of the project will be affected, and Critical path of the project won't change.
usually the length of critical path will increase.
Can be applied to resources on critical path. Doesn't apply to resources on critical path.
Free and total float (or slack) may be used. Free and total float (or slack) are used.
Will optimize all the resources and may change May not be able to optimize all the resources
the duration of the project. if sufficient slack (or float) isn't available, but
does not change the duration of the project.
Risk: May change the critical path and hence the Risk: Loss of flexibility due to reduction in
duration. slack. Hence chances of increase in number
of near-critical activities.
Image 58: Taken from Satya Narayan Dash Nov.3 2015 MPUG
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 231
.4 Data analysis — There are a number of data analysis techniques the team
can use, but PMI® calls out two specifically: what-if scenario analysis; and
simulations.
What-if scenario analysis is much older than you might expect. It is the
process of creating a range of unique conditions with definable variables and Slide 179
then evaluating them when changes are made to the specific drivers. It is
asking the question, “what is the result if this variable changes?” What-If
scenario analysis increases in popularity as the risk of the project rises, and
has been greatly impacted by advances in computer technology. This
technology allows project teams to quickly set up their basic model and then
move individual variables to determine the impact of one driver at a time.
Simulations allow the team to pretend to complete project work without
actually doing it or incurring the expense. This is done to evaluate area of
uncertainty to gain a better understanding of how specific aspects of the
project are impact the whole. The most common simulation technique is a
Monte Carlo analysis. Monte Carlo analysis is relatively new, and is a
result significant advances over the last ten years in computer processing
power. Monte Carlo analysis begins with the user establishing a basic
equation that describes the situation. This can be as simple as:
Activity A Duration + Activity B Duration + Activity C Duration = Total
The user then defines the curve of each variable. This is where the
distribution types discussed in the last process come into play. Imagine our
scenario with A having a normal distribution, B having a binomial
distribution and C having a triangular distribution. With each variable the
user also defines what are called the “tails” or the limits of the variable’s
potential values. Once that is complete the user initiates the analysis and the
program generates 1,000 instances of the model randomly selecting values
for each variable using the curve and defined range. Once complete, the user
can then determine the probability of achieving any result in seconds. At the
simplest level, a Monte Carlo analysis allows the team to determine the
likelihood of completing the project by a specific target date and what must
change to improve those chances.
.5 Leads and lags — Leads and lags are used to allow dependent tasks,
activities or deliverables to begin either prior to their predecessor being
completed or after a delay, based upon the nature of the work or on other
conditions. Both leads and lags can significantly impact a schedule.
.6 Schedule compression — Schedule compression is shrinking the
schedule to meet a specific target such as a deadline. A major assumption
with schedule compression is that the project scope is maintained. When
compressing a schedule there are only two choices:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 232
Fast Tracking — Fast Tracking is doing dependent items in parallel. Slide 180
It amounts to changing a finish-to-start relationship to a start-to-start
or a finish-to-finish relationship. For the exam it is important that you
remember that the negative impact of Fast Tracking is the potential
for rework.
Crashing — Crashing is increasing the number of hours worked.
This can be done by adding resources assigned to a task, activity or
deliverable or by simply working overtime. The negative impact of
Crashing that must be remembered is a likely increase in costs.
.7 Project management information system — Throughout this process we
have described many situations making use of computer technology. The
PMIS is often the tool providing these capabilities and is therefore a critical
tool.
.8 Agile release planning — In agile development a release is a group of
iterations put into production together to gain some advantage. In Scrum,
those iterations are called sprints and the team might choose to group three or
four sprints together because the organization has set production windows
that allow for the introduction of new functionality. The process of release
planning involves the team determining the number of small iterations in the
project and how they will be combined into sprints. Then the team places
this information on a calendar to provide a product roadmap that is typically
three to six months in length. This information allows the customer to
understand when they will receive the various components of functionality
based on the current information.
The outputs to the Develop Schedule Process include the following:
.1 Schedule baseline — The schedule baseline represents what the project
manager and team have committed to the sponsor in terms of when the
various project tasks, activities and deliverables will be completed. It is the
basis of measuring progress on the project and is required for any time-based
variance analysis. For the exam, make sure that you can differentiate
between the schedule and the schedule baseline.
.2 Project schedule — The project schedule is a living, breathing document.
It is constantly being reviewed and changed to reflect reality. It is the
document that shows when different project tasks, activities or deliverables
are to be completed. At a minimum, the schedule should include the planned
start and finish date for each activity although it is slightly different for an
agile project. PMI® also suggests three visual aids to help with the
presentation of the schedule.
A bar chart is perhaps the most common tool used in linear project
methodologies. It appears as a Gantt chart with the bars representing
project work over time represented horizontally. The Gantt chart also has the
advantage of showing precedence diagram dependencies, milestones, the
critical path, and resourcing which is why it is the most popular project
display used today. Image 59 shows a sample Gantt chart.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 233
Slide 181
Slide 182
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 234
In some situations the team may not use any advanced technology to
represent their schedule. In these cases the team might simply present the
schedule using a schedule network diagram using the activity-on-node
format describe earlier in this section.
.3 Schedule data — Schedule data includes any information about delayed
tasks, activities or deliverables with explanations and/or schedule forecasts.
.4 Project calendars — The project calendars show the team and other
stakeholders when things are supposed to happen.
.5 Change requests — Almost any of the defined process can generate a
requested change as the team and organization learn new information about
the project. It is always critical that you work to first understand the change
and then follow whatever change management process the team has defined.
.6 Project management plan updates — Based on the schedule, it might be
necessary to update the various project plan with new information.
.7 Project document updates — All of this information could have a
significant impact on the project’s documentation. It is important that you
update those documents.
6.6 Control Schedule
The last process in the schedule Monitoring & Controlling Process Group
management knowledge area is the Slide 183
control schedule process. This
process moves us out of the planning
process group and into the
monitoring and controlling process
group. The control schedule process
is part of the integrated change
control process that is defined in the Image 61: Sample Gantt Chart
integration management knowledge
area. The primary goal of the control schedule process is to determine the
current status of the project in terms of the schedule. However, it is also the
process that is used to manage changes to the schedule and to make sure that
only good changes occur.
The inputs to the control schedule process include the following:
.1 Project management plan — The project management plan is a large set
of documents and PMI® specifies several components for controlling the Slide 184
schedule including: the schedule management plan, the schedule baseline,
the scope baseline, and the performance management baseline. The first
three of these defines the work to be completed and how long the team
thought it was going to take to complete the work. The last item, the
performance measurement baseline is used when the team is implementing
earned value analysis to compare forecasts to actuals and determine if a
change, corrective action, or preventive action is necessary.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 235
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 236
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 237
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 238
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 239
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 240
18. You and your project team have obtained estimates for your project, assigned
resources, and developed a precedence diagram of the project. Several of
your resources are very concerned that two of the activities are not being
focused on enough and will end up delaying the project because they are
critical components of the project’s end product. What is the best thing to
do?
A. Sit down with the resources to discuss the project Gantt chart.
B. Determine if the activities in question are on the critical path.
C. Examine the project’s risk register.
D. Evaluate alternative project execution paths.
19. Which of the following best describes the impact of multiple critical paths on
a project?
A. The project takes longer to complete.
B. The project is more expensive.
C. The project takes more resources to manage.
D. The project risk increases.
20. You and your project team have just completed the development of your
PDM diagram. The current diagram shows there are three critical paths in
your project. What is the best thing to do next?
A. Re-evaluate the network for errors.
B. Develop the project schedule.
C. Examine the project risk register.
D. Discuss alternative networks with your team.
21. In discussing your project with management you determine that the project
schedule is the most flexible and the project scope is the least flexible. If the
allowable monthly project expenditures are fixed, then what is the best thing
to do?
A. Level the resources.
B. Examine the project’s critical path.
C. Analyze the project’s life cycle costs.
D. Crash the project.
22. Your manager asks you to produce a report on your project for management.
Which of the following would best meet the request?
A. Bar chart
B. PERT chart
C. Milestone chart
D. Gantt chart
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 241
23. You and your project team have just completed the development of your
project schedule. Based on the constraints provided by the project sponsor,
the project is scheduled to be completed after the project deadline. Assuming
that costs are the least important constraint and scope is the most important
constraint, which of the following is the best thing to do?
A. Fast track the project.
B. Crash the project.
C. Reassess the critical path.
D. Develop a critical chain model for the project.
24. You and your project team have just completed the development of your
project schedule. Based on constraints provided by the project sponsor, the
project is scheduled to be completed after the project deadline. Assuming
that costs are the most important constraint and scope is the least important
constraint, which of the following is the best thing to do?
A. Crash the project.
B. Reassess the critical path.
C. Develop a new project schedule.
D. Fast track the project.
25. Your manager comes to you and demands that you complete your project
three weeks early. What is the best thing to do?
A. Meet with your project team to examine alternatives for crashing and
fast tracking.
B. Tell your boss the project critical path does not allow for a three week
early completion.
C. Ask the project to work overtime.
D. Ask your manager if you can reduce the scope of the project.
26. When evaluating the impact that crashing will have on your project, which of
the following should be included in the evaluation?
A. The project sponsor’s interest.
B. Risks associated with the schedule changes.
C. The amount of overtime to be worked.
D. The impact of a reduction in project scope.
27. Which of the following PM processes requires the project manager to reach
an agreement with the activity resources on the calendar date for each
activity?
A. Sequence activities.
B. Estimate activity durations.
C. Estimate resources.
D. Develop schedule.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 242
28. It is late Friday afternoon when your project sponsor informs you that the
project schedule has been reduced by two weeks. What is the best thing to
do?
A. Meet with your project team to determine options for schedule
compression.
B. Cut the project scope.
C. Crash the project.
D. Inform management that the date cannot be met.
29. As the project manager, you estimate the time that is needed for each activity,
assign tasks to specific resources and then add the estimates to create the
project estimate. You then use this value to establish the project delivery
date which you provide to the project sponsor. What is incorrect with this
process?
A. The project manager created the estimates without the team.
Additionally, summing the tasks will lead to a significantly longer
project duration.
B. Project duration estimates should be developed by the project
sponsor.
C. The project manager created the estimates without the project
resources and did not use a network diagram to define the critical
path.
D. The project completion date should be derived from an evaluation of
the triple constraints.
30. You are the project manager for a large construction project. It is early in the
project lifecycle and you have completed the activity definition. In
analyzing the activities you see a number of activities that are dependent on
each other but can start at the same time. Which methodology is the best one
to properly evaluate this project?
A. CPM
B. PDM
C. AOA
D. GERT
31. You are the project manager for a $250,000 software development project.
You are working with your project team and you determine that the project
has a number of project tasks that are dependent on each other. However,
one of your team members also points out that the tasks can finish at the
same time. Which of the following is the best technique to understand this
situation?
A. Critical path method
B. Activity on arrow method
C. Precedence diagramming method
D. Program evaluation and review technique
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 243
32. You are the project manager for a large consulting company leading a
process improvement project for your organization’s largest client. The
project currently has a CPI of 1.04 and SPI of .98. Your customer has just
asked if you can produce a diagram that shows the probabilistic project path.
Which of the following tools would be best in this situation?
A. Graphical evaluation and review technique
B. Program evaluation and review technique
C. Critical path method
D. Precedence diagramming method
33. Which of the following is best suited to define a project network that has
potential looping of the activities, deliverables or tasks?
A. PERT
B. CPM
C. GERT
D. PDM
34. You are the project manager for a software development project with an
estimated budget of $650,000. You have just completed the duration
estimates, and activity sequencing for your project. Which of the following
do you still need to complete the initial project schedule?
A. Performance measurement baseline
B. Contingency reserves
C. Schedule data
D. Schedule management plan
35. You are just taking over for a project manager who was forced to take a
medical leave of absence. Your project has a CPI of .93 and an SPI of .89.
To gain a better understanding of how the previous project manager was
managing schedule changes, to which of the following would you turn?
A. The project plan
B. The project schedule
C. The schedule management plan
D. The project Gantt chart
36. You are taking over for a project manager who was terminated. The previous
project manager was using weighted average duration estimates to develop
the schedule network. What type of modeling are you using?
A. Monte Carlo analysis
B. Project evaluation and review technique analysis
C. Critical chain analysis
D. Critical path analysis
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 244
37. You are the project manager for a large mechanical engineering project. You
have completed your scope statement, the WBS, the resource estimate,
duration estimates, and the network diagram. Which of the following is the
thing you should do next?
A. Create the schedule
B. Complete the cost estimates
C. Define the project budget
D. Solicit purchase
38. You work as a project manager and have completed the scope statement,
resource estimates, and the WBS. You’ve just received the activity duration
estimates. Which of the following is your best course of action?
A. Finalize the schedule
B. Compress the schedule
C. Complete the risk register
D. Develop RFPs
39. One of your resources comes into your office to discuss their task. The
project has a CPI of .89 and an SPI of .92. The resource’s task has an early
start of week 14 and a late start of week 17. What do you know about this
activity?
A. It is ahead of schedule
B. It is behind schedule
C. It is on the critical path
D. It is not on the critical path
40. You have an activity that has an ES of 12 weeks, an LS of 15 weeks, an EF
of 21 weeks, and an LF of 24 weeks. What do you know about this activity?
A. It is not on the critical path
B. It is ahead of schedule
C. It is behind schedule
D. It is on the critical path
41. You are leading a project that you have just learned is 3 weeks behind
schedule. The dependencies are discretionary. The project has an SPI of .81
and a CPI of .83. Due to cost overruns you cannot add more resources. What
is the best thing to do?
A. Move resources from tasks with discretionary dependencies
B. Complete activities in parallel where possible
C. Reduce resources
D. Reduce project scope
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 245
42. You’ve been brought into the organization because senior management is
struggling to get a strong understanding of the state of their projects. You
only have a week to prepare a 30 minute presentation on the status of all the
projects. Which of the following would best help senior management
understand the current portfolio status?
A. Project management plan executive summaries
B. Detailed cost and schedule analysis
C. Milestone charts
D. Gantt charts
43. Sally is a brand new project manager within a company that manufactures
household products. She’s just taken over a project that is seriously over
budget and behind schedule. Originally, the project was slated to have spent
$135,000 and they have already spent $170,000. It appears that most of the
overage is because of flawed original estimates. This project is critical to the
organization’s success. Who has primary responsibility to solve these
issues?
A. The project sponsor
B. The project manager
C. The project team
D. Senior management
44. You are the project manager for a project that you have just learned is 30
days behind schedule. You do not have any additional resources that may be
engaged. The project has a CPI of .84 and an SPI of .79. The BCR is 1.45
and only a few of the project tasks have mandatory dependencies. What is
the best thing to do?
A. Meet with the project sponsor to inform them of the delay.
B. Reduce the project scope to meet the deadline.
C. Crash the project.
D. Make more activities concurrent.
45. Rearranging dependent tasks or activities so they are done in parallel is
called what?
A. Fast tracking
B. Leveling
C. Paralleling
D. Crashing
46. Rearranging resources and resource workloads so that the amount of work
done in each month or specified time period is constant is called what?
A. Fast tracking
B. Paralleling
C. Leveling
D. Crashing
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 246
47. Adding additional resources to reduce the schedule time of a task or activity
is called what?
A. Fast tracking
B. Crashing
C. Paralleling
D. Leveling
48. Which of the following is a benefit of a three point project estimate?
A. It shows a better understanding of the task.
B. It allows the project manager to better manage stakeholder
expectations.
C. It helps determine if the project will meet the schedule.
D. It provides a probabilistic estimate.
49. Which of the following is a benefit of analogous project estimates?
A. It helps to raise questions about expectations.
B. The estimates will more accurately reflect actuals.
C. It helps the project resources understand their obligations.
D. It helps senior management feel better about the estimates.
50. Which of the following is an advantage of parametric estimating?
A. It accounts for estimating uncertainty.
B. It provides for improved communication.
C. It provides a quantifiable deterministic estimate.
D. It provides estimates at the lowest possible level.
51. You are the project manager for a very large and important project within
your organization. Your project has been progressing very well until the last
couple of weeks when you began to experience a large number of scope
changes. Your current CPI is 1.02 and your SPI is .98. As the project
manager, what should you do?
A. Maintain the baseline and make approved changes.
B. Maintain the baseline and resist all changes.
C. Make only the changes approved by the project sponsor.
D. Initiate a discussion with management about the level of changes.
52. Your boss asks you to change a presentation slide showing a network
diagram to one showing a bar chart. Which of the following best explain this
request?
A. Bar charts show logical relationships more effectively than network
diagrams.
B. Bar charts better display resource trade-offs than network diagrams.
C. Bar charts better show the critical path than network diagrams.
D. Bar charts better display progress or status.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 247
53. You are leading a large project for your organization. Early in the project the
sponsor informs you that neither time nor costs are as important as the
number of resources used each month. Which of the following is the best
thing for you to do?
A. Level the project resources
B. Crash the project
C. Fast track the project
D. Apply a heuristic
54. Upon presenting your plan to your sponsor you are informed that the
schedule exceeds the target completion date the sponsor desired. If the
project network diagram cannot change, but the sponsor offers extra
resources what is the best thing to do?
A. Crash the project
B. Fast track the project
C. Level the resources
D. Perform a Monte Carlo analysis
55. You’ve determined that crashing your project is the best option for reducing
your project schedule. The best approach to crashing would also include
looking at the:
A. Sponsor’s opinion of which activities to crash.
B. Risk impacts of crashing each activity.
C. Customer or end user’s opinion of which activities to crash.
D. When in the project timeline the activities occur.
56. You are assigned as the project manager for a manufacturing project within
your organization. During the planning phase of the project, you estimate
the time needed for each activity and then add the estimates to create the
project estimate. You then commit to delivering the project by the defined
date. What is wrong with this scenario?
A. The team did not create the estimate, and compilation was not used.
B. The estimate is too short and should be created by management.
C. The team did not create the estimate and a network diagram was not
used.
D. The estimate should be matched to the customer’s required
completion date.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 248
57. You have a project with the following activities: Activity A takes 40 hours
and is the first task. Activity B takes 25 hours and should happen after the
project starts. Activity C must happen after activity A and takes 35 hours.
Activity D must happen after activities B and C and takes 30 hours. Activity
E must take place after activity C and takes 10 hours. Activity F takes place
after activity E and takes 22 hours. Activities F and D are the last activities
of the project. Which of the following is true if activity B actually takes 37
hours?
A. The critical path is 67 hours.
B. The critical path changes to Start, B, D, End.
C. The critical path is Start, A, C, E, F, End.
D. The critical path increases by 12 hours.
58. The WBS, activity duration estimates, and the precedence diagram are
completed. Which of the following should you do next?
A. Validate project scope.
B. Identify project risks.
C. Sequence the activities.
D. Create a preliminary schedule and get the team’s approval.
59. You are leading an engineering project for your organization and have
developed a six level WBS that has been sequenced using PDM. The
activity duration estimates have been received. What should you do next?
A. Create an activity list.
B. Begin the work breakdown structure.
C. Finalize the schedule.
D. Compress the schedule.
60. You are the project manager for an information technology project within
your organization. A five-level work breakdown structure has been
developed for the project. The network diagram and duration estimates have
been created and the schedule has been developed and compressed. Which
of the following time management activities should you do next?
A. Gain approval.
B. Estimate activity resources.
C. Use parametric estimating.
D. Control the schedule.
61. The project is calculated to be completed two weeks after your sponsor’s
deadline. You have been told there are no additional resources. The project
is low risk, the benefit cost ratio is expected to be 1.71, and the project
dependencies are preferential. What is the best thing to do?
A. Remove non-critical activities from the project.
B. Make more activities concurrent.
C. Cut resources from non-critical activities.
D. Move resources from preferential dependencies to external
dependencies.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 249
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 250
11. Answer B. PMBOK® Guide p. 192. Lead time represents the amount of
time one activity can begin prior to the completion of its preceding
dependent task. Lead time is used to compress a schedule and can run the
risk of rework.
12. Answer A. PMBOK® Guide p. 189-190. The network diagram is
specifically designed to allow you to determine all the potential project paths
and the longest time the project can take. A work breakdown structure is
used to show the project deliverables. Changing the end date of a project
does not necessarily change a network diagram and the critical path never
contains dummy tasks.
13. Answer C. PMBOK® Guide p.157. A milestone is a marker representing
the completion of a task, activity or deliverable. It never has duration of any
length.
14. Answer A. Standard deviation allows you to determine the amount of
dispersion from the mean that your estimates have. The more dispersed the
estimates, the more variance exists between the estimates — and therefore
the greater the risk is.
15. Answer B. PMBOK® Guide p. 213. Several of these answers are close, but
the correct answer is to gain an indication of the risk in the project. Monte
Carlo simulations will not tell you about specific risk. They reveal the
probabilistic nature of risk. A Monte Carlo simulation enables the user to
determine the probability that a result will occur within a given range. The
wider the range, the greater the uncertainty or risk.
16. Answer D. PMBOK® Guide p.210. Slack or float represents the amount of
time a specified activity may be delayed without impacting the project’s
critical path. Only items not on the Critical Path have slack or float. It is the
difference between the early finish and late finish or the early and late start.
17. Answer A. PMBOK® Guide p.210. Slack or float represents the amount of
time a specified activity may be delayed without impacting the project’s
Critical Path. Only items not on the Critical Path have slack or float. It is
the difference between the early finish and late finish or the early and late
start. In this case the best answer is to first determine if the task is on the
Critical Path and find out how much slack or float it has.
18. Answer B. PMBOK® Guide p.210. Slack or float represents the amount of
time a specified activity may be delayed without impacting the project’s
Critical Path. Only items not on the critical path have slack or float. It is the
difference between the early finish and late finish or the early and late start.
In this case the best answer is to first determine if the tasks are on the Critical
Path and find out how much slack or float it has.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 251
19. Answer D. PMBOK® Guide p.210. Multiple critical paths are not unusual
in the real world. This simply means that if any of the activities on any of
the Critical Paths are delayed, the entire project will be delayed. This
sometimes causes an increase in project resources or cost and it might cause
the project to take longer. However, it is a guarantee that the project has an
increase in risk because the project now has more chance for an activity
delay to impact the delivery of the project.
20. Answer B. PMBOK® Guide p.210. Multiple critical paths are not unusual
in the real world. This simply means that if any of the activities on any of
the critical paths are delayed the entire project will be delayed. Therefore,
the existence of multiple critical paths does not represent an error in your
process. The development of the PDM Diagram is part of activity
sequencing. The next step in the process is developing the project schedule.
21. Answer A. PMBOK® Guide p.211. This is a triple constraints question. If
the project schedule is the most flexible, this means the project could
continue for several months past the original forecast. This is especially true
because the project has an inflexible scope. Because the project cost is fixed
on a monthly basis — but not on a total basis — the best thing to do is level
the resources to ensure the monthly project costs do not exceed the allowable
amount.
22. Answer C. PMBOK® Guide p.218. The best tool for reporting to
management is a milestone chart. This provides the correct level of
information for management.
23. Answer B. PMBOK® Guide p.215. The best thing to do in this case is crash
the project. This usually entails adding resources to the project to get project
work done more quickly. This will cause a likely increase in project costs.
Fast tracking is doing tasks in parallel which decreases the schedule, but this
often causes rework which in this case is unacceptable.
24. Answer D. PMBOK® Guide p.215. The best thing to do in this case is fast
track the project. This is because you do not have the ability to increase the
cost by adding resources (crashing). Reassessing the critical path and
developing a new schedule are not preferred alternatives.
25. Answer A. PMBOK® Guide p.215. Whenever your due date is reduced, the
first thing to do evaluate the two alternatives you have. You can either crash
or fast track the project.
26. Answer B. PMBOK® Guide p.213. Whenever doing any type of evaluation
of a project it is always critical that you analyze the risks associated.
27. Answer D. PMBOK® Guide p. 205. Develop schedule is the process where
the basic schedule is applied to a calendar.
28. Answer A. This is a PMIism. The best option is always to determine
alternatives before you do anything else.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 252
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 253
times are not the same. This means the task must not be on the critical path.
In addition, this question tests whether or not you know that ES stands for
early start, LS stands for late start, EF stands for early finish and LS stands
for late finish.
41. Answer B. PMBOK® Guide p. 191-192; 215. Two pieces of knowledge are
important to this question. First, you must understand the different types of
dependencies (mandatory, discretionary, internal and external). Secondly,
you must know that whenever a schedule needs to be shortened you can
either crash the schedule or fast track it. Fast tracking is the correct answer
because you cannot add resources.
42. Answer C. PMBOK® Guide p. 218. Whenever it is a question about the
type of reporting for senior management the answer is always Milestone
Reports. You may provide a lot of other information, but the Milestone
Report always comes first.
43. Answer B. PMBOK® Guide p. 175. Hopefully, this was an easy one. The
project manager is always the first line. Although they can get help from
their project team, they are ultimately responsible.
44. Answer D. PMBOK® Guide p. 215. Making more activities concurrent is
another way of saying fast track the project. It is one of only two ways to
reduce a project schedule without reducing project scope. The other is
crashing — which is adding resources to the project. Crashing is not an
option in this case. Reducing the scope is not an option until you have first
tried the other alternatives.
45. Answer A. PMBOK® Guide p. 215. Fast tracking is the technique where
you change the scheduling of dependent tasks so they are done in parallel.
46. Answer C. PMBOK® Guide p. 211. The process of changing work
assignments or resourcing so that the amount of work done in each month or
specified time period is called resource leveling.
47. Answer B. PMBOK® Guide p. 215. Crashing is the schedule compression
technique that reduces the amount of time that specific activities take by
adding resources to those tasks. It runs the risk of increasing project costs.
48. Answer D. PMBOK® Guide p. 201. A three point estimate forces a normal
distribution when used with the PERT analysis technique. This is a
probabilistic technique. When using a PERT Standard Deviation you get the
probability that the real duration comes within a range.
49. Answer A. PMBOK® Guide p. 200. Analogous estimating is an inexact
estimating technique because it is a top down technique. It is best used early
in the project when inexact estimates are expected to raise concerns or
questions about expectations.
50. Answer C. PMBOK® Guide p. 200. Parametric estimating provides project
estimates based upon some form of mathematical model. It is quantitative
and deterministic.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 254
51. Answer A. PMBOK® Guide p. 189-190. Changes are a fact of life for a
project manager. The key is that you use your change control process, only
implement those changes approved by management, and always maintain the
project baseline. If you do not maintain the baseline you have nothing with
which to compare.
52. Answer D. PMBOK® Guide p. 209-210. Progress or status is not
effectively displayed with a network diagram. Network diagrams are very
good at displaying logical relationships and the critical path. Bar charts can
be used to display progress.
53. Answer A. PMBOK® Guide p. 215. Both fast tracking and crashing will get
the project done faster, but neither control the number of resources used in a
month. In fact, crashing will increase the number of hours worked. The only
answer that manages the hours worked by a resource is leveling.
54. Answer A. PMBOK® Guide p. 215. The definition of crashing is increasing
the number of hours worked. This is done by working overtime or by adding
people to the project.
55. Answer B. PMBOK® Guide p. 215. Project risks must always be
considered. It is said that risk management is simply project management for
adults. None of the other alternatives are common requirements for proper
crashing.
56. Answer C. PMBOK® Guide p. 189-190. In terms of process, this question
highlights the concept of compilation and summing. Just adding all the totals
together is summing. To correctly compile the schedule, a network diagram
must be built first.
57. Answer C. PMBOK® Guide p. 210-211. To correctly answer this question
you must weed through the long wording and build a precedence diagram.
The described network has three possible paths. If the duration of activity B
changes from 25 to 37, the activity will take 12 additional hours which
changes the duration of that path from 55 to 67 hours. Since the critical path
has a duration of 107 hours the delay of activity B has no impact on the
critical path.
58. Answer D. PMBOK® Guide p. 187-190; 205-221. Sequencing the activities
is the same as creating a network diagram, so that has already been done.
The verify scope process is done during the monitoring and controlling
process group and not during the planning process. Since a schedule is a
critical input to risk management you cannot do that yet. This leaves
creating the preliminary schedule and getting the team’s approval.
59. Answer D. PMBOK® Guide p. 195-204. If you read carefully, you will
notice that this question is really asking what you should do after the activity
duration estimating process. The WBS and activity list are created before the
estimate activity durations. The schedule is not finalized until after schedule
compression. Therefore compressing the schedule is done next.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 6 — Schedule Management
Page 255
60. Answer A. PMBOK® Guide p. 205. This question is a bit tricky for two
reasons. First, it looks like the question above, and control the schedule is
the next step in the process. However, you have not yet completed the
develop schedule process because you still need to gain approval from the
stakeholders before proceeding.
61. Answer B. PMBOK® Guide p. 215. In this question you are being asked for
the best way to deliver the project when you are exceeding the deadline. The
first choice is to always maintain the scope and either fast track or crash the
project. Making more activities concurrent is a fancy way of saying fast
track and it is the only viable option.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 256
Cost Management
Overview
The sister process to schedule management is found Slide 187
in chapter seven of the PMBOK® Guide. It is the
cost management knowledge area. Cost management
shares many of the same tools and techniques with
time management. Cost management includes all the
processes involved in planning, estimating,
budgeting and controlling costs so the project is
completed within the approved budget. Image 61
shows the processes involved in cost management.
These processes are primarily concerned with the
cost of resources, although there are several other
factors which must be examined:
Life-cycle costing — Life-
cycle costing is the process by Slide 185
which the product or service of
the project is examined to
determine not only the cost of
the project which will produce
it, but also the costs associated
with operating and disposing of Image 61: The Cost Management Processes
the product, service or result
when its useful life has ended. The project manager has responsibility to
determine the overall costs of both the product and the project.
Opportunity cost — The opportunity cost is the determined by the value of
the next highest alternative. Imagine there are three potential projects (A, B,
and C). You can only choose to do one project and the criteria is selecting
the project with the highest payout. Project A has a payout of 100. Project B
has a payout of 75, and Project C has a payout of 50. Project A would be the
choice with the highest payout, but its opportunity cost would be 75, as the
next highest value is Project B. The concept here is based upon the
understanding of mutually exclusive options, meaning you cannot
simultaneously choose to do Projects A and B. Selecting A means you are
consciously choosing not to do Project B.
Sunk costs — Sunk costs are monies that have already been spent. They
cannot be refunded or returned. It is important that a project manager never
makes future project decisions based on money that has already been spent.
A good project leader must always look to the future and use forecasts for
decisions.
Value Analysis — Sometimes referred to as value engineering. Its goal is
to find a less costly way to do the same work. The required project functions
are systematically identified, and values are then assigned to those functions
and work to provide each function at the lowest possible cost.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 257
Cost Risk — Cost risk is exactly what the name implies. It addresses the
question, “What are the cost-related risks?”
7.1 Plan Cost Management
The PMBOK Guide® is now very consistent. Every Slide 189
one of the knowledge areas begins with a process to
develop a management plan to direct that area. For
cost management, that process is called plan cost
management. Just like all the other “plan” processes,
this one has the goal of producing the “X”
management plan. In this case cost.
The inputs to the plan cost management process are Slide 190
as follows:
.1 Project charter — This is used to provide the
limits of authority, business need, justification,
constraints and assumptions.
Image 62: 7.1 Plan Cost Management
.2 Project management plan — The scope
baseline and other information such as cost, risk, and communication
information.
.3 Enterprise environmental factors — Items such as organizational
culture and structure, resource availability and skills, as well as commercial
information all might be included.
.4 Organizational process assets — This is a standard input to all processes
that can be fairly assumed.
There are three tools and techniques used the plan cost management process.
These include the following:
.1 Expert judgment — As has been previously repeatedly stated, PMI
prefers expert judgment over any other technique. As a project manager,
your first inclination should always be to trust your subject-matter experts.
.2 Data analysis — There are many different ways to analyze the costs of a
project to determine which techniques are best. You might choose a
statistical model, an examination of previous similar projects, or an Excel
spreadsheet.
.3 Meetings — Communication is key to good project management. That
means getting your team together and talking about various issues.
The only output of the plan cost management process is the cost management
plan. The plan defines the rules and processes the project will use to manage
project costs. With cost there are several specific things the team must provide.
These include the units of measure, level of precision and level of accuracy.
Each of these is important in providing information about how the team is
supposed to report out and track project costs.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 258
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 259
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 260
.1 Cost estimates — The cost estimates are the detail cost estimates for the
individual project work packages.
.2 Basis of estimates — The basis of estimates is the explanation and details
for how the estimates were generated. It also includes any constraints and
assumptions that were used to created the estimates. It is similar to the WBS
dictionary or activity attributes.
.3 Project documents updates — The detailed costs estimates require many
project documents to be updated with the newly determined information.
Make sure to specifically examine the assumption log, the lessons learned
register and the risk register.
As the project team goes through the process of estimating costs, it is important
to remember there are two different types of project estimates that may be done.
Rough Order of Magnitude — There is some disagreement in PMI’s Slide 193
resources concerning a ROM estimate. Earlier editions of the PMBOK®
Guide and many other resources suggest a ROM estimate is plus or minus
50% of the likely actual project costs. While the 6th edition of the PMBOK®
Guide says it is –25% to +75% [PMBOK® Guide 6th ed. p. 241]. A ROM
estimate is often used in the early stages of a project when the details are
very vague. A ROM estimate is often used to test the resolve and risk-
tolerance of the project sponsors.
Budget Estimate — The budget estimate, or project budget, is the detailed
project budget. The budget estimate has a variance of +10% to –5%
[PMBOK® Guide 6th ed. p. 241].
7.3 Determine Budget
Slide 194
The next process in the cost management knowledge
area is the determine budget process. Notice the
process is not called the estimate budget process. This
is because estimating has already been completed.
Once the estimates are created the process continues
to determine what the estimates mean. Determine
budget is the process of aggregating the cost estimates
into a single project budget, and then spreading it over
time to generate the cost baseline. The cost baseline
is the basis of cost comparison for the rest of the
project. When graphically represented, the cost
baseline is often represented as an S-curve like what
is usually seen as the result of a logistic regression Image 64: 7.3 Determine Budget
equation. The curve represents the total or cumulative project costs to-date on
one axis and time on the other. Image 65 on the next page shows a sample cost
curve. In addition to understanding the cost curve, there are a number of
accounting terms you need to understand and be able to compare and contrast for
the exam. It is often easier to understand these terms if you imagine working at
the Acme widget factory where you are mass producing widgets, having to deal
with inventory, components, and paying rent.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 261
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 262
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 263
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 264
Slide 197
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 265
®
.3 Project document updates — PMI specifically calls out the updating of
the cost estimates, project schedule and risk register as all three can be
significantly altered by the process of generating a project budget.
Depreciation
The next topic to review for the test is depreciation. Depreciation provides a
series of financial calculations to account for the wearing out of equipment
within the organization. This is important to an organization because of an
earlier topic: assets and liabilities. Two key elements are relevant to understand
this concept. First, you must consider yourself the project leader for an
American organization. Secondly, go back to the scenario of being a project
manager at the widget factory. Imagine purchasing a $100,000 widget stamping
machine. From the federal government’s perspective you still have a $100,000
worth of assets in the organization. However, as soon as you start using that
widget stamping machine, is anyone going to pay you the full $100,000 to take
that machine off your hands? The answer is, of course, “No!” The machine is
now used and worth less. So why should your company continue to pay taxes on
the asset as if it were brand new? It shouldn’t, and depreciation provides the
method to reduce this burden. As you can imagine, most organizations want to
reduce this burden as quickly as possible. The speed at which you can
depreciate an asset is defined by its depreciation schedule. For the PMP® exam,
it is not expected that you are a subject matter expert on depreciation. It is
enough for you to know the basic calculations, the differences between the types,
and that it is governed by the Generally accepted accounting principles
(GAAP). Remember, you always can rely on your team’s expert judgment.
Before discussing the specifics surrounding depreciation, there are a few terms
you need to know. These terms include the following:
Useful life — The useful life represents how long it is until the asset cannot
be used for tax purposes. Most assets have supposed useful lives of five
years or less so this value has little to do with how long the asset is really
used.
Residual value — Also referred to as the scrap or salvage value. The
residual value refers to the supposed value of an asset after its useful life has
been expended. It answers the question how much would the junk dealer pay
for the machine when all they were going to do is melt it down for the metal.
Again, this is a value obtained from your subject matter experts.
Cost — An asset’s cost is how much was paid to obtain the asset.
Depreciation is largely broken into two groups, standard and accelerated. The
difference between these two is that accelerated depreciation makes the asset
worth less, more quickly. For the exam there are four types of depreciation you
must be able to solve. Two methods are standard and two methods are
accelerated.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 266
The first depreciation method is the oldest and easiest. It is called straight line
depreciation (SLD) and it is the first standard depreciation method. SLD is
defined using the formula:
Straight Line
cost – residual value Depreciation
Current Asset Value — useful life
Formula
Let’s go back to our widget factory to get a better understanding. Imagine your
team purchased a widget stamping machine that cost $100,0000. Your
accounting expert tells you the allowed depreciation schedule is five years, and
your machine expert says when the machine is all worn out you can sell it to the
scrap dealer for $25,000. The straight line depreciation formula would be as
follows:
Year 1 = $100,000 — (($100,000—$25,000) / 5) = $85,000
Year 2 = $85,000 — (($100,000—$25,000) / 5) = $70,000
Year 3 = $70,000 — (($100,000—$25,000) / 5) = $55,000
Year 4 = $55,000 — (($100,000—$25,000) / 5) = $40,000
Year 5 = $40,000 — (($100,000—$25,000) / 5) = $25,000
There are three points with regard to this calculation and its results. First, notice
that each annual calculation is run at the end of its year. Second, notice that the
final result at the end of the useful life or schedule period is exactly equal to the
salvage value. This will be the case in all instances except when using the
double declining balance or the units of production method of calculating
depreciation. The final point is that you need to be careful in answering any
depreciation question, as they are unlikely to ask what the value of the asset
would be at the end of the useful life, as that will almost always be the salvage
value. More than likely you will be asked to solve for one of the interim periods.
Imagine being asked—in the case above—what the asset value would be at the
end of year three. The answer would be $55,000.
Production Method of Depreciation
The second standard depreciation method is the units of production (UOP)
method of depreciation. This method is commonly used in manufacturing
environments where the life expectancy of a piece of equipment is best defined
by the number of units it can produce. The formula to calculate the production
method of depreciation is as follows:
( ( ))
cost – residual value Units of
Current Asset Value — Units Produced * estimated units of useful life (production) Production
Formula
In the units of production method of depreciation, our subject matter experts
must provide two additional pieces of information before we can complete the
calculation. To successfully complete the calculation, we need to know how
many units the widget stamping machine can produce before wearing out, and
how many units have been produced. In this case, imagine our subject matter
expert informs us that the stamping machine can produce 10,000,000 widgets
before wearing out and it has produced 750,000 units. With this new piece of
data our calculation now is as follows:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 267
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 268
price minus the salvage value. Third, subtract this new result from the value. Slide 200
Let’s look at an example to better understand SYD. Returning to our widget
factory machine with a purchase price of $100,000, a salvage value of $25,000
and a term of five years, the process would be as follows:
1 + 2 + 3 + 4 + 5 = 15 (the sum of the five year term)
$100,000 — $25,000 = $75,000 (the purchase price—residual value)
Year 1 = $100,000 – (5/15 * $75,000) = $75,000
Year 2 = $75,000 – (4/15 * $75,000) = $55,000
Year 3 = $55,000 – (3/15 * $75,000) = $40,000
Year 4 = $40,000 – (2/15 * $75,000) = $30,000
Year 5 = $30,000 – (1/15 * $75,000) = $25,000
Notice that the SYD method will always conclude at the end of the term exactly
at the salvage value. This is a good test to ensure you have not made a mistake
on the exam.
Take a few moments to complete the depreciation exercise on the following page
before continuing on to the next topic.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 269
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 270
5. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year three using straight line depreciation.
Assuming the asset costs $250,000 to purchase, has a residual value of
$50,000, and is depreciated based on a five year schedule what is the
assessed value?
A. $210,000
B. $175,000
C. $130,000
D. $110,000
6. You are a project manager for a manufacturing company. You are asked to
determine the depreciated value for a piece of equipment using the UOP
method. If the piece of equipment initially cost $1,000,000, has a residual
value of $25,000, has a useful life of 10,000,000 units produced, and has
already produced 1,000,000 units what is its current value?
A. $900,000
B. $902,500
C. $875,000
D. $800,000
7. You are a project manager for a manufacturing company. You are asked to
determine the depreciated value for a piece of equipment using the UOP
method. If the piece of equipment initially cost $750,000, has a residual
value of $40,000, has a useful life of 8,000,000 units produced, and has
already produced 2,500,000 units what is its current value?
A. $375,500
B. $768,250
C. $625,500
D. $528,125
8. You are a project manager for a manufacturing company. You are asked to
determine the depreciated value for a piece of equipment using the UOP
method. If the piece of equipment initially cost $500,000, has a residual
value of $65,000, has a useful life of 7,500,000 units produced, and has
already produced 310,000 units what is its current value?
A. $365,500
B. $532,250
C. $482,020
D. $525,010
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 271
9. You are a project manager for a manufacturing company. You are asked to
determine the depreciated value for a piece of equipment using the UOP
method. If the piece of equipment initially cost $250,000, has a residual
value of $15,000, has a useful life of 5,500,000 units produced, and has
already produced 4,100,000 units what is its current value?
A. $72,652
B. $74,818
C. $76,534
D. $81,225
10. You are a project manager for a manufacturing company. You are asked to
determine the depreciated value for a piece of equipment using the UOP
method. If the piece of equipment initially cost $2,000,000, has a residual
value of $68,000, has a useful life of 15,000,000 units produced, and has
already produced 7,200,000 units what is its current value?
A. $1,072,640
B. $1,528,860
C. $925,310
D. $875,687
11. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year two using DDB. Assuming the asset
costs $100,000 to purchase, has a residual value of $25,000, and is
depreciated based on a five year schedule what is the assessed value?
A. $60,000
B. $36,000
C. $25,000
D. $21,400
12. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year three using DDB. Assuming the asset
costs $250,000 to purchase, has a residual value of $35,000, and is
depreciated based on a five year schedule what is the assessed value?
A. $54,000
B. $64,000
C. $90,000
D. $150,000
13. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year four using DDB. Assuming the asset
costs $650,000 to purchase, has a residual value of $52,000, and is
depreciated based on a five year schedule what is the assessed value?
A. $390,000
B. $234,512
C. $140,375
D. $84,240
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 272
14. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year two using DDB. Assuming the asset
costs $79,800 to purchase, has a residual value of $12,000, and is depreciated
based on a three year schedule what is the assessed value?
A. $26,600
B. $12,000
C. $6,500
D. $18,460
15. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year two using DDB. Assuming the asset
costs $150,000 to purchase, has a residual value of $10,000, and is
depreciated based on a three year schedule what is the assessed value?
A. $50,000
B. $36,450
C. $16,667
D. $10,000
16. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year three using SYD. Assuming the asset
costs $100,000 to purchase, has a residual value of $25,000, and is
depreciated based on a five year schedule what is the assessed value?
A. $55,000
B. $45,000
C. $40,000
D. $35,000
17. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year two using SYD. Assuming the asset
costs $250,000 to purchase, has a residual value of $29,000, and is
depreciated based on a three year schedule what is the assessed value?
A. $65,833
B. $59,561
C. $55,610
D. $49,900
18. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year three using SYD. Assuming the asset
costs $350,000 to purchase, has a residual value of $33,000, and is
depreciated based on a four year schedule what is the assessed value?
A. $48,750
B. $55,800
C. $61,900
D. $64,700
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 273
19. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year two using SYD. Assuming the asset
costs $450,000 to purchase, has a residual value of $41,000, and is
depreciated based on a four year schedule what is the assessed value?
A. $159,900
B. $163,700
C. $165,500
D. $169,200
20. You are a project manager and have been asked to assess the value of an
asset on your project at the end of year three using SYD. Assuming the asset
costs $550,000 to purchase, has a residual value of $62,500, and is
depreciated based on a four year schedule what is the assessed value?
A. $111,250
B. $118,500
C. $125,200
D. $130,500
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 274
2. Answer C. This question requires you to calculate the depreciation using the
formula below then subtracting that result from the purchase price three
times. cost – residual value
Current Asset Value — useful life
3. Answer D. This question requires you to calculate the depreciation using the
formula below then subtracting that result from the purchase price one time.
cost – residual value
Current Asset Value — useful life
4. Answer A. This question requires you to calculate the depreciation using the
formula below then subtracting that result from the purchase price three
times.
cost – residual value
Current Asset Value — useful life
5. Answer C. This question requires you to calculate the depreciation using the
formula below then subtracting that result from the purchase price three
times. cost – residual value
Current Asset Value — useful life
(
Current Asset Value — Units Produced * ( cost – residual value
))
estimated units of useful life (production)
(
Current Asset Value — Units Produced * ( cost – residual value
))
estimated units of useful life (production)
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 275
(
Current Asset Value — Units Produced * ( cost – residual value
))
estimated units of useful life (production)
(
Current Asset Value — Units Produced * ( cost – residual value
))
estimated units of useful life (production)
10. A: The Unit of Production Method, or UOP is defined by first calculating the
amount of value the asset loses with each unit produced. This is done with
the formula below. This result is the multiplied by the number of units
produced giving you the lost value. By subtracting this number from the
original purchase price you obtain the current value.
(
Current Asset Value — Units Produced * ( cost – residual value
))
estimated units of useful life (production)
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 276
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 277
The third and final process found in the cost management knowledge area is the
control costs process. It is one of the most important processes to study for the
PMP® exam because it provides the primary focus on the earned value
technique (EVT) otherwise known as the earned value management system
(EVMS). There are a number of calculations and graphing skills that must be
mastered to successfully understand this process.
The control costs process is concerned with influencing the factors that create
changes to the cost baseline, ensuring requested changes are agreed upon,
managing the actual changes as they occur, and assuring that potential cost-
overruns do not exceed the authorized funding, periodically and in total for the
project. As with any of the processes which have the word “control” in them,
control costs is part of integrated change control.
Most of this section will focus on EVT, but let’s begin with the inputs, tools and
techniques, and outputs of the control costs process. The inputs to the control Slide 202
costs process include:
.1 Project management plan — Within the project management plan there
are three components which are critical to controlling project costs. The first
is the cost management plan which describes how the project costs are
managed and controlled, and the second is the cost baseline, which provides
the primary point of comparison for the actual result. The third and final
component is the performance measurement baseline.
.2 Project documents — Although you might need to examine a lot of
different project documents as you go through the process of controlling
costs, the one PMI® specifically calls out is the lessons learned register
because the team uses it to see where other projects have had trouble
controlling costs and how they solved specific cost problems.
.3 Project funding requirements — The funding requirements define how
much money is needed to complete the project, and when the money is
required.
.4 Work performance data — The work performance information explains
which deliverables have started, their progress, and which deliverables have
finished. It also includes information about incurred actual costs, authorized
costs, and estimates for both schedule and cost completion.
.5 Organizational process assets — Many organizations have processes,
policies and templates that deal with project cost control. All of these should
be included if they are available.
The tools and techniques used in the control costs process include the following:
.1 Expert judgment — To accurately control project costs, the team needs
to have real world experience. It is that expert judgment that PMI® calls on
to ensure the team has success.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 278
Data analysis — There are a number of data analysis techniques the team
might use to control costs, but PMI® specifically calls out four that are
critical. For the exam it is absolutely critical that you know these cold. They
include:
Earned value management — EVT or EVMS is PMI’s preferred
method for measuring progress on a project because of its
quantitative nature and focus on future predictability.
Variance analysis — Variance analysis is largely tied to earned
value. It is the process of comparing your actual results to what you
promised and then understanding the difference.
Trend analysis — Trend analysis involves understanding the
collective movement of the project costs, where they have been and
where they are going. A big part of this is forecasting the future
project costs.
Reserve analysis — If you recall from earlier in our course, reserves
come in two forms: contingency and management reserves. Here we
are specifically looking to ensure we have set aside enough money to
complete the project should the unexpected occur.
.3 To-complete performance index — The TCPI is the calculated projection
of cost performance that must be achieved on the remaining work to meet a
specified goal. The TCPI is an earned value calculation.
.4 Project management information system— Because of the number of
calculated fields, often project management software makes the process of
controlling costs much easier.
The outputs to the control costs process include the following:
.1 Work performance information — The primary work performance
measurements are all earned value measures such as CV, SV, CPI, and SPI
done at the control account level within the WBS.
.2 Cost forecasts — The budget forecast is also an earned value calculation
using the EAC value.
.3 Change requests — The ongoing analysis of project performance often
causes stakeholders to request changes in one or more aspect.
Organizational process assets updates — Specific updates might include
causes of variances, corrective actions taken with explanations, or other
types of lessons learned.
.4 Project management plan updates — Your measurements might cause
updates to the cost baseline, the cost management plan, and the performance
measurement baseline.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 279
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 280
Slide 203
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 281
is equal to that week. This allows us to now go through the analysis using
the $1,000 instead of always referring back to the one week. The planned
value provides the baseline against which all comparisons are made. In a
perfectly run project, both the AC and EV lines appear exactly on top of the
PV line. Also notice that the BAC is at the end of the PV line at a point
where it has flattened out. This flattening occurs because the project reached
its total budget without being completed so time continues but the PV line
remains flat. The PV is another way of saying the cost baseline or budget. It
also can be used to represent the amount of work to be completed in any
period.
AC — The actual costs is the easiest of the earned value variables. It
represent the actual money spent on the project.
EV — The earned value is often the most difficult variable for exam
candidates to learn. However, it is also the most important of the three major
variables (AC, EV and PV) because all the major calculations begin with the
earned value. The earned value represents the scope leg of the triple
constraints. It is the amount of work product that has been produced by the
project. The trick is converting work into dollars. The major requirement to
accomplish this feat has already been achieved. The key element to
reporting progress using earned value is progress must be reported at the
work package level of the WBS. Once the initial budget for a work package
is established so is its value because they are the same thing. If you planned
on spending $1,000 in total on a work package then the work package is
worth $1,000. If you are 50% done with the work package you have earned
$500 in value. Finally, a work package can NEVER be worth more than you
planned on it costing to produce.
EAC — The estimate at completion is one of three forecasts that is
calculated using the three base variables (AC, EV and PV). It answers the
question how much in TOTAL are we now expecting the project to cost. It
includes an estimate of the remaining work costs (ETC) and the already
accrued actual costs.
The discipline of earned value is rooted in four calculations which are found in
Image 68. This image is the best way of memorizing the basic earned value
Slide 204
Page 282
calculations. Begin by noticing the three major earned value variables discussed
above (AC, EV and PV) appear at the top of the graphic in alphabetical order.
All of the calculations begin in the middle with the Earned Value (the name of
the technique) and work outward. On the far left are two variables that begin
with the letter C. These variables measure cost performance. On the far right
side are two variables which begin with the letter S. These measure schedule
performance. The two letter calculations (CV and SV) are variances which show
the actual over or under performance in currency terms. The three letter
calculations (CPI and SPI) are performance indexes which measure the variances
as a percentage. As you will see, the performance indexes are usually more
valuable than the variances. The four basic earned value equations defined by
Image 68 are:
CV = EV — AC
CPI = EV / AC
SV = EV — PV
SPI = EV / PV
To read these calculations an exam candidate only needs to remember a few
simple rules. These rules are:
If it is a two letter abbreviation the target is zero.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 283
9%), and a CPI of 1.06 means the project is 6% under budget. The same logic
works for the schedule performance index. An SPI of .88 means the project is
12% behind schedule and an SPI of 1.04 means the project is 4% ahead of
schedule. Both of these statistics are incredibly useful in telling the project
manager where the project is right now. However, neither tells the PM how the
project is going to end. To provide that information the PM must turn to the
earned value forecasting measures.
Earned Value Forecasting
There are three primary forecast values which a project manager might need to
calculate on any project, and with each value there are multiple methods to
obtain an answer. For the certification exam it is very important that you
understand each of these methods and when they should be used.
ETC — Estimate to complete answers the question how much MORE money is Estimate to
the project going to take to complete. There are four methods which may be used Complete
to calculate ETC. Each method is based upon a different assumption. These Formulas
include the following:
ETC based on new estimate — There is no formula if the Estimate to Slide 205
Complete is being based upon an entirely new estimate. The project
manager and the team simply develop a new estimate. This method is used
whenever the original estimate is believed to be flawed beyond recovery.
This method is not often found on the exam beyond the term and explanation
because it is impossible to develop a mathematical question when the new
estimate is developed by an external process.
ETC based on atypical variances — Atypical variances means the
variances are not commonly occurring. For the project manager, it means
whatever caused the variances is not expected to continue, and future
forecasts can be based on whatever the original budget was. The formula for
an ETC with atypical variances is ETC = BAC-EV. If you examine the
definitions provided a few pages earlier, you will notice this is the same
equation to define the remaining work. It is a fancy way of saying you will
produce the remaining work for exactly what you said it would cost. This
equation might be on the exam, but it is not the most likely. Watch for the
phase “atypical variances” on the exam to clue you in.
ETC based on typical variances — An estimate to complete based upon
typical variances is the most common ETC seen on the exam. It assumes
that whatever has been the rate of progress will continue in the future. In
most cases it means whatever has been causing you problems will keep
causing you problems. The formula to calculate the ETC using typical
variances is ETC = (BAC-EV)/CPI. Notice this equation also makes use of
the mathematical expression for remaining work (BAC-EV), but it has been
factored by the actual performance rate.
ETC based on both the CPI and SPI — The final method for calculating
the estimate to complete makes use of both the cost performance index and
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 284
the schedule performance index. This method assumes both a negative cost
performance to-date and requirement to hit a specific target date. This
method is most commonly used when the project schedule is a driving force
impacting the ETC. The formula to calculate the ETC using both the CPI
and SPI is ETC = (BAC-EV)/(CPI*SPI). This formula makes use of the
mathematical expression for remaining work (BAC-EV) and the Critical
Ratio (CPI*SPI).
The next set of calculations used the underlying assumptions of the same four Estimate at
ETC calculations, and simply adds the actual costs to date to them. This creates Completion
the Estimate At completion or EAC. The EAC answers the question, “How Formulas
much in TOTAL will the project cost?”. The calculations for EAC are as
follows:
EAC using a new estimate — As with the ETC, this calculation is unlikely Slide 206
to be on the exam past a definitional question because it is impossible to
develop a mathematical question when the formula is based outside the
question parameters. The formula for the EAC when an entirely new ETC is
developed is EAC = AC + ETC.
EAC assuming atypical variances — The second possible calculation for
Estimate at completion takes the remaining current budget and adds it to the
actual costs to-date. It assumes that whatever has been causing problems on
the project will not continue to do so in the future. As with the ETC, this
method is assuming atypical variances. The formula for the atypical
variance EAC is EAC = AC + (BAC-EV).
EAC Assuming typical variances — The EAC method that assumes typical
variances makes use of the cost performance index (CPI) to factor the
remaining work based on actual project cost performance and then adds the
costs to date. It assumes the rate of cost performance achieved to date will
remain consistent in the future. The formula for EAC assuming typical
variances is EAC = AC + ((BAC-EV)/CPI).
EAC using both CPI & SPI — The EAC using the critical ratio (CPI*SPI)
makes the same assumption as the ETC using the critical ratio, that it is
critical to hit a specific schedule target previously defined. The formula for
the EAC using the critical ratio is EAC = AC + ((BAC-EV)/(CPI*SPI)).
The final cost forecast calculation you must learn for the PMP® exam is the to- To-Complete
complete performance index or TCPI. The TCPI is a calculated projection of Performance
the cost performance, which must be achieved on the remaining work to hit a Index
desired target. In the simplest terms, the TCPI is the remaining work divided by Formulas
the remaining funds . Typically, the EAC target is either the BAC or a new
EAC. The TCPI is often used when the original budget is recognized as
unrealistic and a new EAC is developed. The formula for the TCPI — when the
goal is to hit the original budget—is as follows:
TCPI = (BAC-EV) / (BAC-AC) Slide 207
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 285
If the goal is to achieve a new target based upon a specified EAC, the formula
for TCPI is as follows:
TCPI = (BAC - EV) / (EAC - AC)
In addition to the earned value management calculations specified which target
project costs, earned value provides calculations that address forecasting the
project schedule. In the PMBOK® Guide these calculations are discussed in the
schedule management knowledge area, but we list them here to consolidate all
the earned value discussion to a single location. The two equations used to
forecast schedule in earned value management are as follows:
Schedule Est. = Original Project Duration / SPI (This is often used as a
minimum schedule estimate)
Schedule Est. = Original Project Duration / (CPI * SPI) (This is often
used as the maximum schedule estimate to allow for a range)
The next calculation and definition you must know for the exam is variance at Variance at
completion or VAC. VAC is defined as how much over or under budget the Completion
project will be at the end. The formula used to calculate VAC is as follows: Formula
BAC—EAC
With the 6 edition of the PMBOK® Guide introduces the concept of earned
th
schedule to earned value. The earned schedule replaces the schedule variance
used in earned value. The team still looks for zero as the break between being
behind and ahead of schedule. Earned schedule theory also provides formulas
for forecasting the project completion date, using the earned schedule, actual
time and estimated duration. However, it also introduces a number of new
variables. It is important that you understand these new variables.
Slide 208-
Schedule at completion or SAC — This is the original planned completion 210
duration of the project.
Earned schedule or ES — The earned schedule is the duration from the
beginning of the project to the date on which the planned value is supposed
to equal to the budget at completion.
Actual time or AT — This is the duration from the beginning of the project
to status date.
Time variance or TV — The TV is a measure of schedule performance in
time units rather than cost units and is defined by the formula:
Time
TV = ES – AT Variance
Formula
The time variance uses zero as its measurement mark. If this value is
negative the project is behind schedule, and if it is positive it is ahead of
schedule. This is exactly the same as the schedule variance time. However, it
is technically not the same as the schedule variance.
Time estimate at completion or TEAC — The TEAC represents the
forecast of time at completion and is similar to EAC. It uses the same basic
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 286
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 287
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 288
7. Which of the following variables represents the formula: Earned Value minus
Planned Value?
A. SPI
B. CV
C. CPI
D. SV
8. Your boss enters your office and asks for the cost variance on your project
that has an AC of $290, a PV of $300, and an EV of $270. What value do
you provide them?
A. -30
B. 0.95
C. 0.92
D. -20
9. Your boss enters your office and asks for the cost variance on your project
that has an AC of $400, a PV of $405, and an EV of $391. What value do
you provide them?
A. -5
B. 1.30
C. 1.08
D. -9
10. You are preparing your monthly status report for your project. Your project
had an original budget of $150,000 and an original schedule of 18 months.
You currently have spent $65,000 and had budgeted to spend $60,000. You
have produced $55,000 worth of product. Your Vice President is very eager
to review your report as your project is important to the company’s success.
What is the Cost Variance for the project?
A. -10,000
B. -5,000
C. 0.85
D. 0.92
11. You are preparing your monthly status report for your project. Your project
had an original budget of $950,000 and an original schedule of 11 months.
Your currently have spent $400,000 and had budgeted to spend $405,000.
You have produced $391,000 worth of product. Your Vice President is very
eager to review your report as your project is important to the company’s
success. What is the Schedule Variance for the project?
A. -9,000
B. 0.98
C. 14
D. -14,000
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 289
12. You are leading a project that is a low profile project for the organization.
The project was originally scheduled to take 10 months at a total cost of
$70,000. Your title is that of a project coordinator, and you often have to
struggle to get the resources you need. You have already spent $40,000 even
though you were only scheduled to spend $37,500. If you have already
produced $37,500 worth of work what is your current SPI?
A. -2.50
B. 0
C. 1.00
D. It cannot be determined
13. You are the program manager for a large software development company.
You are currently leading a project that has an original budget of $35,000 and
an original schedule of seven months. Currently the project has delivered on
$27,500 of the project. It has also spent $29,000. If the project was forecast
to spend $30,000 to date, what is the project’s SPI?
A. 0.95
B. 0.92
C. 0.87
D. -1.5
14. What is the Critical Ratio for a project that had an original budget of
$25,000, an original schedule of ten months, actual costs of $10,000, has
produced $9,000 worth of work, and was scheduled to have spent $10,000?
A. 0.90
B. -1
C. 0.81
D. It cannot be determined
15. What is the Critical Ratio for a project that had an original budget of
$75,000, an original schedule of twelve months, actual costs of $45,000, and
has produced $50,000 worth of work?
A. 1.11
B. 1.25
C. 1.39
D. It cannot be determined
16. What is the Critical Ratio for a project that had an original budget of
$950,000, an original schedule of eleven months, actual costs of $400,000,
has produced $391,000 worth of work, and was scheduled to have spent
$405,000?
A. 0.94
B. 0.98
C. 0.97
D. It cannot be determined
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 290
17. You are a project manager working on a project that had an original budget
of $30,000 and was forecast to take eight months. The project currently has
delivered on $18,000 worth of the project and has spent $22,500. If the
variances to date are believed to be atypical and the project had planned to
spend $20,000 what is the estimate at completion?
A. $34,500
B. $37,500
C. $42,670
D. It cannot be determined
18. You are a project manager working on a project that had an original budget
of $250,000 and was forecast to take 54 weeks. The project currently has
delivered on $90,000 worth of the project and has spent $100,000. If the
variances to date are believed to be atypical and the project had planned to
spend $80,000 what is the estimate at completion?
A. $277,780
B. $260,000
C. $246,910
D. It cannot be determined
19. You are a project manager working on a project that had an original budget
of $300,000 and was forecast to take seventy-two weeks. The project
currently has delivered on $65,000 worth of the project and has spent
$100,000. If the variances to date are believed to be atypical and the project
had planned to spend $75,000 what is the estimate at completion?
A. $461,540
B. $532,540
C. $335,000
D. $235,000
20. You are a project manager working on a project that had an original budget
of $300,000 and was forecast to take seventy-two weeks. The project
currently has delivered on $65,000 worth of the project and has spent
$100,000. If the variances to date are believed to be typical and the project
had planned to spend $75,000 what is the estimate at completion?
A. $335,000
B. $532,540
C. $235,000
D. $461,540
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 291
21. You are a project manager working on a project that had an original budget
of $500,000 and was forecast to take eight months. The project currently has
delivered on $35,000 worth of the project and has spent $50,000. If the
variances to date are believed to be typical and the project had planned to
spend $40,000 what is the estimate at completion?
A. $515,000
B. $816,330
C. $465,000
D. $714,290
22. You are a project manager working on a project that had an original budget
of $150,000 and was forecast to take eighteen weeks. The project currently
has delivered on $53,000 worth of the project and has spent $61,000. If the
variances to date are believed to be typical and the project had planned to
spend $57,250 what is the estimate at completion?
A. $172,640
B. $158,000
C. $186,490
D. $150,000
23. You are working on a project that had an original budget of $200,000 and
was originally forecast to take sixty weeks. As the project coordinator, you
have been somewhat frustrated with your project’s performance. To date you
have delivered on $79,000 of the project’s deliverables while you had
budgeted $93,000 and actually spent $98,000. The project has been
progressing consistently and you expect the trends the project has shown to
continue. Based upon this information, what do you expect the project’s
estimate at completion to be?
A. $219,000
B. $248,000
C. $292,000
D. $256,000
24. You are currently leading a project that had an original budget of $300,000
and an original schedule of twenty-seven weeks. You currently have spent
$100,000 and are currently over budget by $15,000. Your boss comes into
your office and wants to discuss your project. Specifically, she wants to
know how much more money it is going to take to complete the project.
Assuming you have completed $ 78,000 of the deliverables and you expect
the performance trends to not continue what do you tell her?
A. $222,000
B. $285,000
C. $419,000
D. $322,000
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 292
25. You are preparing your monthly status report for your project. Assuming the
variances to date are typical, what would the ETC be assuming your project
was budgeted to cost $125,000 and take twelve months and if you have
actually spent $42,000, have produced $37,500 worth of product and were
scheduled to have spent $39,000?
A. $87,500
B. $129,500
C. $140,000
D. $98,000
26. You are preparing your monthly status report for your project. Assuming the
variances to date are typical, what would the estimate to complete the project
be assuming your project was budgeted to cost $90,000 and take thirty-six
weeks if you have actually spent $50,000, have produced $65,000 worth of
product and were scheduled to have spent $60,000?
A. $25,000
B. $64,000
C. $69,000
D. $19,000
27. Which of the following is the calculated projection of cost performance that
must be achieved on the remaining work to meet a specified management
goal?
A. CPI
B. TCPI
C. EAC
D. ETC
28. You are asked to produce an estimate of the performance rate that must be
achieved to meet the targeted budget at completion. If the project currently
has an EV of 18, a PV of 20 and an AC of 22.5. If your original budget was
30 and you are using the EAC method, what estimate do you provide?
A. 0.80
B. 6.40
C. 0.81
D. 0.78
29. You are asked to produce an estimate of the performance rate that must be
achieved to meet the targeted budget at completion. The project currently
has an EV of 27.5, a PV of 30 and an AC of 29. If your original budget was
35 and you are using the EAC method, what estimate do you provide?
A. 0.21
B. 0.91
C. 0.95
D. 0.72
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 293
30. You are asked to produce an estimate of the performance rate that must be
achieved to meet the targeted budget at completion. The project currently
has an EV of 18, a PV of 17.5 and an AC of 20. If your original budget was
55 and you are using the EAC method, what estimate do you provide?
A. 0.90
B. 1.03
C. 0.93
D. 1.50
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 294
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 295
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 296
21. Answer D. PMBOK® Guide p. 261-267 – The key to this question is the
fact that the variances are believed to be typical. This means whatever is
happening will continue to happen at approximately the same rate. With this
piece of information you should have known to use the following formula:
EAC = AC + ((BAC - EV)/CPI).
22. Answer A. PMBOK® Guide p. 261-267 - The key to this question is the fact
that the variances are believed to be typical. This means whatever is
happening will continue to happen at approximately the same rate. With this
piece of information you should have known to use the following formula:
EAC = AC + ((BAC - EV)/CPI).
23. Answer B. PMBOK® Guide p. 261-267 - The key to this question is the fact
that the variances are believed to be typical. This means whatever is
happening will continue to happen at approximately the same rate. With this
piece of information you should have known to use the following formula:
EAC = AC + ((BAC - EV)/CPI).
24. Answer A. PMBOK® Guide p. 261-267 - To correctly answer this question
you must first determine exactly what is being asked. In this question you are
being asked for an estimate to complete the project (ETC). In this case you
are told that the variances that have been seen to date are not typical.
Therefore, your correct formula is ETC = BAC – EV.
25. Answer D. PMBOK® Guide p. 261-267 - To correctly answer this question
you must first determine exactly what is being asked. In this question you are
being asked for an estimate to complete the project (ETC). In this case you
are told that the variances that have been seen to date are typical. Therefore,
your correct formula is ETC = (BAC – EV) / CPI.
26. Answer D. PMBOK® Guide p. 261-267 - To correctly answer this question
you must first determine exactly what is being asked. In this question you are
being asked for an estimate to complete the project (ETC). In this case you
are told that the variances that have been seen to date are typical. Therefore,
your correct formula is ETC = (BAC – EV) / CPI.
27. Answer B. PMBOK® Guide p. 261-267 – The To-Complete Performance
Index is the calculated projection of cost performance that must be achieved
on the remaining work to meet a specified management goal, such as the
BAC or the EAC.
28. Answer A. PMBOK® Guide p. 261-267 – This question requires you to
calculate the TCPI or the To-Complete Performance Index using the EAC
formula. This formula is: (BAC – EV) / (EAC – AC). The EAC is
calculated using the CPI method.
29. Answer C. PMBOK® Guide p. 261-267 – This question requires you to
calculate the TCPI or the To-Complete Performance Index using the EAC
formula. This formula is: (BAC – EV) / (EAC – AC). The EAC is
calculated using the CPI method.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 297
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 298
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 299
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 300
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 301
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 302
25. If you have a burn rate of .92 which of the following is true?
A. The AC is 110 and the EV is 120
B. The AC is 120 and the EV is 110
C. The AC is 120 and the PV is 110
D. The EV is 110 and the PV is 120
26. If you have a burn rate of 1.21 which of the following is true?
A. The AC is $84,000 and the EV is $102,000
B. The AC is $102,000 and the EV is $84,000
C. The AC is $84,000 and the PV is $102,000
D. The EV is $102,000 and the PV is $84,000
27. Your manager comes into your office to discuss a project you are leading. In
your latest status report you indicated a burn rate of 0.86. If you have spent
$192,000 what else do you know to be true?
A. You had budgeted to spend $165,000
B. Your SPI is 0.86
C. You have produced $165,000 of work
D. Your cost variance is less than your schedule variance
28. You have been assigned a project to deploy new desktop computers
throughout your organization. Your assignment to the project has occurred
after the project estimates have been completed and baselines have been
established. You are concerned that the cost estimates are unrealistic based
upon your previous experience. Which of the following is the best thing to
do?
A. Determine if the contingency budget will cover the additional costs
B. Bring your project team together to determine the best solution
C. Meet with the project sponsor to examine possible solutions
D. Meet with the people who generated the cost estimate
29. In preparing your monthly status report you determine that your project is
behind schedule. You believe the variances are typical and using Earned
Value Analysis you determine the project is 16% behind schedule. Your boss
has offered to provide access to an additional six resources, but you are
concerned about the impacts of Brooke’s Law and also not providing
appropriate reward for the cost of the additional resources. Your concerns
are best expressed by which of the following?
A. Crashing
B. Parkinson’s law
C. Pareto principle
D. Law of diminishing returns
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 303
30. You have been asked to take over a project that senior management feels is
critical to the organization, but has also determined to be failing. Originally,
the project had a budget of $550,000. The project has only produced 2/3 of
the required deliverables and has already spent $500,000. The $500,000
expenditure represents which of the following?
A. Capital expenditure
B. Sunk cost
C. Indirect expenditure
D. Direct cost
31. In which of the following steps would a project manager allocate overall cost
estimates to the individual activities, tasks, deliverables or work packages to
establish a performance measurement baseline?
A. Estimate costs
B. Determine budget
C. Cost baselining
D. Cost control
32. You are part of a project management office within a large organization. All
of the organization’s resources are currently allocated to projects. A new
project has just been brought to the PMO by senior management that must be
given priority. To complete this new project you will have to take resources
from the other projects which will cause them to be delayed. From which of
the following projects should you take the resources?
A. Project A with 17 resources, a NPV of $225,000, and no change
management plan.
B. Project B with nine resources, an IRR of 19%, BCR of 1.4, and no
project cost control plan.
C. Project C with seven resources, a benefit cost ratio of 1.2, and no
project charter.
D. Project D with 11 resources, capital expenses of US $195,000, a burn
rate of 1.25 and no schedule management plan.
33. Which of the following is not a tool or technique used in the control costs
process?
A. Forecasting
B. Variance analysis
C. Project management software
D. Reserve analysis
34. Which of the following is a tool or technique used in the control costs
process?
A. Forecasting
B. Funding limit reconciliation
C. Reserve analysis
D. Parametric analysis
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 304
35. Which of the following is not an output of the Control Costs Process?
A. Work performance measurements
B. Budget forecasts
C. Approved changes
D. Change requests
36. Parametric estimating:
A. Uses project characteristics in a mathematical model
B. Uses an algorithm to calculate project costs
C. Uses top-down estimating
D. Represent the most common estimating technique
37. Analogous estimating:
A. Works best when done from the bottom up
B. Uses actual costs from previous projects
C. Can be done at any time in the project
D. Is frequently used in the late planning phase of a project
38. An executive is evaluating project A with BCR of 1.2 and project B with an
NPV of $380,000. The two projects are mutually exclusive. The cost of
choosing one of these projects and not obtaining the benefits of the other is
called:
A. Sunk cost
B. Lost cost
C. Opportunity cost
D. Portfolio cost
39. Jim and Sally are two project managers working for a large manufacturing
organization who are discussing Jim’s latest project. Sally comments that it
is important that Jim consider both the operational and maintenance costs of
the product being created in his project decisions. To what is Sally referring?
A. Jim’s professional responsibility
B. Total project costing
C. Parametric estimating
D. Life cycle costing
40. You are in the process of establishing the cost performance measurement
system you will be using for a software development project. Which of the
following methods would be best?
A. Ask each resource for a percent of the deliverables that are complete
and forecast future performance.
B. Use the physical percent complete of the work product to calculate
earned value and then forecast future performance.
C. Use a 0% / 100% rule of reporting deliverable completeness and
forecast future performance.
D. Focus on the amount of money budgeted and actually spent in each
period and then forecast future performance.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 305
41. You are the project manager on a project that has a CPI of 0.92. What do
you know?
A. The project is currently 8% behind schedule.
B. When the project is delivering 92% of the work product.
C. The project will end up being 92% over budget.
D. The project is currently 8% over budget.
42. You are the project manager on a project that has a cost performance index of
0.79. What does this mean?
A. The project is only producing 79 cents of value for every dollar
invested.
B. The project is 21% behind schedule.
C. The project is 79% over budget.
D. The project is likely to cost 79% more than planned.
43. Your project has a CPI of 0.87. What does this mean?
A. You are behind schedule.
B. You are 13% under budget.
C. It is costing you more to produce each deliverable than forecasted.
D. You are 87% over budget.
44. Your project has a SPI of 0.91 what does this tell you?
A. You will likely deliver the project 9% behind schedule.
B. You are currently 9% behind schedule.
C. Your project has achieved 91% of its objectives.
D. You are 9% over budget.
45. You are the project manager on a large road project that has a current CV of
$176,000. What does this mean?
A. The project is $176,000 over budget.
B. The project is $176,000 ahead of schedule.
C. The project is $176,000 behind schedule.
D. The project is $176,000 under budget.
46. You are leading a project that is using resources in four different locations.
Management has mandated that you use Earned Value Analysis. If the
project is a software development project which of the following would not
be necessary to determine the initial cost baseline?
A. WBS
B. Network diagram
C. Scope change management plan
D. Risk register
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 306
47. You are the project manager for a major road project. You have been asked
to estimate the cost for your project using the formula of number of miles of
road multiplied by the number of lanes multiplied by the cost per lane mile
of road. What kind of estimate is this?
A. Parametric estimate
B. Analogous estimate
C. Rough order of magnitude estimate
D. Bottom up estimate
48. In which of the project management process groups would you make a ROM
estimate?
A. The planning process group
B. The executing process group
C. The monitoring and controlling process group
D. The initiating process group
49. You have been asked to choose between two different projects that your
organization might undertake. Which of the following would not be grounds
for comparison?
A. BCR
B. Marginal analysis
C. IRR
D. NPV
50. Which of the following is a tool for determining when investing any
additional money will not produce an equivalent return?
A. Marginal analysis
B. Benefit cost ratio analysis
C. Cost benefit ratio analysis
D. Internal rate of return analysis
51. You have been asked to choose one of three projects. Project A has an NPV
of $75,000. Project B has an NPV of $81,000. Project C has an NPV of
$62,500. What is the opportunity cost of selecting Project B?
A. $81,000
B. $62,500
C. $75,000
D. $6,000
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 307
52. You are placed in charge of a software development project. As part of your
team building you determine that your resources do not have all the
necessary skills. To improve their skills you decide to send them to an
external class to obtain the required skills. Which of the following would
best categorize this expense?
A. Indirect cost
B. External cost
C. Fixed cost
D. Direct cost
53. You are meeting with the project sponsor. They voice concern about the
setup costs of the project escalating. You assure them that this is not an
issue. Why?
A. Because good project management will ensure the costs do not
escalate.
B. Because project setup represents an opportunity cost.
C. Because project setup represents an overhead cost.
D. Because project setup represents a fixed cost.
54. You have been asked to determine a less costly way to complete the same
work. Which of the following tools would you use?
A. Value analysis
B. Six sigma analysis
C. Marginal analysis
D. Benefit cost analysis
55. When working with earned value management which primary term
represents the actual output or work product?
A. Planned value
B. Earned value
C. Actual cost
D. CPI
56. You have been asked to select one of three projects for your organization
using NPV. Project A has an NPV of $23,000 and will take two years to
produce. Project B has an NPV of $41,000 and will take three years to
produce, and Project C has an NPV of $35,000 and will take three years to
produce. Which project would you select?
A. Project A
B. Project B
C. Project C
D. It cannot be determined
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 308
57. You are leading a project for an external customer. The client representative
asks that you provide a written cost estimate that is 25% higher than your
estimate of the project’s cost. They justify the request by telling you their
company budgeting process requires managers to estimate pessimistically to
ensure enough money is allocated for projects. What is the best way to
handle this?
A. Add the 25% as a lump sum contingency to handle project risks.
B. Add the 25% to the cost estimate by spreading it evenly across all
project activities.
C. Create one cost baseline for budget allocation and a second one for
the actual project management plan.
D. Ask for information on risks that would cause your estimate to be too
low.
58. What type of cost is team development?
A. Direct
B. Indirect
C. Required
D. Fixed
59. Value analysis is performed to get:
A. The team to buy into the project.
B. More value from the cost analysis.
C. A less costly way of doing the same work.
D. Management to buy into the project.
60. You have been assigned as the project manager for a medium-sized
information technology project. Upon receiving your charter, the project
sponsor asks if the project can be completed within the target budget. Which
of the following is the best way to handle this?
A. Build an estimate in the form of a range of possible results.
B. Ask the team members to help estimate the cost based on the project
charter.
C. Based on the information you have, calculate a parametric estimate.
D. Provide an analogous estimate based on past history.
61. Early in the life of your project, you are having a discussion with the sponsor
about which estimating techniques should be used. You want a form of
expert judgment, but the sponsor argues for analogous estimating. It would
be best to:
A. Agree to analogous estimating, as it is a form of expert judgment.
B. Suggest life cycle costing as a compromise.
C. Determine why the sponsor wants such an accurate estimate.
D. Try to convince the sponsor to allow expert judgment because it is
typically more accurate.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 309
62. You have just completed the initiating processes of a small project and are
moving into project planning when a project stakeholder asks you for the
project’s budget and cost baseline. What should you tell her?
A. The project budget can be found in the project charter, which has just
been completed.
B. The project budget and baseline will not be finalized and accepted
until planning processes are completed.
C. The project management plan will not contain the project’s budget
and baseline; this is a small project.
D. It is impossible to complete an estimate before the project
management plan is created.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 310
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 311
10. Answer D. Life cycle costing is often combined with value engineering to
improve decision making, reduce costs and execution time, and to improve
the quality of the project.
11. Answer A. PMBOK® Guide p. 235 – Although it is not formally called out
in the cost management processes, the PMBOK® Guide specifies that the
cost management plan is initially produced as part of the development of the
project management plan.
12. Answer B. Price is made up of the cost of the item plus the desired profit.
Cost simply represents what the item took to produce in monetary terms.
13. Answer B. PMBOK® Guide p. 241. Early in a project’s life cycle you are
not likely to have a lot of detailed information. Therefore, you need to
provide a wide ranging estimate. The Rough Order of Magnitude estimate
does just that. It is a range of +75% to –25% of the original estimate.
14. Answer D. PMBOK® Guide p. 241. The definitive estimate is the final
project estimate given to all management and resources. It is never a single
number and always represented by a range. The correct range for a definitive
estimate is +10% to –5%.
15. Answer C. PMBOK® Guide p. 241. Remember, according to PMI®, you
never give a single number. You always provide a range. In this case that
fact excludes two of the answers. Since you are in the execution phase of the
project you are using the definitive estimate which is +10% to –5%. That
provides a range of 261,250 to $302,500.
16. Answer D. PMBOK® Guide p. 241. Remember, according to PMI®, you
never give a single number. You always provide a range. In this case that
fact excludes two of the answers. Since you are in the initiation phase of the
project you are using the ROM estimate which is +75% to –25% . That
provides a range of 375,000 to $875,000.
17. Answer B. PMBOK® Guide p. 241. Remember, according to PMI®, you
never give a single number. You always provide a range. In this case that
fact excludes one of the answers. Since you are in the planning phase of the
project you are using the definitive estimate which is +10% to –5%. That
provides a range of $237,500 to $275,000.
18. Answer D. PMBOK® Guide p. 171 – Enterprise environmental factors are
factors or conditions that exist within the area that the project resides. When
discussing the factors for the estimate cost process, PMI® specifically calls
out two:
Market conditions
Published commercial information
Exchange rates and inflation
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 312
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 313
28. Answer B. Your best answer is to always work with your project team first
to determine alternatives. Remember, the PMI® standards are all about
examining alternatives and presenting recommendations. You would not
want to meet with anyone else until you have met with your team.
29. Answer D. The law of diminishing returns argues that in every scenario
there is a point where spending money will not get an equal amount of value
in return. The rest of the question is simply subterfuge and should be
ignored.
30. Answer B. Sunk costs represent monies that have already been spent. They
cannot be recovered. They are important to project managers because many
organizations make project decisions based upon the money that has already
been spent. This often leads to good money following bad.
31. Answer B. PMBOK® Guide p. 248-256 – Determine budget involves
aggregating the various estimated costs for all the tasks, activities,
deliverables, and/or work packages to establish a total cost baseline for the
project.
32. Answer C. Each of these projects is in trouble, but only one of them should
have never been started. That is project C. Project C does not have a project
charter and should have never been started. Therefore, it should be the first
place you go for resources. Remember, you never do a project without a
charter no matter what the numbers say.
33. Answer D. PMBOK® Guide p. 257 – The tools and techniques used in the
control costs process include:
Expert judgment
Data analysis
To-complete performance index (TCPI)
Project management information system
34. Answer A. PMBOK® Guide p. 167 – The tools and techniques used in the
control costs process include:
Expert judgment
Data analysis
To-complete performance index (TCPI)
Project management information system
35. Answer C. PMBOK® Guide p. 167 – The outputs from the cost control
process include:
Work performance measurements
Cost forecasts
Change requests
Project management plan updates
Project document updates
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 314
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 315
56. Answer B. This is a trick question of sorts. The question provides both the
term of the project and the NPV. This would seem to indicate that you must
do something with the term. However, the NPV takes into account the
project term making this information unnecessary. All you have to do is
select the largest value.
57. Answer D. This is an ethics question. PMI’s standards are very clear in this
area. Although it is a largely western way of thinking about this topic you
should only present the actual estimate.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 7 — Cost Management
Page 316
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 317
Quality Management
Overview
The next knowledge area found Slide 213
in the PMBOK® Guide is quality
management. According to the
PMBOK® Guide, quality
management is concerned with
“all the activities of the
performing organization that
determine quality policies,
objectives, and responsibilities,
so that the project will satisfy the
needs for which it was
undertaken”. This is another
relatively small knowledge area
in terms of the number of Image 69: The Quality Management Processes
processes it contains, and most candidates only have a moderate level of
difficulty with it. For many, the greatest area of difficulty is differentiating
between the perform quality assurance and perform quality control processes, so
make sure the differences are clear in your mind before proceeding to the next
knowledge area.
As with several knowledge areas, quality management places an emphasis on the
project manager understanding their role in managing the quality of both the
project and the product, or service of the project. To some extent, this is similar
to saying you must ensure the project delivers the right product or service and
the delivery is done well. Success with the quality management knowledge area
also requires memorization of a number of key terms and thought leaders. These
include the following:
Gold plating — Giving the product extra functionality past the point of Slide 214-
worth adds no value to the project. PMI® argues against gold plating. 215
Marginal analysis — Finding the point where the cost of the incremental
improvement in quality equals the value of the improvement.
International organization for standardization (ISO) — The United
Nations of standards bodies. It is composed of national standards bodies,
one per economy and, is based on Geneva, Switzerland. It was founded in
1947. The PMBOK® Guide is the ANSI standard for project management
(American National Standards Institute).
Total quality management (TQM) — The original continuous process
improvement methodology, TQM was created by Juran and provides the
starting point for more current methodologies such as Six Sigma and Lean.
Six Sigma — A continuous process improvement framework or
methodology made famous by Jack Welch and General Electric.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 318
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 319
change — or, in his terms, cultural resistance — was the root cause of quality
issues. For Juran, quality is defined based on a product or service’s “fitness
for use” or ability to meet its intended purpose. The fitness for use concept
is key for the PMP® exam.
Philip Crosby — Crosby became famous after initiating the zero defects
program at the Martin Company Orlando, Florida, plant. As the quality
control manager of the Pershing missile program, Crosby was credited with a
25% reduction in the overall rejection rate and a 30 percent reduction in
scrap costs. He developed the principle of “doing it right the first
time” (DIRFT). He would also include four major principles:
the definition of quality is conformance to requirements
the system of quality is prevention
the performance standard is zero defects
the measurement of quality is the price of nonconformance
Kaoru Ishikawa — Ishikawa introduced the concept of quality circles in the
1960s. However, he is best known for developing cause-effect (fishbone)
diagrams and innovating design statistics.
Genichi Taguchi — Taguchi is influential in industrial statistics. Key
elements of his quality philosophy, which became known as the Taguchi
method include the following:
The Taguchi Loss Function, used to measure financial loss to society
resulting from poor quality;
The philosophy of off-line quality control, designing products and
processes so that they are insensitive (“robust”) to parameters outside
the design engineer’s control
Innovations in the statistical design of experiments, notably the use of
simulations for factors that are uncontrollable in real life, but are
systematically varied in the experiment.
To prepare for the PMP® exam, there are a few general concepts you must
understand. The concepts include the following:
Project management and quality management are separate but
complementary disciplines that both place significant importance on
customer satisfaction.
®
PMI focuses most of its attention on the prevention of quality problems
rather than inspection. Remember, you cannot inspect quality into a product.
You can only prevent the poor products from getting to your stakeholders.
®
It has already been said, but it will be again and again: PMI emphasizes
continuous improvement. You must continue to get better.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 320
For a project to succeed, all parties must engage. However, success is still a
central management responsibility.
Agile development uses the retrospective process to create frequent review steps
throughout the project. Whereas reviews examine the product of the project,
retrospectives examine the process. They allow the team to gather and evaluate
what is going well and not without interference from stakeholders.
8.1 Plan Quality Management
The plan quality management process is where
the project manager and team identify which Slide 217
quality standards are relevant to the project and
determine how to satisfy them. The plan quality
management process is performed in parallel with
the other planning processes. For the exam, it is
important to remember that quality is planned,
designed, and built-in, but cannot be inspected
into a product or service. The primary output of
Image 70: The Plan Quality Mgmt.
the plan quality management process is the
quality management plan, which defines which quality standards are relevant to
the project, how the team will meet those standards, the relevant quality metrics,
and how the project will continuously be improved. It is important to recognize
that quality management is one of the few knowledge areas with a formal
process designated to create its management plan.
Slide 218
The inputs to the plan quality management process include the following:
.1 Project charter— The project charter provides the project five-line
including the business need, justification, success criteria, constraints and
assumptions, and project prioritization.
.2 Project Management Plan — If managing quality is really about
delivering expected requirements, then it is important to know what those
requirements are, as well as all other rules the team has agreed to. The
specific documents called out by PMI® include: the requirements
management plan, the risk management plan, stakeholder engagement plan,
scope baseline.
.3 Project documents — There are a number of documents that the team
needs to examine including the assumption log, requirements documentation,
requirements traceability matrix, risk register, stakeholder register.
.4 Enterprise environmental factors — Like most of the 47 processes,
enterprise environmental factors can impact the planning of quality and are
thus are an important input.
.6 Organizational process assets — Any policies, procedures, or existing
plans that might aid in planning quality should be used.
The tools and techniques used in the plan quality management process include
the following:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 321
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 322
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 323
SIPOC helps the team find or identify all the relevant elements of a
process improvement project before work actually begins.
The acronym SIPOC stands for Suppliers, Inputs, Process, Outputs,
and Customers, which each form columns in a table or diagram. The
steps used to create the diagram include the following:
Create an area that will allow the team to post additions to the
SIPOC diagram. This could be a transparency (to be projected Slide 223
by an overhead) made of the provided template, flip charts
with headings (S-I-P-O-C) written on each, or headings
written on post-it notes posted to a wall.
Begin with the process. Map it in four to five high level steps.
Identify the outputs of this process.
Identify the customers that will receive the outputs of this
process.
Identify the inputs required for the process to function
properly.
Identify the suppliers of the inputs that are required by the
process.
Optional: Identify the preliminary requirements of the
customers. This will be verified during a later step of the Six
Sigma measurement phase.
Discuss with project sponsor, Champion, and other involved
stakeholders for verification.
A SIPOC model can be especially useful when attempting to answer
questions like the following:
Who supplies inputs to the process?
What specifications are placed on the inputs?
Who are the true customers of the process?
What are the requirements of the customers?
Slide 224
Page 324
Logical data model — A logical data model is also referred to as a Slides 225-
logical schema. It is a data model of a specific problem domain that 226
is expressed independently of any specific named database product or
storage technology. Instead, it focuses on the foundational data
structure and its elements such as relational tables, columns, object-
oriented classes and/or XML tags. It represents the abstract structure
of a domain of information. A logical data model is most often used
in business process seeking to capture the important aspects of the
organization and how they relate to one another. The logical data
model is the basis for the physical data model. It is sometimes used
as a synonym for a domain model, but the two are not the same. A
domain model is more focused on capturing the concepts in the
problem domain rather than the structure of the data associated with
that domain. Make sure you understand the differences between a
conceptual, logical, and a physical data model. Use the table below
to avoid confusion.
Conceptual Data Model Logical Data Model Physical Data Model Slide 227
Includes high-level data constructs Includes entities (table), attributes Includes tables, columns, keys data
(columns/fields) and relationships types, validation rules, database trig-
(keys) gers, stored procedures, domains, and
access constraints.
Non-technical names, so that exec- Uses business names for entities and Uses more defined and less generic
utives and managers at all levels attributes specific names for tables and columns,
can understand the data basis of such as abbreviated column names,
architectural description limited by the database management
system (DBMS) and any company
defined standards.
Uses general high-level data con- Is independent of technology Includes primary keys and indices for
structs from which architectural (platform, DBMS) fast data access.
descriptions are created in non-
technical terms.
May not be normalized. Is normalized to forth normal form May be de-normalized to meet perfor-
(4NF) mance requirements based on the nature
of the database. If the nature of the
database is online transaction pro-
cessing (OLTP) or operational data
store (ODS) it is usually not de-
normalized. De-normalization is com-
mon in data warehouses.
Represented in the DIV-1 view- Represented in the DIV-2 Viewpoint Represented in the DIV-3 Viewpoint
point (DoDAF V2.0) (DoDAF V2.0), and OV-7 View (DoDAF V2.0), and SV-11 View
(DoDAF V1.5) (DoDAF V1.5)
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 325
S Supplier
Item on left influences item at top
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 326
.6 Test and inspection planning — Every industry is different, but Slide 231-239
regardless of the products, services or results being created by the project
team testing and inspection is critical. Although how you will test might be
different, there are some commonalities we can establish. The first is that
every project team must spend time during the planning phase of the project
to determine how they will test or inspect their results to ensure they meet
the defined project success criteria. This becomes increasing complex when
you factor in the various project methodologies. The software industry talks
about alpha, beta, red, green and refactoring as part of their testing and
inspection processes and this is just one industry. Engineering adds field
tests, load tests, and nondestructive tests. This is a lot of testing. The key is
that the team defines their testing process as part of planning.
.7 Meetings — You have spent enough time in the field as a project manager
to qualify for the PMP® you know that you spend a huge amount of your
time in meetings collecting information and communicating with people.
The outputs of the plan quality process include the following:
.1 Quality management plan — The quality management plan defines how the
project manager and the team will implement the organization’s quality policy.
It becomes part of the project management plan. It specifically defines how the
organization will control quality, do quality assurance, and provide for
continuous process improvement on the project.
.2 Quality metrics — Quality metrics define how the project manager and the
team will measure the quality performance of the project. It also defines the
tolerances for those metrics. According to the PMBOK® Guide “specifically
describes a project or product attribute and how the control quality process will
verify compliance to it.” [6th ed. p. 287]
.3 Project management plan updates — We consistently see the planning
processes causing the team to revisit other plan documents with updates. This is
true here as well. Most likely to be impacted are the risk management plan and
the scope baseline.
.4 Project documents updates — Although any of the project documents might
need to be updated, the PMBOK® Guide lists the lessons learned register, the
requirements traceability matrix, the risk register, and the stakeholder register.
8.2 Manage Quality
With the 6th edition of the PMBOK® Guide changed Slide 240
the second process found in quality management
from perform quality assurance to manage quality.
This change dramatically reduced the amount of
confusion found in quality management and made
the knowledge area more consistent with the rest of
the Guide. The concept is you first plan the area,
then you manage the area before finally controlling Image 78: The Manage Quality
Process
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 327
the area. The manage quality process is all about translating the quality
management plan into the activities that translate the quality policies into
positive outcomes for the project. One aspect of this process that did not change
with the name was the importance of quality assurance within its framework.
This means that the manage quality process includes all quality assurance
activities and also addresses product design and process improvements. It
provides an umbrella for continuous improvement. The plan quality process
answers the question: “How will the project team achieve quality?” The quality
management process answers the question: “Are we following our standards?”
This process focuses on determining if the various project activities comply with
organizational and project policies, procedures, and processes. It uses the
measurement information from the control quality. What makes it so confusing
is the fact that it is often going on at the same time and using information from
the control quality process.
The inputs to the manage quality process include the following:
.1 Project management plan — Within the project management plan, the Slide 241
quality management plan is specifically called out. It defines how the team
intends to manage quality on the project.
.2 Project documents — The project documents provide the team with the
lessons learned register, quality control measurement, quality metrics, and
risk reports. Quality control measurements are the results of quality control
activities. They are important to evaluate and analyze the quality standards
and processes of the performing organization. Quality metrics include things
such as on-time performance, failure rates, availability, defect frequency, and
other such measures.
.3 Organizational process assets — Many organizations have policies,
procedures, and guidelines directing projects in the area of quality. Along
with these policies and procedures they often provide checklists, test plans
and other tools to give the team a jump start. If these items exist, the team
should take advantage of them.
Many of the tools and techniques found in the manage quality process are the
same as what was found in the plan quality management process. They include
things such as cost-benefit analysis, cost of quality, control charts,
benchmarking, and flowcharting. The tools and techniques used in the manage
quality process include the following:
.1 Data gathering — As part of the data gathering process, it often makes a
lot of sense to make use of a checklist of some kind. Remember, a checklist
is used to verify that a set of required processes or steps have been performed
or to ensure a set of requirements have been completed. The risk with
checklists is that users believe they have covered everything and do not think
beyond the checklist. Therefore, you must use other data gathering
techniques as well.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 328
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 329
much more overt focus on the decision making process. One of the most
common tools used in this process is multicriteria decision making or
MCDM. This process is actually a subdiscipline of operations research that
evaluated situations where there are multiple conflicting criteria in the
decision making process. A simple example of this concept is the
relationship between price and functionality.
.4 Data representations — As the team progresses through this process,
they often need one or more ways of visually representing the information
they are collecting and analyzing. PMI® lists a number of possibilities
including:
Affinity diagrams — An affinity diagram is one of the “Seven Slide 244
Management and Planning Tools”, and was originally devised by Jiro
Kawakita in the 1960s. It is also sometimes referred to as the KJ
Method. Affinity diagrams are commonly used in project
management to sort a large number of ideas created during
brainstorming based on their natural relationships for review and
analysis. To organize ideas using brainstorming the team uses the
following steps:
Record each idea on card or PostIts™ Slide 245
Look for ideas that seem related
Sort the cards into groups until all the cards have been used.
Once the cards are sorted create clusters or subgroups for
easier analysis.
Once completed, the affinity diagram can be transitioned to a cause
and effect diagram for further analysis and discussion. Image 79
below shows a simple affinity diagram.
Slide 246
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 330
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 331
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 332
Slide 252
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 333
.5 Audits — Many people are familiar with the term audit, but most believe
it is something negative and only applies to the world of accounting. This is
not true. An audit is simply a structured process completed by someone
independent from the organization who examines processes, procedures and/
or records to ensure the team is complying with existing rules and standards.
A quality audit in project management is often conducted by members of the
PMO or an external auditor to ensure best practices are implemented,
offering assistance to improve productivity, or to identify nonconformity and
shortcomings. These audits can be scheduled or random.
.6 Design for X — Design for X or design for excellence (DfX) are terms Slide 253
and expressions used interchangeably in the engineering world. The X can
have a number of potential meanings depending on the industry, but common
substitutes include: assembly (DfA), cost (DfC), logistics (DfL),
manufacturing (DfM), reliability (DfR), and serviceability (DfS). Each
design guideline addresses a specific issue that is caused by, or affects the
traits of, a product. The design guidelines usually propose an approach and
corresponding methods that may help to generate and apply technical
knowledge to control, improve, or even invent particular traits of a product.
A common part of the DfX concept is mistake proofing the various
processes. Mistake proofing is the idea that you make the process such that
it only can be done one way, the right way. In a manufacturing process,
imagine creating the parts so that some are square and others round. The
square parts only fit in the square hole and the round only in the round hole.
It is not physically possible to put the square peg in the round hole even if
the worker wants it to. Another common principle is simplifying the design
by minimizing the total number of parts, using logical labels on parts and
guides, and making spare parts readily available.
.7 Problem solving — Thomas J. D'Zurilla in 1988 defined problem solving Slide 254
as a “cognitive–affective–behavioral process through which an individual (or
group) attempts to identify, discover, or invent effective means of coping
with problems encountered in every day living”. Problem solving is used in
when products or processes fail, so corrective action can be taken to prevent
further failures. It can also be applied to a product or process prior to an
actual fail event, i.e., when a potential problem can be predicted and
analyzed, and mitigation applied so the problem never actually occurs.
Techniques such as failure mode effects analysis can be used to proactively
reduce the likelihood of problems occurring. There are a wide range of
problem solving methods such as GROW model, How to Solve It, OODA
loop, PDCA, Rapid Problem Resolution and many others.
.8 Quality improvement methods — There are a large number of quality
improvement methods available today. TQM, Six Sigma, PDCA, and Lean
are just some of the alternatives available to a project manager.
The outputs to the perform quality assurance process include the following:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 334
.1 Quality reports — Quality reports provide both the team and leadership
with graphical, numerical or qualitative information about what is going on
within the quality processes. This information can include
recommendations, bug fixes, corrective action recommendations, quality
management issues, and a wide range of other quality information depending
on what is happening with the project.
.2 Test and evaluation documents — Test and evaluation documents are not
used in every industry, but for some the represent important outputs to
evaluate the achievement of quality objectives. They can come in many
forms such as checklists or requirements traceability matrices.
®
.3 Change requests — As with most of the processes found in the PMBOK
Guide, the manage quality process can generate change requests. In this
case, the changes are often focused on quality improvements that could be
made.
.4 Project management plan updates — The manage quality process can
cause updates to several components of the project management plan, such
as the quality management plan, the scope baseline, the schedule baseline or
the cost baseline.
.5 Project document updates — The manage quality process can also cause
updates to other project documents such as the issue log, lessons learned
register or the risk register
8.3 Control Quality
The final process found in the quality management knowledge area is the control
quality process. This process
occurs throughout the project and is Slide 254
focused on monitoring and
recording the results of executing
the various quality activities, as
defined in the quality management
plan and other components of the
project management plan. Specific
project results — such as Image 86: The Perform Quality Control Process
deliverable production, schedule and
cost performance — are often included in the analysis. PMI® assumes the
project team has at least a rudimentary working knowledge of statistics to
perform this function because several of the tools and techniques used involve
statistics. This is also the most lengthy process found in the quality management
knowledge area. Fortunately, most of the information follows basic common
sense so it is not difficult, so long as you are comfortable with the relationship
between this process and the manage quality process.
The inputs to the control quality process include the following:
.1 Project management plan — The specific component of the project
Slide 255
management plan that is of the most interest is the quality management plan.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 335
®
.2 Project documents — PMI calls out three documents that are part of the
project documents. These include the lessons learned register, quality
metrics, test and evaluation documents. The lessons learned register is
important because it provide insight from past projects on the topic of
quality. The quality metrics include things such as on-time performance,
failure rates, availability, defect frequency and other such measures. The test
and evaluation documents describe how the team plans on handling major
components of quality.
.3 Approved change requests — Approved change requests can include
things such as defect repair, revised work methods, and a revised schedule.
It is important to implement any approved changes as quickly as possible.
.4 Deliverables — Notice the input is not the final product, service or result
of the project. It is the deliverables defined in the WBS.
.5 Work performance data — The work performance measurements of
concern here are all comparisons of actual results to the planned results in the
areas of cost, schedule and technical performance.
.6 Enterprise environmental factors— The project management
information system, quality management software the team is using to track
errors and variances both could be powerful inputs to controlling quality.
Additionally, any applicable government regulations or rules, standards, or
guidelines that are specific to the industry also might be important to
controlling quality.
.8 Organizational process assets — Quality standards and policies, work
guidelines, issue and defect reporting procedures, and communication
policies can all be organizational process assets that are inputs to the Control
Quality Control Process.
Most consider Kaoru Ishikawa, a professor of engineering at Tokyo University to
be the father of modern quality management techniques. He argued there are
seven basic tools of quality. The 5th edition of the PMBOK® Guide specifically
called out his seven tools of quality management. However, in the 6th edition of Slide 256
the Guide the tools are not called out as a set. Instead, most of Ishikawa’s Seven
Basic Tools of Quality appear specifically within the tools and technique
sections of either the manage quality or control quality processes. If you
struggle in understanding any of these research the Seven Basic Tools of Quality
for more information.
The tools and techniques used to control quality include:
.1 Data gathering — Data gathering is a simple group heading, but don’t be
fooled. A number of these tools are used repeatedly throughout the project
management process. For the control quality process, the list includes:
checklists, check sheets, statistical sampling, and questionnaires and surveys.
We have already talked about checklists extensively in this course. However,
we have not visited check sheets, and the two are not the same. A check
sheet is also sometimes referred to as a tally sheet. They are simple grids
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 336
∑ = Sum of ...
X = the value of the case
X = Mean
N = Number of cases
Page 337
2. Take each of the cases and subtract the mean. Then square the
result.
(1-3)2 , (2-3)2, (3-3)2, (4-3)2, (5-3)2
3. Next, add the results. = 4+1+0+1+4 = 10
Divide this result by the number of cases minus one or 10/(5-1) =
3. 2.5 This result is called the Variance of the population.
4. Finally, take the square root of the variance or the SQ. Root of 2.5
= 1.58 This is the Standard Deviation.
Questionnaires and surveys can be either formal or informal. Both collect
information from a group of individuals in a way that can be tabulated and
summarized for analysis.
®
.2 Data analysis — There are two types of data analysis called out by PMI .
These are performance reviews and root cause analysis. Both tools have
been discussed previously in this course. The less technical is the
performance review which reviews measures before comparing and
analyzing the quality metrics defined in the quality management plan against
results.
.3 Inspection — An inspection is the examination of a work product to
determine whether or not it conforms to documented standards.
®
.4 Testing / product evaluation — PMI defines testing as an organized and
constructed investigation conducted to provide objective information about
the quality of the product or service under test in accordance with the project
requirements. The intent of testing is to find errors, defects, bugs, or other
nonconformance problems in the product or service [PMBOK® 6th Ed.
P.303]. Test techniques include the process of executing a program or
application with the intent of finding software bugs (errors or other defects),
and verifying that the software product is fit for use.
.5 Data representation — How are you going to present information to the
team and stakeholders so they clearly understand what is happening in terms
of the quality of the project? Common tools include Ishikawa diagrams,
control charts, histograms, and scatter diagrams.
.6 Meetings — Regardless of the other tools and techniques you might use,
meetings are still an important aspect of how the project leader delivers
results.
The outputs to the control quality process include the following:
.1 Quality control measurements — The documented results of the various
quality control activities. It is important that they are presented in the format
defined in the quality management plan.
.2 Verified deliverables — A key goal of quality control is to determine the
correctness of the deliverables defined in the WBS and WBS dictionary.
This is the big output from the control quality process.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 338
Page 339
®
Metrics — Make sure you understand the important role PMI believes
metrics has on the successful delivery of quality. Quantification is a key
element of success.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 340
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 341
5. The project has had a major defect, and the project manager has involved the
project team in analyzing the situation. One of the group says that the real
fault is the technology being used. Another says it is the age of the material.
To address the root of the problem, the project manager decides to use a
Control Chart. Which of the following BEST describes the step of the quality
management process in which the group is involved in this situation?
A. Analyze quality
B. Control quality
C. Manage quality
D. Plan quality management
6. The project has had a major defect, and the project manager has involved the
project team and process engineers in analyzing the situation. One of the
group says that the real fault is using a new machine when an older machine
was specified. Another says it is a change in subcomponent suppliers. To
address the root of the problem, the project manager decides to use a cause
and effect diagram. Which of the following BEST describes the step of the
quality management process in which the group is involved in this situation?
A. Perform quality analysis
B. Control quality
C. Manage quality
D. Plan quality management
7. Which of the following is NOT a valid definition of project quality?
A. The degree to which the project team meets customer expectations
B. The degree to which a set of characteristics fulfill requirements
C. The degree to which a product has no obvious defects
D. Quality is something that both the project manager and project
management team are responsible for delivering
8. Which of the following is the first process in quality management?
A. Manage quality
B. Control quality
C. Plan quality management
D. Perform quality definition
9. In which of the following processes do you ensure that the quality standards
will allow the project to achieve its desired quality goals?
A. Control quality
B. Manage quality
C. Plan quality management
D. Perform quality definition
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 342
10. Which of the following is not an input to the quality planning process?
A. Product scope baseline
B. Risk register
C. Enterprise environmental factors
D. Organizational quality metrics
11. Which of the following is a tool and technique used in the plan quality
management process?
A. Project charter
B. Process analysis
C. Cause and Effect Diagrams
D. Design of Experiments
12. What is the effect of a project product, service or result that meets customer
requirements while being ahead of schedule and over budget?
A. The project is successful.
B. The project is significantly over budget.
C. Project quality has been achieved.
D. The project is behind schedule.
13. Which of the following statements best describes marginal analysis?
A. The process of determining the point at which the value of
incremental quality improvements will not equal the cost to attain
them.
B. The process of determining the point at which the value of
incremental quality improvements equal the cost of those
improvements.
C. The process of determining the optimal quality standards for the
project.
D. The process for determining the optimal profitability based on the
differentiation of the cost and pricing.
14. Sally is talking to a coworker and states she believes her boss is being unfair
with her regarding her current project and the project’s level of quality. Who
is owns final responsibility for project quality?
A. Project resources
B. Project sponsor
C. Project manager
D. The entire project team
15. Your project team is currently using Cost-Benefit Analysis. In which of the
quality management processes are you in?
A. Plan quality management
B. Manage quality
C. Control quality
D. Integrated change control
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 343
16. You are a project manager leading a team that is currently using the cost of
quality to evaluate the project. In which of the quality management processes
are you in?
A. Manage quality
B. Control quality
C. Develop project management plan
D. Plan quality management
17. You are leading an engineering project. Your team is completing a quality
audit. In which of the quality management processes are you in?
A. Manage quality
B. Quality planning
C. Control quality
D. Close project
18. Your project team is using control charts to determine the current quality
status of your project. In what part of the quality management process are
you in?
A. Plan quality
B. Control quality
C. Manage quality
D. Direct and manage project execution
19. You are the project manager on a project that has struggled with the quality
of the deliverables throughout the entire project. Your boss, the Senior Vice
President has come to you and stated that quality is the most important
project constraint. On Monday morning you come into the office and find
that another problem with quality has occurred. What is the best thing for
you to do?
A. Absorb a cost increase to fix the root cause of the problem.
B. Fix the problem immediately.
C. Cut project costs and allow the schedule to slip.
D. Allow project risks to increase by allowing the schedule to slip.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 344
20. You are a project manager leading a project that has an SPI 1.03 and a CPI
1.05. The ETC is $247,905. In a meeting you are conducting with your
team to discuss the quality of the project one of your team members
complains that the schedule is seriously compressed and you do not have
time for the meeting. You have consistently rewarded your team according
to the reward system you put in place and have a great team that has worked
well together. Which of the following best explains why the complaining
individual is wrong?
A. Improved quality leads to increase productivity, decreased cost
effectiveness, and increased technology risks.
B. Improved quality leads to increased productivity, increased cost
effectiveness, and decreased cost risk.
C. Improved quality leads to increased productivity, increased cost
effectiveness, and increased cost risk.
D. Improved quality leads to increased productivity, decreased cost
effectiveness, and decreased cost risk.
21. Quality attributes from the perspective of a project:
A. Provide the basis for judging the project’s success or failure.
B. Determine how effectively the team supports the project.
C. Are specified characteristics for which a product is designed and
tested.
D. Are objective criteria that must be met.
22. Which of the following best defines quality?
A. Meeting and exceeding the customer’s expectations.
B. Conformance to management’s objectives.
C. Adding extras to keep the customer happy.
D. The degree to which the project meets requirements.
23. You are a project manager working through some issues on your project. A
member of your team suggests you make use of a Pareto diagram. Why
might a Pareto diagram be helpful?
A. Focus on the most critical issues to improve quality.
B. Allow you to effectively brainstorm.
C. Examine potential future outcomes.
D. Determine if a process is out of control.
24. As a project manager which of the following will a Control chart help you
do?
A. Focus on the most critical issues to improve quality.
B. Determine if a process is functioning within set limits.
C. Allow you to effectively brainstorm.
D. Examine potential future outcomes.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 345
25. You are a project manager trying to decide the best way to evaluate the
quality of a manufactured product. Which of the following best explains
why you choose not to test the entire population?
A. It would create noise in the data.
B. It would exclude other testing methods.
C. It would take too long.
D. It would show type II errors.
26. All of the following are examples of the cost of conformance except:
A. Auditing
B. Controlling
C. Appraisal
D. Expediting
27. All of the following are examples of the cost of nonconformance except:
A. Expediting
B. Warranty service
C. Auditing
D. Recalls
28. You are a project manager working on a large, highly visible project. Your
most recent control chart shows seven consecutive points on one side of the
mean. What should you do next?
A. Find the cause of the change.
B. Nothing. The project is not necessarily in trouble.
C. Notify your sponsor that there is a problem.
D. Adjust the chart to reflect the new mean.
29. You are a project manager leading a large project within your organization.
Last week you were on vacation. Upon your return you discover the team
added several deliverables to the project because they determined it would
benefit the customer. What is wrong with this situation?
A. The project manager was not present when the decision was made.
B. Nothing, this is the best way to have a happy customer.
C. Nothing. The team needed to keep moving in your absence.
D. The team is gold plating.
30. You are working on creating a financial plan for your project. If you are
planning on using JIT, how much inventory should you plan on maintaining?
A. 0%
B. 15%
C. 25%
D. 40%
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 346
31. When planning your project which would generally have the highest priority:
schedule, cost or quality?
A. Quality
B. Schedule
C. Cost
D. It should be determined for each project.
32. You are a project sponsor with several projects falling within your authority.
You are concerned about the accuracy of the performance reporting you have
recently been receiving. Which of the following would best allow you to
validate your concerns?
A. Control charts
B. Quality audits
C. Monte Carlo analysis
D. Logit analysis
33. You are leading a large manufacturing project for a new automobile. The
current design allows for a 1.3% defect rate and expects to produce 1.2
million units. In which of the following would you document quality
control, quality assurance, and quality improvements?
A. The quality policy
B. The project management plan
C. The quality management plan
D. Organizational processes and templates
34. You are a project manager leading a road construction project. The road is
almost 80% complete according to your most recent EVMS report when a
senior executive informs you that she is worried the project will not meet the
quality standards. What should you do in this situation?
A. Assure the executive that during the plan quality process it was
determined that the project would meet the quality standards.
B. Use EVMS to predict future results.
C. Check the results from previous projects’ quality management plans.
D. Form a quality assurance team.
35. You are a project manager leading a small information technology project.
You ask two members of your team to select tools and techniques to
implement a quality assurance program that will be combined with existing
quality control activities. Which of the following would you not expect to
see in the program?
A. Histograms
B. Focus groups
C. Quality audits
D. Statistical sampling
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 347
36. You are the project manager on a major engineering project. You are
working with the quality assurance department to make sure everyone has
confidence that the project will satisfy the quality standards. Which of the
following must you have before starting the process?
A. Defined areas of concern
B. Requested quality improvements
C. Quality control measurements
D. Rework
37. You have just taken over a project from another project manager. The
project is currently in the execution process group. The previous project
manager created a project budget, determined communications requirements,
and went on to complete work packages. What should you do next?
A. Complete the WBS.
B. Complete the identify risk process.
C. Complete the project according to the plan.
D. Identify the quality standards.
38. You are a project coordinator leading an information technology project.
Your project is facing major changes to its deliverables. If you are involved
in determining which quality standards are relevant to the changes, you must
also be involved in:
A. Quality management
B. Manage quality
C. Plan quality management
D. Control quality
39. You are the project manager for a large manufacturing project in the
electronics industry. Your project has completed all of its deliverables. As
you examine the lessons learned you conclude that the project has added five
areas of performance and three areas of functionality. The customer has
signed off on the delivery of the product of the project and is very happy
with the results. What does this mean in terms of success of the project?
A. The project was unsuccessful because it was gold plated.
B. The project was successful because the team learned from the effort
and the customer was satisfied.
C. The project was an unqualified success.
D. The project was unsuccessful because making the customer happy
meant the team had to do more work.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 348
42. The project has had a major defect, and the project manager has involved the
project team and process engineers in analyzing the situation. One of the
group says that the real fault is the age of the equipment. Another says it is
the lack of a material for the correct quality. To address the root of the
problem, the project manager decides to use an Ishikawa diagram. Which of
the following BEST describes the step of the quality management process in
which the group is involved in this situation?
A. Perform quality analysis
B. Manage quality
C. Control quality
D. Plan quality management
43. An external stakeholder suggests to the project manager that the team does
not have enough time to hold quality meetings when the schedule has been
significantly compressed. The current CPI is 1.12 and the team has
performed very well under adverse circumstances. Which of the following
best explains why the stakeholder is wrong?
A. Improved quality leads to increased productivity, increased cost
effectiveness, and decreased cost risk.
B. Improved quality leads to increased productivity, decreased cost
effectiveness and increased cost risk.
C. Increased quality leads to increased productivity, increased cost
effectiveness, and increased cost risk.
D. Improved quality leads to increased productivity, decreased cost
effectiveness, and decreased cost risk.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 349
44. You are leading a project to develop food packaging equipment. The current
specifications call for less than one percent spillage per container. In which
of the following do you document quality control, quality assurance, and
quality improvements for the project?
A. Quality management plan
B. Quality policy
C. Project documents
D. Project management plan
45. As the project manager, you have created a plan for how the team will
implement the quality policy. It addresses the organizational structure,
responsibilities, procedures, and other information about plans for quality. If
this plan changes during the project, which of the following plans will also
change?
A. Quality assurance plan
B. Quality management plan
C. Project management plan
D. Quality control plan
46. You are in the middle of a major new facility construction project. The
structural steel is in place and the heating conduits are going into place when
a senior manager informs you that he is worried the project will not meet the
quality standards. When should you do in this situation?
A. Assure senior management that during the plan quality process, it was
determined that the project would meet the quality standards.
B. Analogously estimate future results.
C. Form a quality assurance team.
D. Check the results from the last quality management plan.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 350
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 351
11. Answer D. PMBOK® Guide p. 277 – The tools and techniques used in plan
quality management include:
.1 Expert judgment
.2 Data gathering
.3 Data analysis
.4 Decision making
.5 Data representation
.6 Test and inspection planning
.7 Meetings
12. Answer C. The only thing that can be stated definitively is that the project’s
quality level has been achieved. With the information provided you cannot
be sure the project was successful as the project is over budget. However,
you also cannot tell if the project is significantly over budget. The project is
not behind schedule.
13. Answer B. Marginal analysis is an analytical process used in determining
the point at which spending any more money to improve the project quality
will exactly match the value of the improvements. It is a one for one
exchange.
14. Answer C. PMBOK® Guide p. 273-275 – The project management team
and not the entire project team is ultimately responsible for the level of
quality on a project. However, in this case the best answer is the project
manager.
15. Answer A. PMBOK® Guide p. 272 – Cost-benefit analysis is a tool and
technique used in the Plan Quality Management Process.
16. Answer D. PMBOK® Guide p. 272 – Benchmarking is a tool and technique
used in the plan quality management process.
17. Answer A. PMBOK® Guide p. 288 – A quality audit is a tool or technique
used in the perform quality assurance process.
18. Answer B. PMBOK® Guide p. 304 – Control charts are one of several tools
and techniques that make up the control quality process.
19. Answer A. The key phrase in the answers is “root cause”. Only A fixes the
root cause of the problem. B might only be a temporary solution. Neither C
nor D provide a solution to the quality problem.
20. Answer B. This is a very long winded question, but is typical for the exam.
Most of the question has little to do with coming up with the correct answer.
Just remember from PMI’s perspective improving the quality of the project
will lead to lot of good stuff including decreasing the long term cost of the
project, making the team more productive and reducing risks.
21. Answer C. PMBOK® Guide p. 273-274 – This question is almost a straight
definitional question. Quality is “the degree to which a set of inherent
characteristics fulfill requirements.”
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 352
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 353
32. Answer B. PMBOK® Guide p. 294 – This question reflects the definition of
a quality audit. It is a structured, independent review to determine whether
project activities comply with organizational and project policies, processes,
and procedures.
33. Answer C. PMBOK® Guide p. 277 – The quality management plan is where
all aspects for how quality will be managed on the project are defined.
34. Answer D. The real question here is which option helps ensure you meet the
appropriate quality standards. The only choice is forming a quality
assurance team.
35. Answer B. PMBOK® Guide p. 288 – This question is basically asking
which item from the list is not a tool or technique from manage quality and
control quality processes combined. The tools and techniques from control
quality and manage quality combined include:
Data gathering
Data analysis
Data representation
Decision making
Audits
Design for X
Problem solving
Quality improvement methods
Inspection
Testing / product evaluations
Meetings
36. Answer C. The key word in this question is must. The only one of the four
items you must have is the quality control measurements. Everything else is
optional.
37. Answer D. For some this is an easy question because it appears in the
quality section. However, if you did not know which process group you
were in would you have gotten it correct? Identifying the quality standards is
the correct answer because no one has yet completed the planning process.
The next step in that process calls for the creation of the quality standards,
and then completing the identify risks process. The WBS is already done
and you cannot execute the project until the planning is complete.
38. Answer C. Although quality planning usually occurs during project
planning, sometimes you have to go back to planning from other processes to
re-evaluate or make another decision.
39. Answer A. This question might be considered a trick by some, but it is not.
The correct answer is the project was gold plated (you have no information
that the customer approved the changes prior to implementation). So even
though they were happy with the product of the project it was gold plated
and that is bad. This is a situation with a great product and a failed project.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 8 — Quality Management
Page 354
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 355
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 356
The inputs to the plan resource management process are as follows: Slide 269
.1 Project charter — The project charter provides the project team and
stakeholders with the project’s top level information, that which we have
called the five-line including the business need and justification, the success
criteria, any constraints and assumptions, and
.2 Project management plan — The project management plan contains
most of the critical information about what the project includes and what the
resources are required to do. PMI® draws special attention to the quality
management plan and scope baseline because the quality management plan
informs the team about the level of resources required to achieve and
maintain the core metrics defined, and the scope baseline defines the
deliverables so the team understands the types and quantities of resources
required to generate the correct work product.
.3 Project documents — The team may need to examine a lot of additional
documents that are part of the “other” project documents. These include the
all important project schedule, the requirements documentation, the risk
register, and the stakeholder register. Each of these informs the project team
about the work that must be accomplished and when it should be done.
.4 Enterprise environmental factors — Key enterprise environmental
factors include the following:
The organizational structure and culture
Any existing resources
Existing human resource policies
Marketplace conditions
.5 Organizational process assets — Items such as organizational standards,
policies, and standard role descriptions, as well as templates, organizational
charts, and position descriptions, can all impact the development of the
Human Resources Plan. Additionally, historical information can provide
important information.
The tools and techniques used in the plan resources management process include
the following:
.1 Expert judgment — You have already seen that expert judgment is
almost always PMI’s preferred tool and technique. When dealing with
resource management planning team leaders must be able to negotiate for the
resources they need to successfully deliver the project. They also must have
the experience to manage and develop people. One of the biggest problems
real-world project managers face is either not understanding the
organizational culture or estimates being based upon having more
experienced resources than are actually assigned to the project. A true
project management professional knows to avoid this issue.
.2 Data representation — Data representations represents visual methods
of providing information in a way that allows the team to make effective use
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 357
of it. When done correctly, these tools ensure that each work package is
owned by someone who has not doubt they own the package and all the other
resources understand their
role with the package. PMI® Slide 271
lists three groups of tools
within this area hierarchical
charts, assignment matrices,
and text-oriented formats.
Hierarchical charts are used to
show each member of the
team how they fit into the
project organization.
Typically, these tools show a Image 90: A Sample Resource Breakdown Structure
top-down view of the
organization. Examples of this kind of image include work breakdown
structures (WBS), organizational breakdown structures (OBS) or a resource
breakdown structure (RBS). Image 90 shows resource breakdown structure.
Notice that is presents a simple hierarchy of boxes or positions.
The second group of visual tools are called assignment matrices. Assignment
matrices or RAMs bring together resources and work packages or activities
which is different from hierarchical charts that either show work packages or
resources but not typically both. A Responsibility Assignment Matrix
(RAM) such as the one shown in Image 91. A common form of a RAM is a
RACI diagram. The RACI acronym stands for Responsible, Accountable,
Consult and Inform. It defines the role each resource has for each
deliverable or activity.
Slide 272
Image 91: A Responsibility Assignment Matrix. Also, called a RACI diagram for Responsible,
Accountable, Consult, Inform
The third group of items within data representation are text-oriented formats.
These are typically verbal descriptions of the work to be done and the role
for each team member.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 358
.2 Organizational theory — The area requiring the most study in the project
resources management knowledge area is that of organizational theory. As
you study these theories remember they are just theories. Many of them are
contradictory and you do not necessarily have to agree with any of them.
However, you must be able to compare and contrast the different theories.
Maslow’s Hierarchy of Needs — The first theory is Maslow’s
Hierarchy of Needs. Abraham Maslow argued in 1943 that people do
not work for money or security. They work for something he called
self-actualization. However, Maslow contended that one could not
attain self-actualization until they had taken care of lesser needs. To
explain these needs Maslow created a hierarchy with self-
actualization at the top. Image 88 shows Maslow’s Hierarchy. At the
bottom of the pyramid are the physiological needs such as air, water,
food, housing and clothing. Once these needs are taken care of a
person progresses to the next level, safety, and they must address
those needs before continuing up the pyramid until reaching the top.
A project manager must address these issues because the best workers
are at the top of the pyramid.
Slide 273
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 359
Theory Z — Theory Z was developed by William Ouchi in his 1981 Slide 277
book, Theory Z: How American Business Can Meet the Japanese
Challenge. Theory Z is often referred to as the 'Japanese'
management style. Theory Z essentially advocates a combination of
all that's best about McGregor's XY Theory and modern Japanese
management, which places a large amount of freedom and trust with
workers, and assumes that workers have a strong loyalty and interest
in teamwork and the organization. It also places more reliance on the
attitude and responsibilities of the workers, whereas McGregor's XY
Theory is mainly focused on management and motivation from the
manager's and organization's perspective. Theory Z focuses on
enabling workers to become generalists, rather than specialists to
increase their knowledge of the company and its processes through
job rotations and continual training.
McClelland Theory of Needs — David McClelland proposed that an
individual's specific needs are acquired over time and are shaped by
one's life experiences. Most of these needs can be classed as either
achievement, affiliation, or power. A person's motivation and
effectiveness in certain job functions are influenced by these three
needs. McClelland's theory sometimes is referred to as the three need
theory or as the learned needs theory.
.4 Meetings — In addition to all the specific tools, a project manager must
meet with the team and other stakeholders to ensure the human resource
management plan reflects the true resources needs.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 360
Knowing the organizational theories and being able to compare and contrast
them is critical to passing the exam. There are three outputs to this first resource
management process. They include:
.1 Resource management plan — the resource management plan is the Slide 278
most important output from this process. It provide key guidance on how the
team plans to categorize, allocate, manage and release resources on the
project. When you think about the resource management plan it is important
that you think practically about the different things it is designed to do. Most
importantly, the resources management plan identifies the resources needed
to complete the project. It also defines how the team intends to obtain the
team and other physical resources necessary to complete the project. Many
of these plans define the role, level of authority, specific responsibilities and
required skills of the team members. Often the resource management plan
includes organization charts or other visual tools to help in this definition. It
also defines various strategies for training team members and developing the
team as a cohesive unit.
.2 Team charter — Just as the project has a charter which defines the high
level of the project, so too does the team itself. The team charter establishes
the basic ground rules the team agrees to use to function as a collective unit.
It includes the team’s values, agreements, and operational guidelines in areas
such as communication, decision making, conflict resolution, and meetings.
.3 Project document updates — As part of planning the project resource
management area, the team often discovers new information that requires
them to update their assumption log or risk register because often resourcing
a project involves making significant assumptions which are found to be
untrue later in the process. As soon as the new information is discovered,
regardless of area, the team must update the appropriate documents.
9.2 Estimate Activity Resources
The second process in the project resource management knowledge area is
estimate activity resources. If you are at all familiar with the PMBOK® Guide Slide 279
you recognize this as a new process in the 6th edition of the Guide. However, it
is not really new. The 5th edition of the Guide positioned the same process as the
4th process in the time management knowledge area
(now called schedule management). This change is a
nod to common sense organization as the process is all
about defining the number and types of people,
equipment and other supplies necessary to complete the
work of the project. Remember, many of these
processes are going on at the same time and/or directly
relate to one and other even though they cross
knowledge areas.
Image 96: Acquire Project Team
The estimate activity resources process begins by
examining the primary inputs defining the deliverables and work of the project
to ensure those defining resources clearly understand the stakeholders’
expectations. These inputs include:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 361
.1 Project management plan — Within the project management plan, the Slide 280
team must examine the resource management plan and the scope baseline.
The first defines how the team plans to acquire, train and manage the project
resources. The second define the agreed upon project work at that moment
in time.
.2 Project documents — Hopefully, the process of examining these
processes is beginning to sound repetitive. That is because it is! Many of
these processes look very much like one and other. With almost every
process the team considered the project management plan and other project
documents as key inputs. This process is no different. When working to
estimate the required activity resources to complete the project the team must
look at the list of activities, the activity attributes, assumption log, cost
estimates, resource calendars, and the risk register to gain a full picture of
project what is needed.
.3 Enterprise environmental factors — If the team is using the tried and
true why stop with just the project management plan and project documents?
Enterprise environmental factors are always at play so they fit as an input
here.
.4 Organizational process assets — Most organizations have tools in place
to assist the project leader in the definition and acquisition of resources.
These tools often provide valuable inputs as the team attempts to define the
required resources.
The tools and techniques used in this process are going to seem very familiar.
That is because you used most of them just a few chapters prior when we
discussed estimating costs. These include:
.1 Expert judgment — Just as we have seen in most other processes, the
tool or technique is expert judgment. It is absolutely critical that project
leaders trust their team and surround themselves with individuals who
possess significant knowledge about the work of the project.
Bottom-up estimating — When combined with expert judgment, bottom-up
estimating is PMI’s preferred way of generating estimates of anything. This
is because your subject matter experts have the most knowledge and are most
likely to be accurate at the lowest or smallest unit of delivery.
.3 Analogous estimating — Early in the project’s life cycle the team often
lacks critical information to make a highly accurate estimate. In these
situations the team still needs to generate an estimate knowing it will be
refined later when more information becomes available. In these situations,
analogous estimates are often preferred. An analogous estimate uses the
actual results from a previous, similar project to estimate the current one in
question.
.4 Parametric estimating — Parametric estimating involves generating an
estimate using a mathematical model. A simple example might involves
estimating the number of developers on a software project based on the total
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 362
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 363
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 364
When dealing with team members you must also be aware of the halo effect.
The halo effect is the tendency to rate team members high or low on all factors
due to the impression of a high or low rating on one particular factor.
The outputs to the acquire resources process include the following:
.1 Physical resource assignments — Physical resources represent the
equipment, supplies and materials the team needs to deliver the project.
When appropriate, it can also represent the physical locations.
.2 Project team assignments — The project is considered “staffed” when
appropriate people have been assigned to the project, which can include a
project team directory, memos to team members, and/or resource names
inserted into the project plan.
.3 Resource calendars — Resource calendars document when each resource
is available to work on the project.
.4 Change requests — As the team acquires the resources it needs to deliver
the project many factors surrounding the project can change. This output
allows the team to recognize the new information and run the change through
the change management process.
.5 Project management plan updates — Specifically, acquiring the project
team might require the updating of the resource management plan or the cost
baseline.
.6 Project documents updates — As resources are applied to the project a
lot can change. Therefore, teams might have to update the lessons learned
register, the project schedule, the resource breakdown structure, resource
requirements, risk register, and/or the stakeholder register to account for
those changes.
.7 Enterprise environmental factors updates — This is the first time you
have seen updates to the enterprise environmental factors, but stop and think.
Your project could easily impact resource availability within the organization
and/or the amount of material resources the organization has on hand.
.8 Organizational process assets updates — Just as your project likely
impacts the enterprise environmental factors, you also may impact
organizational process assets.
9.4 Develop Team
Once the team is acquired, the next step in the resource management knowledge Slide 283
area is to develop the team so they have the necessary skills to complete the
project successfully. A key goal of the project manager is to improve skills, team
interaction, and overall team environment. In any project, teamwork is a critical
factor for success. Team development is a project manager’s responsibility. The
develop team process is a relatively straightforward process focused on the
different ways to develop skills and teamwork.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 365
The inputs to the develop team process include the following: Slide 284
.1 Project management plan — Within the
project management plan the resource management
plan defines all the rules and processes to obtain,
manage and train the team.
.2 Project documents — Within the project
documents there are a number of documents to
help develop the team grow and develop. These
include the lessons learned register, the project
schedule, the project team assignments, resource
calendars, and the team’s charter. Each of these
documents help the project leader understand who
is on the team, their role, what they need to do, and
what they already know. Image 98: Develop Team
.3 Enterprise environmental factors — The organization often has human
resources policies. Performance reviews and reward and recognition already
in place that will impact the team’s ability to develop.
.4 Organizational process assets — The organizational process assets that
can quickly impact the team as it develops is any historical relationships and
the lessons learned repository.
The tools and techniques used in the develop team process include the following:
.1 Colocation — This is the second time the term colocation has been used.
PMI® recognizes that teams are more effective when everyone is able to sit at
the same location. Unfortunately, this is not always realistic. Many of the
agile methods suggest colocation is an imperative, but again, it is not always
possible. In those situations, the team may need to look to the second tool on
the list.
.2 Virtual teams — When it is not possible to have the team physically sit in
the same physical location modern technology makes virtual teams possible.
The use of virtual teams can often allow projects to bring additional
specialized resources to the team that would not be available if it was
required than all team members be collocated.
.3 Communication technology — The ability to quickly use internet
technology to video conference in an entire team, share a presentation, team
board or other information radiator makes the demand that a team be
collocated less stringent than in the past.
.4 Interpersonal and team skills — Interpersonal and team skills are those
skills used to relate with people and engage with them on a one-on-one basis
or in small groups. Remember, teamwork is critical to the success of the
project, and no tool is more important to developing good teamwork than
interpersonal skills. PMI® groups five specific tools and techniques in this
area:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 366
As you review the table, keep in mind that a number of factors can
influence the resolution of the conflict including its importance, any
time pressure, and the relative power of the players.
Influencing — PMI® does not ever assume that the project manager
has full or direct authority over the project. Without that level of
authority, a project leader must rely on the ability to influence
stakeholders at all levels of the organization to ensure project success.
Motivation — Motivation represents providing a reason for someone
to act. Most teams are motivated by being empowered to plan and
manage their own work. This is a core aspect of agile methods.
Negotiating — Negotiating has already been discussed extensively.
Team building — Team building is the responsibility of the project
leader. It is the process of leading activities that enhance the team’s
social relations and build an environment where people want to work
together. It leads to higher degrees of cooperation and collaboration.
Every day, the successful project leader must do something to
increase the levels of team effectiveness.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 367
®
.5 Recognition and rewards — PMI does not assume the project leader
has unlimited resources to develop rewards and recognition for the project
team, but it does suggest having them is critical to success and it is your
responsibility that they happen.
.6 Training — Training refers to activities that lead the overall improvement
of skills for the team. Over the last several years how training is done has
changed dramatically. Now, a significant portion of training is done using
the internet as the delivery vehicle.
.7 Individual and team assessments — Individual and team assessments or
evaluations represent methods used to determine what the team does well
and what it does not. There are a wide range of these tools available to the
team. Typically, these assessments are looking for major areas of
improvement often in topics dealing with social interaction. An example of a
team assessment is found in the Table Group’s Five Dysfunctions of a Team
Assessment based on Patrick Lencioni’s best selling book of the same title.
Best selling author
Patrick Lencioni is often Slide 288
cited by Agilists to
describe common
dysfunctions
experienced by even the
best team. Lencioni
identified five specific
but all too common
dysfunctions. All teams
have the potential to
become dysfunctional
because they are made
up of people whose
needs must be met.
Understanding what the
potential dysfunctions
are and how to
overcome them are Image 100: Lencioni’s Five Dysfunctions of a Team
critical to the success of any team.
Absence of Trust
Trust is the real foundation of team structure. Often team members don’t
feel comfortable enough with the other members to fully disclose or share
information that is needed for the team to succeed. Common indicators that
your team is struggling with an absence of trust include:
Concealing weaknesses and/or mistakes Slide 289
Not asking for help or providing constructive criticism
Not offering to help other team members outside their own areas
Quickly jumping to conclusions
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 368
To be able to deal with the fear of conflict try the following techniques:
Conflict Mining — Create situations within the meeting to make the
conflicts come into the conversation and force people to talk about Slide 292
them.
Real Time Permission — You must have a culture where it is
acceptable to have a difference of opinion and your people must be
willing to express those opinions.
Thomas-Kilmann Conflict Mode Instrument (TKI) — This tool is
similar to a personality test but brings out conflict in a very thought-
provoking way for the team to discuss.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 369
Lack of Commitment
The third major dysfunction of a team is a lack of commitment. When an
organization suffers from a lack of commitment they rarely stick with
difficult decisions or find it impossible to make the decisions necessary to
ensure project success. Often these issues create exponentially increasing
problems as project resources become more and more frustrated. Each of the
following represent telltale signs of a lack of commitment within an
organization:
Ambiguity about direction and priorities. Slide 293
Paralysis by analysis.
Lack of confidence and fear of failure.
Revisiting discussions and decisions repeatedly.
Second guessing amongst the team.
If you identify that you have a commitment issue within your team or
organization, implement the following:
Cascading Messaging — Ensure messaging flows from the top of
Slide 294
the organization. Senior management must have belief in their ideas
and set a consistent direction for the organization.
Deadlines — Set deadlines and make everyone live up to them.
Contingency and Worst-case Analysis — Make sure you have
contingency plans in place and conduct a worst-case analysis of all
plans to ensure that you and the team can deal with it.
Low-risk Exposure Therapy — Identify the risk exposure
tolerances within the organization and your team.
Avoidance of Accountability
Without committing to a clear plan of action, even the most focused and
driven team members will hesitate to call out actions and behaviors that seem
counterproductive to the good of the project and organization. Members will
hold deep seeded resentment for team members that fail to live up to their
standards, although they may say nothing. The avoidance of accountability
is exemplified by the following indicators:
Resentment among team members of different performance Slide 295
standards.
Encouraged mediocrity.
Missed deadlines and key deliverables.
Team leader is the sole source of discipline.
If you identify that you have an accountability issue within your team or
organization, implement the following:
Publish goals and standards for all team members.
Slide 296
Simple and regular progress reviews.
Team rewards.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 370
Inattention to Results
Inattention to results occurs when team members put their individual needs
(such as ego, career development, or recognition) above the collective goals
of the team. This will cause the team to fail to meet most, if not all, of the
original objectives of the project. Inattention to results can be indicated by
any of the following:
Team stagnates and fails to grow.
The organization rarely defeats a competitor. Slide 297
Loses achievement-oriented employees.
Team members encouraged to focus on their own goals.
Easily distracted.
If you identify that you have an inattention to results issue within your team
or organization, implement the following:
Public declaration of results
Results-based rewards Slide 298
.8 Meetings — Meetings are still the constant tool of the project leader
regardless of how much things change. You must always consider them
something available as a core tool.
The outputs from the develop team process include the following:
.1 Team performance assessments — The team performance assessments
include how well the team is doing on assigned work, where knowledge gaps
exist, and how the team is functioning as a unit. Specific measures might be
reduced staff-turnover rates or improvements in assessed skills.
.2 Change requests — Going through the process of developing your team
often causes you to learn things about the project. When this happens the
team must follow its own change management process or no one else will
either.
.3 Project management plan updates — Just as going through the process
of developing the team can cause changes, it can also cause updates to the
project management plan. Specifically, this process can change the resource
management plan.
.4 Project document updates — The process of developing your team can
also cause updates to documents outside the project management plan.
These documents include: the lessons learned register, the project schedule,
project team assignments, resource calendars, and the team charter.
.5 Enterprise environmental factors updates — As the project progresses,
the environment is likely to change. It is important the project manager
recognizes the changes and adapts the organization as required. Specific
environmental factors that might be updated include things such as employee
training records and/or skills assessments.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 371
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 372
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 373
Resolution Concern
Mode Style Personal Goals Relationship
Withdrawal Lose—Leave Low Low
Smoothing Yield—Lose Low High
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 374
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 375
Slide 302
focus on the Goleman model and think about a four-square grid. At the top
of the grid are the two column headings, self and social. Self describes how
we manage ourselves while social describes how we handle relationships.
The two rows represent recognition or who the individual is, and regulation
or what the individual does with respect to both themselves and others. The
first quadrant is self-awareness. This quadrant represents a person’s ability
to recognize and understand your moods, emotions and drives as well as their
effect on others. Leaders who are self-aware display self-confidence as well
as a strong sense of emotional self-awareness. They also display the ability
to accurately assess themselves. Those around the self-aware leader has
significant personal power.
The other quadrant that appears in the top row of the image is the social or
other awareness. This is the ability to understand the emotional makeup of
other people, and represents a skill in treating others according to their
individual emotional reactions. It is highlighted by empathy and both a
situational awareness that is combined with a clear understanding of the
organization and a strong service orientation. These two quadrants define
who the individual truly is according to emotional intelligence believers.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 376
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 377
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 378
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 379
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 380
Hersey and Ken Blanchard. The Theory was first introduced as "Life Cycle Slide 308
Theory of Leadership”. The theory holds there is no single “best” style of
leadership. Effective leadership is task-relevant and that the most successful
leaders are those that adapt their leadership style to the maturity of the
individual or group they are attempting to lead/influence, and that effective
leadership varies, not only with the person or group that is being influenced,
but it will also depend on the task, job or function that needs to be
accomplished. Within this theory there are four styles of leadership:
Telling — is characterized by one-way communication in which the
leader defines the roles of the individual or group and provides the
what, how, why, when, and where to do the task.
Selling — while the leader is still providing the direction, he or she is
now using two-way communication and providing the socio-
emotional support that will allow the individual or group being
influenced to buy into the process.
Participating — this is now shared decision making about aspects of
how the task is accomplished and the leader is providing less task
behaviors while maintaining high relationship behavior.
Delegating — the leader is still involved in decisions; however, the
process and responsibility has been passed to the individual or group.
The leader stays involved to monitor progress.
How a leader gets their power is also important. There are several sources of
power you must know to prepare for the exam. These sources are not
exclusive. Meaning the total power possessed by any leader is a combination
of the power provided and is defined by the equation below.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 381
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 382
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 383
allocated to the project are actually available as planned. It is also the process
where the project leader works to monitor the team’s actual resource utilization
versus what was planned and take any required corrective action. Be very
careful with this process. Human resources are managed in the last process.
This process is focused on the physical resources such as equipment, materials,
facilities and infrastructure. Do not get confused on this point.
Slide 314
The inputs to the control resources process include:
.1 Project management plan — The key component of the project
management plan included in this process is the resource management plan
created at the beginning of this knowledge area. It defines how resources are
to be managed within the project.
.2 Project documents — The resource management plan found in the
project management plan. It is missing a lot of key information. Much of
that needed information is founded in the additional project documents.
Specifically, PMI® lists the issue log, any physical resource assignments, the
project schedule, the resource breakdown structure, the resource
requirements, and the risk register. Each of these documents is critical to the
leader understanding how the project is being resourced.
.3 Work performance data — The work performance data for controlling
resources tells the project manager about the number and type of resources
used on the project.
.4 Agreements — Often projects rely on the purchasing of equipment or sub-
systems from outside vendors to complete project work. This means there
are also often contracts or other agreements in place defining the way that
work is conducted. The project leader must have access to this information
to successfully control project resources.
.5 Organizational process assets — Within the performing organization,
there is often organizational process assets such as escalation procedures for
handling issues within the performing organization, the lessons learned
repository for information about past projects, and any policies about
resource control and reassignment.
There are four primary tools and techniques used to control resources according
to PMI®
.1 Data analysis — Controlling resources on a project requires a significant
amount of both time and energy analyzing information from the project to
ensure the resources are completing the necessary work. This is done using
alternatives analysis, cost-benefit analysis, performance reviews, and trend
analysis.
.2 Problem solving — No project ever goes exactly as planned. When the
unexpected happens a good leader knows they must examine the current
information and solve problems. It is about finding solutions. Weak leaders
tend to throw up their arms in frustration.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 384
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 385
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 386
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 387
7. You are a project manager managing a resource who has been an outstanding
performer in the past. On your project she has repeatedly missed deadlines.
You discover she is going through a difficult divorce. According to Maslow,
which of the following needs is most likely not being met for this resource?
A. Self-actualization
B. Physiological
C. Safety
D. Social
8. Which of the following is the ultimate goal in Maslow’s Hierarchy of Needs?
A. Self-actualization
B. Esteem
C. Social
D. Physiological
9. Sally has been a senior technical resource with her company. She is
considered the best technical resource in her organization. One day she is
told she is being promoted to be the project manager on a large complex
project. Which of the following best describes Sally’s situation?
A. Promoting within
B. The halo effect
C. Ensuring technical competence
D. A good general business practice is to move people from technical
fields to project management because they will best understand the
project needs.
10. Which of the following is not one of the terms represented by the acronym
RACI?
A. Responsible
B. Accountable
C. Consult
D. Initiates
11. Which of the following is not a primary need in McClelland’s Theory of
Needs or the Acquired Needs Theory?
A. Need for achievement
B. Need for affiliation
C. Need for esteem
D. Need for power
12. Which of the following is not a hygiene factor in Herzberg’s Theory?
A. Responsibility
B. Personal life
C. Relationships at work
D. Status
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 388
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 389
19. You are a project manager leading a bridge construction project. One day
you are meeting with one of your resources when they exclaim, “I cannot
deal with this right now!” What conflict resolution technique are they using?
A. Confronting
B. Smoothing
C. Forcing
D. Withdrawal
20. What does a resource histogram show that a RAM does not?
A. Reporting relationships
B. The person responsible for each activity
C. Key activities
D. Time
21. It is the first day on your new job as a project manager at a large snack food
manufacturing facility. You are taking over a project for a PM that has gone
on maternity leave that is approximately 40% complete and is expected to
take another seven months to complete. There are 15 people working on the
project. You need to determine who is responsible for doing the specific
activities for the entire project. Where would you find this information?
A. Responsibility assignment matrix
B. Brakestone organization chart
C. Team board
D. Control chart
22. You are the new project manager on a project that is significantly behind
schedule. The organization uses a matrix structure. You determine that three
additional resources are required. From whom would you request these
resources?
A. Project team
B. Project manager
C. Functional manager
D. Project sponsor
23. You have just been brought into an organization as a project management
consultant to work with an inexperienced project manager. Upon examining
the project with the PM you discover several important tasks are expected to
get behind because the assigned resource lacks the specific experience to
perform the required work. After doing some research you find there isn’t
another resource available that is better qualified. What is the best solution
for this situation?
A. Provide the resource with greater time reserves to complete the work.
B. Hire a new resource to complete the work.
C. Provide the resource with additional incentives if they complete the
work on time.
D. Arrange for the team member to obtain the necessary training to
perform the task.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 390
24. You are leading one of five sub-teams for a large project. One of the sub-
teams is consistently late with their deliverables forcing your sub-team to
have to crash the critical path repeatedly. What should you do?
A. Meet with the project manager and the leader of the consistently tardy
team together
B. Meet with the project manager alone
C. Meet with the leader of the consistently tardy team alone
D. Meet with the leader of all the sub-teams together
25. You are leading your first project with a very experienced team. The team
has 25 resources fully dedicated to the effort. Approximately 35% through
the execution of the project one of the stakeholders requests a major change
to the scope of the project. Unfortunately, two of your most senior resources
have very different opinions on how the changes should be accomplished.
How should you deal with this conflict?
A. Listen to the different opinions, determine the best choice and
implement that choice.
B. Postpone further discussions, meet with each team member, and
determine the best approach.
C. Listen to the different opinions, encourage logical discussions, and
facilitate an agreement.
D. Help the team focus on the agreeable aspects of their opinions and
build unity by using team building exercises.
26. Today is your first day with XYZ Company. You have been hired to lead a
new project with 8 different departments, 45 different resources, and a single
project sponsor. You must maintain less than a 10% variance on both
schedule and cost. What type of management power will best help you gain
the cooperation of others?
A. Referent
B. Expert
C. Fear
D. Formal
27. Today is your first day with XYZ company. You have been hired to lead a
new project with 8 different departments, 45 different resources, and a single
project sponsor. Unfortunately, two of your most senior resources have very
different opinions on how the project testing should be accomplished. One
says the systems should be integrated before testing and the other maintains
each system should be tested before integration. The sponsor is demanding
the project is completed on time. What is the best thing to do to resolve the
conflict?
A. Force a solution on both parties.
B. Refocus the parties on the project goals.
C. Table the discussion until the next meeting.
D. Require the team to do limited testing before integration and finish
testing after integration.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 391
28. A two year project is coming to an end. It has been a difficult project to
complete due to three major overhauls, two of which involved replacing the
project manager. When you came in this morning one of your senior
resources was waiting in your office to inform you that one of the last key
deliverables did not pass its QA test and the resource working on the item
has been moved off the project by their direct supervisor. Additionally there
is an email in your in box requesting a major shift in scope. With whom
should you address these issues?
A. Senior management
B. Project sponsor
C. The customer
D. The team
29. You are eating lunch with a friend who is explaining why they love their
organization. The friend says, “The team really enjoys our leadership team.
The set clear goals for our performance and explain why those performance
goals are important for our mission. They also establish excellent rewards
for achieving those goals. The best part is, everyone can see the rewards
happening along with the achievement of our goals. Which of the following
theories best describes this scenario?
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 392
31. You are leading a project that contains a great deal of stress. The entire team
has been on edge due to a very tight deadline. This tension has grown to the
point that many team meetings end in shouting matches with little work
being accomplished. Several key stakeholders have asked that scope be
added to the project to better meet their needs. The sponsor has heard
rumors that the project might be having difficulties and wants to attend a
team meeting to get a better sense of how the project is doing and any issues
involved with achieving the desired targets. In this situation, it would be best
for the project manager to:
A. Hold a team-building session that involves all team members.
B. Meet with each resource individually to determine the real issues.
C. Create and implement new ground rules for the team.
D. Ask the sponsor if you can send a written report instead of wasting
their time in the meeting.
32. Which of the following describe how an individual team member is
performing on the project?
A. Project performance appraisals
B. Team performance appraisals
C. Annual performance reviews
D. Project performance plans
33. In January you make a decision as the project manager on a complex issue
facing your project. Everything goes smoothly until July when the same
issue reappears. What did you most likely not do?
A. Proper risk analysis
B. Quantify the risk
C. Have the project sponsor validate the solution
D. Confirm the solution solved the problem
34. The halo effect refers to the tendency to:
A. Promote from within
B. Hire the best
C. Move people into project management because they are good in their
technical fields
D. Move people into project management because they have had project
management training
35. You have just been assigned as a project manager for a large information
technology project. This one-year project is about halfway. The project
team consists of seven external resources and 30 internal resources. You
want to understand who is responsible for doing what on the project. Where
would you find such information?
A. Responsible assignment matrix
B. Resource histogram
C. Bar chart
D. Project organization chart
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 393
36. During your regular status meetings you ask each resource to describe the
work they are doing and then you assign new activities to the resources as
required. The length of these meetings has increased because of the many
different activities requiring assignment. This could be happening for all the
following reasons except:
A. A lack of a WBS
B. A lack of a RAM
C. A lack of resource leveling
D. A lack of involvement in project planning
37. You are leading a large manufacturing project in a weak matrix organization.
Given that you lack the ability to reward your team, none of the resources
report to you, and the project is complicated and difficult, which of the
following types of project management power will likely be the most
effective?
A. Referent
B. Expert
C. Penalty
D. Formal
38. One of your team members is not performing well because they are
inexperienced in the particular technical skill. You do not have any other
resources available to complete the work. Which of the following is the best
thing to do?
A. Consult with the functional manager to determine project completion
incentives for the team member.
B. Obtain a new resource with more technical skills.
C. Arrange for the team member to get training.
D. Allocate some of the project schedule reserve.
39. You are leading your first project and have a very experienced team. The
product of your project is highly technical and represents something your
organization has never done. However, your team is very confident. There
are more than 30 resources on the project; 15 of these resources are
considered true subject matter experts. In one of your team meetings you are
reviewing a preliminary WBS when one of the experts argues a deliverable
should not be done at all. Another of the experts says the deliverable should
be broken into three distinct deliverables and a third expert agrees with both
of them. How should the project manager deal with this conflict?
A. Listen to the differences of opinion, determine the best choice, and
implement accordingly.
B. Postpone further discussions, meet with the experts individually, and
determine the best approach.
C. Listen to the differences of opinion, encourage logical discussions,
and facilitate an agreement.
D. Help the team focus on agreeable aspects of their opinions and build
unity by focusing on team building.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 394
40. You have just been hired as the project manager for a $2,000,000
manufacturing project that has been underway for six months. The project
draws on resources from more than a dozen different departments and has
three primary sponsors. The project has more than 50 major requirements
that must be met. During your first meeting with the primary sponsors you
are told the project must maintain an SPI of between .95 and 1.05.
Additionally, the project has a CPI of .97. Which of the following types of
project management power will best help the project manager gain the
cooperation of the team?
A. Formal
B. Referent
C. Penalty
D. Expert
41. The project manager is trying to settle a dispute between two subject matter
experts who are team members on their project. One says the systems should
be integrated before testing, and the other maintains each system should be
tested before integration. The project involves more than 50 people and 15
different systems must be integrated. The sponsor is demanding the project
be completed on time. What is the best statement the project manager can
make to resolve the conflict?
A. Do it my way.
B. Let’s calm down and get the job done.
C. Let’s deal with this again next week after we all calm down.
D. Let’s do limited testing before integration and finish testing after
integration.
42. The installation project has a CPI of 1.06 and an SPI .97. There are 21 team
members. The project manager was careful to ensure each resource had
input into the schedule and project management plan. The customer has
accepted the six deliverables completed so far and the RAM has not changed
since the project began. The project is being completed in a matrix
environment and there are no external resources being used on the project.
Although the sponsor is happy with the status of the project, one of the team
members is always complaining about how much time his deliverables are
taking. Which of the following would be the best thing for the project
manager to do?
A. Review the reward system for the project.
B. Try to improve the project schedule performance.
C. Meet with the customer to try and extend the schedule.
D. Gain formal acceptance in writing from customer.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 395
43. The project manager is looking at the project’s resource needs and lessons
learned from past projects. This information causes the project manager to
be concerned about the ability to acquire enough resources for the project in
six months. Which of the following would be the least effective preventive
action?
A. Make sure functional managers have a copy of the resource
histogram.
B. Show the sponsor the data and explain the project manager’s concern.
C. Determine metrics to use as an early warning sign that resources will
not be available.
D. Ask functional managers for their opinions.
44. A large project is underway when one of the team members reviews the
project status report. He sees the project is currently running late. As he
looks at the report further he notices the delay will cause one of his activities
to be scheduled during a time he will be out of the country and cannot work
on the activity. This is of great concern to the team member because he is
very committed to the success of the project and he does not want to be the
cause of the project being further delayed. What is the best thing for him to
do?
A. Contact the project manager immediately to provide the project
manager with his schedule.
B. Include the information in his next report.
C. Request the issue be added to the project issue log.
D. Recommend preventive action.
45. There have been many work packages completed successfully on the project,
and the sponsor has made some recommendations for improvements. The
project is on schedule to meet an aggressive deadline when the successor
activity to a critical path activity suffers a major setback. The activity has 14
days of float and is being completed by four people. There are two other
team members with the skill set to assist the troubled activity, if needed. The
project manager receives a call that three other team members are attempting
to be removed from the project because they do not feel the project can be
successful. When the project manager pursues this, he discovers that those
team members have issues that have not been addressed. Which of the
following is the best thing to do to improve the project?
A. Have the team members immediately assist the troubled activity.
B. Investigate why the project schedule is aggressive.
C. See who can replace the three team members.
D. Create an issue log.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 396
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 397
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 398
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 399
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 9 — Project Resource Management
Page 400
43. Answer A. Sending data without pointing out the issue does not mean the
communication will be adequately decoded by the recipient. The other
choices describe more effective communication in this instance.
44. Answer D. Notice the question asks what the team member should do. It is
important for the project manager to understand the team member’s role and
possibly even instruct team members on how to work on projects and what is
expected of them. Providing the project manager with his schedule,
including the information in a report, and requesting that the issue be added
to the issue log have one thing in common. They all involve the team
member asking the project manager to do something. In reality, it may very
well be the team member who will come up with a solution. Therefore,
recommending preventive action is the best choice for the team member.
45. Answer D. Sometimes complex problems are caused by not doing simple
things. The data in the first part of the question, once you read the choices, is
completely extraneous. The troubled activity has float and so does not need
immediate attention. It may not be necessary for additional team members to
assist the troubled activity, but none of the choices suggest investigating
whether the amount of float is enough to cover any delay caused by the
trouble. Rather the choices take you in different directions. Investigating
why the schedule is so aggressive should have been done before the project
began. Replacing team members does not solve the root cause of the
problem. Wouldn’t it be more effective to discover the root cause of those
troubled team members’ concerns so the problem does not surface again?
The creation of an issue log will let the troubled team members know their
concerns have been heard, are noted, and will be resolved. This might be
enough to stop them from leaving and avoid the resultant project delays and
confusion if new team members must be added.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 401
Communications Management
Overview
Chapter ten of the PMBOK® Guide is dedicated to the Slide 318
communications management knowledge area. There
are three processes found in the communications
management knowledge area. These processes include
the following:
Plan communications management
Manage communications
Monitor communications
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 402
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 403
Slide 322
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 404
and add two more. To answer this question you must first determine the
channels for each population (7 and 9) and then determine the difference as
shown below.
(7(7-1))/2 = (7*6)/2 = 42/2 = 21
(9(9-1))/2 = (9*8)/2 = 72/2 = 36
36 – 21 = 15
The correct answer is 15.
For the exam it is also important that you learn the communication styles that
may be used to convey information. These styles are as much about how
stakeholders perceive the project manager as they are about how the project
manager is trying to sound. The styles may be combined to create an individual Slide 325
style. These styles include the following:
Authoritarian — When using an authoritarian style the sender gives
expectations and specific guidance. The sender is the person in authority.
Promotional — A sender using a promotional style attempts to cultivate
team spirit and excitement around the information being conveyed.
Facilitating — A sender using a facilitating style gives guidance as required,
but acts only in a non-interfering manner. They are the keepers of the
process, but do not take a position on the issue.
Conciliatory — A sender who uses a conciliatory style is friendly and
agreeable with the goal of building a compatible team.
Judicial — A sender who uses a judicial style wants to be perceived as using
sound judgment or being logical.
Ethical — A sender who is ethical is seen as being honest, fair, or “by the
book.”
Secretive — A sender who is perceived as secretive is not open or outgoing.
They do not share information with the team or stakeholders. This is usually
to the project’s detriment.
Disruptive — A sender who is disruptive works to break apart the unity of
the group, and is often perceived as an agitator. This is usually seen as a
negative impact on the group, but is not seen as threatening to anyone.
Intimidating — A sender using an intimidating style is perceived as a
“tough guy,” who is attempting to influence the group through fear. This can
lower morale.
Combative — A sender who is combative is seen as eager to fight or be
disagreeable with others. This is usually to the detriment of the team.
10.1 Plan Communications Management
The first process in the communications management knowledge area is plan
Slide 326
communications. This is the process of determining the project stakeholder
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 405
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 406
Page 407
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 408
management plan. This process is performed throughout the entire project and
in all its management processes. This process also includes responding to
unplanned requests for information concerning the project.
The inputs to the manage communications process include the following:
.1 Project management plan — The project management plan includes a lot
of information. To successfully manage communications the team must
examine the resource, communications, and stakeholder engagement plans to Slide 332
understand the communications needs and expectations.
.2 Project documents — If the project management plan provides a lot of
documents, the project documents package provides a huge number.
Specific to the manage communication process is the change log, the issue
log, the lessons learned register, the quality report, risk report, and the
stakeholder register.
.3 Work performance reports — Work performance reports are used to
show project performance and status information. According to the
PMBOK® Guide, these should be made available prior to project meetings.
A key element of any performance report is the forecasting information
indicating when the project is expected to finish. These reports are discussed
in more detail in the Report Performance Process section that follows.
.4 Enterprise environmental factors— What is happening around the
project has a great deal to do with what is communicated.
.5 Organizational process assets — Any policies, procedures or guidelines
held by the organization that may aid in the distribution of information.
The tools and techniques used in the manage communications process include
the following:
.1 Communication technology — The 21st century has added a wealth of
technology-based tools for project managers to use towards improved
communication. Examples include SharePoint, VersionOne, or EPM.
.2 Communications methods — Communication methods are generally
broken into two types and two categories: they are verbal and written, and
formal or informal.
.2 Communication skills — There are a number of key skills that are used
in managing communication. These include:
Communication competence — A combination of tailored
communication skills that considers factors such as clarity of
purpose in key messages, effective relationships and
information sharing and leadership behaviors.
Feedback — Feedback represents the returned information
about communication in terms of a reaction, a deliverable, or
a situation. It is a key element of interactive communication.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 409
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 410
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 411
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 412
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 413
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 414
13. Which of the following is the first process found in the communications
Management Knowledge Area?
A. Plan communications management
B. Identify stakeholders
C. Distribute information
D. Report performance
14. Your organization is having a difficult time managing all of its projects. You
have been asked to help senior management get a better understanding of the
problems. What do you do first?
A. Meet with individual project managers to get a better sense of what is
happening.
B. Send a formal memo to all project managers requesting their project
plans.
C. Meet with senior managers to help them develop a new tracking
system for managing projects.
D. Review the project charters and Gantt charts for all projects.
15. Project A has had poor project meetings since its inception. There have been
complaints that information does not get to the right people, some people are
talking too much during the meeting, and the right people are not there to
resolve issues. What is most likely missing from this project?
A. A scope management plan
B. A responsibility chart
C. A communications management plan
D. A resource matrix
16. A company asks one of the project managers to lead a project to create a
substantially improved version of one of the company's best selling products.
The project manager is given total freedom of decision and resources,
including whether to utilize contractor services and/or the company's
resource pool. Under these circumstances, which of the following would be
the best way for the project manager to build the team?
A. She should choose her team from the top developers and fabrication
workers in the company.
B. She should create a team of company line workers and contracts the
development services under a "cost reimbursable" contract with
provisions to protect confidentiality.
C. She should contract the entire team utilizing a "cost plus incentive
fee" type of contract.
D. She should contract selected team members on an ad hoc and as
needed basis utilizing a "time and materials" type of contract.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 415
17. While creating the agenda for a status meeting with the team, a project
manager receives input from one team member that an item should be added.
Another team member says the team is not ready to resolve the item during
the meeting. After much discussion, the project manager decides to put the
item on the agenda as an initial discussion item only. Which conflict
resolution technique is the project manager using?
A. Compromise
B. Smoothing
C. Forcing
D. Withdrawal
18. To a project manager, what is a disadvantage of progress reports over
watching what is going on in a project, asking questions, and assisting team
members?
A. Progress reports include information from all the team.
B. Progress reports include information from stakeholders.
C. Progress reports generally show problems after they have occurred.
D. Progress reports supply information about trends.
19. A resource assigned to your project contacts you, trying to get off the team.
He knows that an important project in his department is going to be approved
and will take place at the same time as yours. He wants to work on the other
project. Under the circumstances, what should you do?
A. Release him from the team.
B. Talk to the functional manager about releasing him from the team.
C. Release him after he finds a suitable replacement.
D. Speak with the project sponsor about releasing him from the team.
20. A large, one-year telecommunications project is about halfway done when
you take the place of the previous project manager. The project involves
three different sellers and a project team of 30 people. You would like to see
the project's communications requirements and what technology is being
used to aid in project communications. Where will you find this information?
A. Project management plan
B. Information distribution plan
C. Stakeholder management plan
D. Communications management plan
21. As a project manager you are dealing with a series of communication
blockers. The most likely result of communication blockers is that:
A. Conflicts will occur
B. The project sponsor will be unsatisfied
C. The project will fail to meet its schedule target
D. Trust will be improved
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 416
22. One of the key issues when dealing with didactic communication is that the
sender ______ the receiver.
A. Uses more than one channel with
B. Shows concern for the perspective of
C. Enunciates clearly to
D. Talks more loudly to
23. When is it most likely that formal written communication with the customer
is required?
A. Quality audits fail
B. Stakeholders request additional features not specified in the contract
C. Changes to the critical path are required to meet the deadline
D. The project has cost overruns
24. You are managing a large textile project and have discovered one of your
resources is significantly underperforming. What is the best form of
communication for addressing this problem?
A. Informal verbal communication
B. Informal written communication
C. Formal verbal communication
D. Formal written communication
25. When communicating within the boundaries of a contract which
communication style tends to be most prevalent?
A. Informal verbal
B. Informal written
C. Formal verbal
D. Formal written
26. You are leading a U.S. $250,000 information technology project. Your SPI is
1.04 and your CPI is 0.99. You are 70% through the deliverables of the
project. When you do your weekly status updates, which type of
communication does it represent?
A. Informal verbal
B. Informal written
C. Formal verbal
D. Formal written
27. You are leading an effort to complete negotiations for a major new initiative
for your organization. In this situation how important are nonverbal
communication skills?
A. Not important
B. Very important
C. Important only when dealing with requirements
D. Important to ensure you win
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 417
28. You are preparing to lead a large project within your organization that will
require over 40 resources and likely take more than 18 months. Where will
you likely define the communication requirements and technology used to
support good project communication?
A. The stakeholder management strategy
B. The communications management plan
C. The information distribution plan
D. The project management plan
29. You are leading a $300,000 manufacturing project. The project has been
going for six months and has another four months scheduled. Project
information has consistently been delivered in accordance with the
communications management plan, and all scope changes have followed the
appropriate change management guidelines. One day you are approached by
a key stakeholder who is very surprised to learn about a change that was
approved two months ago and received by all stakeholders. What should you
do?
A. Ask the sponsor why the stakeholder did not understand their
responsibilities.
B. Address the situation in the next steering committee meeting to
ensure no one else missed the change.
C. Review the communications management plan to see what revisions
are necessary.
D. Determine why the stakeholder did not receive the information and
let them know when it was published.
30. You are leading a manufacturing project for your organization that started
five months ago. In your latest status meeting two of your resources argue
about what needs to be done to complete a work package. To best
understand what is going on you should pay the most attention to what?
A. What is being said and when.
B. What is being said, who is saying it, and the time of day.
C. Physical mannerisms and what is being said.
D. The pitch and tone of the voices and the physical mannerisms.
31. You have been selected to lead a major project for a large petroleum
company. The project is critical to the organization’s success. The project is
going to consist of resources from three different continents. What type of
communication should be used?
A. Informal verbal
B. Informal written
C. Formal verbal
D. Formal written
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 418
32. It is Friday afternoon and you are conducting your normal end-of-week
status meeting. Unfortunately, it is not going well. Everyone is talking over
each other, some team members are not participating, and topics are being
raised and discussed totally randomly. Which of the following rules for
effective meeting management is not being followed?
A. Every meeting must have a purpose and the correct participants in
attendance.
B. Meetings should be scheduled in advance.
C. Create and publish an agenda with a set of rules for controlling the
meeting.
D. Participants should demonstrate courtesy and take turns speaking.
33. You are on a business trip visiting a client site at a location that is in a time
zone two hours ahead of the client site. As the project manager you are
conducting your weekly status meeting with your team via telephone. Which
of the following is the most important to ensure good communication with
your team?
A. Review the list of attendees and deliverables
B. Ask team members to repeat back what you ask them to do
C. Ask the team members to discuss change requests
D. Review work status
34. Which of the following are always stakeholders?
A. A person who does not want the project completed
B. A union worker who will use the product or service
C. A functional manager from the finance department
D. A worker who might lose their job because of the project
35. Six months into a one-year project everything is going well. The project
currently has an SPI of 1.05 and a CPI of .99. The stakeholder management
strategy has worked well and the BCI has been steadily improving. The
sponsor just left your office after expressing their gratitude for you and your
team’s hard work. You get a call from one of your resources saying the
deliverable from the completion of their activity’s predecessor is three days
late. Which of the following reasons would best describe why this occurred?
A. The project manager was focusing on the sponsor’s needs.
B. The successor activities should have been watched, not the
predecessors.
C. Functional management was not included in the communications
management plan.
D. The right people were invited to the milestone party.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 419
36. You are leading a small information technology project which is scheduled to
take one year and is approximately halfway complete. You have just taken
over as the project manager. The project involves four different external
resources and a project team of 25 people. You would like to see the
project’s communications requirements and what technology is being used to
aid in project communications. Where will you find this information?
A. The project management plan
B. The information distribution plan
C. The bar chart
D. The communications management plan
37. Changes to some project deliverables have been documented in the project
management plan. These changes, and other project information, have been
distributed according to the communications management plan. One
stakeholder expressed surprise to the project manager upon hearing of a
documented change to a project deliverable. All stakeholders received the
communication containing notification of the change. What should the
project manager do?
A. Determine why the stakeholder did not receive the information and
let him know when it was published.
B. Ask the functional manager why the stakeholder did not understand
his responsibility.
C. Review the communications management plan and make revisions if
necessary.
D. Address the situation in the next steering committee meeting so
others do not miss published changes.
38. Two people are arguing about what needs to be done to complete a work
package. If the project manager wants to know what is going on, she should
pay most attention to:
A. What is being said and when
B. What is being said, who is saying it, and the time of day
C. Physical mannerisms and what is being said
D. The pitch and tone of the voices, and physical mannerisms
39. A project manager has a project team consisting of people in four countries.
The project is very important to the company, and the project manager is
concerned about its success. The length of the project schedule is
acceptable. What type of communication should he use?
A. Informal verbal communication
B. Formal written communication
C. Formal verbal communication
D. Informal written communication
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 420
40. The project status meeting is not going well. Many attendees are talking at
the same time, there are people who are not participating, and any topics are
being discussed at random. Which of the following rules for effective
meetings is not being adhered to?
A. Demonstrate courtesy and consideration of each other, and control
who is allowed to speak.
B. Schedule meetings in advance.
C. Have a purpose for the meeting, with the right people in attendance.
D. Create and publish an agenda and a set of rules for controlling the
meeting.
41. A project manager overhears a conversation between two stakeholders who
are discussing how unhappy they are with the impacts of the project on their
own departments. Stakeholder A asks if the project is on time, and
stakeholder B replies that the SPI is 1.05. Stakeholder A asks if the project
manager for the project knows of stakeholder B’s concern. Stakeholder B
responds that he is not sure. What is the best thing for the project manager to
do?
A. Make sure the stakeholders see that the project manager overheard.
Then ask them to direct any questions in writing to the project
manager.
B. Make a presentation to all the stakeholders regarding the status of the
project.
C. Send both stakeholders a copy of the issue log and ask for additional
comments.
D. Arrange a meeting with both stakeholders to allow then to voice any
concerns they may have.
42. During the middle of the project, things have been going well. The work
authorization system has allowed people to know when to start work, and the
issue log has helped keep track of stakeholders’ needs. The sponsor has
expressed has appreciation for the team members’ efforts by hosting a
milestone party. The project manager gets a call from a team member saying
the results from the completion of her activity’s predecessor are two days
late. Which of the following reasons would best describe why this occurred?
A. The project manager was focusing on the sponsor’s needs.
B. Functional management was not included in the communications
management plan.
C. The successor activities should have been watched, not the
predecessors.
D. The right people were not invited to the milestone party.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 421
43. You are leading a project that has 20 team members and affects more than a
dozen departments in the organization. Your project has been going well and
you are approximately 1/3 complete and the project has been going so well
that you decide to hold a party to celebrate. You invite all the key
stakeholders to the party so the team can have the opportunity to
communicate informally with the stakeholders about their efforts. At the
party, you walk around to try to discover any relevant information that would
help you make the project even more successful. You happen to hear one of
the senior stakeholders talking about setting up more regular meetings on the
project. Which of the following would be the best thing to do?
A. Review the information distribution methods on the project.
B. Provide the executive a copy of the communications management
plan and remind them that all such concerns should be brought to
you, the project manager.
C. Record the effectiveness of the party in the lessons learned for future
events.
D. Arrange the requested meeting with the stakeholder and team.
44. The requirements from several of your stakeholders were not approved for
inclusion in your project, and you had a difficult time receiving formal
approval of the project management plan. The stakeholders argued and held
up the project with meeting after meeting about their requirements. The
project was finally approved and work began three months ago. All of the
following would be good preventive actions to implement except which:
A. Maintain an issue log.
B. Ensure the change control process is not used to reintroduce the
requirement back into the project.
C. Hold meetings with the stakeholders to go over the work that will not
be added to the project.
D. Keep a log of the not included requirements.
45. One of your project resources calls in to a normal status meeting. During
their update you cannot hear them well due to interference from their cell
phone. A few weeks later you call the resource to locate a past due
deliverable and the resource reminds you that they had told you previously
that the deliverable would be late. You do not remember being told and
question when the resource informed you of the delay. They tell you it was
during the meeting where they were on the phone. What could have been
done to avoid this problem?
A. Para-lingual communication
B. Feedback during the communication
C. Better attention to determining communication requirements
D. Adding to the issue log after the phone call
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 422
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 423
14. Answer A. Always remember, the first step is to analyze the situation to see
what is happening. If this is a choice take it!
15. Answer C. A common cause of project failure is not having a
communication management plan. It is a simple document that provides
significant help managing expectations.
16. Answer A. Hopefully, this was an easy one. The key here is remembering
to always take the best resources you can. Most of the question is a ruse
designed to distract you.
17. Answer A. This question moves back into the resource management
knowledge area. Of the choices given, compromise is the lesser of four
evils.
18. Answer C. This question is driving at the important distinction between
being reactive and proactive. As a project manager your goal is to always be
proactive.
19. Answer B. There are two issues here. First, a resource that does not want to
be on your project is likely not going to be that committed to the effort.
Secondly, if you are willing to try to help the resource out you can build trust
with them for the next project.
20. Answer D. This is a simple definitional question. The communication
management plan defines all aspects of communication for the project.
21. Answer A. The single most common result of blocked or poor
communication is conflict. Remember, conflict is not necessarily bad. How
we choose to handle it will define whether it is good or bad.
22. Answer B. Didactic communication, or one-on-one communication, is most
successful when the sender displays empathy for the receiver’s perspective.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 424
23. Answer B. The introduction of the word contract creates a level of formality
that does not exist in the other options. It is therefore the best option.
24. Answer A. This question is about communication between two parties. The
first thing you need to do is let the resource know you are not happy with
their performance and only when that does not work go to more formal styles
of communication. Note that this does not mean you do not keep a record of
the communication.
25. Answer D. Whenever a contract becomes involved communication tends
toward the formal and written style.
26. Answer D. Weekly status reports are assumed to be a formal written part of
the project management process unless specifically defined otherwise.
27. Answer B. Remember that nonverbal communication accounts for 55% of
understanding in any communication scenario.
28. Answer B. Although the communications management plan is part of the
project management plan, the communications management plan is the best
answer as it directly answers the question.
29. Answer C. This is a trick question of sorts. The question states that all
stakeholders received the information about the change so option D is out.
The next best option is reviewing the communications management plan and
determining what changes need to be made.
30. Answer D. The question amounts to asking you where do we get most of
our understanding. We get 55% from nonverbal communication. We get
38% from tone and the remaining 7% from the actual words being said.
31. Answer D. Distance, the potential for language barriers, time barriers and
cultural barriers make formal written communication the best choice.
32. Answer C. This is a problem where the meeting participants lack any
structure and are therefore not achieving the desired results. Meetings
should always have an agenda, and the team needs to have a standard set of
rules by which it will operate.
33. Answer B. This question is taking you back to the didactic communication
model. That model describes the importance of two loops. The initial
communication loop goes from the sender to the receiver and the second
loop (required to ensure good communication) goes from the receiver back to
the sender.
34. Answer B. The user of the result of a project is always a stakeholder. The
others might or might not be stakeholders.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 425
35. Answer C. Since the question does not provide any information about the
sponsor, focusing on their needs cannot be the answer. A good project
manager watches both predecessors and successors, and notifying different
people about the achievement of milestones would not impact the call you
received. Often we forget the bosses of team members in the communication
management plan. If the functional manager of the team member assigned to
the predecessor activity had been included, he or she would have known
when the team member was needed to do work and the impact of any delay.
36. Answer D. Although the information is found within the project
management plan, the communications management plan is the best answer
because it directly answers the question.
37. Answer C. The question states that all stakeholders received the
information, so the issue is not that this stakeholder did not receive it. The
problem presented here illustrates that there is something missing in the
communications management plan. The best answer is to review the
communications management plan in order to prevent future problems and
find any instances of similar problems.
38. Answer D. Remember that nonverbal communication represents 55%,of all
communication. The choice including para-lingual communication (pitch
and tone), as well as physical mannerisms, is the best choice.
39. Answer B. Because of the differences in culture and the distance between
team members, formal written communication is needed.
40. Answer D. Courtesy and consideration is not a “rule” for effective meetings.
Since there is no indication that the meeting was not scheduled in advance or
that there isn’t a purpose, these cannot be the best answers. “Discussed at
random” implies no agenda. If an agenda is issued beforehand, people will
follow the outline and should not need random discussions.
41. Answer D. This is another question with more than one right answer.
Would asking for something in writing be the best way to communicate? In
this particular situation, asking for the concern to be in writing might alienate
the stakeholders. The issue log is where the issue should be listed, but the
situation does not say if the project manager knows what the stakeholders’
concern is. Therefore, using the issue log cannot be the best choice. This
problem would likely require informal verbal communication to discover the
real problem. Arranging a meeting with the concerned stakeholders is
therefore the best choice.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 10 — Communications Management
Page 426
42. Answer B. Since there is no information about the sponsor or his needs in
this situation, focusing on his needs cannot be best. The statement that
successor activities should have been watched, rather than predecessors, is
not a correct statement. A good project manager always watches both. Often
forgotten in communications management plans are the bosses of team
members. In addition, it helps the functional managers to manage their
resources effectively. If the functional manager of the team member
assigned to the predecessor activity had been included in the project planning
processes, he would have known when the team member was needed to do
the work for the project and the impact of any delay. They communications
management plan should have also included a method to communicate
potential delays.
43. Answer A. This is another example of a question where you might want to
do several of the items listed. The real question is what would you do first?
In this case you must realize that the fact that one of your key stakeholders is
asking for more meetings means they are not getting the information they
need. Adding more meetings will not solve the problem and often too many
meetings is a key problem for project managers. The correct answer is figure
out why the stakeholder is not getting the information they require which
requires a review of the information distribution methods of the project.
44. Answer C. You have already held a lot of meetings which added little value.
Holding more meetings will not help to convince the stakeholders about
something they feel passionate about. The best you can hope for is
establishing parameters to protect the project.
45. Answer B. Giving and requesting feedback is always the best way to ensure
understanding. Para-lingual is simply dealing with the pitch and tone of
communication and adds no value. The issue log would not have prevented
the problem as the project manager did not know what to write.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 427
Risk Management
Overview
Chapter eleven of the
PMBOK® Guide is Slide 337
dedicated to the risk
management knowledge
area. There are seven
processes found in the risk
management knowledge
area. These processes
include:
11.1 Plan risk management
11.2 Identify risks
11.3 Perform qualitative risk Risk
analysis Management
11.4 Perform quantitative risk is the most
analysis difficult
11.5 Plan risk responses knowledge area on
11.6 Implement risk responses the exam.
11.7 Monitor risks Dedicate extra
Image 112: Plan Risk Management time to learning it.
The risk management knowledge area includes the processes concerned with
conducting risk management planning, identification, analysis, responses and
monitoring and control on a project. It is typically one of the most difficult
knowledge areas on the exam for three reasons. First, risk management requires
you to memorize and understand the six processes exactly in order without
variation. This includes having a very strong understanding of the inputs, tools
and techniques, and the outputs of each process. Second, PMI’s understanding
of risk is likely very different from the one you are used to. Finally, the risk
management knowledge area provides the last major set of calculation and
modeling techniques that must be learned in this course. As we progress through
this chapter, several techniques will be provided to help you memorize the
processes involved in risk management.
So what is risk? Risks are simply unknown events which might happen. Slide 338
According to PMI®, risks exist at two levels for every project. The first level is
the individual project risk. This level addresses an uncertain event or condition
that, if it occurs, has a positive or negative effect on one or more project Risks can be
objectives. The second level of project risk is overall project risk. This is the positive or
effect of uncertainty on the project as a whole, arising from all sources of negative.
uncertainty including individual risks, representing the exposure of stakeholders
to the implications of variations in project outcome, both positive and negative.
[PMBOK® Guide 6th Ed. p. 397]
The goal of risk management is to increase the probability and impact of positive
risks and decrease the probability and impact of negative risks, realizing that
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 428
Slide 339
risks often have more than one cause and more than one impact. Project risk
management is absolutely critical to project success because it impacts every
other knowledge area. Risks can occur any where at any time and successful
project managers know they must effectively manage the risks to deliver results.
The definition of a risk gets more complicated. Not only are there two types of
risks, good and bad risk, there are also two further categories within each of
these: known unknowns and unknown unknowns. Are you confused yet?
An unknown is just something that might happen. Its result could be good or
Slide 340
bad. The real question is do you know whether it is a possibility or not? If the
possible future event is visible to you, i.e. you know it might happen, we say that
is a known unknown. If the risk is something which is not visible to you or you
do not know about it, we call it an unknown unknown. Why the distinction?
Known unknowns can be planned for and become the responsibility of the
project manager. Unknown unknowns cannot be planned for and require
management reserves or general contingency. Unknown unknowns can only be
recognized once they have occurred. Up to 90% of the risks on a project fall into
the known unknown category and can be identified, investigated, and planned
for.
Before discussing the processes involved with the risk management knowledge
area, a few terms must be defined.
Risk Tolerance — Risk tolerance is the amount of risk a person or group of Slide 341
people is willing to accept. It is the project manager’s responsibility to
ensure that the project operates within the risk tolerance of the sponsor and
key stakeholders.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 429
Risk Averse — Someone who is risk adverse has a low risk tolerance. A
sponsor or key stakeholder who is risk adverse can significantly impact the
delivery of a project by limiting the choices the project manager and team
may make to achieve desired project results.
Risk Factors — Risk factors are drivers or descriptors of a project risk. The
key risk factors are largely common sense and are listed below.
Probability & Impact — Probability defines how likely the risk is to
occur. Impact defines the result of the risk. Typically, project risks
are scored using a probability and impact (or PI) score which will be
described later in this chapter.
The range of possible outcomes — Many risks have more than one
possible outcome. Understanding that range can be an important
element in successfully managing the project risk and delivering the
project.
Expected timing in the project life-cycle — When a risks occurs, it
can have a significant impact on the overall success of the project.
For example, many risks that occur early in the project are easier to
overcome than those which occur late in the timeline.
Variability risk — This is a non-event risk. Uncertainty exists about some
Slide 342
key characteristics of a planned event, activity, or decision. Variability risks
include things such as productivity being above or below a target, the error
count found during testing being higher or lower than expected, or weather
conditions impacting construction.
Ambiguity risk — Uncertainty exists about what might happen in the future.
This risk deals with the fact that there are areas of imperfect knowledge that
might impact the team’s ability to achieve the project’s objective. Examples
changes in regulation or law, or inherent systemic complexity.
Project resilience — Resilience is the ability to overcome unknown risks
when they occur. Resilient projects have a much higher probability of
success.
Integrated risk management — Integrated risk management provides a
coordinated approach to enterprise-wide risk management to ensure
alignment and coherence to ensure risks are managed across all levels of the
organization. Using an integrated approach to risk management build risk
efficiency into the structure of the performing organization.
11.1 Plan Risk Management
The first process in the risk management knowledge area is plan risk Slide 343
management. The plan risk management process is focused on deciding how to
approach and conduct risk management activities for a project. Like the other
planning processes within the PMBOK® Guide, the primary output of the plan
risk management process is the risk management plan. As the project manager
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 430
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 431
of others. This requires getting together and actually talking to each other.
The most important meeting is the project kick-off meeting because it is the
first meeting of the project.
The entire purpose of this process is to develop a single output, the risk Slide 345
management plan. This plan has a number of components that you must know
for the exam. These include the following:
Methodology — Methodology defines the processes and practices the team
intends to use to manage the project risks. It answers the question how?
Make sure to
Roles and Responsibilities — The roles and responsibilities define who will know what is
do what to manage the various project risks using the defined methodology. included in a
Risk
Budgeting — Budgeting defines how much money is available for the Management Plan.
various risk management activities and when that money will be available.
Timing — A key question in risk management is: when do the various risk
management activities need to occur? We are not referring here to the risks
themselves, which will later be defined.
Risk Categories (RBS) — Establishing the categories which will be used
can be an important tool to manage project risks. The most common form of
categorization is a risk breakdown structure, or RBS. This is one of two
definitions for the acronym RBS. The other is a resource breakdown
structure, which is used in project resources management to define the
organization of the project team. A risk breakdown structure shows the risks
organized into groups or categories without any prioritization or other
measure. It is a visual representation of the statement, these risks go
together. Image 115 shows a sample risk breakdown structure.
Slide 346
Page 432
Revised stakeholder tolerances — The tolerance data tells the team how
much risk the various stakeholders feel comfortable accepting. Keeping this
information updated is critical to managing stakeholder expectations.
Reporting formats — Reporting formats define how the outcomes of the
risk management processes will be documented, analyzed and
communicated. It defines both the content and format of the risk register.
Tracking — Tracking documents are how the various risk activities will be
recorded for both the current project and lessons learned.
Definitions of probability and impact — Risks are typically prioritized
according to their potential implications for having an effect on project
objectives. There are a number of scales which may be used to represent
both the probability and impact of a project risk. The most common
measures use linear, non-linear, or relative scales to represent the data. The
most common risk categories to be represented using these scales are cost,
time, scope, and/or quality.
Linear Scale — A linear scale increments a consistent amount as Slide 347
values climb the scale. The most common example of a linear scale
occurs in measuring the probability of a project risk occurring and
often uses values of 1, .3, .5, .7, .9.
Non-linear Scale — A non-linear scale climbs the scale using some
factor that is not linear. A common example is an impact scale where
the scores double at each interval such as with the values .05, .10, .20,
.40, .80.
Relative — A relative scale is one where the distance between one
measure and the next may not be measured or interpreted. A simple
example is seen with the values very low, low, medium, high, very
high.
Matrices — The purpose of the matrices during planning is to define impact and
probability ratings. These will be used to evaluate risks that will be identified
later. Image 116 shows a sample impact matrix which could be used to score
potential project risks. Think of it as the rules for scoring project risks.
Slide 348
Page 433
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 434
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 435
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 436
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 437
Page 438
Page 439
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 440
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 441
hierarchical charts come into play. Bubble charts are one example of
this multi-dimensional visual tool.
.7 Meetings — Most of the processes you have seen have involved meetings
because they involve the project leader using their facilitation skills to gain
information from stakeholders to benefit the project. Meetings are used here
as well.
The only output from the perform risk qualitative analysis process are project
document updates, primarily in the form of updates to the risk register and risk
report. Think back for a moment to the beginning of the risk management
knowledge area. The first step was to create the risk management plan. Then
the risk register was created based upon the rules and processes established in
the plan. The risk register at this point contains an unordered listing of all the
potential risks for the project. In the third step we took that list and ordered the
list so the most significant risk was at the top and the least significant risk is at
the bottom. The best way to accomplish this ordering is to add a column to the
risk register — called the PI score — for probability and impact. Now you have
an ordered risk register and are ready to move onto the next step. You also may
have updates to the assumption and issue logs.
11.4 Perform Quantitative Risk Analysis
In the perform quantitative risk analysis process the risks found in the newly
ordered risk register are more carefully examined to understand in detail the
significance of each risk. This is done starting at the top of the list with the
highest scoring risk and working down. At some point the team reaches a risk Slide 362
that requires more effort and expense to analyze than the risk is worth in terms of
its potential impact. At this point analysis is
ended.
The inputs to the perform quantitative risk
analysis process include the following:
.1 Project Management Plan — The project
management plan establishes the rules, tools,
and processes that are used to manage the
project. To understand the significance of
each risk the team needs to exam the risk
management plan, the scope baseline, the Slide 363
schedule baseline, and the cost baseline.
.2 Project documents — To understand the Image 120: The Quantitative
significance of the defined project risks the Risk Analysis Process
team also must examine a large number of the documents defined outside the
project management plan. These include the assumption log, the basis of
estimates, the cost estimates and forecasts, the duration estimates, the
milestone list, the resource requirements, the risk register and risk report, and
the schedule forecast. Remember the goal of this process is to understand
each risk enough to answer the question, how significant is the risk really?
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 442
This analysis is much more robust that the one done for qualitative analysis.
.3 Enterprise environmental factors — Often the organization has access
to industry studies from similar projects or other published commercial
information that can aid in the quantitative analytical process.
.4 Organizational process assets — The organizational process assets that
apply to the perform quantitative risk analysis process include any
information from prior, similar projects.
The tools and techniques used in the perform quantitative risk analysis process
include the following:
.1 Expert judgment — The use of expert judgment has been consistent
throughout the course. It is used here because the team hopefully has
experience with similar projects and can evaluate the significance of the
identified risks.
.2 Data gathering — Data gathering can represent a wide range of
techniques and tools. They can be as simple as interviewing and analyzing
historical data from past projects.
.3 Interpersonal and team skills — The team must come together to discuss
the information collected about the types and impacts of project risks
discovered. The project leader must add their facilitation skills to this
process for success.
.4 Representations of uncertainty — How likely is any risk to occur, and
how confident is the team in both that likelihood and the analysis of the
project impact? Until the risk actually occurs, the answers to these questions
is some form of a guess, often based on some kind of a belief in an
understanding of the type of data. Teams regularly use curves to represent
this data such as the various distributions we discussed earlier in this course
(normal, triangular, beta, etc.)
.5 Data analysis — There are a number of data analysis techniques used in
this process that are important for test takers to understand. These include:
Sensitivity Analysis — Sensitivity Analysis examines the extent to
which uncertainty affects the objective being examined when all else
is equal. A common display for sensitivity analysis is a tornado
diagram.
Simulations — The common form of simulations are Monte Carlo
simulations. Monte Carlo simulations are advanced computer models
that have only been available for the last five to ten years. They
allow the project team to pretend to execute the project 1,000
different times to determine the likelihood of a particular outcome or
risk. For the exam you must remember that Monte Carlo simulations
require a significant amount of expertise and also provide the greatest
accuracy. The most common Monte Carlo simulations use the WBS
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 443
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 444
Slide 366
Outcome Cost Probability Product
Optimistic Outcome $150,000 .20 $30,000
Likely Outcome $225,000 .50 $112,500
Pessimistic Outcome $300,000 .30 $90,000
$232,500
Image 122: An Expected Monetary Value Example
will see they sum to 100%. To illustrate further, imagine having three
tasks on a project (A, B, and C). A has a 36% chance of costing X. B
has a 49% chance of costing Y, and C has a 68% chance of costing Z.
Why don’t the percentages sum to 100%? The answer is that A, B,
and C are not mutually exclusive options. You have to do all three
tasks on the project. To calculate the EMV for each row, simply
multiply the variable—in this case cost—by the probability to
achieve the product column, then add the results together. This
provides the cumulative result.
Decision Trees — Decision trees provide a visual methodology to
calculate outcomes that involve a chance event and the implications
of each of the available choices. Decision Trees incorporate cost,
probability, and results. Imagine that you are leading a project and
have a choice to make. In the choice you can either be conservative
or aggressive, but regardless of your decision there is some chance
event which might impact the project. Image 123 shows this simple
example.
Slide 367
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 445
Slide 368
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 446
The image is broken into columns. The first column is the pre-
decision point and should be ignored. Column A shows the costs of
the two choices. Because they are expenses, or outflows of capital
for the organization, the values are both negative ($-250K and $-
350K). Column B shows the probability of getting the outcome
should the choice (either OTS or Develop) be made and the result, or
payout, from making that choice. Column C shows the net outcome
which is the outcome from column B minus the cost of making that
choice (Column A). Column D takes the net outcome from Column
C and multiplies it by the probability to have that outcome found in
Column B. The final outcome for each choice is derived by summing
the two possible outcomes for each branch. In Image 124 the best
choice is the OTS Option because it has a payout of $72.5K versus
the Develop Option which only has a value of $66K.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 447
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 448
5. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of $75,000
with a probability of 30%, a most likely case estimate of $86,250 with a
probability of 40%, and a worst case estimate of $99,188 with a probability
of 30% what is the EMV for the project?
A. $86.756
B. $87,247
C. $87,691
D. $88,121
6. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of $30,000
with a probability of 24%, a most likely case estimate of $34,500 with a
probability of 56%, and a worst case estimate of $45,540 with a probability
of 20% what is the EMV for the project?
A. $35,121
B. $35,628
C. $36,222
D. $36,92
7. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of $35,000
with a probability of 15%, a most likely case estimate of $40,250 with a
probability of 60%, and a worst case estimate of $54,338 with a probability
of 25% what is the EMV for the project?
A. $41,652
B. $42,111
C. $42,984
D. $43,596
8. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of $20,000
with a probability of 10%, a most likely case estimate of $23,200 with a
probability of 65%, and a worst case estimate of $32,480 with a probability
of 25% what is the EMV for the project?
A. $23,950
B. $24,220
C. $24,880
D. $25,200
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 449
9. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of $5,000
with a probability of 30%, a most likely case estimate of $5,900 with a
probability of 45%, and a worst case estimate of $8,024 with a probability of
25% what is the EMV for the project?
A. $6,161
B. $6,437
C. $6,918
D. $7,020
10. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of $7,500
with a probability of 20%, a most likely case estimate of $9,150 with a
probability of 55%, and a worst case estimate of $11,529 with a probability
of 25% what is the EMV for the project?
A. $8,919
B. $9,126
C. $9,415
D. $9,783
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 450
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 451
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 452
4. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $663,500 and B will cost
$589,000. There is a 66% chance that project A will be successful, which
will result in a gain of $1,399,000. If project A fails there will be a loss of
$663,500. There is a 69% chance project B will be successful, and that will
result in a $1,005,000 gain. If Project B fails there will be a loss of $225,000.
Based on this information, what is the value of the best alternative?
A. $34,250
B. $34,700
C. $68,950
D. $68,525
5. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $79,250 and B will cost $75,500.
There is a 71% chance that project A will be successful, which will result in a
gain of $690,000. If project A fails there will be a loss of $309,500. There is
a 75% chance project B will be successful, and that will result in a $570,500
gain. If Project B fails there will be a loss of $219,500. Based on this
information, what is the value of the best alternative?
A. $320,895
B. $618,395
C. $297,500
D. $648,716
6. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $40,000 and B will cost $55,000.
There is a 59% chance that project A will be successful, which will result in a
gain of $151,000. If project A fails there will be a loss of $94,000. There is a
55% chance project B will be successful, and that will result in a $168,500
gain. If Project B fails there will be a loss of $72,500. Based on this
information, what is the value of the best alternative?
A. $5,500
B. $15,600
C. $10,550
D. $21,525
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 453
7. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $77,230 and B will cost $91,980.
There is a 63% chance that project A will be successful, which will result in a
gain of $740,000. If project A fails there will be a loss of $300,000. There is
a 77% chance project B will be successful, and that will result in a $500,000
gain. If Project B fails there will be a loss of $225,000. Based on this
information, what is the value of the best alternative?
A. $703,200
B. $425,230
C. $277,970
D. $256,990
8. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $210,000 and B will cost
$255,000. There is a 60% chance that project A will be successful, which
will result in a gain of $650,000. If project A fails there will be a loss of
$325,000. There is a 65% chance project B will be successful, and that will
result in a $550,000 gain. If Project B fails there will be a loss of $207,750.
Based on this information, what is the value of the best alternative?
A. $79,788
B. $29,788
C. $27,970
D. $50,000
9. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $12,500 and B will cost $15,250.
There is a 72% chance that project A will be successful, which will result in a
gain of $65,000. If project A fails there will be a loss of $31,000. There is a
66% chance project B will be successful, and that will result in a $56,500
gain. If Project B fails there will be a loss of $22,500. Based on this
information, what is the value of the best alternative?
A. $14,390
B. $19,780
C. $25,620
D. $40,010
10. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $241,250 and B will cost
$225,500. There is a 65% chance that project A will be successful, which
will result in a gain of $550,500. If project A fails there will be a loss of
$310,000. There is a 60% chance project B will be successful, and that will
result in a $568,000 gain. If Project B fails there will be a loss of $270,000.
Based on this information, what is the value of the best alternative?
A. $7,300
B. $8,075
C. $11,650
D. $15,375
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 454
11. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $500 and B will cost $750.
There is a 65% chance that project A will be successful, which will result in a
gain of $2,500. If project A fails there will be a loss of $1,650. There is a
59% chance project B will be successful, and that will result in a $3,000
gain. If Project B fails there will be a loss of $1,750. Based on this
information, what is the value of the best alternative?
A. $303
B. $548
C. $641
D. $850
12. You are asked to choose between two projects, A or B, based on the highest
gain (or the lowest loss). Project A will cost $194,500 and B will cost
$175,000. There is a 66% chance that project A will be successful, which
will result in a gain of $645,000. If project A fails there will be a loss of
$315,500. There is a 55% chance project B will be successful, and that will
result in a $715,500 gain. If Project B fails there will be a loss of $220,500.
Based on this information, what is the value of the best alternative?
A. $115,960
B. $119,300
C. $123,930
D. $243,230
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 455
Answer C. To answer this question you must calculate the expected
monetary value of each choice using the decision tree model found in your
LGd training guide and then compare the options. Whichever option has the
greatest value is the one you should choose.
Answer B. To answer this question you must calculate the expected
monetary value of each choice using the decision tree model found in your
LGd training guide and then compare the options. Whichever option has the
greatest value is the one you should choose.
Answer B. To answer this question you must calculate the expected
monetary value of each choice using the decision tree model found in your
LGd training guide and then compare the options. Whichever option has the
greatest value is the one you should choose.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 456
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 457
10. Answer B. To answer this question you must calculate the expected
monetary value of each choice using the decision tree model found in your
LGd training guide and then compare the options. Whichever option has the
greatest value is the one you should choose.
11. Answer B. To answer this question you must calculate the expected
monetary value of each choice using the decision tree model found in your
LGd training guide and then compare the options. Whichever option has the
greatest value is the one you should choose.
12. Answer C. To answer this question you must calculate the expected
monetary value of each choice using the decision tree model found in your
LGd training guide and then compare the options. Whichever option has the
greatest value is the one you should choose.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 458
The only output from the perform quantitative risk analysis process are updates
to project documents, again primarily in the form of information being added to
the risk register. These updates add a number of columns to the register such as:
An assessment of overall project risk exposure — This assessment looks
at two key areas. First, it looks at the chances of overall project success.
Second, it looks at the degree of inherent variability remaining within the
project at the time the analysis was conducted, or in other words, how much
confidence do we have in the analysis.
Probabilistic analysis of the project — This analysis answers the question
how likely is the project to hit its product targets which allow for the
development of contingency reserves.
Probability of achieving cost and time objectives — These probabilities
also aid in the development of contingency reserves.
A prioritized list of quantified risks — This is a listing of the risks which
pose the greatest threat or opportunity. A tornado diagram can be an
effective tool to visualize the prioritized list.
Trends — Any trends noticed through the analysis process should be
documented in the Risk Register.
For the exam it is important you can compare and contrast the qualitative and
quantitative risk analysis processes on four different levels. In each of these the
amount of effort, accuracy, expertise and precision is greater when doing the
quantitative analysis than when doing the qualitative analysis. The four
categories are as follows:
Level of detail
Time for analysis
Cost and schedule implications
Expertise of analysis
11.5 Plan Risk Responses
The next risk process is found in the planning process group for the risk
management knowledge area is plan risk Slide 370
responses. The plan risk responses process is
about developing options and determining
actions to enhance opportunities and reduce
threats to the project’s objectives. It also
addresses the risks by their priority, inserting
resources and activities into the budget, schedule,
and project management plan, as needed.
The inputs to the plan risk responses process
include the following:
.1 Project management plan — There are
Slide 367
Image 125: Plan Risk Responses
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 459
three key components the team must examine within the project management
plan. The first is the risk management plan that defines the roles,
responsibilities, processes, and procedures used to plan and manage the
project risks. The team must also examine the resource management plan so
they understand the resources available to them to build their risk responses
and finally, they must look to the cost baseline so they understand the cost
expectations for the project.
.2 Project documents — If the task is determining the best way to respond
to various project risks then the team needs to examine all the documents that
could potentially influence how the team intends to respond to the risks.
Within the project documents, the team must examine the lessons learned
register, the project schedule, the project team assignments, resource
calendars, the risk register, the risk report, and the stakeholder register.
.3 Enterprise environmental factors — The biggest enterprise
environmental factor is the organization’s willingness to accept risks. This is
called the organization’s risk tolerance.
.4 Organizational process assets — Often organizations have standardized
processes, templates and responses in place for project risks.
The tools and techniques for the plan risk responses process are the most
important part of this process for the exam. They include the following:
.1 Expert judgment — Expert judgment is a critical input to planning risk
responses as the subject matter experts know the risks best.
.2 Data gathering — The project leader must go to the team to determine
the best response to various project risks. This is the process of conducting
interviews.
.3 Interpersonal and team skills — This is another situation where the
leader must draw on basic skills to succeed. Here we are talking about your
facilitation skills as you bring team members and stakeholders together to
discuss the best way to respond to project risks.
.4 Strategies for negative risk or threats — There are three strategies Slide 372
which are exclusive to negative risks or the potential bad things which might
happen on the project. These include the following:
Avoid — Risk avoidance involves changing the project to make the STOP! You
risk impossible. must know
the risk
Transfer — Risk transference occurs when the risk is moved from response
the project to make it someone else’s problem. The most common strategies.
form of risk transfer is insurance.
Mitigate — Mitigation is the process of reducing the probability and/
or the impact of the risk occurring.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 460
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 461
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 462
Keeping track of identified risks and those on the watch list — This is a
simple monitoring process to see if the risks still matter to the project.
Reviewing the execution of risk responses while evaluating their
effectiveness — This process answers the question, did our risk response
have the desired affect?
Reanalyzing existing risks — Project risks must constantly be reviewed to
ensure they are still appropriate.
Monitoring residual risks — Residual risks are those risks which remain
after the risk response strategy is employed. Think of these as the crumbs in
a meal that must be cleaned up.
The inputs to the monitor risks process include the following:
.1 Project management plan — The specific document of concern from the Slide 377
project management plan is the risk management plan which defines the
processes and procedures being used throughout risk management.
.2 Project documents — There are a number of project documents
important to the monitoring of project risks. This includes, the issue log,
lessons learned register, risk register and the risk reports.
.3 Work performance data — The work performance information defines
what is happening on the project such as cost, schedule and deliverable
performance.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 463
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 464
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 465
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 466
7. Which of the following is a tool or technique used in the plan risk responses
process?
A. Risk response analysis
B. Risk response planning
C. Contingent response strategies
D. Strategic risk response planning
8. Which of the following is NOT a tool or technique used in the plan risk
response process?
A. Strategies for negative risks or threats
B. Strategies for positive risks or opportunities
C. Expert judgment
D. Contingency reserve analysis
9. Which of the following is NOT an tool and technique to the monitor risks
process?
A. Risk urgency assessment
B. Risk audits
C. Status meetings
D. Technical performance measurement
10. Which of the following is a tool or technique used in the monitor risks
process?
A. audits
B. Interpersonal and team skills
C. Expert judgment
D. Decision making
11. Which of the following is NOT a tool or technique used in the implement
risk responses process?
A. Expert judgment
B. Interpersonal and team skills
C. Technical performance measurements
D. Project management information system
12. Which of the following is a tool or technique used in the implement risk
responses process?
A. Data gathering and representation techniques
B. Project management information systems
C. Risk data quality assessment
D. Planning meetings and analysis
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 467
13. You are acting as the portfolio manager and must select a project to execute
from a pool of three choices. Each of the choices has an expected payout of
$20,000 and an equal 75% chance of succeeding. In this situation what does
$15,000 represent?
A. Net present value
B. Risk value
C. Expected monetary value
D. Simple interest
14. You are leading a large complex project within your organization that is
forecast to continue for ten more months. The project has an 18% chance of
being impacted in a given month by a particular risk. What is the probability
that the project will be impacted by the risk in the 3rd month?
A. 18%
B. 36%
C. 54%
D. 72%
15. You are acting as an outside project management expert consultant for a
struggling project. The project is important to the chief executive officer
who is concerned the project is not going to hit its schedule date. Which of
the following is most likely to impact achieving the schedule target?
A. Significant increases in component costs.
B. Delays in obtaining required sponsor approvals.
C. Date slippages as stakeholders fail to attend sprint reviews.
D. Disputes with contractors over increase costs.
16. You have been asked to select one of four projects for your organization to
execute. The organization is very risk adverse. If you assume the ends of a
range of estimates are +/- 3 sigma from the mean, which of the following
range estimates involves the least risk?
A. Mean of 33 days.
B. 40 days plus or minus 8 days.
C. 32 – 46 days.
D. Optimistic = 33 days, most likely 40 days, pessimistic 46 days.
17. You have been asked to select one of four projects for your organization to
execute. The organization is very risk adverse. If you assume the ends of a
range of estimates are +/- 3 sigma from the mean, which of the following
range estimates involves the least risk?
A. Optimistic = 21 days, most likely 27 days, pessimistic = 32 days.
B. 26 days plus or minus 5 days.
C. 20 – 33 days.
D. Mean of 26 days.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 468
18. Which of the following is not a factor in the assessment of project risk?
A. Transference costs
B. Risk probability
C. Value at stake
D. Risk event
19. You take over a project from a previous project manager. As part of the turn
over process they hand you a risk watch list. What should be done with the
risks on the watch list?
A. Add the information to your takeover report.
B. Add them to the lessons learned for future projects.
C. Read over the watch list as they are already covered in the properly
completed contingency plans.
D. Read over the watch list then revisit during monitoring and
controlling.
20. Which of the following is not always an input to the risk management
process?
A. Work breakdown structure
B. Lessons learned
C. Project status reports
D. Historical information
21. It is very important that the project manager determine risk tolerances in
order to help:
A. The sponsor understand how the resource managers will act.
B. Schedule the project.
C. Rank the project risks.
D. Estimate the project duration.
22. Which of the following is not a common result of risk management?
A. The communications management plan is changed.
B. The project charter is changed.
C. The schedule management plan is changed.
D. The project management plan is changed.
23. Which of the following risk strategies is represented by insurance?
A. Avoidance
B. Acceptance
C. Transfer
D. Mitigation
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 469
24. It is your first day at a new job and you are asked to evaluate the risks on a
large project managed by the PMO. Unfortunately, you cannot evaluate the
exact cost impacts of the risks you are analyzing. Based on this situation you
should evaluate the risks on a:
A. Statistical basis
B. Qualitative basis
C. Quantitative basis
D. Mathematical basis
25. In which of the following risk management processes are you most likely to
be required to find workarounds?
A. Monitor risks
B. Plan risk responses
C. Identify risks
D. Quantitative risk analysis
26. You have just determined that you need to transfer a risk. In which of the
following risk management processes are you?
A. Identify risks
B. Plan risk responses
C. Monitor and control risks
D. Perform quantitative risk analysis
27. You are acting as the project manager for a large project $1,500,000 within
your organization. You have just finished the risk response plan for your
project. Which of the following should you probably do next?
A. Begin a project risk reassessment.
B. Begin to analyze the risks that appear in major project documents.
C. Complete the work breakdown structure.
D. Determine the overall risk rating for the project.
28. You are in the process of quantifying risks on a project you are leading.
Several of your key resources are non-collocated and have needed input.
How can this be done?
A. Make use of the Delphi technique.
B. Make use of Monte Carlo analysis.
C. Make use collaboration software.
D. Apply critical chain modeling.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 470
29. During the plan risk management process the project team you are leading
discovers 387 risks and 32 major causes of those risks. The project is part of
a major program within the organization and must be completed. Your team
is very experienced and has worked together for several years. You have also
worked with the sponsor for several years as well, and they are very
supportive of your efforts. Significant time has been spent to ensure the
project scope and WBS is complete and it has been signed off by all the key
stakeholders. Unfortunately, your team has not been able to determine an
effective way to mitigate or insure against the one of those major risks. It is
something that must be done by the internal team and cannot be outsourced.
It also cannot be deleted from the project. What would be the best solution?
A. Determine a way to transfer the risk
B. Determine a way to avoid the risk
C. Continue to investigate ways to mitigate the risk
D. Accept the risk
30. You are the project manager on a large IT project. You have assembled your
team, identified the major risks on the project, determined what would
trigger those risks, rated the risks on a rating matrix, tested the major risk
assumptions, and assessed the quality of the data used. The team is
continuing to move through the risk management process. What have you
forgotten to do?
A. Involve other stakeholders.
B. Use a Monte Carlo simulation.
C. Mitigate the risks.
D. The overall risk ranking for the project.
31. You have worked with different stakeholders to determine the probability
and impact of a project’s risks. You have also analyzed the assumptions.
Before you move on to the next step in the risk management process, what
do you need to do?
A. Identify and evaluate triggers.
B. Develop your risk rating matrix.
C. Evaluate the trends in risk analysis.
D. Create a contingency plan.
32. You apply for a job with a large consulting company. As part of the
interview process you are provided with a sample project charter and asked
to provide an analysis of the project risks. Which of the following would
best help you complete the exercise?
A. The PMBOK® Guide.
B. A discussion with several team members within the organization from
a similar project that failed in the past.
C. The scope statement from the project planning process.
D. The resource plan from the project planning process.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 471
33. You are working as a project manager on a large new product development
project. While preparing your risk responses your team identifies additional
risks. What should you do?
A. Get management to allocate another 5% to the project budget to cover
the risks.
B. Determine the risk events and the associated cost, then add the cost to
the project budget as a reserve.
C. Document the risks, and calculate the expected monetary value based
on the PI score that result from the risk occurrence.
D. Add reserves to the project to accommodate the new risks and notify
management.
34. You are leading a project that has an SPI of 0.69 and a CPI of .71. The
project has more than 1,000 work packages, and it is being completed over
three years. The team has not worked together before, and the project has
not been well supported. Which of the following is the best thing to do?
A. Update the risk register with any new risks and analysis.
B. Examine the WBS for unnecessary work packages.
C. Examine the RAM for necessary changes.
D. Examine the budget for necessary changes.
35. Your project is very close to completion when an unidentified risk occurs.
This risk could affect the project’s overall ability to deliver. What should
you do first?
A. Develop a risk response plan.
B. Develop a workaround.
C. Alert the project sponsor to the potential impacts to the schedule,
costs, and scope of the project.
D. Qualify the risk.
36. You are the project manager on a multi-year facilities development project.
Significant spring rains caused major flooding that caused power outages and
the loss of all project records not stored on your laptop. What should have
been done to prevent this problem?
A. Approve a larger contingency reserve.
B. Plan for a larger management reserve.
C. Maintain the records outside a flood plain.
D. Monitor the weather and have a contingency plan.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 472
37. You have been asked to lead a mission-critical project for your organization.
The project is very large, will take approximately 3 years, and will be highly
visible to the senior leadership of the organization. Unfortunately, your
company does not have a very good track record at handling risks and rarely
seems to follow its risk management policies and procedures. You have less
than a month until your first major milestone. If senior management is
expecting to see an analysis of the project’s risks and response strategies
which of the following groups or individuals is least important?
A. The sponsor.
B. The project team members.
C. The individuals responsible for the risk policies and procedures.
D. Key stakeholders.
38. You are leading a high technology product development project that was
originally scheduled to take 18 months. The project has faced significant
problems and has had to use all its reserves. You currently have an SPI of
0.68 and a CPI of 0.73. There are only six deliverables left and three of them
are on the critical path. The project sponsor has just told you that you only
have four weeks to finish the project or risk losing all funding and support.
This is three weeks faster than your current ETC. In response, you send out
an RFP to four vendors for some of the work that the internal team was going
to perform hoping an external organization could get the work done faster.
This can best be described as an effort on the part of the project manager to
work with:
A. Contingencies
B. Threats
C. Opportunities
D. Reserves
39. Which of the following is a primary characteristic of the Delphi Technique?
A. Expert opinion.
B. Simulation modeling in a hierarchical process.
C. Use of heuristic analysis.
D. Extrapolation from historical documents.
40. You are leading a large IT project that is nearing completion. Your sponsor
requests a change to the project that would increase the project risk. What
should you do first?
A. Update the risk register.
B. Gain an understanding of why the sponsor wants the change.
C. Analyze the impacts of making the change with the project team.
D. Calculated the EMV of the risk and create a new cost estimate.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 473
41. You are leading a major construction project. During project execution a
major problem occurs that does not appear in the risk register. What should
you do first?
A. Inform the project stakeholders.
B. Look for secondary risks.
C. Exam the identify risks process for flaws.
D. Create a workaround.
42. You are leading a research and development project. You are in the
executing process group when one of your senior resources identifies a risk
that is not listed in the risk register. What should you do?
A. Determine how the team member identified the risk.
B. Analyze the risk.
C. Inform the sponsor and key stakeholders of the risk.
D. Place the risk in the risk register.
43. You are taking over a $50,000 IT project for your organization. The project
is entering its third phase. Although there appear to be many risks on the
project, no one has evaluated them to assess the range of possible impacts.
What needs to be done?
A. Perform qualitative risk analysis
B. Plan risk management
C. Plan risk responses
D. Monitor risks
44. Which of the following best describes a heuristic?
A. An advanced statistical calculation used to model risks.
B. A simulation used to model risks.
C. A rule of thumb.
D. A calculation used to produce a weighted measure of risk.
45. Monte Carlo analysis is used to:
A. Get an indication of the risk involved in a project.
B. Simulate the order in which activities occur.
C. Estimate an activity’s length.
D. Measure project risk level.
46. You are working with your team to complete the risk response plan.
However, every time the team develops a risk response, another risk is
identified as being caused by the suggested response. Which of the
following is the best thing for the project manager to do?
A. Return to the identify risks process as something is amiss.
B. Document the new risks and continue the plan risk responses process.
C. Return to the define scope process to determine what is missing.
D. Get more stakeholders involved in the identify risks process as so
many were missed.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 474
47. From which of the following processes would you expect to generate a watch
list?
A. Plan risk management
B. Identify risks
C. Perform qualitative risk analysis
D. Plan risk responses
48. Which of the following must be an agenda item at all team meetings?
A. Review of project issues
B. Identification of new assignments
C. Status of all activities
D. Discussion of project risks
49. Which of the following is not always an input to the risk management
process?
A. Project status reports
B. Historical information
C. Lessons learned
D. The work breakdown structure
50. You are struggling to evaluate the exact cost impact of risks on your project.
You would be advised to evaluate on a:
A. Qualitative basis
B. Quantitative basis
C. Numeric basis
D. Cost basis
51. You have just finished the risk response plan for your US $250,000
information technology project. Which of the following should you probably
do next?
A. Determine the overall risk rating for the project.
B. Add needed work packages to the work breakdown structure.
C. Hold a project risk reassessment.
D. Begin to analyze the risks that appeared in the technical design.
52. You have just completed the determination of probability and impact of your
defined project risks. You have also analyzed the assumptions and are ready
to move on to the next step of risk management, but based upon the
information what have you forgotten to do?
A. Identify triggers.
B. Evaluate trends in the risk analysis.
C. Create a fallback plan.
D. Provide a standardized risk rating matrix.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 475
53. As the project manager you have assembled your team and identified more
than 100 risks on your project. You and the team have rated them on a risk
rating matrix, tested their assumptions, and assessed the quality of the data
used. The team is continuing to move through the risk management process,
but what have you forgotten to do?
A. Risk mitigation.
B. Overall risk ranking for the project.
C. Involve other stakeholders.
D. Monte Carlo analysis.
54. Your team has come up with 521 risks and 42 major causes of those risks.
Your team has worked on several projects together and your project sponsor
is both influential and supportive. You and your team have invested
significant time to make sure the project work was completed and signed off
by all key stakeholders. However, during the planning phase, the team was
unable to come up with an effective way to mitigate or ensure against a
particular risk. The work cannot be outsourced or deleted from the project.
Which of the following represents the best solution?
A. Accept the risk.
B. Look for ways to transfer the risk.
C. Look for ways to avoid the risk.
D. Continue to look for ways to mitigate the risk.
55. You are leading a large, multi-year engineering project designed to impact
multiple locations within your company. A tornado destroys the
headquarters location and all the project records including all project
reporting and historical information with no way of recovering the
information. What should have been done to prevent this problem?
A. Purchase insurance.
B. Monitor the weather and have a contingency plan.
C. Plan a reserve fund.
D. Schedule the installation outside of tornado season.
56. During the project execution phase of a project you are leading one of your
subject matter experts identifies a risk that is not in the risk register. What
should you do?
A. Disregard the risk because it was not identified in risk identification.
B. Inform the sponsor of the risk.
C. Analyze the risk.
D. Discuss with the resource how they identified the risk to ensure
others were not missed.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 476
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 477
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 478
6. Answer A. PMBOK® Guide p. 396 – The tools and techniques used in the
perform quantitative risk analysis process include:
Expert judgment
Data gathering
Interpersonal and team skills
Representations of uncertainty
Data analysis
7. Answer C. PMBOK® Guide p. 396 – The tools and techniques used in the
plan risk responses process include:
Expert judgment
Data gathering
Interpersonal and team skills
Strategies for negative risks or threats
Strategies for positive risks or opportunities
Contingent response strategies
Strategies for overall project risks
Data analysis
Decision making
8. Answer D. PMBOK® Guide p. 396 – The tools and techniques used in the
plan risk responses process include:
Expert judgment
Data gathering
Interpersonal and team skills
Strategies for negative risks or threats
Strategies for positive risks or opportunities
Contingent response strategies
Strategies for overall project risks
Data analysis
Decision making
9. Answer A. PMBOK® Guide p. 396 – The tools and techniques used in the
monitor risks process include:
Data analysis
Audits
Meetings
10. Answer B. PMBOK® Guide p. 396 – The tools and techniques used in the
monitor risks process include:
Data analysis
Audits
Meetings
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 479
11. Answer C. PMBOK® Guide p. 396 – The tools and techniques used in the
implement risk responses process include:
Expert judgment
Interpersonal and team skills
Project management information system
12. Answer B. PMBOK® Guide – The tools and techniques used in the
implement risk responses process include:
Expert judgment
Interpersonal and team skills
Project management information system
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 480
21. Answer C. Risk tolerances, or how much risk various stakeholders are
willing to accept. This is a critical piece of information used to rank the
project risks.
22. Answer B. Of the choices the project charter is the least likely to be
changed because of the risk management process. Remember, the charter
authorizes the project.
23. Answer C. Insurance is the most common type of risk transfer. It is making
the risk someone else’s problem.
24. Answer B. The question tells you that you cannot find the exact impacts.
This excludes statistical, quantitative and mathematical basis of measure.
You are left with qualitative such as high, medium and low.
25. Answer A. Workarounds—by definition—are responses created for risks not
included in the risk register.
26. Answer B. Be careful here. The question states you have just determined
that you NEED to transfer a risk. This is done in the plan risk response
process.
27. Answer C. Finishing the risk response plan is done in the planning process
group. The only of the options that is also in the planning process group is
the completion of the work breakdown structure.
28. Answer A. The Delphi Technique is specifically designed to survey your
experts, aggregate their responses and then feed the aggregated result back to
them for confirmation. This is the best option in a situation where the
resources are not all together.
29. Answer D. There are two important aspects to this question. Firstly, did you
notice that everything but the last four sentences is unnecessary? Secondly,
this question really reflects the real world. The question excludes everything
but acceptance. Sometimes in the real world all you can do is accept a risk.
30. Answer A. There is nothing wrong with this process. It simply needs to be
continued. The best answer in this case is to involve other stakeholders
31. Answer B. Before you can move on to the next step in the process you need
a definition for how you will be rating the risks.
32. Answer B This question centers on imagining where you are in the project.
The question gives you a charter and nothing else. Therefore, you must
assume you are in the initiating process. Two of the other choices say they
are from the planning process and therefore not available. The PMBOK®
Guide is a nice framework, bur remember PMI® suggests the situation is
critical.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 481
33. Answer C. Before you can determine the appropriate response you have to
determine the value or cost of the risk as well as the impacts. Only then can
you determine if you or management needs to add reserves or another
response is needed.
34. Answer A. To answer this question correctly you had to notice the project is
already significantly over budget and behind schedule. Changing the WBS,
RAM, or budget should only happen in response to risks that occur. So you
should start there.
35. Answer D. The first thing you always do is analyze the situation and
develop alternatives. Only then do you proceed.
36. Answer D. With the information provided you do not know what the best
solution would have been. The only thing you can say for sure is that you
should have had a contingency plan—oh, and watching the weather probably
wasn’t a bad idea either…
37. Answer A. Although sponsors are often involved in the identification of
risks, they are usually not as involved in the development of response plans.
All the other answers are key resources in the development of response
plans.
38. Answer C. This is a bad situation, but that does not impact the answer.
Only the last three sentences matter. You are trying to gain an opportunity to
do the project more quickly.
39. Answer A. The Delphi Technique is a process where you survey your
subject matter expert, aggregate their responses, and then feed back the
aggregation for confirmation.
40. Answer C. According to PMI®, the first thing you must do in any situation
is understand the impacts. Only then can you devise the correct response.
41. Answer D. This is a risk that has already happened. The first thing you
need to do is deal with the problem and then take the workaround to the
sponsor and key stakeholders.
42. Answer B. The first thing you always do is analyze the risk. Only then can
you determine what should be done next.
43. Answer B. The project has started, and it should complete the risk
management process. That process begins by planning risk management.
Since that step has not already occurred it needs to be completed first.
44. Answer C. A heuristic is simply a rule of thumb. There is no calculations
involved.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 482
45. Answer A. Several of these answers are partially correct. The Monte Carlo
Analysis could help you know that an activity needs to change, but not what
the estimate should be. The Monte Carlo analysis is a simulation tool, but it
typically is used to simulate time or cost and not ordering of the activities. It
can also be used to measure the probabilities of risk or the likelihood of
being on the critical path. However, the best answer is getting an overall
analysis of the project risk.
46. Answer B. Don’t get misled by the fact that the process generated so many
new risks. The key is that you follow your process. In this case it is working
as it should. You should expect the identify risk responses process to
generate new risks.
47. Answer C. A watch list is made up of low priority risks that, in the perform
qualitative risk analysis process, were determined to be too low priority or
low impact to move further in the risk process.
48. Answer D. According to PMI®, risks are a critical area that impacts all other
areas of project management. It is so important it should be discussed at
every meeting.
49. Answer A. Although project status reports can be an important input to the
risk management process, when you are first completing the process you
likely will not have any status reports yet.
50. Answer A. If you cannot determine the exact costs of a risk you should use
qualitative estimates such as low, medium and high.
51. Answer B. Based upon the description, this situation is in the planning
process group. You must complete the planning before moving on. The only
process in planning is adding work packages to the WBS.
52. Answer D. In this case you are in the Perform Qualitative Risk Analysis
process. There are two key activities in this process: assumption testing and
probability and impact matrix development. The matrix is missing. All the
other options will occur later in risk management.
53. Answer C. You might look at this question as a trick of sorts. The process
described is fine. The only issue is you have not involved other stakeholders
to identify more risks.
54. Answer A. Most of this question is useless. You cannot remove the work nor
can you insure or outsource it to transfer the risk. The only option left is
acceptance.
55. Answer B. The risk is the loss of the data due to the weather. Purchasing
insurance does nothing to mitigate the problem. Creating a reserve fund is a
form of risk acceptance. Avoiding the tornado by scheduling the project
when it wasn’t tornado season could negatively impact the project. The best
choice is to monitor the weather and know when to implement the
contingency plan.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 11 — Risk Management
Page 483
56. Answer C. This is another example of those “what would you do first?”
questions. As always, the right answer is analyze the situation.
57. Answer C. The Delphi Technique uses expert judgment to build a consensus
opinion. The expert judgment is its key feature.
58. Answer B. The ability to potentially outsource some of the deliverables is
an example of taking advantage of an opportunity.
59. Answer C. The plan risk responses processes should include the
involvement of all the risk response owners and possibly other stakeholders.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 484
Procurement Management
Overview
Chapter 12 of the
PMBOK® Guide is Slide 381
dedicated to the
procurement management
knowledge area. There
are three processes found
in the procurement
management knowledge
area. These processes include the
following:
12.1 Plan procurement
management
12.2 Conduct procurements
12.3 Control procurements
Image 128: The Procurement Management Processes
The procurement management
knowledge area includes the processes necessary to purchase or acquire the
products, services, or results needed from outside the project team to perform
project work. A few exam prep writers believe the procurement management
knowledge area is difficult. I do not. Compared to areas such as risk,
scheduling or cost, procurement is relatively simple. However, there are three
important aspects of procurement management you must remember for the
PMP® exam.
First, PMI’s view of procurement management is likely much more inclusive
than what you are used to. For the exam, it is important to remember the type of
project you are leading (a large, multi-national project for a manufacturing or
engineering concern, involving millions of dollars and hundreds of resources,
across multiple time zones). As part of this project you are responsible for the
selection criteria of the sellers, managing them, and managing their payments.
Secondly, unless an exam question says something to the contrary, and we have
never heard of one, you are always the BUYER in a procurement situation.
Remember, for the exam you are always acting in the role of the project manager
trying to get your project completed. In this situation you might need to You are
purchase goods, services or consultants to help you complete the project. always the
However, there are a lot of different terms questions can use to reference you in BUYER!
the role of the buyer. You might be called the client, customer, requestor or
purchaser. When PMI® references the seller the exam could use terms such as
seller, contractor, prime contractor, sub-contractor, bidder, selected source, or
vendor. Do not be fooled by the term used. Always remember your role.
The third key to passing the procurement management portion of the exam is to
learn the type of contracts which may be used by the project manager. These
contract types are discussed in detail in the first process below.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 485
It is also a good idea to learn several PMIisms which can be used to prepare for
the exam. These PMIisms include the following:
Slide 382
All product and project management requirements for the procurement work
should be specifically stated in the contract.
If it is not in the contract, it can only be done if a formal change order to the
contract is issued.
If it is in the contract, it must be done or a formal change order to the
contract must be issued cancelling it.
Changes must be submitted and approved in writing.
Contracts are legally binding; both parties are obligated to perform per the
terms of the contract.
Contracts should diminish project risks.
There are also a number terms you must know to be successful with the exam.
Many of these terms deal with the legalities of procurement management which
are another difference from other knowledge areas. PMI® does NOT expect the
project manager to be a trained expert in all the laws and regulations dealing
with procurement management, but does expect you to have enough familiarity
with the topics to make intelligent decisions regarding contracts and contractual
relationships [PMBOK® Guide 6th ed. p. 460]. PMI® also does NOT assume
the PM has authority to sign any legal agreements binding the organization.
Remember, PMI® is trying to reflect what is generally happening in the real
world. The terms you should still know include:
Force majeure — This is a situation which may be considered an act of Slides 383-
God, and is an allowable excuse for either party not meeting contractual 386
requirements. Usually the risk is covered by the seller for which they will
often carry insurance.
Liquidated damages — These are estimated damages for specific defaults,
described in advance.
Retainage — This is an amount of money—usually 5% to 10%—withheld
from each payment. This money is paid when all the final work is complete.
Its purpose is to help ensure proper completion.
Time is of the essence — This phase means delivery dates are strictly
binding and will be stringently enforced. The seller is placed on immediate
notice that any delay is considered a material breach.
Material breach — The breach is so large that it may not be possible to
complete the work under contract.
Work for hire — The work provided will be owned by the buyer.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 486
Price — The amount charged to the customer. It is defined as the cost plus
profit.
Profit — The amount of money given to the seller above and beyond the
costs incurred to produce a product. Typically, the seller has a target margin
desired to sell a product.
Cost — This is how much an item costs the seller to create, develop, or
purchase a product. A buyer’s cost includes both the seller’s cost plus profit
and is the same as the price.
Target price — This is another way of saying planned or expected price. It
is used as a point of comparison with the final actual price paid.
Sharing ratio —The sharing ratio describes how cost overruns will be split
between the buyer and seller.
Ceiling price — This is the highest price the buyer will pay for a product or
service.
Master services agreement — An MSA is a governing agreement that is
used for the overall engagement. MSAs are often used on large projects
where parts of the project is managed using an agile method and other parts
use a more traditional method. Any adaptive work is placed in an appendix
or supplement which allows changes to occur on any adaptive scope without
impacting the overall contract.
Point of Total Assumption — This only relates to fixed price incentive fee
contracts and refers to the amount above which the seller bears all the loss of
a cost overrun. Costs that go above the PTA are assumed to be due to
mismanagement. Sellers will sometimes monitor their actual costs against
the PTA to make sure they are still receiving a profit for completing the
project. It is defined with the following formula:
(Ceiling Price—Target Price) PTA
PTA = + Total Cost Formula
Buyer’s Share Ratio
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 487
contracting process (not a formal process in the PMBOK® Guide) and the
contract types.
The inputs to the plan procurements process include the following: Slide 388
.1 Project charter — The project charter provides the overview of the
project. Keep in mind the previously discussed project five-line.
.2 Business documents — The two specific documents described are the
business case which describes why the organization needs the project, and
the benefits management plan which explains the benefits the organization
expects to receive by completing the project.
.3 Project Management Plan — The project management plan contains all
the other plans that are a big part of procurements. The scope, quality and
resource management plans along with the scope baseline each describe key
aspects of the project that may need to be purchased from outside the
organization.
.4 Project documents — Information not contained in the project
management plan, but still critical to determining what the team intends to
obtain from outside the organization are found in the project documents such
as the milestone list, project team assignments, requirements documentation,
requirements traceability matrix, resource requirements, risk register, and
stakeholder register. Remember, when looking at procurements we might
also be talking about bringing contractors in to complete work which the
team lacks the expertise to complete.
.5 Enterprise environmental factors — The key enterprise factors that can
influence the plan procurements process include items such as marketplace
conditions, the items that are available in the market, supplier information
such as past performance or reputation, typical terms and conditions for
products, services and results, and unique local conditions.
.6 Organizational process assets — The organizational process assets
which can influence the plan procurements process include things such as:
formal processes, procedures and templates concerning procurement,
standard organizational contracts, non-disclosure agreements, or prequalified
seller lists.
The tools and techniques used in the plan procurements process are as follows:
.1 Expert judgment — A project’s subject matter experts can, and should,
be a critical resource in determining which items on the project should be
procured externally and which processes should be used. Examples of
applicable subject matter experts include lawyers, contracting officers, or
industry experts.
.2 Data gathering — The process of data gathering when planning
procurements largely centers on market research to understand industries
and specific seller capabilities.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 488
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 489
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 490
Page 491
Image 130: Comparison of Procurement Documents PMBOK® Guide 6th ed. p.481
As you prepare for the PMP® exam there are a number of processes presented
that are likely very different from what you are used to. PMI’s view of the
project manager’s role in contracting is of much greater influence than many real
-world PM’s experience. To prepare for the exam you must understand what
PMI® means by a contract: a contract is a legally binding agreement between
two parties for the exchange of value. One party agrees to provide a product,
service or result in exchange for some form of remuneration. A contract is
usually written, but does not have to be. They can be simple or complex. A
contract is subject to remedy in the courts. Contracts are typically subject to an
approval process. Contracts also have their own life cycle. In addition to
understanding the basic definition of a contract you must also be familiar with
the types of contracts.
The best way to understand the various types of contracts is to think of a
continuum that begins with cost plus percentage of cost contracts and ends with
a firm fixed price or lump sum contract. Setting the continuum is the risk
relationship between the buyer and the seller. As the risk for one goes up the risk
for the other goes down. This relationship defines the major decision criteria for
selecting a contract type. Selecting a contract type is about dealing with
unknowns. The more well understood a need, the more the project aligns to a
firm-fixed price contract. The more risk involved with the need, the more a cost
plus percentage of costs contract makes sense. Image 131 shows the contract
type continuum. The types of contracts are as follows:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 492
Slide 395
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 493
The inputs to the conduct procurements process include the following: Slide 397
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 494
The tools and techniques used in the conduct procurements process include the
following:
®
.2 Expert judgment — Like most of the processes found in the PMBOK
Guide, expert judgment may be used to evaluate seller proposals.
Commonly used expertise includes: contracting, legal finance, accounting,
engineering, and specific technical disciplines for the project.
.2 Advertising — To increase the number of potential sellers, advertisements
may be placed in newspapers, trade publications or on the internet.
.3 Bidder conferences — Bidder conferences have many different names.
You might see contractor conferences or pre-bid conferences in addition to
bidder conferences. These are meetings with all the perspective sellers, prior
to the submission of bids or proposals, that allow the sellers to ask questions
and receive information so all the sellers have the same information.
.4 Data analysis — Many of the processes already discussed have made
extensive use of data analysis to examine key elements of process. Here, you
are evaluating the proposals received by the team.
.5 Interpersonal and team skills — The key kind of interpersonal and team
skill is negotiation. Negotiations are used to clarify the structure,
requirements, and other terms of the purchases so that both the seller and the
buyer can come to an agreement. This facilitates signing a contract so that
the buyer can obtain the products or services required to complete the
project. There are a number of negotiation tactics that you should know for
the exam. These are as follows:
Attacks — To criticize or condemn another person or organization. Slides 398-
400
Personal insults — Making derogatory comments about another to
distract from the issue or objective.
Good Guy / Bad Guy — One person is helpful to the other side and
the other is difficult.
Deadline — Setting a hard deadline to complete the negotiations.
Lying — Not telling the truth to the other party.
Limited Authority — Claiming the power to negotiate only within
certain boundaries.
Missing Man — Being unable to make the decision because the
appropriate party is not present.
Fair and Reasonable — Asking the other party to accept the current
offer as it is a fair offer to all parties.
Delay — This is a stall tactic used to push the decision to the last
minute.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 495
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 496
The inputs to the control procurements process include the following: Slide 402
.1 Project Management Plan — The project management plan has been the
dominant document collection throughout the entire project and it isn’t about
to change this late in the course. Within the project management plan, the
team must use the requirements management plan, the risk management
plan, the procurement management plan, the change management plan, and
the schedule management plan.
.2 Procurement documents — The procurement documents contain all the
supporting records for administration of the procurement processes.
Therefore, you need to consider the assumption log, the lessons learned
register, the milestone list the quality reports showing the quality of the
vendor’s delivery, requirements documentation showing what was to be
delivered, the requirements traceability matrix so you know where
requirements came from, the risk register, and the stakeholder register.
.3 Agreements — If any agreements have been negotiated and signed, these
provide the basis of understanding of performance.
.4 Procurement documentation — Your procurement documentation
contains all the records of the administration of the procurement agreements.
Whatever you purchased for the project will have some kind of
documentation here. Think of the SOWs, payment information, contractor
work performance reports, plan or drawings just to name a few.
.5 Approved change requests — Notice these are not simply change
requests. They are approved change requests. Items such as changes to the
terms and conditions of the contract could be placed here or any changes to
the work itself. The key here is that all the changes are approved.
.6 Work performance data — The work performance information in
question includes any information concerning the extent to which quality
standards are being met, the incurred costs, and paid seller invoices.
.7 Enterprise environmental factors — The specific enterprise
environmental factors at play are your contract change control system,
marketplace conditions, financial management and accounts payable system
and the buying organization’s code of ethics. You should also consider
PMI’s code of conduct as well.
.8 Organizational process assets — The team needs to specifically consider
the organization’s procurement policies.
The tools and techniques used in the control procurements process include the
following:
.1 Expert judgment — Project teams must make use of subject matter
expertise in all relevant functional areas to effectively control procurements.
.2 Claims administration — Claims administration deals with contested
claims. A contested claim occurs any time the buyer and seller cannot agree Slide 403
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 497
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 498
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 499
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 500
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 501
12. In which of the following processes would you find bidder conferences?
A. Plan procurement management
B. Conduct procurements
C. Administer procurements
D. Monitor procurements
13. You are leading a project that has a number of work packages that are being
completed by external resources. One work package is being completed by a
contractor working on a cost reimbursable contract. You have determined
that the scope of the project must be expanded for this contractor.
Additionally, you are concerned about cost control and would like to change
the contract to a firm fixed price contract. All of the following are the
seller’s options except:
A. Starting over with a new contract.
B. Negotiating a fixed price contract that includes all the desired work.
C. Completing the original work and rejecting the additional scope.
D. Completing the original work using the original cost reimbursable
contract and then negotiating a new firm fixed price contract for the
additional work.
14. Which of the following is a reason for centralized contracting?
A. Deeping expertise.
B. No single location.
C. Increased loyalty to the project.
D. Easier access to expertise.
15. You are leading a large project and are attempting to negotiate a complex
contract. In the middle of the meeting the selected seller informs you that
“they need to finish up in the next 90 minutes so they can catch an airplane.”
What kind of negotiating strategy is this?
A. Extreme demands
B. Delay
C. Good cop, bad cop
D. Deadline
16. You have been tasked with establishing a records management system for a
large project. You are trying to make sure all the records from the
procurements are properly documented and indexed. Which of the following
are you not concerned about?
A. Negotiation process
B. Proposal
C. Procurement statement of work
D. Terms and conditions
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 502
17. You have been asked to lead a mid-sized project for your organization. Your
sponsor is very concerned about one particular seller that must be used on the
project and wants to make sure you are minimizing the risk to your
organization. You suggest using a firm fixed price contract. Which of the
following explains the recommendation?
A. Schedule risk will be fixed.
B. Cost risk will be lower.
C. The buyer owns most of the risk.
D. Risk is shared equally by all parties.
18. You are leading a project that has been in process for 13 months. You are
nearing the completion of a major deliverable that was completed by an
external resource using a cost reimbursable contract. You have entered the
close procurements process. Which of the following must you remember to
do?
A. Make sure the seller is not adding work to the contract.
B. Make sure the seller is not adding resources.
C. Audit the seller’s cost submittals.
D. Decrease the risk rating of the project.
19. You have been asked to lead a mid-sized project for your organization. Your
sponsor is very concerned about one particular seller that must be used on the
project and wants to make sure you are minimizing the risk to your
organization. You suggest using a firm fixed price contract. In a firm fixed
price contract, the fee or profit is:
A. Specifically stated as a line item in each invoice.
B. Determine through negotiation at the end of the contract.
C. Unknown.
D. Part of the negotiation involved in paying every invoice.
20. You are leading a large engineering project for your organization. As part of
the standard reporting process you are required to submit earned value
calculations such as SPI, CPI and TCPI. One day your sponsor comes into
your office concerned about your largest contractor gaining extra profit on
the CPFF contract. You explain that they should not be worried about this
issue. Which of the following best justifies this statement?
A. All cost invoices are being audited.
B. The seller only receives their fee once the project is completed.
C. You are making sure the seller does not cut scope.
D. There can only be a maximum 10% increase if there is an unexpected
overrun.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 503
21. You are the project manager on a project that is part of a large space
program. Another project manager on the program has just come to you for
advice. Their project currently has limited scope definition and she is very
concerned about protecting the organization from financial risks. Which is
the best contract type to choose?
A. Firm fixed price
B. Cost plus fixed fee
C. Cost plus percentage of cost
D. Cost plus incentive fee
22. You are leading an especially difficult team attempting to complete a large
project that has significant risk to the organization. You are in the middle of
your standard Monday morning meeting where you are attempting to
determine whether the team should produce a particular deliverable
themselves or outsource it to an external party. In what part of the
procurement process are you currently?
A. Plan procurement management
B. Conduct procurements
C. Control procurements
D. Close procurements
23. Your team is meeting and discussing the proposals received to produce a
large required deliverable. The team is about equally split on which provider
they prefer. In what part of the procurement process are you currently?
A. Plan procurement management
B. Conduct procurements
C. Control procurements
D. Close procurements
24. In what part of the procurement process are you in if you are attempting to
complete procurement negotiations?
A. Plan procurement management
B. Conduct procurements
C. Control procurements
D. Close procurements
25. You are leading a project and have just lost a critical internal resource due to
illness and long-term disability. The work is very important and cannot be
done by an internal resource. You have decided to make use of an external
contractor to complete the deliverable. Time is of the essence and the
deliverable must be completed quickly. Under these circumstances, which of
the following would be the most helpful to add to the contract?
A. A force majeure clause
B. Schedule targets
C. A clear procurement statement of work
D. Incentives
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 504
26. With which type of contract is the seller to be most likely concerned about
project scope?
A. Cost plus fixed fee
B. Cost plus incentive fee
C. Fixed price plus incentive fee
D. Firm fixed price
27. You are leading a very complex project. Part of your job required you to
negotiate the contract with a large reseller. Throughout the negotiations you
required minutes to be kept which you also required the reseller to sign as
true and accurate. Now, several months later the seller is claiming they are
not required to complete certain components of work because they appear in
your notes and not the contract. In this case the seller is:
A. Generally incorrect, because all signed agreements must be upheld.
B. Correct because there was a tender and agreement.
C. Generally correct, because both parties are only required to perform
what is in the contract.
D. Incorrect, because both parties are required to comply with what they
agreed upon.
28. You are the project manager on a large petrochemical project. You have
awarded the primary contract to build the required facility to a large
European engineering firm. Within the contract is specific language that
requires the contract to submit a work plan to you for approval prior to
initiating work. However, the seller has failed to provide one prior to
commencing work. Which is the best thing for you to do?
A. Develop the work plan and provide it to the contractor.
B. File a letter of intent.
C. Issue a default letter.
D. Stop the project until the contractor develops a work plan.
29. Which type of contract is best if you do not have the manpower to audit the
submitted contractor invoices?
A. Firm fixed price
B. Fixed price plus incentive fee
C. Cost plus incentive fee
D. Cost plus fixed fee
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 505
30. You are leading a contracting team for a project making use of three external
contractors. You submit a deliverable that the project manager believes is
substandard. The project manager refuses to accept the deliverable and
refers you to the technical specifications section of the contract that
specifically addresses the deliverable in question. You examine the
specification and agree the deliverable failed to meet the specification. What
is the best thing to do?
A. Call your team together to review the contract.
B. Work with the project manager to issue a change order.
C. Enter into negotiations with the project manager to change the
contract.
D. Review the requirements and the WBS with your team.
31. Once signed, a contract is legally binding unless:
A. One party is unable to perform.
B. Both parties are unable to perform.
C. It is declared null and void by counsel.
D. It is in violation of applicable law.
32. All of the following statements concerning procurement documents are
incorrect except which one:
A. Well-designed procurement documents can simplify comparison of
responses.
B. Procurement documents must be rigorous with no flexibility to allow
consideration of seller suggestions.
C. In general, procurement documents should not include selection
criteria.
D. Well-designed procurement documents do not include a procurement
statement of work.
33. A seller is working on a cost reimbursable contract when the buyer decides
they would like to expand the scope of services and change to a fixed price
contract. All of the following are the seller’s options except which one:
A. Completing the original work on a cost reimbursable basis and then
negotiating a fixed price for the additional work.
B. Completing the original work and rejecting the additional work.
C. Starting over with a new contract.
D. Negotiating a fixed price contract that includes the work.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 506
34. The sponsor is worried about the seller deriving extra profit on the cost plus
fixed fee contract. Each month he requires the project manager to submit
CPI calculations and an analysis of the cost to complete. The project
manager explains to the sponsor that extra profits should not be a worry on
this project because:
A. The team is making sure the seller does not cut scope.
B. All costs invoiced are being audited.
C. There can only be a maximum 10% increase if there is an unexpected
cost overrun.
D. The fee is only received by the seller when project is completed.
35. The sponsor and the project manager are discussing what type of contract the
project manager plans to use on the project. The sponsor points out that the
performing organization spent a lot of money hiring a design team to come
up with the design. The project manager is concerned that the risk for the
buyer be as small as possible. An advantage of a fixed price contract for the
buyer is:
A. Cost risk is lower.
B. Cost risk is higher.
C. There is little risk.
D. Risk is shared by all parties.
36. You are in the middle of a complex negotiation when the other party says,
‘We need to finish in one hour because I have to catch my plane.” That
person is using which of the following negotiation strategies?
A. Good guy, bad guy
B. Delay
C. Deadline
D. Extreme demands
37. Your company has an emergency and needs contracted work done as soon as
possible. Under these circumstances, which of the following would be the
most helpful to add to the contract?
A. A clear procurement statement of work.
B. Requirements as to which subcontractors can be used.
C. Incentives.
D. A force majeure clause.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 507
38. The project team seems to like to argue; they have argued about everything.
Luckily the project set in place a reward system and team-building sessions
that will help and encourage the team to cooperate more. The latest thing
they are arguing about is whether they should complete a work package
themselves or outsource the work to someone else. What part of the
procurement process must they be in?
A. Conduct procurements
B. Plan procurement management
C. Administer procurements
D. Claims administration
39. Your program manager has come to you, the project manager, for help with a
bid for her newest project. You want to protect your company from financial
risk, and you have limited scope definition.
A. Firm fixed price
B. Cost plus percentage of cost
C. Time and material
D. Cost plus fixed fee
40. Negotiations between two parties are becoming complex, so Party A makes
some notes that both parties sign. However, when the work is being done,
Party B claims they are not required to provide an item they both agreed to
during negotiations because it was not included in the subsequent contract.
In this case, Party B is:
A. Incorrect, because both parties must comply with what they agreed
on.
B. Correct, because there was an offer.
C. Generally correct, because both parties are only required to perform
what is in the contract.
D. Generally incorrect, because all agreements must be upheld.
41. Your project has just been fast-tracked and you are looking to quickly bring
in a subcontractor to complete networking. There is no time to issue a
request for proposal, so you choose to use a company you have used many
times before for software development. A primary concern in this situation
is:
A. Collusion between subcontractors.
B. The subcontractor’s qualifications.
C. The subcontractor’s evaluation criteria.
D. Holding a bidder conference.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 508
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 509
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 510
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 12 — Procurement Management
Page 511
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 512
Stakeholder Management
Overview Slide 406
Chapter 13 of the PMBOK®
Guide is dedicated to the
stakeholder management
knowledge area. There are
four processes found in the
stakeholder management
knowledge area, which include the following
processes:
13.1 Identify stakeholders
13.2 Plan stakeholder engagement
13.3 Manage stakeholder engagement
13.4 Monitor stakeholder engagement
The stakeholder management
knowledge area first appeared in the
2012 5th edition of the PMBOK®
Guide. In previous editions, most
of the exact same information was
found in the communications
management knowledge area. In
the 6th edition of the Guide it is Image 133: The Stakeholder Management Processes
still a short knowledge area that
does not typically cause problems for students.
13.1 Identify Stakeholders
The first process found in the stakeholder management
knowledge area is the identify stakeholders process. Slide 407
This process is one of the two processes found in the
initiating process group and occurs prior to what most
project managers consider the “real-world” beginning
of project management. The identify stakeholder
process is somewhat different than the other processes
defined in the PMBOK® Guide in that it is
both a defined process that happens at a Image 134: 13.1 Identify Stakeholders
specific time in the project timeline, and it is
also a process that goes on constantly throughout the project. Don’t be surprised
if you see questions which seem to contradict each other. One question might
ask in which specific process are you to examine the stakeholders and their
needs while another might ask when should you examine the needs of the
stakeholders. The answer to the first question is the identify stakeholders
process while the answer to the second question is “all the time.”
The inputs to the identify stakeholders process include the following:
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 513
.1 Project charter — The project charter may be used to obtain information Slide 408
about people—both internal and external to the project — who may be
affected by the project.
.2 Business documents — This is one of the first two processes in any
project. As such, the business documents are very important to the process.
These documents include the business case and benefits management plan.
These two documents explain the business need and the expected business
benefits from the project.
.3 Project management plan — Don’t be confused by the fact that the
project management plan is listed as an input. PMI® recognizes the project
management plan is not available to this process when it is first initiated.
However, it is intended to be an iterative process and in later efforts the
information contained in the communications management plan and the
stakeholder engagement plan.
.4 Project documents — It is also unlikely that any of the additional project
documents will be available when the team begins to identify stakeholders,
but the change log, the issue log, and the requirements documentation will be
available for future iterations of the process.
.5 Agreements — Various types of agreements might be in place before the
project begins. The signors of those agreements are stakeholders for the
project
.6 Enterprise environmental factors — Items such as organizational
structure or governmental and industry standards can be key inputs to
understand a project’s stakeholders.
.7 Organizational process assets — Items such as stakeholder register
templates, lessons learned from previous projects, and/or stakeholder
registers from previous projects can help determine the players for your
project.
The tools and techniques used in the identify stakeholders process include the
following:
®
.1 Expert judgment — Like most of the processes found in the PMBOK
Guide, expert judgment is used in the identify stakeholder process.
.2 Data gathering— Data gathering is something we have talked about
extensively in this course. Now that we are in our 13th chapter, it should be
readily familiar to you. To identify stakeholders it is common to use Slide 409-
questionnaires and surveys as well as various brainstorming techniques. On 410
specific technique that you should add to your library is brain writing. Brain
writing is a refinement of brainstorming that allows individual participants
time to consider the question(s) individual before the group creativity session
is held. The information can be gathered in face-to-face groups or using
virtual environments supported by technology. [PMBOK® Guide 6th ed. p.
511].
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 514
.3 Data analysis — A big part of data analysis is stakeholder analysis. Slide 411
Stakeholder analysis is the process of systematically gathering and analyzing
both qualitative and quantitative data to determine what is driving the various
stakeholders’ participation in the project. Drivers can include interest, rights
such as legal or moral, ownership, knowledge and contribution. The team
should also consider document analysis.
.4 Data representation — When identifying stakeholders, the team may find
need to represent the gathered information visually. These methods provide
way to visually categorize stakeholders. If your project is small these models
are less important that a project with many stakeholders. As you study the
listed tools remember to think about the Acme Widget Factory team and how
they would need to look at stakeholders. Remember, it is important that you
recognize the real-world problem of your limited time, and your
stakeholders’ differing levels of influence within the organization. This
means you cannot treat all your stakeholders the same. You are going to be
required to spend more time with some and less with others. So how are you
going to ensure you correctly allocate your time to the “right” stakeholders?
Potential techniques include:
Grids — Grids are two axis representations of stakeholder
characteristics. In most cases, these are tools used in brainstorming
where the team is sitting together, whether in person or via
technology, discussing who the stakeholders are and how the team
views them. The process begins with each member of the team
brainstorming about who they think potential stakeholders are. As
they come up with names they write them on stickies that are then
placed on the poster paper or Slide 412-
the whiteboard. The facilitator 413
then draws a large four square
grid on the whiteboard or
poster paper. The grid is
defined by two axis such as
power and influence, power
and interest or support and
power. The team then places
each stakeholder in one of the
four quadrants. Image 135
shows a sample support/
influence grid. Image 135: Power vs. Influence Grid
Stakeholder cube — A stakeholder cube is built on the previously
discussed grids. It simply adds a third dimension or variable to the
grid.
Salience model — A salience model describes classes of
stakeholders based on assessments of their power (level of authority
or ability to influence the outcomes of the project), urgency (need for
immediate attention, either time-constrained or relating to the
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 515
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 516
Slide 415
Page 517
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 518
Page 519
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 520
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 521
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 522
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 523
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 524
A. Project charter
B. Enterprise environmental factors
C. Business documents
D. Statement of work
2. Which of the following is an input to the identify stakeholders process?
A. Work breakdown structure
B. Stakeholder management strategy
C. Agreements
D. Stakeholder identification strategy
3. Which of the following is a tool and technique used in the identify
stakeholder process?
A. Expert judgment
B. Communication models
C. Communication methods
D. Interpersonal skills
4. Which of the following is an output from the identify stakeholders process?
A. Project document updates
B. Communication management strategy
C. Stakeholder analysis
D. Stakeholder register
5. Which of the following is an input to the plan stakeholder engagement
process?
A. Communications management strategy
B. Stakeholder management plan
C. Agreements
D. RACI diagram
6. Which of the following is NOT an input to the plan stakeholder engagement
process?
A. Enterprise environmental factor
B. Stakeholder register
C. Project management plan
D. Organizational process assets
7. Which of the following is NOT a tool or technique used in the plan
stakeholder engagement process?
A. Organizational process assets
B. Expert judgment
C. Meetings
D. Decision making
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 525
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 526
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 527
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 528
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 13 — Stakeholder Management
Page 529
12. Answer B. PMBOK Guide p. 526-528 – The tools or techniques used in the
manage stakeholder engagement process include the following:
Expert judgment
Communication skills
Interpersonal and team skills
Ground rules
Meetings
13. Answer B. PMBOK Guide p. 528-529 – The outputs from the manage
stakeholder engagement process include the following:
Change request
Project management plan updates
Project document updates
Page 530
18. Answer A. PMBOK Guide p. 535-536 – The outputs from the control
stakeholder engagement process include the following:
Work performance information
Change requests
Project management plan updates
Project documents updates
19. Answer D. PMBOK Guide p. 535-536 – The outputs from the control
stakeholder engagement process include the following:
Work performance information
Change requests
Project management plan updates
Project documents updates
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 531
Professional Responsibility
Overview
There is not a section on the exam for professional responsibility. It is a topic
that appears in every section. PMI® addresses the topic in four areas:
responsibility, respect, fairness and honesty. Most of this topic is
straightforward. However, it is important to remember that PMI® uses a North
American perspective on these topics. As you study and work to complete your
exam, there are some important points to always keep in the forefront of your
mind. These rules or guidelines can be broken into four different categories:
Your duty to the profession
Scope and estimates
Authority
Above all else
If you remember these guidelines throughout your preparation, you will find
many of the questions much easier.
Your Duty to the Profession
The first category of guidelines is your duty to the profession of project Slide 428
management. The guidelines are based on PMI’s Code of Ethics and
Professional Conduct found on PMI’s website at:
http://www.pmi.org/About-Us/Ethics/Code-of-Ethics.aspx
PMI® demands compliance with all organizational rules and policies, and
compliance with PMI’s Code of Ethics and Professional Conduct. It is expected
that you will advance the profession.
Another key part of these obligations is the management of conflicts. As the
project manager you must manage conflict of interest situations and other
prohibited professional conduct. However—be careful here. Conflicts of
interest are not necessarily bad. They represent situations where stakeholders or
you have different interests that are opposed to each other. It is the project
manager’s job to balance these competing and sometimes conflicting interests.
It is also the project manager’s responsibility to make sure they are never in a
situation where they have competing agendas. The project manager must always
have the best interests of the project and their organization front and center.
For the exam, it is also important to remember the type of project you are
leading. It is a large, multi-national project and it is therefore important that you
understand the culture of foreign project locations and follow their customs and
rules.
Scope and Estimates Slide 429-
430
The second set of guidelines to remember for the exam focus on the area of
scope and estimates. It is critically important that you involve the stakeholders
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 532
in the development of scope and engage them early in the process. Furthermore,
do not perform project tasks until the scope is verified. When asked to make
scope changes, do so only through the scope management process, and don’t add
any work without the sponsor’s approval.
The PMBOK® Guide is not prescriptive, as it supports a number of
methodologies each with different phases and structures. Therefore, it is
important that scope verification is done at the end of each phase. As a basic
rule, all deliverables must be quantifiable, and the project manager must ensure
that the team develops tasks and assigns resources to all tasks to complete the
scope. The project manager must also ensure the team reviews all deliverables
and doesn’t allow incomplete or incorrect deliverables to be released.
Another key project manager role is the preparation and publishing of accurate
estimates. Sometimes this also includes the requirement to cut schedules or
budgets. If forced to cut either, it’s best not to make across the board reductions.
Cuts should be made where they will have the greatest impact. When this occurs,
the project manager must also modify scope and quality to fit the reduced budget
or schedule.
Authority
The third area of focus is the project manager’s authority. In the real world this Slide 431
is often an area of frustration for PM’s due to the frequent perceived lack of
authority they hold. For the exam, focus on the following four keys:
Work should not begin without a charter. If the project does not have a
charter, the project manager cannot be sufficiently empowered to do any
work or get resources to do work.
A project manager must understand the limits of their authority and only take
actions within the limits of that authority.
A project manager should never misrepresent their authority to anyone for
any reason.
When something is beyond the limits of a project manager’s authority, they
must escalate those items to senior management and/or the project sponsor.
This is critical to ensure the credibility and success of all involved.
Above All Else…
The two most important concepts to remember for the exam impact almost every Slide 432-
question. First, you must remember that you are looking for the BEST answer to 433
the question, and not the perfect answer. Many questions will only provide
answers that are sub-optimal. Rarely will you see an answer that is a direct
quote from the standards.
The second concept is regarding the process a project manager should use to
resolve any situation. In every case the project manager should first evaluate the
event and evaluate the event’s impact to the project’s cost, schedule, scope,
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 533
quality, and customer satisfaction. Based upon this analysis, the project team
should then develop alternatives and offer a recommendation. Only then should
the project manager approach the sponsor and/or management. The key here is
that a project manager never simply drops a problem off with their manager.
They always bring solutions.
Other less critical concepts include the fact that negotiations can involve items
other than money because many internal items can be bartered. The project
manager is often responsible for the development of the processes used on a
project, therefore it is important that they never shortcut the defined processes.
If the project manager does not follow the process, no one else will either.
Project managers who do a poor job planning their projects are likely to be out of
work because poorly planned projects are most likely to be cancelled.
When reporting to senior management and/or project sponsors, milestone reports
are the appropriate level of detail. This is often different from many candidates’
real world experience.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 534
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 535
4. You are given the opportunity to interview for your dream position. It is the
opportunity to lead a large global project with several dozen resources across
three continents. The project will require the team to work almost entirely
virtually. Unfortunately, you do not have any experience working with
virtual teams. What should you do when discussing the project with the
sponsor?
A. Because you are PMP® certified inform the sponsor that you have the
necessary experience.
B. Inform the sponsor you lack the requisite experience and decline the
offer.
C. Since you have led large international teams before convince the
sponsor that you have the experience.
D. Inform the sponsor that you have not led virtual teams before, but
highlight why you believe you are a good fit for the project.
5. You are one of five project managers who have been asked to participate in
an upcoming portfolio management meeting. The purpose of the meeting is
to help leadership select the best of several projects to complete. Each of the
participating project managers has a vested interest in one of the particular
projects and is therefore biased. The selected project will be highly visible
and likely a great success. How should you and the other project managers
proceed?
A. You each should not give opinions as you are not objective.
B. As a group you should make a single Ben Franklin T that shows the
pros and cons of each project.
C. You each should explain why the project you would lead would be
best and provide as much supporting documentation as possible.
D. You each should recommend the project that would be best for the
organization in the long run, regardless of who will run it.
6. You are leading a large engineering project in a foreign country. As part of
the project you are required to move several very large machine components
from the dock facilities to the project location. To ensure the machinery is
transported successfully, your local contact informs you that a local police
fee will have to be paid for traffic coordination. What should you do?
A. Pay the fee.
B. Find another way to complete the project.
C. Do not pay the fee because it is a bribe.
D. Do not pay the fee unless it was included in the project estimate.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 536
7. You are a functional manager who has been tasked with providing several
key deliverables for a project that is strongly supported by senior
management. You and the project manager strongly disagree on the tasks
that need to be done, how the project should proceed, and in the project
itself. The project manager is relatively new and you have significant
organizational experience. What should you do?
A. Ask to have the work reassigned.
B. Sit down with the project manager and attempt to describe why the
project should not be done.
C. Provide the project manager with what they need.
D. Inform your manager of your concerns and get their support.
8. You are managing a large team. One of your resources has been tasked with
writing a report which they are several days late producing. Just 30 minutes
before a meeting to discuss the report, they hand you the completed report.
Quickly reviewing the report, you notice several errors. What should you
do?
A. Cancel the meeting and rewrite the report.
B. Continue with the meeting as planned.
C. Allow the meeting to continue, but require the resource to discuss
how they plan to deal with the errors.
D. Cancel the meeting until you can fully review the report and it can be
fixed.
9. You need to schedule a meeting with your team. As you review everyone’s
calendar you notice that one of your resources has scheduled a meeting with
a critical stakeholder who is a member of the senior leadership team. You
were not aware of the meeting. What should you do?
A. Address the concern with the resource.
B. Ignore it. It is part of their job.
C. Discuss the situation with your boss.
D. Ask to be included in the meeting.
10. You are leading a large process improvement project within your
organization. Once completed, it is expected the project will save the
organization 20% on its fixed costs. Your team has spent four weeks
planning the project and has prepared detailed estimates for all deliverables.
When you present the schedule and budget to senior management you are
told to cut the budget by seven percent. What should you do?
A. Reduce the budget as requested and note the changes in the risk
register.
B. Provide the accurate estimate of costs and be able to support it.
C. Meet with the project team and work together to reduce the budget as
requested.
D. Revisit your plan projections to find additional project outcomes that
justify the higher project costs.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 537
11. You are one of six project managers leading a major program. You just
completed preparing your status report for the current reporting period which
shows a CPI of 0.86 and an SPI of 0.84. As you prepare for the status
meeting tomorrow afternoon, you recall that another project manager on the
program has had several major deliverables you knew were late, but they still
are reporting they are on schedule. What should you do?
A. Stop using EVMS and simply report on schedule and budget.
B. Bring up the issue in private with the program manager.
C. Meet with the other project manager to discuss the issue.
D. Develop a risk strategy in case the other project truly is late and it
impacts you.
12. You have a meeting scheduled for the next day with a contractor to complete
the negotiations to have them deliver a major component of your project
when you discover your project is likely to be cancelled. What should you
do?
A. Postpone the negotiations.
B. Use the meeting to inform the contractor it is likely to be cancelled.
C. Cut the meeting short.
D. Only negotiate the key elements.
13. You are taking over a project for a large manufacturing organization. The
project was originally scheduled to take 22 months and is currently 14
months into the schedule. The previous project manager consistently
reported the project as both on time and on budget. However, after a careful
review of the project documentation and interviews with the project team
you have discovered the project is significantly over budget and behind
schedule. In fact the project is likely to cost twice the original budget and
will likely take 36 months to complete. What should you do?
A. Decline to accept the project.
B. Move forward with the original schedule and report the missed
targets.
C. Meet with the team to restructure the project to meet the project
deadline.
D. Report your assessment to the project sponsor.
14. You are reviewing the implementation plan for a major project you are
leading. As you review the documentation you discover a key error that will
prevent you from meeting a key milestone. What should you do?
A. Change the milestone date.
B. Develop alternatives to meet the milestone date.
C. Discuss with the team the importance of hitting milestones at the next
team meeting.
D. Inform the sponsor of the missed milestone.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 538
15. You work as a project manager for an IT consulting organization. Your boss
has promised you a percentage of a major contract bonus if you achieve
specific contractually-based performance incentives. As you complete the
second-to-last major deliverable, your team informs you of a situation that
will prevent you from achieving the performance incentive. What should
you do?
A. Continue the project as planned.
B. Alter the project schedule to achieve the incentive.
C. Inform your manager that you will not achieve the target.
D. Negotiate with the client to achieve the bonus and provide the desired
result.
16. You work as a project manager for an IT consulting organization. Your boss
has promised you a percentage of a major contract bonus if you achieve
specific contractually-based performance incentives. You are on target to
achieve the incentive target, but your team has discovered that meeting the
letter of the contract will not meet the customer’s functional requirements.
What should you do?
A. Continue the project as planned.
B. Inform your boss.
C. Inform the customer of the situation and work out a mutually
agreeable solution.
D. Add as much functionality as you can while maintaining the
incentive.
17. You work as a contract project manager and have been provided with a
significant amount of data from your various clients that is proprietary. The
daughter of your next door neighbor contacts you for help on her masters’
thesis that would require you to share some of the proprietary data for
academic research purposes only. What should you do?
A. Refuse to share the information.
B. Contact your clients and seek permission to disclose the information.
C. Share the information, but ask the student to not disclose any client
names.
D. Release the information without any direct client references.
18. Which of the following is not a responsibility of the project manager?
A. Provide accurate and truthful representations of cost estimates.
B. Maintain all customer confidentialities.
C. Determine the legality of company project management procedures.
D. Ensure that a conflict of interest does not compromise the legitimate
interest of the customer.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 539
19. You are leading a $9,600,000 software development project when you
discover that the firm providing your project with several key resources is
struggling to maintain resources due to a labor dispute. Yours is one of five
projects within your organization that is using the same firm for development
resources. What should you do?
A. Negotiate with the firm to ensure your project maintains proper
resourcing.
B. Cancel the contract with the firm.
C. Inform the other project managers about the labor issue.
D. Contact the firm and advise it that you will cancel the contract if it
does not settle the labor dispute.
20. You are managing a large team. One of your resources has been tasked with
writing a report which they are several days late producing. Just 30 minutes
before a meeting to discuss the report, they hand you the completed report.
Quickly reviewing the report, you notice several errors. How could this
situation have been prevented?
A. Postpone the meeting earlier when you did not receive the report.
B. Coach and mentor the employee.
C. Require more frequent updates from the employee.
D. Ensure the employee was properly trained to do the job.
21. You are leading a road construction project. The effort requires your
company to pour more than 24 miles of eight lane highway. You have
completed more than 80% of the project and are now reviewing the latest
quality test results. The tests show 40% of the poured concrete does not
meet your company’s quality standard, but is only slightly below standard.
You are certain the concrete will function as is, and do not believe the slight
variance is significant. What should you do?
A. Ensure the remaining concrete meets the standards.
B. Report the lesser quality level and try to find a solution.
C. List in the next report that the concrete “meets the quality needs”.
D. Ask management to change the quality standard to the achieved level.
22. You are a PMP® certified project manager and are contacted by PMI®
regarding your best friend who is also a PMP®. PMI® is asking about
information you have regarding unethical behavior by your friend. You
know the accusations are true, but do not want to incriminate your friend.
What should you do?
A. Stay out of the situation and ignore the information request.
B. Contact PMI® and provide the factual information you have as
required by the PMI® code of conduct.
C. Contact PMI® and deny the accusation.
D. Contact PMI® and recuse yourself from the situation because of your
personal relationship with the accused.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 540
23. You have been asked to lead a $60,000 petrochemicals project for your
company. The project will require the cooperation of more than 50 resources
across three continents. These resources speak five different primary
languages and most of the work will be completed via virtual teams. What is
the best way to ensure cultural differences do not derail the project?
A. Always choose your words carefully whenever you communicate
with the team.
B. You should spend more time on the WBS to make absolutely sure it is
complete.
C. At a team meeting ask each team member to describe something
unique about their culture.
D. Make sure you encode all communications.
24. You are leading an IT project within your organization. As you are preparing
your weekly status report, you see that two of your resources are not
reporting actual hours and are only reporting percent complete. This is
skewing the EVMS reporting. What is the best thing to do?
A. Report the resources to their functional managers.
B. Discuss the impacts of these actions with the resources.
C. Continue reporting the information as received.
D. Continue reporting the information as received, but report the missing
data.
25. Your company president has asked that you contract part of your latest
project to a firm the organization has used many times before. As the project
manager, what should you be most concerned about in this situation?
A. Meeting management’s schedule expectations.
B. The contract terms and conditions.
C. Meeting management’s cost expectations.
D. Making sure the firm has the qualifications to complete the project
work.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 541
26. You have been asked to lead a $60,000 petrochemicals project for your
company. The project will require the cooperation of more than 50 resources
across three continents. These resources speak five different primary
languages. To help ensure a tightly knit team you initiate some team-
building games during team meetings. However, two of your resources
refuse to participate and inform you that such activities are culturally
unacceptable in their country. What should you do?
A. Tell the team members they need to be familiar with how things are
done in the headquarters company’s country and they should
participate.
B. Excuse the team members from playing and arrange to discuss
alternative activities with which they would be more comfortable.
C. Ask to have the team members removed from the team as they are
likely going to have other issues as well.
D. Excuse the team members from the activity and any future team-
building activities.
27. It is the first day of your new job with a large manufacturing organization.
You are taking over as the project manager on a project that has been
ongoing for nine months. As part of your review of the project
documentation you discover the previous project manager made a US
$2,500,000 payment that was not approved in accordance with the
organization’s policies. The project currently has an SPI of 0.98 and a CPI
of 1.14. What should you do?
A. Ignore the payment as it happened prior to your arrival.
B. Ignore the payment because both the CPI and SPI are within
acceptable boundaries.
C. Put the payment in an escrow account.
D. Contact your manager and inform them of the discrepancy.
28. A project manager is being considered as the potential leader of a project
which will deal exclusively with a virtual team located on several different
continents. What should they do when discussing the opportunity with the
sponsor?
A. Decline the assignment because they do not have experience with
virtual teams.
B. Point out to the sponsor that they have not had experience with
virtual teams, but also explain why they think they would be an
excellent fit for the project.
C. Avoid any conversation regarding the types of teams involved so the
sponsor does not know they lack experience in this area.
D. Since they have managed many projects with a wide range of teams,
it does not matter that the new project involves virtual teams and they
should tell the sponsor they have the relevant experience.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 542
29. While staffing a project in another country, the project leader from that
country comes to you with a suggested team consisting of members of the
project leader’s family. Your first course of action should be to:
A. Inquire if hiring only through family lines is common practice in the
project leader’s country.
B. Review the resumes of the individuals to see if they are qualified.
C. Ask the project leader to provide additional names of people
unrelated to him/her.
D. Use a different project leader to prevent problems later in the project.
30. A major negotiation with a potential subcontractor is scheduled for tomorrow
when you discover there is a good chance the project will be cancelled.
What should you do?
A. Do not spend too much time preparing for the negotiations.
B. Cut the negotiations short.
C. Only negotiate major items.
D. Postpone the negotiations.
31. One of your project resources is three days late with a report. Five minutes
before the meeting where the topic of the report is to be discussed, they hand
you the report. You notice some serious errors in it. What should you do?
A. Cancel the meeting and reschedule when the report is fixed.
B. Go to the meeting and tell the other attendees there are errors in the
report.
C. Ask the employee to do the presentation and remain silent as the
other attendees find the errors.
D. Cancel the meeting and rewrite the report yourself.
32. You are leading a project that is part of a large, critical program. At a high-
level status meeting, you hear another project manager report their project is
on schedule even though you remember several deliverables from their
project arrived late to you and negatively impacted your schedule. What
should you do?
A. Meet with the program manager.
B. Develop a risk control plan.
C. Discuss the issue with your boss.
D. Meet with the other project manager.
33. A large, complex construction project in a foreign country requires
coordination to move needed equipment through crowded streets. To ensure
the equipment is transported successfully, your contact in that country
informs you that you will have to pay the local police a fee for coordinating
traffic. What should you do?
A. Do not pay the fee because it is a bribe.
B. Eliminate the work.
C. Pay the fee.
D. Do not pay the fee unless it is part of the project estimate.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 543
34. You are in the fifth year as a project manager for your organization and have
successfully managed over a dozen projects. Your manager has consistently
asked you to cut your budgets by ten percent after you have given it to them.
You have been assigned to lead a new project with more than twenty major
stakeholders and the scope is somewhat vague. This project has a high
priority and is very visible throughout the organization. Which of the
following is the best thing to do?
A. Reduce the estimates prior to delivery to the sponsor and note the
changes in the risk register.
B. Provide accurate estimates for the project costs and be able to support
them.
C. Meet with the project team and identify where you can cut ten
percent of the costs.
D. Re-plan the project to exceed the stakeholders’ expectations.
35. You are in the middle of a large project for your organization when you
discover that an external contractor your project is using is having significant
issues with its employees due to a labor dispute. There are several other
projects within your organization also using this contractor. What should
you do?
A. Cancel the contract with the contractor.
B. Inform the other project managers about the labor dispute.
C. Contact the contractor and advise them you will cancel the contract
on your project unless the labor dispute is settled.
D. Attempt to keep the contractor’s resources on your project.
36. You are finalizing the monthly project status report due to the project sponsor
when you discover several of your resources have not been reporting their
actual hours spent on project activities. This has resulted in skewed project
statistics. What is the most appropriate action to take?
A. Discuss the impacts of these actions with team members.
B. Continue reporting the information as presented to you.
C. Report the ream member’s actions to their functional managers.
D. Provide accurate and truthful representations in all project reports.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 544
37. Five interns from another country are working on your project. You have
arranged for the entire project team to participate in some games as team-
building activities to help improve team dynamics. At the event the interns
refuse to participate, claiming the games involve unacceptable behavior in
their country and they would feel uncomfortable participating. What should
you do?
A. Tell the students they need to become familiar with how things are
done in their host country.
B. Excuse the students from playing the game and arrange to discuss
alternative team- building activities in which they would feel more
comfortable participating.
C. Report the interns to their functional manager and request they be
removed from the project so their attitude does not negatively impact
the project.
D. Tell the students they are excused from the games and to not attend
any team-building activities in the future.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 545
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 546
11. Answer C. You should first confront the other project manager in private to
get an explanation rather that creating a public issue without justification.
12. Answer A. You are ethically obligated to not waste your contractor’s time
and be above board with information you have. Therefore, you should at the
least postpone the negotiations.
13. Answer D. You already have expectations that are being missed. The best
answer would be to evaluate the situation and bring alternatives to the
sponsor. However, that is not one of the choices. The best of the given
choices is to inform the sponsor.
14. Answer B. Remember, you always develop options before you do anything
else. Only then do you go to management. In this case developing
alternatives is one of the choices so take it!
15. Answer A. Contract incentives are provided as a means to achieve goals that
are beyond the requirements. Missing an incentive does not mean you are
not delivering. The best option is to continue the project as planned.
16. Answer C. In this case, your first responsibility is to ensure the product you
develop meets the customer’s needs. The contract puts you at odds with this
goal. You could easily meet the contract specifications and receive the bonus
without meeting the customer’s real needs. Therefore, you should inform
them of the situation and negotiate a mutually agreeable solution.
17. Answer B Many companies are willing to share their information for
academic purposes so long as they receive derivative works. However, you
may only disclose such information with the client’s permission.
18. Answer C. As a project manager, unless previously agreed upon, it is not
your role to determine the legality of any organizational procedure as you
likely lack the specific training required.
19. Answer C. Your first responsibility is to do what is in the best interest of
your company. Therefore, you should inform the other project managers and
work together with the contractor to resolve the situation.
20. Answer A. This question is very tricky and requires you to read the choices
carefully. The objective is to pick the choice that has the highest probability
of preventing the problem situation, a meeting with a poorly prepared report.
The only option that does that is postponing the meeting more quickly. All
the other choices might solve the problem, but there are no guarantees.
21. Answer B. Reporting the lesser quality level and trying to find an answer is
the closest solution to a perfect world. All other choices fail to meet your
ethical obligations.
22. Answer B. Hopefully, this was an easy one for you, at least in theory. You
are required to provide information about any unethical situation to which
you are privy.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 547
23. Answer C. This is a trick question of sorts. The only answer that does not
only involve you is asking the team to describe a unique aspect of their
culture. All the others only address your issues.
24. Answer B. The only answer that attempts to resolve the issue without
escalation is discussing the impacts of these actions with the resources. Only
if this does not work should you go to the resource managers.
25. Answer D. Management has selected the firm. Your primary driver is
making sure the firm has the ability to actually do the specified work.
26. Answer B. Team building is critical to any team’s success. However, it is
also important that a project manager is sensitive to cultural differences. The
only option that takes this into account is excusing the team members from
playing the activity and arranging to discuss acceptable alternatives.
27. Answer D. Ignoring the actions of the previous project manager is not an
option regardless of how well the project is doing. The only viable answer is
to tell your manager immediately.
28. Answer B. It is always important to point out key deficiencies. However, it
is also reasonable for the project manager to explain why they believe they
are a good fit. So long as the project manager has provided all the pertinent
facts to the sponsor they have done their job.
29. Answer A. This is one of those questions where you have to ask, what
would you do first? The answer is find out if hiring family members is a
common practice.
30. Answer D. Postponing the negotiations is the most ethical choice and shows
good faith. Spending time negotiating at this time would be a waste.
31. Answer A. Allowing an employee to deliver an inaccurate report, even one
they create is a public condemnation of the employee and should never be
done. It is best to privately discuss the issue with the employee after
cancelling the meeting and give them the opportunity to correct the report.
32. Answer D. This question requires you to go back to your conflict resolution
methods. The best way to resolve a conflict is through confrontation or
problem solving. This means meeting with the other project manager to
resolve the issue before going to anyone else.
33. Answer C. This is a fee paid to a governmental organization for services
and is not a bribe. Do not get tricked because a bribe is listed in the possible
answers.
34. Answer B. If your estimates are accurate you are obligated to stick to them.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Chapter 14 — Professional Responsibility
Page 548
35. Answer B. There is nothing in the question which indicates the dispute has
caused a problem on the project, so there is no need to cancel the contract.
Additionally, cancelling the contract requires following the termination
procedures outlined in the contract and cannot be done unilaterally. Keeping
all the resources yourself puts your interests above the organizations. The
only answer which is viable is to inform the other project managers.
36. Answer D. A project manager should always report truthfully.
37. Answer B. It is important to remember that a professional project manager
always respects cultural differences. Respecting differences requires the
project manager to allow the interns to not participate, but also find other
activities they can do so as to not demean them.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 549
PMP 2018 Exam Prep
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
Course Structure
Application & Exam
Types of Questions
PM Basics
Ten Knowledge Areas
Professional Responsibility
Practice Exams
The Application & Exam
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 550
PMP Application & Exam
Extra Reading
Project and Program Risk Management, R. Max Wideman, Editor
Quality Management for Projects and Programs, Lewis R. Ireland
Doing Business Internationally, Walker, Walker and Shmitz
The Cultural Dimensions of International Business, Gary P. Ferraro
Global Literacies, Robert Rosen
How to Lead Work Teams, Fran Rees
Principles of Project Management, PMI®
Project Management A Systems Approach, Harold Kerzner
Human Resource Skills for the Project Manager, Vijay K. Verma
Earned Value Practice Standard, PMI®
The Scrum Guide™ , Jeff Sutherland and Ken Schwaber
PMP Application & Exam
The Acme Widget Factory
You are a project manager for a large multinational.
You are managing 100 resources located in five different
time zones on two different continents.
A matrixed organization and none of the resources are
dedicated to only your project or report directly to you.
Your Challenges
Significant Scope Change Problems with Product Quality
Schedule & Cost Overruns Resource Burnout
Problems with Resource Many Don’t Like Your Processes
Constraints
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 5
PMP Application & Exam
What do the letters PMP mean?
• Project Management Professional.
What are the benefits of being a PMP?
• Higher income potential.
• Shows knowledge of international standards.
• Is required by a growing number of employers.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 551
PMP Application & Exam
Work
How Do I Become A PMP?
Experience
Application Application Applicant
Pass Exam
Submission Completeness Payment
(1 year)
90 Days Review Process
Contact
Hours
Receive
Certification
PMP
PMP Application
Applying online is the fastest way
http://www.pmi.org/certification/project‐
management‐professional‐pmp.aspx
Mailing Address
PMI Certification Department
Fourteen Campus Boulevard
Newtown Square, PA. 19073
PMP Exam
Percentage of
Domain Questions
Initiation 13%
Planning 24%
Executing 31%
Monitoring & Controlling 25%
Closing 7%
Total Number of Scored Questions 175
Total Number of Unscored Questions 25
Total Questions on Exam 200
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 552
PMP Exam
Task Initiating – 13%
Task 1 Perform project assessment based upon available information, lessons
learned from previous projects, & meetings with relevant stakeholders in
order to support the evaluation of the feasibility of new products or services
within the given assumptions and/or constraints.
Task 2 Identify key deliverables based on the business requirements in order to
manage customer expectations & direct the achievement of project goals.
Task 3 Perform stakeholder analysis using appropriate tools & techniques in order to
align expectations & gain support for the project.
Task 4 Identify high level risks, assumptions, & constraints based on the current
environment, organizational factors, historical data, & expert judgment, in
order to propose an implementation strategy.
Task 5 Participate in the development of the project charter by compiling & analyzing
gathered information in order to ensure project stakeholders are in agreement
on its elements.
PMP Exam
PMP Exam
Task Planning – 24%
Task 1 Review & assess detailed project requirements, constraints, & assumptions
with stakeholders based on the project charter, lessons learned, & by using
requirements gathering techniques in order to establish detailed project
deliverables.
Task 2 Develop a scope management plan, based on the approved project scope &
using scope management techniques, in order to define, maintain, & manage
the scope of the project.
Task 3 Develop the cost management plan based on the project scope, schedule,
resources, approved project charter & other information, using estimating
techniques, in order to manage project costs.
Task 4 Develop the project schedule based on the approved project deliverables &
milestones, scope & resource management plans in order to manage timely
completion of the project.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 553
PMP Exam
Task Planning – 24%
Task 5 Develop the human resource management plan by defining the roles &
responsibilities of the project team members in order to create a project
organizational structure & provide guidance regarding how resources will be
assigned & managed.
Task 6 Develop the communications management plan based on the project
organizational structure & stakeholder requirements, in to define & manage
the flow of project information.
Task 7 Develop the procurement management plan based on the project scope,
budget, & schedule, in order to ensure that the required project resources will
be available.
Task 8 Develop the quality management plan & define the quality standards for the
project and its products, based on the project scope, risks & requirements, in
order to prevent the occurrence of defects & control the cost of quality.
PMP Exam
Task Planning – 24%
Task 9 Develop the change management plan by defining how changes will be
addressed & controlled in order to track & manage change.
Task 10 Plan for risk management by developing a risk management plan; identifying,
analyzing, & prioritizing project risk; creating the risk register; & defining risk
response strategies in order to manage uncertainty & opportunity throughout
the project life cycle.
Task 11 Present the project management plan to the relevant stakeholders according
to applicable policies & procedures in order to obtain approval to proceed
with project execution.
Task 12 Conduct kick‐off meeting communicating the start of the project, key
milestones, & other relevant information in order to inform & engage
stakeholders & gain commitment.
Task 13 Develop the stakeholder management plan by analyzing needs, interests, &
potential impact in order to effectively manage stakeholders’ expectations &
engage them in project decisions.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 14
PMP Exam
Task Executing – 31%
Task 1 Acquire & manage project resources by following the human resource &
procurement management plans in order to meet project requirements.
Task 2 Manage task execution based on the project management plan by leading &
developing the project team in order to achieve project deliverables.
Task 3 Implement the quality management plan using the appropriate tools &
techniques in order to ensure that work is performed in accordance with
required quality standards.
Task 4 Implement approved changes & corrective actions by following the change
management plan in order to meet project requirements.
Task 5 Implement approved actions by following the risk management plan in order
to minimize the impact of the risks & take advantage of opportunities on the
project.
Task 6 Manage the flow of information by following the communications plan in
order to keep stakeholders engaged & informed.
Task 7 Maintain stakeholder relationships by following the stakeholder management
plan in order to receive continued support & management expectations.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 15
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 554
PMP Exam
Task Monitoring & Controlling – 25%
Task 1 Measure project performance using appropriate tools & techniques in order
to identify & quantify any variances & corrective actions.
Task 2 Manage changes to the project by following the change management plan in
order to ensure that project goals remain aligned with business needs.
Task 3 Verify that project deliverables conform to the quality standards established in
the quality management plan by using appropriate tools and techniques to
meet project requirements and business needs.
Task 4 Monitor & assess risk by determining whether exposure has changed &
evaluating the effectiveness of response strategies in order to manage the
impact of risks & opportunities on the project.
Task 5 Review the issue log, update if necessary, & determine corrective actions by
using appropriate tools & techniques in order to minimize the impact on the
project.
Task 6 Capture, analyze, & manage lessons learned, using lessons learned
management techniques in order to enable continuous improvement.
Task 7 Monitor procurement activities according to the procurement plan in order to
verify compliance with project objectives.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 16
PMP Exam
Task Closing – 7%
Task 1 Obtain final acceptance of the project deliverables from relevant stakeholders
in order to confirm that project scope & deliverables were achieved.
Task 2 Transfer the ownership of deliverables to the assigned stakeholders in
accordance with the project plan in order to facilitate project closure.
Task 3 Obtain financial, legal, & administrative closure using generally accepted
practices & policies in order to communicate formal project closure & ensure
transfer of liability.
Task 4 Prepare & share the final project report according to the communications
management plan in order to document & convey project performance &
assist in project evaluation.
PMP Exam
Task Closing – 7%
Task 5 Collate lessons learned that were documented throughout the project &
conduct a comprehensive project review in order to update the organization’s
knowledge base.
Task 6 Archive project documents & materials using generally accepted practices in
order to comply with statutory requirements & for potential use in future
projects & audits.
Task 7 Obtain feedback from relevant stakeholders using appropriate tools &
Techniques & based on the stakeholder management plan in order to evaluate
their satisfaction.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 555
PMP Exam
Must get 61% or better
There is no penalty for wrong answers
Fees:
PMI members pay $405
Non‐members pay $555
Each applicant has one (1)
year to take exam
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 19
PMP Exam
The exam is NOT based on the PMBOK Guide®.
The exam requires more than memorization.
Almost half of the exam requires you to identify what
you would do in a given situation.
The exam emphasizes the five (5) process groups, ten
(10) knowledge areas and 47 processes.
Exam requires you to answer the questions from
PMI’s perspective based on the RDS.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 20
PMP Exam
Rarely will the answer be a direct quote from the
PMBOK Guide.
Questions can be series based, i.e. you must answer
the first question correctly to answer the next three (3)
or four (4) questions.
A small percentage of the questions will be based on
the inputs and outputs from the PMBOK Guide.
Earned Value, Critical Chain, PERT, EMV, and CPM will
almost certainly be on the test.
Approximately 10%‐15% of the exam will require the
use of other formulas.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 21
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 556
PMP Exam
Test‐Taking Strategies
Predict the answer.
Your first instinct.
Read the whole question.
Look for wrong answers.
Don’t overanalyze.
Key words.
Confusing answer choices.
True statements.
No pattern.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 22
Types of Exam Questions
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
Types of Questions
Two Right Answers
Remember, what would you do first.
Made up Terms
Failing to know the key terms &
acronyms will = failure.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 557
Types of Questions
Two Right Answers
During your daily standup, a teammate reports that
they are struggling with a critical task that is causing
the project backlog item to be delayed. What should
you do?
A. Immediately inform the sponsor and key stakeholders.
B. Evaluate alternatives with the team.
C. Trust the team to handle it.
D. Keep pushing ahead as there is nothing you can do.
Types of Questions
Situational Questions
Molly works for a large multi-national organization that
manufactures steel as a project coordinator. Her organization
is matrixed. She is responsible for three different projects,
each with teams of ten to 20 team members who are also
assigned to multiple projects. Yesterday she received an
email from the vice president of stamped products
complaining that one of her three projects was failing to meet
the customer’s expectations, and they had sent notification of
their intent to cancel the contract. What is the most likely
cause of this problem?
A. The customers in question were not involved early enough in the
process.
B. Customer sign-off was not obtained for the scope statement.
C. Scope definition happened too late in the process.
D. The customer did not read their e-mail.
Types of Questions
Extraneous Information
You are the project coordinator for a textile
manufacturing company that is based in Southeast Asia.
Your project’s original budget was $648,000 USD, and
you have already spent $462,000 USD. You currently
have a CPI of 0.86 and an SPI of 0.62. Your project has
an EV of US $399,000 and an ETC of $288,316. You are
more than halfway through your project, and have a
TCPI of 0.86. Your sponsor has just requested a major
shift in project scope; what should you do?
A. Try to convince the sponsor to change their mind.
B. Agree to implement the changes immediately.
C. Evaluate the changes for impacts to the cost and schedule.
D. Stop the project until the issue is resolved.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 558
Types of Questions
Understanding vs. Memorization
At lunch you are sitting with a new employee within the
organization. They are an experienced scrum master and
commenting about how frustrated they are with the organizational
requirement to use a Work Breakdown Structures for their
projects especially early in the process when requirements are so
poorly defined. You comment that a properly done WBS is similar
to an FBS and an important tool for project success even early in
the project. Which of the following statements best justifies this
statement?
A. The WBS is a great communication tool.
B. A well formed WBS provides a strong visualization of the product of
the project across its phases.
C. A well formed WBS is similar to a FBS allowing for task assignments.
D. The WBS allows for progressive elaboration using placeholder work
packages.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 28
Types of Questions
Questions With Invented Terms
Your boss wants to know what cost performance measures your
team must achieve to complete the project within the original
budget. Which of the following do you provide to her?
A. The Cost Performance Index
B. The To‐Complete Performance Index
C. The Remaining Budget Ratio
D. The Estimate For Completion
Types of Questions
Answers With More than One
Component
According to the PMBOK® Guide, how stringently must a project
manager ensure that all the defined process interactions occur?
A. Interactions within the planning process are dependent on the nature
of the project, and so there is a great deal of flexibility.
B. Interactions within the planning process are not dependent on the
nature of the project and are only depend on the PMBOK® Guide, so
there is not significant flexibility.
C. Interactions within the planning process group are not dependent on
the nature of the project but there is significant flexibility based on the
definitions in the PMBOK® Guide.
D. None of the above is true.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 559
Recurring Themes
PMI’isms
There is a basic assumption that you keep historical
records for all your projects.
You must understand the process of project
management (what to do first, second, etc.).
You must not only understand the topics, but also why
you should care about them.
Everything should be coordinated with the
stakeholders of a project and expectations managed.
Recurring Themes
PMI’isms
All roles and responsibilities must be clearly defined.
A project plan is not a Gantt chart.
A WBS is not an org chart but is a wonderful and key
element of successful project management.
Project managers are awesome and are very skilled.
PMI does not support gold plating (adding extra
functionality).
Expert judgment and bottoms up is preferred.
Environmental factors are influencing the project.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 32
The Exam – Why People Fail
Belief that they can pass the test from their
experience (not studying).
A lack of PM experience.
Failure to read the questions.
Failure to read all of the choices.
Not trusting their knowledge.
Nervousness.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 560
Organizations and
Project Management
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
Organizations
Differentiation vs. Integration
The need for specialized areas of
expertise (Production,
Marketing, Finance, etc.). The
level of differentiation
hinges on the needs of the
organization.
Organizations
Organic or Simple
Small, startup organizations.
Every member of the team has multiple roles
and responsibilities.
No one in the organization has a project
management title.
The project managed by the owner with no
administrative support.
Is the weakest organizational structure.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 36
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 561
Organizations
A Functional Organization
Project
Chief Executive Coordinator
Organizations
Potential Advantages of a Functional
Organization
Clear reporting relationships.
Highly specialized expertise.
Homogeneous groups.
Drive for technical excellence.
Clear career path.
Creates high quality organizational knowledge within
the functional area.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 38
Organizations
Potential Issues with a Functional
Organization
Conflicting priorities from overlapping projects.
Project boundaries limited to discipline.
Barrier to customer influence & satisfaction.
Employee development opportunities limited.
Project Manager is dependent on personal influence.
Hierarchical decision and communication processes.
Overwork technical issues vs. build to a standard.
Fosters part‐time roles.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 39
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 562
Organizations
A Projectized Organization (PBO)
Chief Executive
Or Program Mgr.
Organizations
Potential Advantages of a Projectized
Organization
Strong project manager role.
Full‐time administrative staff clear accountability.
Fosters collocation.
Improves focus.
Cost & performance tracking of projects.
Decision‐making based on overall project view.
Customer relationships tied to various projects
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 41
Organizations
Potential Issues with a Projectized
Organization
Reduction of employee’s professional identity.
Reduced focus on technical competence.
Leadership by the non‐technically skilled.
Focus on administrative work vs. technical work.
De‐valuing of functional managers.
Process vs. deliverable emphasis.
Creates redundancy of efforts.
Project end can be traumatic event.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 42
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 563
Organizations
The Matrix Organization
Are a blend of Functional and Projectized
organizations.
They are described as WEAK if they more
closely align to Functional Organizations.
They are described as STRONG if they more
closely align to Projectized Organizations.
Organizations
A Weak Matrix Organization
Chief Executive
Project
Coordinator Resources Assigned to a Given Project
Organizations
A Balanced Matrix Organization
Chief Executive
Resources Assigned to a Given Project
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 564
Organizations
A Strong Matrix Organization
Chief Executive
Resources Assigned to a Given Project
Organizations
Potential Advantages of a Matrix
Organization
Visibility to project objectives.
Improved control of resources by project managers.
Rapid response to contingencies.
Greater support from functional managers.
Coordination of efforts across organization.
Project end is not a traumatic event.
Strong technical base.
More effective dissemination of information.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 47
Organizations
Potential Issues with a Matrix
Organization
Project personnel report to more than one boss.
Complex to monitor and control.
Conflicts with resource allocation and project
priorities.
Potential for duplication of effort with
“independent” projects.
Power struggles and competition for scarce
resources.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 565
Organizations
Organizational Structures
Weak Balanced Strong
Matrix Matrix Matrix
The Basics of Project
Management
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
The Basics of PM
What is Project Management?
The management of a temporary endeavor
undertaken to create a unique product or service.
It requires the project team to deliver the agreed
upon service or product with the agreed upon
functionality on time and on budget with the agreed
upon level of quality.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 566
The Basics of PM
Projects Operations
Have unique charter & goals Usually has semi‐permanent
Might have unique charter
organization Semi‐permanent organization
Develops a unique product Maintains an existing set of
or service practices
Defined start & end dates Provides a standard product
Mostly heterogeneous or service (e.g. an assembly
teams line)
Are continuous
The Basics of PM
A program is a group of related projects
managed in a coordinated way to obtain
benefits and control.
A portfolio is a grouping of related and
unrelated projects and programs managed &
grouped for visibility and control purposes.
Organizational Project Management
Projects Programs Portfolios
Projects have defined objectives. Programs have a larger scope and Portfolios have an organizational scope
Scope Scope is progressively elaborated provide more significant benefits. that changes with the strategic
throughout the project lifecycle. objectives or the organization
Project managers expect change Program managers expect change Portfolio managers continuously
& implement processes to keep from both inside & outside the monitor changes in the broader internal
Change change managed & controlled. program & are prepared to manage to & external environment.
it.
Project managers progressively Program managers develop the Portfolio managers create & maintain
elaborate high‐level information overall program plan & create high‐ necessary processes & communication
Planning into detailed plans throughout the level plans to guide detailed planning relative to the aggregate portfolio.
project lifecycle. at the component level.
Project managers manage the Program managers manage the Portfolio managers may manage or
project team to meet the project program staff & the project managers; coordinate portfolio management staff,
Management objectives. they provide vision & overall or program and project staff that may
leadership. have reporting responsibilities into the
aggregate portfolio,
Success is measured by product & Success is measured by the degree to Success is measured in terms of the
project quality, timeliness, budget which the program satisfies the needs aggregate investment performance &
Success compliance, & degree of & benefits for which it was benefit realization of the portfolio.
customer satisfaction. undertaken.
Project managers monitor & Program managers monitor the Portfolio managers monitor strategic
control the work of producing the progress of program components to changes & aggregate resource
Monitoring products, services, or results that ensure the overall goals, schedules, allocation, performance results, & risk of
the project was undertaken to budget, & benefits of the program will the portfolio,
produce. be met.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 567
The Basics of PM
Key Terms
Project Management Office (PMO) —
Centralizes the management of projects.
Typical 3 structures:
Supportive – Providing a consultative role by
providing templates, best practices, training, access
to information, & lessons learned.
Controlling – Provide support & require
compliance.
Directive – Take control of the projects by directly
managing the projects.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 55
The Basics of PM
Key Terms
Management by Objectives (MBO) — Requires all
processes, initiatives and operations to be tracked
against specific, defined objectives. MBO only works
if management strongly supports it. MBO has three
basic steps:
– Establish unambiguous and realistic objectives.
– Regularly evaluate if the objectives are being met.
– Implement corrective action.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 56
The Basics of PM
Key Terms
Work Performance Data — The raw observations &
measurements identified during activities performed
to carry out project work: % work physically
completed, start & finish dates & technical measures.
Work Performance Information – The performance
data collected from controlling processes: status of
deliverables, status of change requests, forecasted
ETC.
Work Performance Reports – The physical or
electronic representation of work performance
information.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 57
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 568
The Basics of PM
Key Terms
Project Life Cycle — A series of phases that a
project passes through from its initiation to
its closure. It provides the basic framework
for managing the project.
Project Phases – Represent a collection of
logically related project activities that
culminate in the completion of one or more
deliverables.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 58
The Basics of PM
Key Terms – Life Cycles
Predictive — Also known as fully plan driven, are
ones where the scope, time & cost are
determined as early as possible – Waterfall.
Iterative & Incremental – Project phases
intentionally repeat one or more project activities
as the team’s understanding increases.
Adaptive – Change driven or agile are intended to
respond to high levels of change & stakeholder
involvement with fixed time & cost.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 59
The Basics of PM
Key Terms
Constraints — Represent factors that limit options of the
project manager and project team.
• Common constraints include time, budget, requirements,
resources and/or risks.
• Management’s responsibility to set the priority of each constraint.
• Project manager and project team’s responsibility to analyze the
impacts of changes against the project constraints.
Organizational Project Management Maturity Model
(OPM3) — Is PMI’s model to help organizations
determine their level of project management maturity.
Stakeholders & Stakeholder Management —
Stakeholders represent anyone with a vested interest in
the project. v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 60
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 569
The Basics of PM
It’s all about managing
Scope
six (6) things. It’s simple
really…
Risk Quality
Resources Schedule
Budget
The Basics of PM
Plan Do
Monitoring &
Controlling Processes
Planning Processes
Initiating Closing
Processes Processes
Executing Processes
Act Check
The Basics of PM
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 570
The Basics of PM
Project
Boundaries
Monitoring &
Controlling Processes Project End
Deliverables Users
Planning Processes
The Basics of PM
Linear
Well Known Risks,
Sequential,
Limited Scope Change
Waterfall / SDLC
CMM
DOD- STD-2167A
+MIL-STD-1521B
MIL-STD-498
The Basics of PM
The Big 3 Life Cycles
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 571
The Basics of PM
Keys to the Predictive Waterfall Model
The Waterfall Model offers the most number of
standard decision gates.
Examples include:
o Conceptual Design Review
o Requirements Review
o Preliminary Design Review
o Critical Design Review
The Basics of PM
The Basic Predictive Model
Analysis
Design
Development
Testing
Deployment
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 68
The Basics of PM
Keys to the Predictive Model
A waterfall model offers the easiest departmentalization and
managerial control.
A waterfall model forces the team to completely define all
requirements before proceeding to the next phase. This is
also its biggest disadvantage.
The waterfall model has strong emphasis on documentation
and the development of source code.
The waterfall model provides a very structured and
disciplined approach to development. This high degree of
structure may also be seen as a disadvantage by many.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018 2017 Looking Glass Development, LLC. 69
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 572
The Basics of PM
Keys Challenges to the Predictive Model
Real projects rarely follow the sequential flow of
the waterfall model.
At the beginning of a project requirements can
often be uncertain.
Developing in a waterfall model can be a long
process without yielding any results until the very
end.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018 2017 Looking Glass Development, LLC. 70
The Basics of PM
The Iterative Life Cycles
2.Evaluate 1. Determine
Alternatives Objectives
& Prototypes Requirements,
Alternatives, &
Constraints
The Basics of PM
Advantages of the Iterative Model
The spiral model is evolutionary.
The spiral model provides strong focus on project
risk.
Prototypes allow for rapid evaluation.
Can incorporate other models within iterations as
special cases.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 573
The Basics of PM
Challenges of the Iterative Model
Team must have strong risk assessment expertise.
Potentially less ability to control costs and schedule
overruns.
The Basics of PM
Prototyping
Prototyping assumes it is often difficult to
know all the requirements at the beginning of
the project.
Prototyping requires the developer to build a
simplified version of the proposed system and
present it to the customer as part of the
development process.
The prototype should never be deployed!
The Basics of PM
Reasons to Prototype
Prototypes can be used to complete
requirements analysis.
Prototypes can account for design
uncertainty.
Prototypes can allow experimentation
and comparison of multiple solutions.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 574
The Basics of PM
Dangers of Prototyping
False Expectations – “the system is now
complete”.
Increased Expense – must develop
prototype and production system.
Poorly Designed Systems – Prototyping
focuses on rapid development which
can lead to heavy layering and a failure
to make global considerations.
The Basics of PM
Managing WIP
Deliverable 1 In Option 1 the best
Option 1 A A resource for the
deliverable attempts
Option 2 A C A
to do each task for the
Deliverable 2 feature and nothing
Option 1 B B gets delivered.
Option 2 B B C
In Option 2 resourcing
Deliverable 3
is applied based upon
Option 1 C C availability and two
Option 2 features are delivered.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018 2017 Looking Glass Development, LLC. 77
The Basics of PM
Based on industrial process theory.
– Self‐organization
– Emergence
Defined process control vs. empirical process
control.
– Defined Processes ‐ Repeatable processes such as in
manufacturing. Leads to commoditization. In projects
often leads to rework.
– Empirical Processes ‐ Complex processes where it is
difficult to have consistent processes. Focuses on 3
keys.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 575
The Basics of PM
Foundation
Visibility – The aspects of the process that affect
the outcome must be visible to those controlling
the process & what is seen must be true.
Inspection – The various aspects of the process
must be examined frequently enough that
unacceptable variances in the process can be
detected.
Adaptation – If one or more of the processes are
determined out of control the processes change.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018 2017 Looking Glass Development, LLC. 79
The Basics of PM
The Scrum Roles
Product Owner – Responsible for representing
interests of all stakeholders, obtaining funding,
defining initial requirements, ROI, and objectives
(Product Backlog).
The Team – Develops the functionality. Is self‐
managing, self‐organizing, and cross functional.
Scrum Master – Responsible for the Scrum process,
teaching Scrum to everyone, implementing Scrum so
it fits with culture, and that everyone follows Scrum
rules & practices.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018 2017 Looking Glass Development, LLC. 80
The Basics of PM
Scrum
2 – 6 Week
Vision Sprints Daily Scrum
Every 24 Hours
Sprint Review
Not longer than 4 hours
Release Planning
for a 30 day sprint nor
more than 1 hour to plan.
Ranked Product
Backlog
Sprint end date &
deliverables do not
change
PO, SM & Team
conduct Sprint Sprint
Planning Meeting Tasks
Shippable Product
• 1/2 to complete Sprint
grooming. Backlog
• 1/
2 to define tasks &
task estimates in ½
or full days. No task
longer than 1 day.
Sprint Retrospective
Not more than 2 hours for
a 30 day sprint. Not more
Scrum = 3 Roles + 4 Artifacts + 5 Meetings than 1 hour to plan.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018 2017 Looking Glass Development, LLC. 81
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 576
The Basics of PM
A Project Vision
• Serves as a Charter or
Project Vision
• Required to begin any
project.
• Never longer than a single
page.
• Includes 5 key pieces of
information: Need,
justification, success
criteria, prioritization,
constraints & assumptions.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 82
Key Scrum Artifacts
Product Backlog
• A prioritized list of items to
be delivered.
• Each item is “relatively
independent” of the others.
• Backlog may be reprioritized
at any time.
• Items = User Stories or PBIs
• PBI = Product Backlog Item
The Basics of PM
PBI To Do In Progress Validate Impeded Done
5 3 2
PBI TaskTask
TaskTask
PBI Task
Task
Task
PBI Task
Task Task
Task
Task
PBI Task
Task
Technical
Debt
v. 10.0 - © Copyright and all rights reserved –
1/31/2018 2017 Looking Glass Development, LLC. 84
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 577
The Basics of PM
2000
Burndown Chart
1800
1600
Points/Work Remaining
1400
1200
1000
800
600
400
200
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
Time
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 85
The Basics of PM
Sprint Planning Meeting
PO speak to the sprint goal.
Acceptance criteria.
Team forecasts number of stories.
Team breaks PBIs into tasks.
Estimate tasks: 0.5 / 1.
Build sprint burndown and task board.
The Basics of PM
The Daily Scrum
10 to 15 minute meeting for team to answer 3
questions.
Stand up means STAND UP!
Target 10 minutes, 15 max.
Same time every day & don’t miss a day.
Stand in front of the visual progress artifact.
Everybody is present.
No typing during the meeting.
Concentrate on the 2nd and 3rd questions.
Don’t talk to the Scrum Master. Talk to the team.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018 2017 Looking Glass Development, LLC. 87
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 578
The Basics of PM
Sprint Review
Summary of sprint by PO.
PO demonstrates every acceptance criteria of
every story delivered.
Gather feedback from stakeholders and
incorporate into product backlog.
Update release plan and discuss next step.
The Basics of PM
Sprint Retrospective
The most important Scrum meeting.
Important to change something in every
sprint.
Remember: “It’s not a lesson learned until you
do something about.”
Work on only the 2 most important lessons.
The Basics of PM
Day 1 Day 2 ‐ X Last Day
Daily Scrum
Plan Retro & Review
Sprint Work & Backlog Sprint Review &
AM Planning Grooming Sprint Retrospective
1. Free Time
Work & Backlog 2. Google 20% Time
PM Work Grooming 3. Personal Time
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 579
The Basics of PM
PMBOK® Guide Knowledge Areas
Knowledge Areas describe project management
knowledge and practice in terms of their component
processes.
Integration Management Resource Management
Scope Management Communications Management
Schedule Management Risk Management
Cost Management Procurement Management
Quality Management Stakeholder Management
The Basics of PM
Ten Knowledge Areas Extended
4 Integration Management 6.1 Plan Schedule Management
5 Scope Management 6.2 Define Activities
6.3 Sequence Activities
6 Schedule Management
6.4 Estimate Activity Durations
7 Cost Management 6.5 Develop Schedule
8 Quality Management 6.6 Control Schedule
9 Resources Management
10 Communications Management
11 Risk Management
12 Procurement Management
13 Stakeholder Management
The Basics of PM
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 580
The Basics of PM
Ten Knowledge Areas Extended
4 Integration Management 6.1 Plan Schedule Management
5 Scope Management 6.2 Define Activities
6.3 Sequence Activities
6 Schedule Management
6.4 Estimate Activity Durations
7 Cost Management 6.5 Develop Schedule
8 Quality Management 6.6 Control Schedule
9 Resources Management 6.3.1 Inputs
6.3.2 Tools & Techniques
10 Communications Management 6.3.2.1 Precedence diagramming
11 Risk Management method (PDM)
6.3.2.2 Dependency determination
12 Procurement Management and integration
The Basics of PM
The Process Groups &
Knowledge Areas Combined
Project Integration Management
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 581
Integration Management
Initiating Process Group
The processes and activities needed to
identify, define, combine, unify and 4. Project Integration
Management
coordinate the various processes and project 4.1
Develop Project
Charter
management activities within the Project
Management Process Groups. Planning Process Group
4. Project Integration
Management
4.2
Develop Project
Management
Plan
Closing Process Group 4. Project Integration Monitoring & Controlling Process Group
Management
4.3
4. Project Integration
Direct 4. Project Integration
Management & Manage Management
Project Work
4.7 4.5 4.6
Close Project 4.4 Monitor & Perform
Or Phase Manage Control Project Integrated
Project Work Change Control
Knowledge
Integration Management
4.1 Develop Project Charter
Names the project manager & sponsor.
Explains how the project supports the organizational
strategy.
Explains the business need & why the need exists.
Defines any constraints and assumptions that exist (this
includes any deadlines, budget limitations, resource
limitations, any known risks, and scope must haves).
Defines the project success criteria (it is always
recommended that success criteria be quantitative in
nature as subjective success criteria usually leads to
failure. Initiating Process Group
4. Project Integration
Management
4.1
Develop Project
Charter
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 98
Integration Management
4.1 Develop Project Charter
Inputs Tools & Techniques Outputs
.1 Business documents .1 Expert judgment .1 Project charter
.2 Agreements .2 Data gathering .2 Assumption log
.3 Enterprise environmental factors .3 Interpersonal and team
.4 Organizational process assets skills
.4 Meetings
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 582
Integration Management
The Business Case
Benefit Measurement Methods – subjective measures.
Constrained Optimization Methods – linear, integer,
dynamic or multi‐objective programming.
Economic Models
– Payback Period
– Future Value
– Present Value
– Net Present Value (NPV)
– Internal Rate of Return (IRR)
– Benefit / Cost ratio (BCR or BCI)
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 100
Integration Management
The Business Case
Discounting or Present Value – Value today of funds
available in the future.
PV = FV / (1 + i)n
– If you want $1,000 in three (3) years how much do you
have to invest today at 8% to receive your $1,000?
– End of Yr. 1 = $1,000 / (1 + 8%) = $925.93
– End of Yr. 2 = $925.93 / (1 + 8%) = $857.34
– End of Yr. 3 = $857.34 / (1 + 8%) = $793.83
Integration Management
The Business Case
Net Present Value – Present Value minus
present cost.
Internal Rate of Return ‐ Average rate of return
earned over the life of the project. It is where
discounted cash flow – up front cost = 0.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 583
Integration Management
4.2 Develop Project Management Plan
The Project Management Plan is a key project
document that is a collection of the outputs of the
planning processes of the Planning Process Group.
Describes which project management processes will
be used.
Describes how the project is executed, monitored and
controlled, and closed. Planning Process Group
4. Project Integration
Management
Updated throughout the project. 4.2
Develop Project
Management
Plan
Integration Management
4.2 Develop Project Management Plan
Inputs Tools & Techniques Outputs
.1 Project charter .1 Expert judgment .1 Project management
.2 Outputs from planning .2 Data gathering plan
processes .3 Interpersonal and
.3 Enterprise environmental team skills
factors .4 Meetings
.4 Organizational process
assets
Integration Management
Project Management Plan Project Documents
1. Scope management plan 1. Activity attributes 19. Quality control measurements
2. Requirements management plan 2. Activity list 20. Quality metrics
3. Schedule management plan 3. Assumption log 21. Quality report
4. Cost management plan 4. Basis of estimates 22. Requirements documentation
5. Quality management plan 5. Change log 23. Requirements traceability matrix
6. Resource management plan 6. Cost estimates 24. Resource breakdown structure
7. Communications management plan 7. Cost forecasts 25. Resource calendars
8. Risk management plan 8. Duration estimates 26. Resource requirements
9. Procurement management plan 9. Issue log 27. Risk register
10. Stakeholder engagement plan 10. Lessons learned register 28. Risk report
11. Change management plan 11. Milestone list 29. Schedule data
12. Configuration management plan 12. Physical resource assignments 30. Schedule forecasts
13. Scope baseline 13. Project calendars 31. Stakeholder register
14. Schedule baseline 14. Project communications 32. Team charter
15. Cost baseline 15. Project schedule 33. Test & evaluation documents
16. Performance measurement baseline 16. Project schedule network diagram
17. Project life cycle description 17. Project scope statement
18. Development approach 18. Project team assignments
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 105
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 584
Integration Management
Baselines, Logs & Registers
Scope baseline — The scope baseline includes the scope
statement, work breakdown structure (WBS), and WBS
dictionary.
Milestone list — The milestone list is a listing of the major,
defined milestones for the project.
Resource calendars — A good project manager knows when their
resources will be available to complete project work and does
not assume they will simply be there when the schedule says
they will.
Schedule baseline — The schedule baseline represents a
snapshot or picture of the schedule as promised to the sponsor.
It is critical that the project manager is always comparing the
actual delivered results to the scheduled results found in the
schedule baseline.
Cost baseline — The cost baseline is the same as the Schedule
Baseline, except it is focused on the project budget instead of
the schedule.
Risk register — The risk register is a critical document for project
success. The Risk Register documents all the known potential
risks, their triggers, categories, owners, and the response
strategies. The risk register is discussed extensively in the risk
management knowledge area.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 106
Integration Management
Integration Management
4.3 Direct & Manage Project Work
Project Manager, with project team, directs
performance and manages interfaces with the
rest of the organization
4. Project Integration
Management
4.3
Direct
& Manage
Project Work
4.4
Manage
Project
Knowledge
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 585
Integration Management
4.3 Direct & Manage Project Work
Inputs Tools & Techniques Outputs
.1 Project management .1 Expert judgment .1 Deliverables
plan .2 Project management .2 Work performance
.2 Project documents information system data
.3 Approved change .3 Meetings .3 Issue log
requests .4 Change requests
.4 Enterprise .5 Project management
environmental plan updates
factors .6 Project document
.5 Organizational updates
process assets .7 Organizational
process assets
updates
Integration Management
4.4 Manage Project Knowledge
This is the process where the team uses existing
knowledge and also creates new to achieve the
project’s objectives and contribute to organizational
learning.
There are two types of knowledge used in this
process:
Explicit – Knowledge that can be readily codified using
words, pictures, or numbers.
Tacit – Knowledge that is personal and often difficult to
express such as beliefs, insights, experience and know‐how.
Executing Process Group
they know. Direct
& Manage
Project Work
4.4
Manage
Project
Knowledge
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 110
Integration Management
4.4 Manage Project Knowledge
Inputs Tools & Techniques Outputs
.1 Project management plan .1 Expert judgment .1 Lessons learned
.2 Project documents .2 Knowledge register
.3 Deliverables management .2 Project management
.4 Enterprise environmental .3 Information plan updates
factors management .3 Organizational
.4 Interpersonal & process assets
.5 Organizational process
team skills updates
assets
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 586
Integration Management
4.5 Monitor & Control Project Work
Monitoring processes – collect, measure, disseminate,
assess.
Control via corrective actions.
Compare actual work to plans/baselines.
Analyze, track, forecast.
Monitor implemented changes.
Monitoring & Controlling Process Group
4. Project Integration
Management
4.5 4.6
Monitor & Perform
Control Project Integrated
Work Change Control
Integration Management
4.5 Monitor & Control Project Work
Inputs Tools & Techniques Outputs
.1 Project management plan .1 Expert judgment .1 Work performance
.2 Project documents .2 Data analysis reports
.3 Work performance information .3 Decision making .2 Change requests
.4 Agreements .4 Meetings .3 Project management
plan updates
.5 Enterprise environmental factors
.4 Project document
.6 Organizational process assets updates
Integration Management
4.6 Perform Integrated Change Control
Performed from the very beginning to the very end.
Identify that a change has occurred.
Influence factors that circumvent the integrated change
control process.
Review, approve (or reject), monitor change requests.
Maintain integrity of the baselines.
Review and approve all recommended corrective and
preventive actions. Monitoring & Controlling Process Group
Assess impact of proposed
4. Project Integration
Management
4.5 4.6
Monitor & Perform
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 587
Integration Management
4.6 Perform Integrated Change Control
Inputs Tools & Techniques Outputs
.1 Project management plan .1 Expert judgment .1 Approved change
.2 Project documents .2 Change control tools requests
.3 Work performance reports .3 Data analysis .2 Project management
.4 Decision making plan updates
.4 Change requests
.5 Meetings .3 Project documents
.5 Enterprise environmental factors
updates
.6 Organizational process assets
Integration Management
4.7 Close Project or Phase
All the activities necessary to finalize project
activities
Close a phase or the whole project – verify
project deliverables and coordinate
acceptance Closing Process Group
4. Project Integration
Management
4.7
Close Project
Or Phase
Integration Management
4.7 Close Project or Phase
Inputs Tools & Techniques Outputs
.1 Project charter .1 Expert Judgment .1 Project documents
.2 Project management .2 Data analysis updates
plan .3 Meetings .2 Final product,
.3 Project documents service or result
transition
.4 Accepted deliverables
.3 Final report
.5 Business documents
.4 Organizational
.6 Agreements
process assets
.7 Procurement updates
documentation
.8 Organizational process
assets
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 588
Integration Management
Summary
Seven (7) processes.
Role and components of the charter.
Charter issued by party external to the project.
Project management plan is collection of other plans –
level of detail depends on the project.
Change control throughout the project.
Closure = deliverables AND project records.
Environmental factors are at play.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 118
Project Scope Management
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
Scope Management
Scope management is the process of defining what Planning Process Group
work is required and then making sure all of that 5. Project Scope
Management
5.1
work and only that work is done. (PMBOK Guide p.129) Plan Scope
Management
No project is ever conducted without a plan. 5.2
Collect
Requirements
A WBS must be created for all projects.
5.3
Involve all the project stakeholders in requirements Define
Scope
You must obtain approval of the project scope 5.4
Create
WBS
before execution begins.
Do not ever gold plate the project. Monitoring and Controlling Process Group
Scope changes allowed so long as they
5. Project Scope
Management
5.5
Validate
follow the agreed upon change Scope
management process. 5.6
Control
Scope
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 589
Scope Management
The Product vs. Project Scope:
Project Scope –The work that must be
performed to deliver a product, service or
result with the specified features and
functions. PMBOK Guide 2012 p. 555
Product Scope – The features and functions
that characterize a product service or result.
PMBOK Guide 2012 p. 552
Scope Management
The Scope Management Plan Answers…
How will you determine the product scope for the
project? This includes the specific requirements of the
product, service, or result.
How will you balance the needs of all your stakeholders?
What tools and techniques will the project team
specifically use?
Are there enterprise environmental factors and
organizational process assets that must be accounted for
or used?
What will the scope change management process be?
How will you measure scope performance and adjust to
variances as needed?
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 122
Scope Management
The Steps in Scope Management
Determine the product, service, or result
requirements. Make sure all the requirements tie back
to the business need described in the charter.
Balance the needs of the various stakeholders to
determine the correct requirements.
Develop a Work Breakdown Structure according to
PMI® standards that is focused on being deliverable.
Verify that the scope that has been specified is being
accomplished according to the plan.
Measure the project scope performance and adjust it
according to the Scope Change Management Plan.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 123
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 590
Scope Management
How Scope is Measured
Project scope is measured against the project
management plan. Did the team finish the
work they said they would do.
Product scope is measured against the project
requirements.
Scope Management
5.1 Plan Scope Management
Process of creating a scope management plan
that documents how the project scope will be
Planning Process Group
defined, validated & controlled.
5. Project Scope
Management
It tells everyone how scope will be
5.1
Plan Scope
Management
managed throughout the project. 5.2
Collect
Requirements
5.3
Define
Scope
5.4
Create
WBS
Scope Management
5.1 Plan Scope Management
Inputs Tools & Techniques Outputs
.1 Project charter .1 Expert judgment .1 Scope management
.2 Project management plan .2 Data analysis plan
.3 Enterprise environmental .3 Meetings .2 Requirements
factors management plan
.4 Organizational process
assets
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 591
Scope Management
5.2 Collect Requirements
Process of defining and documenting
stakeholders’ need to meet the project
Planning Process Group
objectives.
5. Project Scope
Management
5.1
Plan Scope
Management
This process is directly tied to 5.2
Collect
Requirements
managing expectations.
5.3
Define
Scope
5.4
Create
WBS
Scope Management
5.2 Collect Requirements
Inputs Tools & Techniques Outputs
.1 Project charter .1 Expert judgment .1 Requirements
.2 Project management .2 Data gathering documentation
plan .3 Data analysis .2 Requirements
.3 Project documents traceability matrix
.4 Decision making
.4 Business documents .5 Data representation
.5 Agreements .6 Interpersonal and
.6 Enterprise team skills
environmental factors .7 Context diagram
.7 Organizational process .8 Prototypes
assets
Scope Management
Requirements Data Gathering
Brainstorming
Interviews
Focus groups
Questionnaires and surveys
Benchmarking
Nominal group techniques
The Delphi technique
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 129
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 592
Scope Management
Voting
Voting — This is exactly what it sounds like. Decisions are made
based upon the opinions of a group. There are a number of
ways this can be done:
Unanimity — This is where everyone agrees on a course of
action.
Majority — This is a process where the majority of members
in the group decide direction. Anything over 50% wins.
Plurality — This is used when a simple majority is not
possible. In these cases, whichever group has the largest
number wins—even though it is not a majority.
Autocratic decision making— This is a fancy way of dictatorship.
In this method, one person makes the decision for the group.
Multicriteria decision analysis — Establishes a basic framework
for making a decision when the team is looking at aspects in
conflict with each other. A common example is the relationship
between cost and quality.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 130
Scope Management
Idea Mapping Guidelines
Idea maps use the way the brain processes information
associatively. They are single‐page diagrams that visually
captures ideas in a non‐linear format.
Characteristics of a Mind Map:
1. The main idea, is crystallized in a central image.
2. The main themes radiate from the central image as 'branches’.
3. Each branch comprises a key image or word drawn or printed
on its associated line.
4. Topics of lesser importance are represented as 'twigs' of the
relevant branch.
5. The branches form a connected nodal structure.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 131
Scope Management
Brainstorming Steps
1. A question or problem is posed to the group and
each member silently generates and writes down
their ideas.
2. The moderator writes down the ideas on a flip chart
until all the ideas are recorded.
3. Each recorded idea is discussed until all group
members have a clear understanding.
4. Individual vote privately to prioritize the ideas,
using a scale of 1 to 5, with 1 being the lowest and 5
being the highest. After each vote the ballots are
counted and the team revote until the highest
option is selected.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 132
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 593
Scope Management
5.3 Define Scope
Taking the detailed requirements defined in the
collect requirements process and developing a
detailed description of the product or service
Planning Process Group
that will meet those needs.
5. Project Scope
Management
5.1
Plan Scope
Management
5.2
Collect
Requirements
5.3
Define
Scope
5.4
Create
WBS
Scope Management
5.3 Define Scope
Inputs Tools & Techniques Outputs
.1 Project charter .1 Expert judgment .1 Project scope
.2 Project management .2 Data analysis statement
plan .3 Decision making .2 Project documents
.3 Project documents .4 Interpersonal and updates
.4 Enterprise environmental team skills
factors .5 Product analysis
.5 Organizational process
assets
Scope Management
Charter vs. Scope Statement
Project Charter Project Scope Statement
Project scope description (progressively
Project purpose elaborated)
Measurable project objectives and related success criteria Project deliverables
High‐level requirements Acceptance criteria
High‐level project description, boundaries, and key
deliverables Project exclusions
Overall project risk
Summary milestone schedule
Preapproved financial resources
Key stakeholder list
Project approval requirements (i.e., what constitutes success,
who decides the project is successful, who signs off on the
project)
Project exit criteria (i.e., what are the conditions to be met in
order to close or to cancel the project or phase).
Assigned project manager, responsibility, and authority level.
Name and authority of the sponsor or other person(s)
authorizing the project charter
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 135
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 594
Scope Management
5.4 Create WBS
A WBS is a deliverable‐oriented, hierarchical
decomposition of the work to be executed by the
project team. It enables them to accomplish the
Planning Process Group
project objectives and create the required
5. Project Scope
product, service, or result. Management
5.1
Plan Scope
Management
5.2
Collect
Requirements
5.3
Define
Scope
5.4
Create
WBS
Scope Management
WBS Terminology
Work Packages
Decomposition
Progressive elaboration
Placeholder work packages
Control account
Scope Management
Components of the WBS
The WBS Structure – resembles an organization
chart or decision tree.
The WBS Dictionary – A brief synopsis of the
project and each major component or work
package.
The Code of Accounts – The numbering system
used to reference and roll‐up the WBS.
– The highest level is 1
– The next level is 1.x
– The next level is 1.x.x and so on
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 138
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 595
Effective WBS’s
Basement
Finish
Project
Design Drywall
& HVAC Plumbing Electrical Framing &
Inspections Finish
Rough
Design Inspections Trunk Line Drywall
Electrical
Rough
Rough Design Branch Lines Outlets Mud & Tape
Electrical
Box
Rough Frame Paint
Connections
Final Carpet
Scope Management
5.4 Create WBS
Inputs Tools & Techniques Outputs
.1 Project management .1 Expert judgment .1 Scope baseline
plan .2 Decomposition .4 Project document
.2 Project documents updates
.3 Enterprise environmental
factors
.4 Organizational process
assets
Scope Management
5.5 Validate Scope
Formalizing acceptance of deliverables.
Review deliverables with stakeholders.
Is binary in nature.
Often in parallel with quality control.
Monitoring and Controlling Process Group
5. Project Scope
Management
5.5
Validate
Scope
5.6
Control
Scope
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 596
Scope Management
5.5 Validate Scope
Inputs Tools & Techniques Outputs
.1 Project management plan .1 Inspection .1 Accepted deliverables
.2 Project documents .2 Decision making .2 Work performance
.3 Verified deliverables information
.4 Work performance data .3 Change requests
.4 Project document
updates
Scope Management
5.6 Control Scope
Influence the factors that create project
scope changes.
Control the impact of those changes.
Ensure use of Integrated Change Control.
Manage changes. Monitoring and Controlling Process Group
5. Project Scope
Scope creep.
Management
5.5
Validate
Scope
5.6
Control
Scope
Scope Management
5.6 Control Scope
Inputs Tools & Techniques Outputs
.1 Project management .1 Data analysis .1 Work performance
plan information
.2 Project documents .2 Change requests
.3 Work performance .3 Project management
data plan updates
.4 Organizational .4 Project document
process assets updates
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 597
Scope Management
Project Scope Management ‐
Summary
Six (6) processes.
Project and product scope.
Scope is revised throughout project.
WBS – know its importance and that it is
used in many other processes; and it is
deliverables based.
Schedule Management
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
Schedule Management
All the processes required to ensure timely
completion of the project.
The major output of these processes is the
project schedule.
Planning Process Group
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 598
Schedule Management
6.1 Plan Schedule Management
Defines the “rules” for developing &
managing the schedule.
The benefit of this process is that it
provides guidance & direction
Planning Process Group
on how the schedule will be
managed.
Schedule Management
6.1 Plan Schedule Management
Inputs Tools & Techniques Outputs
.1 Project charter .1 Expert judgment .1 Schedule Management
.2 Project management .2 Data analysis plan
plan .3 Meetings
.3 Enterprise environmental
factors
.4 Organizational process
assets
Schedule Management
6.2 Define Activities
Creating a “list” of all the work that needs to be
done to produce the project deliverables.
Work packages are decomposed into
schedule activities.
These schedule activities provide a Planning Process Group
basis for estimating, scheduling,
executing, and monitoring and
controlling.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 599
Schedule Management
Rolling Wave Planning
Project Analyze Define New Purchase Construct & Test &
Less
Initiation Existing System And Install Test System Implement
Details Components System
Situation Requirements Package
Planning
Details
More
Details
Project Time
Start
Schedule Management
6.2 Define Activities
Inputs Tools & Techniques Outputs
.1 Project management .1 Expert judgment .1 Activity list
plan .2 Decomposition .2 Activity attributes
.2 Enterprise .3 Rolling wave planning .3 Milestone list
environmental factors .4 Meetings .4 Change requests
.3 Organizational process .5 Project management
assets plan updates
Schedule Management
6.3 Sequence Activities
Ordering the activities that have been defined
and assigning logical dependencies.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 600
Schedule Management
6.3 Sequence Activities
Inputs Tools & Techniques Outputs
.1 Project management .1 Precedence .1 Project schedule
plan diagramming network diagrams
.2 Project documents method (PDM) .2 Project document
.3 Enterprise .2 Dependency updates
environmental factors determination and
.4 Organizational process integration
assets .3 Leads and lags
.4 Project management
information system
Schedule Management
PDM
Finish to Start
Start to Start
Finish to Finish
Start to Finish F-S
S – F is not common
A B D
F H
S-S
C E
G F-F
Schedule Management
Conditional Diagramming
GERT is most common.
Allows for probability.
Allows for looping.
80%
A B C
20%
Eyeball Diagram
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 601
Schedule Management
Dependencies
Mandatory (hard logic) — Mandatory dependencies
are defined as situations where the ordering of task,
activities or deliverables is locked into place by the
work itself and there is no other alternative path.
Discretionary (soft logic) — Discretionary
dependencies are situations where there is more than
one possible path to complete the project work, but
someone has chosen a specific path for some reason.
External — External dependencies refer to situations
where dependencies are placed on the project team
by some outside force, regardless of logic or
preference. Regulations and laws are the most
common form of external dependencies.
Dependency Determination
Mandatory Mandatory
External Internal
Dependency Dependency
Discretionary Discretionary
External Internal
Dependency Dependency
Schedule Management
Leads & Lag
Lead time occurs whenever a finish‐to‐start
relationship allows the successor task to start
prior to the completion of the predecessor.
Lag time represents a relationship that requires a
delay between the two tasks.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 602
Schedule Management
Leads & Lag
Schedule Management
6.4 Estimate Activity Durations
Compilation (not the sum) of activity duration
estimates results in the project duration.
All supporting data is documented.
Uses identified risks and cost estimates.
Accuracy improves over time. Planning Process Group
Ranges, e.g. 280 days ‐5% to +10%.
Schedule Management
6.4 Estimate Activity Duration
Inputs Tools & Techniques Outputs
.1 Project management plan .1 Expert judgment .1 Duration estimates
.2 Project documents .2 Analogous estimating .2 Basis of estimates
.3 Enterprise environmental .3 Parametric estimating .3 Project document
factors .4 Three point estimating updates
.4 Organizational process .5 Bottom-up estimating
assets .6 Data analysis
.7 Decision making
.8 meetings
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 603
Schedule Management
Project Evaluation & Review Technique
(PERT)
Schedule Management
Project Evaluation & Review Technique
(PERT)
4X
Most
PERT
Optimistic + Likely + Pessimistic
Weighted =
6
Average
PERT
Pessimistic ‐ Optimistic
Standard =
6
Deviation
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 164
Schedule Management
Distributions
A binomial distribution is used whenever there are only two
possible outcomes.
A uniform distribution represents a scenario where each
value of a random variable has an equal probability of
occurrence.
A triangular distribution is a continuous probability
distribution that begins with a minimum value, ends with a
maximum value, and makes use of a mode, or most likely
value somewhere along the continuum.
A beta distribution represents a distribution of probabilities
when we don’t know what the probability is.
The central limit theorem (CLT) states that the mean of a
large population of independent and random variables, each
having a finite mean and variance will be normally
distributed.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 604
Schedule Management
Reserves
Contingency Reserves — These represent reserves
controlled by the project manager and they are to
be used for know unknowns. This means the
project manager and team can plan for an event
that they see as possible.
Management Reserves — These represent reserves
controlled by the project sponsor or the senior
management. They cannot be accessed without
their permission. Management reserves are used
to respond to unknown unknowns. These are
events that cannot be planned for.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 166
Schedule Management
Agile Estimation
• Ideal Time ‐ Assumes resources 100% dedicated
• Relative Sizing – Often called T‐Shirt sizing.
• Story Points – Aggregates complexity & time.
• Fibonacci Sequence – Another comparison
technique.
• Affinity Estimating – Process of grouping
requirements into categories or collections. Used
to group similarly sized user stories together.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 167
Schedule Management
6.5 Develop Schedule
Iterative.
Determines planned start and end dates for
activities and the whole project.
Baseline for measuring progress. Planning Process Group
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 605
Schedule Management
CPM
The Critical Path is the project path which will
be the longest duration or where all activities
have zero float.
The Critical Path does not necessarily have the
greatest risk.
The Critical Path determines the earliest
completion of the project.
Schedule Management
ES DUR EF
CPM Deliverable
ES ‐ Early Start is the earliest the task can begin. LS Float LF
Dur – Duration is the amount of calendar time the task will take.
EF ‐ The Early Finish is the earliest the task can end.
LS – The Late Start is the latest the task can begin.
LF – The Late Finish is the latest the task can end.
Float ‐ The Slack, slip or float is amount of time the task can delay
without impacting the project end date. Also called Total Float.
Near Critical Path – A network path close in length to the critical path.
Free Float – The amount of time a task can delay without delaying the
early start date
Project Float – The amount of time the project can be delayed without
impacting an externally imposed completion date.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 170
Schedule Management
The Critical Path Method
EF = ES + DUR = Forward Pass ES DUR EF
Deliverable
LS = LF – DUR = Backward Pass
LS Float LF
Float = LF – EF or LS – ES
2 2 4
Deliverable C
6 4 8
2 3 5 8 2 10
Deliverable D Deliverable F
5 3 8 8 0 10
0 2 2 2 4 6 6 2 8
Deliverable A Deliverable B Deliverable E
0 0 2 2 0 6 6 0 8
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 171
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 606
Schedule Management
Resource Optimization
After CPM.
Redistribute resource assignments where a
resource is needed on more than one task in
the same time period.
Can change the critical path.
Schedule Management
Critical Chain Method
Critical Chain = Longest chain of dependent tasks with zero
PDM/CPM
slack taking into consideration resource constraints.
10 15 10
Progress equal burn rate of the buffers vs. work complete.
15 30 10 20
Measurement is done against the Project Buffer.
30 10
OR 10 BL 15 PR 10 FB 10
Using CPM would take an estimated 75 units. Which is then
missed by 100%.
CCPM allows for more accurate estimates with smaller misses.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 173
Schedule Management
A Sample Story Map
The Story Story Story Story Story Story Story Story Story
Backbone Story Story Story Story Story
Sequence
Walking Story Story Story Story Story Story Story Story Story
Skeleton
Story Story Story Story Story
Less
Optional Story Story Story Story Story Story Story Story
Optionality
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 607
Schedule Management
6.5 Develop Schedule
Inputs Tools & Techniques Outputs
.1 Project management plan .1 Schedule network .1 Schedule baseline
.2 Project documents analysis .2 Project schedule
.3 Agreements .2 Critical path method .3 Schedule data
.4 Enterprise environmental .3 Resource optimization .4 Project calendars
factors .4 Data analysis .5 Change requests
.5 Organizational process .5 Leads and lags .6 Project management
assets .6 Schedule compression plan updates
.7 Project management .7 Project document
information system updates
.8 Agile release planning
Schedule Management
Leveling vs. Smoothing
Resource leveling involves adjusting the start
and finish dates of tasks to prevent resources
from becoming over allocated.
Resource smoothing adjust the project activities
so they do not exceed predefined resource
limits. This is different from leveling in that
smoothing does not allow the project’s critical
path to change and the project’s completion
date cannot be delayed.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 176
Schedule Management
Leveling vs. Smoothing
Similarities
Resource Leveling Resource Smoothing
A schedule network analysis A schedule network analysis
technique. technique.
A resource optimization A resource optimization
technique. technique.
Improves resource utilization. Improves resource utilization.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 608
Schedule Management
Leveling vs. Smoothing
Differences
Resource Leveling Resource Smoothing
Aim is to adjust start and end dates of a project Aim is to achieve optimal resource usage by
with resource constraints while balancing avoiding peaks and valleys in the resource
resource requirements and resource availability usage profile. Hence the name smoothing.
Used in resource‐constrained scheduling. Used in time‐constrained scheduling.
Critical path of the project will be affected, and Critical path of the project won't change.
usually the length of critical path will increase.
Can be applied to resources on critical path. Doesn't apply to resources on critical path.
Free and total float (or slack) may be used. Free and total float (or slack) are used.
Will optimize all the resources and may change May not be able to optimize all the resources if
the duration of the project. sufficient slack (or float) isn't available, but
does not change the duration of the project.
Risk: May change the critical path and hence the Risk: Loss of flexibility due to reduction in
duration. slack. Hence chances of increase in number of
near‐critical activities.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 178
Schedule Management
Other Terms
One‐Point Estimate – A single value estimate.
Regression Analysis – A graphic analysis to track if two
variables are related.
Heuristic – A rule of thumb.
Learning Curve – The improvement achieved by doing
an activity more than once.
Monte Carlo Simulation – A computer model which
allows the analyst to simulate an activity 1,000 or more
times to achieve a probability of a result.
v. 10.0 ‐ © Copyright and all rights reserved – 2017
Looking Glass Development, LLC. 1/31/2018 179
Schedule Management
Crashing vs. Fast Tracking
Fast Tracking — Fast Tracking is doing dependent
items in parallel. It amounts to changing a finish‐
to‐start relationship to a start‐to‐start or a finish‐
to‐finish relationship. For the exam it is important
that you remember that the negative impact of
Fast Tracking is the potential for rework.
Crashing — Crashing is increasing the number of
hours worked. This can be done by adding
resources assigned to a task, activity or deliverable
or by simply working overtime. The negative
impact of Crashing that must be remembered is a
likely increase in costs.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 180
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 609
Schedule Management
Gantt Charts
Schedule Management
Milestone Chart
Schedule Management
6.6 Control Schedule
Part of Integrated Change Control.
Determine the current status of the project
schedule.
Influence the factors that create schedule changes.
Determine that the project schedule has changed.
Manage the changes as they occur.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 610
Schedule Management
6.6 Control Schedule
Inputs Tools & Techniques Outputs
.1 Project management .1 Data analysis .1 Work performance
plan .2 Critical path method information
.2 Project documents .3 Project management .2 Schedule forecasts
.3 Work performance data information system .3 Change requests
.4 Organizational process .4 Resource optimization .4 Project management
assets .5 Leads and lags plan updates
.6 Schedule compression .5 Project documents
updates
Schedule Management
Schedule Management – Summary
Six (6) processes.
PERT, GERT, PDM, CPM, CCPM.
Crashing, fast tracking.
Decomposition, baseline, float or slack.
Schedule development is iterative.
Project Cost Management
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 611
Cost Management
All the process involved in planning, estimating,
budgeting, and controlling costs so that the
project can be completed within the approved
budget. Planning Process Group
7. Project Cost
Management
7.1
Plan Cost
Management
7.4 7.3
Control Determine
Costs Budget
Cost Management
Primarily concerned with cost of resources.
Also concerned with
– Life‐cycle costing
– Opportunity cost
– Sunk costs
The Cost Management Plan is part of
overall project management plan.
– Control thresholds
– Earned value rules
– Reporting formats
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 188
Cost Management
7.1 Plan Cost Management
Defining the rules which are used to manage
project costs.
It defines how the team will Planning Process Group
7.1
Plan Cost
Management
7.2
Estimate
Costs
7.3
Determine
Budget
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 612
Cost Management
7.1 Plan Cost Management
Inputs Tools & Techniques Outputs
.1 Project charter .1 Expert judgment .1 Cost management
.2 Project management .2 Data analysis plan
plan .3 Meetings
.3 Enterprise
environmental factors
.4 Organizational process
assets
Cost Management
7.2 Estimate Costs
Developing an approximation of the costs of
the resources needed to complete each
schedule activity Planning Process Group
7. Project Cost
Management
7.2
Estimate
Costs
7.3
Determine
Budget
Cost Management
7.2 Estimate Costs
Inputs Tools & Techniques Outputs
.1 Project management .1 Expert judgment .1 Cost estimates
plan .2 Analogous estimating .2 Basis of estimates
.2 Project documents .3 Parametric estimating .3 Project documents
.3 Enterprise .4 Bottom-up estimating updates
environmental factors .5 Three-point
.4 Organizational process estimating
assets .6 Data analysis
.7 Project management
information system
.8 Decision making
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 613
Cost Management
Accuracy of estimates increases as the
project progresses
Rough Order of Magnitude
‐25% to +75%
Budget Estimate or the Budget
‐5% to +10%
Cost Management
7.3 Determine Budget
Aggregating the cost estimates of
individual activities or work packages to
establish a total Cost Baseline. Planning Process Group
7. Project Cost
Management
7.1
Plan Cost
Management
7.2
Estimate
Costs
7.3
Determine
Budget
Cost Management
Accounting Terms
Variable Costs – Costs that change as the units produced
changes.
Fixed Costs – Costs that do not change with changes to
volume produced.
Direct Costs – Costs that are directly attributed to
project work.
Indirect Costs – Items that benefit more than one
project and are not attributed to a specific activity.
Value Analysis or Engineering – Finding less costly ways
to do the same work.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 195
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 614
Cost Management
7.3 Determine Budget
Inputs Tools & Techniques Outputs
.1 Project management .1 Expert judgment .1 Cost baseline
plan .2 Cost aggregation .2 Project funding
.2 Project documents .3 Data analysis requirements
.3 Business documents .4 Historical information .3 Project documents
.4 Agreements review updates
.5 Enterprise .5 Funding limit
environmental factors reconciliation
.6 Organizational process .6 Financing
assets
Cost Management
The difference
Funding Requirements between the
maximum
funding and the
end of the cost
baseline is
Management
Cumulative $
Reserve.
Cost Baseline
Actual Costs
Funding Requirements
Time
Cost Management
Depreciation
Straight Line Depreciation – Present value
minus present cost.
cost – residual value = Depreciation amt. to deduct
each year till salvage value
useful life is reached
Production Method ‐
cost – residual value Depreciation amt. to
= deduct each year till
estimated units of useful life (production) salvage value is
reached
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 615
Cost Management
Depreciation
Double Declining Balance (DDB) – Accelerated depreciation method. Begin
by dividing 100% by the term of the asset and doubling the result. Each
subsequent year, that same percentage is multiplied by the remaining
balance to be depreciated. Using a purchase price of $100,000 and a
residual of $25,000 on a five (5) year schedule:
100% / 5 Year Term = 20%
Double the 20% rate or 40%
Year 1 value = $100,000 ‐ ($100,000 * 40%) = $60,000
Year 2 value = $60,000 – ($60,000 * 40%) = $36,000
Year 3 value = $36,000 – ($36,000 * 40%) = $21,600
Since this is less than the salvage value it is $25,000
Cost Management
Depreciation
Sum of the Years Digits (SYD) – Accelerated depreciation method.
Begin by adding the number of years in the schedule. For example,
for a five (5) year schedule add 1+2+3+4+5 = 15. Next, take the
asset value minus the residual value and divide it by this result
(15). If the salvage value is $25,000 then:
Year 1 value = $100,000 – (5/15 * $75,000) = $75,000
Year 2 value = $75,000 – (4/15 * $75,000) = $55,000
Year 3 value = $55,000 – (3/15 * $75,000) = $40,000
Year 4 value = $40,000 – (2/15 * $75,000) = $30,000
Year 5 value = $30,000 – (1/15 * $75,000) = $25,000
Cost Management
7.4 Control Costs
Influencing the factors that create changes to the
cost baseline.
Ensuring requested changes are agreed upon.
Managing the actual changes when and as they
occur.
Assuring that potential cost overruns do not exceed
the authorized funding periodically and in total for
the project. Monitoring and Controlling Process Group
7. Project Cost
Management
7.4
Control
Costs
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 616
Cost Management
7.4 Control Costs
Inputs Tools & Techniques Outputs
.1 Project management .1 Expert judgment .1 Work performance
plan .2 Data analysis information
.2 Project documents .3 To-complete .2 Cost forecasts
.3 Project funding performance index .3 Change requests
requirements .4 Project management .4 Project management
.4 Work performance data information system plan updates
.5 Organizational process .5 Project document
assets updates
Cost Management
Cumulative Cost Curve EAC
VALUE PV BAC
SCHEDULE
AC VARIANCE
COST
VARIANCE
EV
SLIPPAGE
TIME
NOW
v. 10.0 - © Copyright and all rights reserved
1/31/2018
– 2017 Looking Glass Development, LLC. 203
Cost Management
In Alphabetical Order
Actual Costs Earned Value Planned Value
Minus Minus
CV = = SV
CPI = = SPI
Divided By Divided By
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 617
Cost Management
Forecasting ‐ ETC
ETC based on new estimate.
ETC based on atypical variances.
ETC = BAC‐EV
ETC based on typical variances.
ETC = (BAC‐EV)/CPI
ETC based on both the CPI & SPI.
ETC = (BAC‐EV)/(CPI*SPI)
BAC = Budget at Completion
BAC-EV = Remaining Work
VAC = Variance at Completion
CPI*SPI = Critical Ratio
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 205
Cost Management
Forecasting ‐ EAC
Using a new estimate
– EAC = AC + ETC
Using remaining budget
– EAC = AC + (BAC‐EV)
Using CPI
– EAC = AC + ((BAC‐EV)/CPI)
Using both CPI & SPI
– EAC = AC + ((BAC‐EV)/(CPI*SPI))
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 206
Cost Management
Forecasting ‐ TCPI
The calculated projection of cost performance
that must be achieved on the remaining work
to meet a specified management goal.
Using BAC
– TCPI = (BAC – EV) / (BAC – AC)
Using EAC
– TCPI = (BAC ‐ EV) / (EAC ‐ AC)
VAC = BAC ‐ EAC
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 207
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 618
Cost Management
Earned Schedule Theory
Provides formulas for forecasting the project
completion date, using the earned schedule,
actual time and estimated duration.
Schedule at Completion (SAC) — This is the
original planned completion duration of the
project.
Earned Schedule (ES) — The duration from
the beginning of the project to the date the
planned value is supposed to equal to the
BAC.
Actual Time (AT) — This is the duration from
the beginning of the project to status date.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 208
Cost Management
Earned Schedule Theory
Time variance or (TV) — A measure of
schedule performance in time units rather
than cost units and is defined by the
formula:
TV = ES – AT
Time Estimate at Completion (TEAC) — The
forecast of time at completion and is
similar to EAC. It uses the same basic
formulas as EAC but replaces cost with
schedule.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 209
Cost Management
Earned Schedule Theory
Time Variance at Completion (TVAC) — The
estimated amount of time either ahead or
behind schedule the project is. It uses the
following formula:
TVAC = SAC – TEAC
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 619
Cost Management
Cost Management – Summary
Four (4) processes.
Earned value concepts and calculations.
Life cycle costing.
Cost baseline.
Estimating vs. budgeting.
Types of estimates and estimating.
Contingency and management reserve.
Project Quality Management
Looking Glass Development, LLC
(303) 663‐5402 / (888) 338‐7447
4610 S. Ulster St. #150 Denver, CO 80237
[email protected]
Quality Management
All the activities of the performing organization
that determine quality policies, objectives, and
responsibilities so that the project will satisfy
the needs for which it was undertaken.
Executing Process Group Planning Process Group
8.2 8.1
Manage Plan Quality
Quality Management
8. Project Quality
Management
8.3
Control Quality
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 620
Quality Management
Key Terms
Project Quality Management must address the
management of the project & product.
Quality ‐ “the degree to which a set of inherent
characteristics fulfill requirements.” (American Society for Quality, 2000)
Gold Plating – Giving the customer extra
functionality, adds no value to the project; PMI
argues against gold plating.
Marginal Analysis – Finding the point where the cost
of the incremental improvement in quality equals
the value of the improvement.
Quality Management
International Organization for Standardization
(ISO)
Total Quality Management (TQM)
Six Sigma
Kaizen
Quality vs. Grade
Precision vs. Accuracy
PDCA
Quality Management
Thought Leaders
W.E. Deming: (PDCA), Quality = results of work efforts /
total costs
J.M. Juran: quality planning, control & improvement.
People are cause. Fitness for Use
P. Crosby: Quality is Free, 0 Defects Conforming to Rqmts,
Doing It Right the First Time" (DIRFT)
K. Ishikawa: Cause‐Effect (Fishbone) Diagram, Design
Statistics, introduced quality circles
G. Taguchi: Quality as part of the Design, not Inspection,
Taguchi Method.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 216
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 621
Quality Management
8.1 Plan Quality
Identifying which quality standards are
relevant to the project, and determining how
to satisfy them.
Performed in parallel with other planning
processes.
Quality is planned, designed, and built in,
not inspected in. Planning Process Group
8. Project Quality
Management
8.1
Plan
Quality
Quality Management
8.1 Plan Quality Management
Inputs Tools & Techniques Outputs
.1 Project charter .1 Expert judgment .1 Quality management
.2 Project management plan .2 Data gathering plan
.3 Project documents .3 Data analysis .2 Quality metrics
.4 Enterprise environmental .4 Decision making .3 Project management
factors .5 Data representation plan updates
.5 Organizational process .4 Project documents
.6 Test and inspection
assets updates
planning
.7 Meetings
Quality Management
Cost of Quality
Conformance Nonconformance
Prevention Planning Scrap Failure
Auditing Expediting
Warranty
Testing
Service
Controlling Recalls
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 622
Quality Management
Flowcharts
Quality Management
Flowcharts
Quality Management
SIPOC
Sometimes called COPIS.
Tool that summarizes the inputs and outputs of
one or more processes in table form.
Acronym SIPOC stands for suppliers, inputs,
process, outputs, and customers which form the
columns of the table.
First used in TQM programs.
Used today in Six Sigma and Lean manufacturing.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 623
Quality Management
SIPOC Steps
1. Create an area that will allow the team to post additions to the
SIPOC diagram. This could be a transparency (to be projected by an
overhead) made of the provided template, flip charts with headings
(S‐I‐P‐O‐C) written on each, or headings written on post‐it notes
posted to a wall.
2. Begin with the process. Map it in four to five high level steps.
3. Identify the outputs of this process.
4. Identify the customers that will receive the outputs of this process.
5. Identify the inputs required for the process to function properly.
6. Identify the suppliers of the inputs that are required by the process.
7. Optional: Identify the preliminary requirements of the customers.
This will be verified during a later step of the Six Sigma
measurement phase.
8. Discuss with project sponsor, Champion, and other involved
stakeholders for verification.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 223
Quality Management
SIPOC
Input Output
Supplier Process Customer
Quality Management
Logical Data Model
A logical data model is also referred to as a logical schema.
It is a data model of a specific problem domain that is expressed
independently of any specific named database product or storage
technology.
It focuses on the foundational data structure and its elements such
as relational tables, columns, object‐oriented classes and/or XML
tags.
It represents the abstract structure of a domain of information.
A logical data model is most often used in business process seeking
to capture the important aspects of the organization and how they
relate to one another.
The logical data model is the basis for the physical data model.
It is sometimes used as a synonym for a domain model, but the two
are not the same. A domain model is more focused on capturing
the concepts in the problem domain rather than the structure of the
data associated with that domain.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 225
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 624
Quality Management
Logical Data Model
Quality Management
Logical Data Model
Conceptual Data Model Logical Data Model Physical Data Model
Includes high‐level data constructs Includes entities (table), attributes Includes tables, columns, keys data types,
(columns/fields) and relationships (keys) validation rules, database triggers, stored
procedures, domains, and access constraints.
Non‐technical names, so that executives Uses business names for entities and Uses more defined and less generic specific
and managers at all levels can understand attributes names for tables and columns, such as
the data basis of architectural description abbreviated column names, limited by the
database management system (DBMS) and any
company defined standards.
Uses general high‐level data constructs Is independent of technology (platform, Includes primary keys and indices for fast data
from which architectural descriptions are DBMS) access.
created in non‐technical terms.
May not be normalized. Is normalized to forth normal form (4NF) May be de‐normalized to meet performance
requirements based on the nature of the
database. If the nature of the database is
online transaction processing (OLTP) or
operational data store (ODS) it is usually not
de‐normalized. De‐normalization is common in
data warehouses.
Represented in the DIV‐1 viewpoint Represented in the DIV‐2 Viewpoint Represented in the DIV‐3 Viewpoint (DoDAF
(DoDAF V2.0) (DoDAF V2.0), and OV‐7 View (DoDAF V1.5) V2.0), and SV‐11 View (DoDAF V1.5)
Quality Management
Matrix Diagrams
Also called a matrix chart.
Used to show the relationship between two, three or four
groups of information.
Six possible shapes to the matrix: L, T, Y, X, C, and roof‐shaped
depending on how many variables or groups are being
compared. Shape # of Groups What the Matrix Shows
L‐Shaped 2 Groups A <—> B (or A <—> A)
T‐Shaped 3 Groups B <—> A <—> C but NOT B <—> C
Y‐Shaped 3 Groups A <—> B <—> C <—> A
C‐Shaped 3 Groups All three simultaneously (3‐D)
X‐Shaped 4 Groups A <—> B <—> C <—> D <—> A but not
A <—> C or B <—> D
Roof‐shaped 1 Group A <—> A when also A <—> B in L or T
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 228
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 625
Quality Management
Matrix Diagram Symbols
Strong relationship + Positive relationship
O Owner
1/31/2018
v. 10.0 - © Copyright and all rights reserved –
229
2017 Looking Glass Development, LLC.
Quality Management
Sample Matrix Diagrams
Customer A Customer B Customer C Customer D
Measure #1 15 22 19 12
Measure #4 41 58 36 61
Y‐Shaped Matrix
Quality Management
Test Driven Development (TDD)
Tests are written BEFORE the code.
A Unit Test is a test of a small, functional piece of code.
Unit Tests are given priority in TDD.
Unit tests make it…
– Easier to find bugs.
– Easier to maintain the code, but not test maintainability or
test readability.
– Easier to have full code coverage.
– Easier to design & develop code.
– Easier to deliver early & often.
– Easier to track performance.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 231
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 626
Quality Management
TDD
3.
1. Red
Refactor
2. Green
Quality Management
Test Driven Development (TDD)
Must be able to make it fail. No code can be
written without a failing test. This mean we
actually run the tests to ensure the failure state
before writing any code.
Running the test to prove failure is a fundamental
difference of TDD.
Make it work. Code must be as simple as possible.
The code must ONLY pass that new test for which it
was designed.
Make it better. This means you must refactor.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 233
Quality Management
Acceptance Test‐Driven Development
Also called ATDD
Moves testing focus from code to business
requirements.
Tests created before coding.
Might use functional test framework such as
FIT (Framework for Integrated Testing) or
FitNesse
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 234
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 627
Quality Management
Acceptance Test‐Driven Development
Four stages:
– Discuss the requirements – during planning meeting
ask acceptance criteria.
– Distill tests in a framework‐friendly format
– Develop the code and hook up the tests
– Demo through exploratory testing
Regardless of method team must think about
how the system will be tested before coding.
Quality Management
Refactoring
Refactoring – Process of changing existing
code to improve the way it functions.
In XP you are not afraid of refactoring.
Refactoring is part of your regular work & not
a separate task.
Quality Management
Types of Refactoring
Yuck – You look at code and it works, but is
unsatisfactory. This is about making small
improvements.
The Not Understood – Code that you look at
and cannot understand what it is doing. You
must make code easier to understand.
New Insights – When new functionality needs
to be added, or you learn something.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 237
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 628
Quality Management
Types of Refactoring
Planned Refactoring – Actually adding refactoring
to your project plan as a deliverable.
– M. Fowler says it should hardly ever be done, because
it represents a failure of the team to do the
refactoring in small enough pieces to be constant.
– Planned refactoring almost always requires
justification.
– Is evidence that you are not doing enough of the
other types of refactoring.
Quality Management
Types of Refactoring
Long Term Refactoring – Trying to get closer to
some large future goal. Get some vision of
where you want things to be in the future.
– Must be done gradually.
– Does not require significant planning.
– The essence is doing small steps.
Quality Management
8.2 Manage Quality
Answers the question are we following the
right standards. e.g. if we follow these
standards what will the results be?
Provides an umbrella for Continuous
Improvement . . .
Completed during execution.
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 629
Quality Management
8.2 Manage Quality
Inputs Tools & Techniques Outputs
.1 Project management plan .1 Data gathering .1 Quality reports
.2 Project documents .2 Data analysis .2 Test and evaluation documents
.3 Organizational process assets .3 Decision making .3 Change requests
.4 Data representation .4 Project management plan
.5 Audits updates
.6 Design for X .5 Project documents updates
.7 Problem solving
.8 Quality improvement
methods
Quality Management
Root Cause Analysis
A Root Cause is ‐ if removing the item from
the problem‐fault sequence prevents the
final undesirable outcome from occurring
then the item is considered a root cause.
A Causal Factor ‐ Removing a causal factor
can benefit the outcome, but it does not
prevent its recurrence with certainty.
Quality Management
Root Cause Analysis
Define and properly describe the event or
problem.
Establish a timeline from the normal situation
until the failure.
Distinguish between root causes and causal
factors.
The team then focuses on problem prediction
to determine when the problem will happen
next and what must happen to prevent future
occurrence.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 243
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 630
Quality Management
Affinity Diagrams
An affinity diagram is one of the “Seven
Management and Planning Tools”.
Created by Jiro Kawakita in the 1960s.
Sometimes referred to as the KJ Method.
Used to sort a large number of ideas created
during brainstorming based on their natural
relationships for review and analysis.
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 244
Quality Management
Affinity Diagrams Steps
1. Record each idea on card or PostIts™.
2. Look for ideas that seem related.
3. Sort the cards into groups until all the cards
have been used.
4. Once the cards are sorted create clusters or
subgroups for easier analysis.
Quality Management
Affinity Diagrams
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 631
Quality Management
Cause and Effect Diagram
(Ishikawa or fishbone Diagram)
Time Machine Method Material
Major
Defect
Potential Causes
Quality Management
Histogram
Quality Management
Scatter Diagram
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development
Course Presentation 632
Quality Management
In Control – When ‘in control’ a process should not be
adjusted.
Specification Limits – Customer expectations or
contract requirements.
UCL x
3ơ
x x 2ơ
x
x x x
1ơ
X x x
x x -1ơ
x
-2ơ
LCL -3ơ
What is ‘out of control’ ?
What is the ‘rule of 7’?
v. 10.0 - © Copyright and all rights reserved –
1/31/2018
2017 Looking Glass Development, LLC. 250
Quality Management
Pareto Diagrams
PMP Exam Preparation Student Guide v.10.0 ©2017 Looking Glass Development