Document No.
KEC/IMS/EHS/07/F/53
CHECKLIST FOR DB Issue. No. 02 Rev. No. 00
ELECTRICAL INSTALLATION Issue. Date 08-12-2018 Rev. Date 00-00-00
Page No. 1
Name of Site / Location : Date :
Name of Contract Agency : DB No :
Inspected by : Work Area :
SR NO POINTS OF INSPECTION YES NO NS REMARKS
1 Metal Clad Distribution Board Provided
2 DB is Earthed Properly
3 Canopy/Shed to DB Provided
4 DB is Properly Anchored
5 30 mA ELCB/RCCB Provided
6 I/C & O/G Cables Properly Terminated
7 Cable gland is provided
Cable Joints Properly Insulated with insulation
8
tape
9 Plug tops (3 Pin) for O/G cables Provided
Cables put under ground in vehicular
10
Movement Area
Flammable items are not kept close to electrical
11
Installation
Danger board with Skull & cross bone sticker
12
displayed
13 Locking provision in DB
14 Electrician contact no. is displayed.
IF any Other Points
REMARKS:-
Signature:
Designation:
N – No, Y – Yes, NS – Not satisfactory