Weekly Work Performance

This document summarizes Yan F Sinulingga's weekly accomplishments and plans for the Wampu HEEP project. Last week they compiled daily records, attended concrete strength tests, reviewed documents, and monitored and supervised the installation of rebar, formwork, and concrete pouring for the main dam, connecting tunnel, and waterway. This week their plans include continuing these tasks as well as monitoring excavation work at the intake and installing rebar and formwork.

Uploaded by

Sinulingga Yan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views1 page

Weekly Work Performance

This document summarizes Yan F Sinulingga's weekly accomplishments and plans for the Wampu HEEP project. Last week they compiled daily records, attended concrete strength tests, reviewed documents, and monitored and supervised the installation of rebar, formwork, and concrete pouring for the main dam, connecting tunnel, and waterway. This week their plans include continuing these tasks as well as monitoring excavation work at the intake and installing rebar and formwork.

Uploaded by

Sinulingga Yan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

WEEKLY ACCOMPLISHMENT & WEEKLY PLAN REVISION: (-)

Project : Wampu HEEP


Name : Yan F Sinulingga
Location Work : Office , Main Dam , Intake , Connecting Tunnel, Waterway
NO WORK ITEM COMP. DATE
th th
A. WEEKLY ACCOMPLISHMENT (for the Period of Oct 25 –Oct 31 2014)
th th
1. Compile of Daily Record and Attending concrete strength test in laboratory Oct 25 –Oct 31 2014
th th
2. Review of Documents (Daily Report, Transmittal Letter, Drawing & Material inspection) from/to contractor for approval Oct 25 –Oct 31 2014
th th
3. Monitoring, supervise and coordination to install rebar and formwork until joint Inspection for pouring concrete of Main Dam Oct 25 –Oct 31 2014
th th
4. Monitoring, supervise and coordination to install rebar and formwork until joint Inspection for pouring concrete of Connecting Tunnel Oct 25 –Oct 31 2014
th th
5. Monitoring and supervise and coordination to install rebar, formwork, excavation for final level until joint Inspection for pouring concrete of Oct 25 –Oct 31 2014
Waterway
th th
6. Monitoring and supervise coordination excavation work at intake , checking elevation like following drawing Oct 25 –Oct 31 2014
th th
7. Make daily activity report , weekly report and monthly progress report civil work Oct 25 –Oct 31 2014
8. Checking BOQ (Bill of Quantity) civil work for interim payment
st th
B. WEEKLY PLAN (for the Period of Oct 01 –Oct 6 2014)
st th
1. Compile of Daily Record and Attending concrete strength test in laboratory Oct 01 –Oct 6 2014
st th
2. Review of Documents (Daily Report, Transmittal Letter, Drawing & Material inspection) from/to contractor for approval Oct 01 –Oct 6 2014
st th
3. Monitoring, supervise and coordination to install rebar and formwork until joint Inspection for pouring concrete of Main Dam Oct 01 –Oct 6 2014
st th
4. Monitoring, supervise and coordination to install rebar and formwork until joint Inspection for pouring concrete of Connecting Tunnel Oct 01 –Oct 6 2014
st th
5. Monitoring and supervise and coordination to install rebar, formwork, excavation for final level until joint Inspection for pouring concrete of Oct 01 –Oct 6 2014
Waterway
st th
6. Monitoring and supervise coordination excavation work at intake , checking elevation like following drawing and Install rebar and formwork Oct 01 –Oct 6 2014
st th
7. Make daily activity report , weekly report and monthly progress report civil work Oct 01 –Oct 6 2014

Prepered by :

Yan F Sinulingga

Page 1 of 1

Wampu HEPP (3x15 MW)