DAILY PROGRESS REPORT
Project Onshore Terminal for KG DWN 98/2 Development Project DPR No 89
Client Oil & Natural Gas Corporation Limited Progress Date 01.12.2020
Contractor Tata Projects Limited DPR Date 02.12.2020
TPIA Rina India Pvt Ltd Location OnShore Teriminal,Mallavaram
TPCA Cerification Engineers International Ltd Works Completion 10/26/2020
FROM Cerification Engineers International Ltd Weather Sunny
SCOPE :Third Party Certification Services for Onshore Terminal Package of KG-DWN-98/2 Project at Mallavaram Terminals and IDC at Kakinada
MALLAVARAM SITE ACTIVITES
1, Later pile load test preparatory works in progress on TP-3
2, Mechanical fabrication yard area development started by manually.
SAFETY
Sl:No Activity Remarks
1Safety inspection at all areas at TP1,2,3 and Surroundings. sludge catcher area
2Safety inspection at all areas at TP4 and Surroundings. CTM area
Man Power Status at Site
Name of Company Man Power Man Hours Cumulative Man Hours Remarks
ONGC 0 0
CA / CEIL 2 16
TPI / Rina 1 8
TATA Const 20 160
Total 23 184 14504
Incident:- Nil
Highlights :
Area of Concern :
TPCA
(CIVIL-V Kartik Reddy / SAFETY - Jithin Shankar)
CEIL
DAILY PROGRESS REPORT
Project Onshore Terminal for KG DWN 98/2 Development Project DPR No 1
Client Oil & Natural Gas Corporation Limited Progress Date 30.08.2020
Contractor Tata Projects Limited DPR Date 31.08.2020
TPIA Rina India Pvt Ltd Location OnShore Teriminal,Odelarevu
TPCA Cerification Engineers International Ltd Works Completion 10/26/2020
FROM Cerification Engineers International Ltd Weather Sunny
SCOPE :Third Party Certification Services for Onshore Terminal Package of KG-DWN-98/2 Project at Odalarevu, Mallavaram Terminals and IDC at Kakinada
MALLAVARAM SITE ACTIVITES
1.Pavment breaking for piling work preparion.on 20.08.2020
2.Pavment thickness measured by breaking pavment by jack hammer .200mm thickness measured.on 21.08.2020
3.Breaking work for cc road for 3 nos pipe.on 22.08.2020
4.Induction and Trainning session done .on 24.08.2020
5.MOM conducted with TPL and inspection activities done.on 25.08.2020
6.No activities carried out due to no manpower available .on 26.08.2020
7.Material shifting(Rebar steels) and Bar bending work in pogress for Test Piles.on 27.08.2020
8. TP1 Location sludge catcher paved area .Breaking work for cc road for 1 nos pipe.on 28/08/2020
9. TP1 & 2 Location sludge catcher paved area .Breaking work for cc road for 2 nos pipe.on 29/08/2020
10. TP4 ,5,6 Location Near Train 7 .3 no of mannual excavation completed , reeinforcment work also in progress 30/08/2020
11. TP4 ,5,6 Location Near Train 7 . mannual excavation pit completed for bentonite mix , 14 mtr cage completed ,reeinforcment work also in progress 31/08/2020
11. HP GAS SEPERATOR unloaded in loading gantry area 31/08/2020
(CEIL representives Mr.Jatin Shankar (Safety -Dy. Manager) & Mr. Karthik Reddy (Civil-Sr.Engineer) at Site)
SAFETY
Sl:No Activity Remarks
1Safety inspection at all areas at TP1,2,3 and Surroundings.
2Safety monitoring of Steel works for fabrication yard
3Safety Monitoring of civil activity at TRAIN 7 area
4safety monitoring of Near loadng gantry area.
5inspection of cranes and heavy equipments
Man Power Status at Site
Name of Company Man Power Man Hours Cumulative Man Hours Remarks
ONGC 0 0
CA / CEIL 2 16
TPI / Rina 0 0
TATA Const 409 3272
Total 411 3288 474158
Incident:- Nil
Highlights :
Entrance to U Field baricated on 23.07.2020. Work resume in U Field 13.08.2020 onwards civil work .And Mechanical work resume 27.08.2020 onwards
Area of Concern :
TPCA
(CIVIL-Mr.R.Balasubramanian/ SAFETY - Geboy George/, MECHANICAL - Mr.Ladi Karnudu,Mr.Subhadatta Dalabehera)
CEIL