This document provides the procedures for the S-11RD2BP1 recompletion and milling project. The objectives are to pull out the existing kill string, run a new 7" packer on a 3-1/2" completion string, and mill out a bridge plug at 9,425 feet and push it down to around 10,600 feet. Well control procedures are outlined, including maintaining kills, barriers during key operations, and responding to potential losses. The project is estimated to take 13 days.

Uploaded by

masgontar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
270 views17 pages

Fakinasol

This document provides the procedures for the S-11RD2BP1 recompletion and milling project. The objectives are to pull out the existing kill string, run a new 7" packer on a 3-1/2" completion string, and mill out a bridge plug at 9,425 feet and push it down to around 10,600 feet. Well control procedures are outlined, including maintaining kills, barriers during key operations, and responding to potential losses. The project is estimated to take 13 days.

Uploaded by

masgontar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 17

PERTAMINA HULU KALIMANTAN TIMUR

S-11RD2BP1 RECOMPLETION AND MILLING PROCEDURE

REPARED BY : HILMAN SITORUS


COMPLETION ENGINEER ____________________

REVIEWED BY : YUDI HANDRADIKA


OPTIMIZATION ENGINEER ____________________

REVIEWED BY : BUDI PRASETYANA


WORKOVER SUPERINTENDENT ____________________

APPROVED BY : EKA PAMBUDI


RIAMBOMO
D & C ENGINEERING MANAGER ____________________

DATE: 15 April 2019

BARGE/RIG : Tirta Rajawali + HWU-225


COST CENTER : 2191BR152
AFE AMOUNT : US$ 1,132,888
ESTIMATED TIME : 13 Days

CC: M. YASIN/DANNY ANDRYANTO ADHI PRATOMO SULISTYO


TM SOUTH OPS OFFSHORE TM ASSET OPTIMIZATION SHELF

WORKOVER SITE MANAGER SIB TEAM


TIRTA RAJAWALI/HWU-225 SULISTYO AP/YUDI HANDRADIKA.

S-11 SUPERINTENDENT
WELL FILE SEPINGGAN OFFSHORE PRODUCTION

SERVICE COMPANIES
BMB/ELNUSA/SLB/EXPRO/TECHNIPFMC/BHGE

Schlumberger-Private
TABLE OF CONTENTS
1 BASIC WELL DATA 3
2 WELL STATUS 3
3 OBJECTIVES 4
4 RECENT HYSTORY 4
5 HEADS-UP LIST 4
6 WELL CONTROL 6
7 PROCEDURE 9
7.1 Well Preparation Prior N/D X-mas tree 9
7.2 N/D X-Mas Tree and R/U HWU-225 10
7.3 Pull Out Kill String 11
7.4 TIH New Completion 11
7.5 Set 7”x-3-1/2”Bluepack packer 14
7.6 N/U Twin BOPs and Run Milling tool 14
7.7 N/D Twin BOPs, R/D HWU-225 and N/U X-Mas Tree 15
8 ATTACHMENT 19

Page 2 of 17

Schlumberger-Private
1.0 B ASIC W E L L D A T A
Well Name S-11RD2BP1
Surface Location S 1° 25' 48.50701", E 116° 56' 1.49822"
Rig Name HWU-225
Rotary Table to Tubing Head 44.20 ft
Water Depth 168.6 ft
Rotary Table to Mud Line 92 ft
Maximum Inclination above target depth 25.78 deg at 10,505 ftMD
Maximum DLS 3.92 deg/100 ft at 3029 ft
Smallest Restriction 2.813” (at X-Nipple)
Fluid Left inside Prod. Casing Completion Brine
Existing production zone:

2.0 WELL STATUS


 Well is shut-in due to mechanical problem
 SITHP = 200 psi and SICHP = 200 psi
2.1 W E L L H E A D , X-M A S T R E E A ND J E W E L RIE S

Wellhead and X-mast tree:

Type Rated Working Pressure Temperature Rating


X-Mas Tree Single Stack 5,000 psi 0 - 250 degF
Wellhead Conventional 5,000 psi 0 - 250 degF

Internal:
 3-1/2” X-landing nipple with PX-Plug installed at 519 ft.
External:
 9-5/8” x 7” ZXP Packer at 3,107ft
 7” ZXP packer at 9,480 ft
 7” Liner hanger flex at 9,501 ft.

2.2 W E L L G EO M E T R Y A N D R E ST RICT IO N
 Maximum dog-leg above target depth is 3.92°/100’ at 3,029 ft and Maximum inclination
above target depth is 25.78° at 10,505 ft
 The smallest restriction is 2.813” at X Landing Nipple @ 519 ft

Page 3 of 17

Schlumberger-Private
2.3. T UB UL A R D A T A
TUBULAR STRENGTHS (No safety factors have been applied to these values)
NOM. WEIGHT GRADE CONNECTIO BURST COLLAPSE MAX. PULL
SIZE N TYPE 1000’S
INCHES #/FT. PSI PSI LB.
3-1/2” 9.2 L-80 TSB 10,160 10,530 207
7” 29 L-80 NSCC 8,160 7,020 676
9-5/8” 47 N-80 BTC 6870 4760 1,086
DIMENSIONS
NOM. WEIGHT O.D. I.D. DRIFT CONN O.D. CONN I.D.
SIZE
INCHES #/FT. INCHES INCHES INCHES INCHES INCHES
3-1/2” 9.2 3.500 2.992 2.867 4.250 2.992
7” 29 7.000 6.184 6.059 7.656 6.184
9-5/8” 47 9.625 8.681 8.525 10.625 8.525

3.0 O B J E CT I V E
 Pull out existing kill string
 Run 7” packer on 3-1/2” completion string c/w bell nipple
 Mill out MRBP @ 9,425’ and push it down to ±10,600 ft.

4.0 R E CE NT H I ST O R Y
 Ran 2.62” DB Underreamer and cut tubing at 9,421’ (May 9, 2019 @21:00)
 Pulled out 3-1/2” completion string (May 11, 2019 @08:30)
 TIH Baker Fishing tool (May 12, 2019 @09:00) and attempted to fish seal assembly and 3-
1/2” remaining tubing cut. It was failed to release Overshot from remaining tubing cut
 E-line ran strip primacord to release fishing tool (May 16, 2019 @10:00)
 TOH Fishing tool (May 17, 2019 @10:00)
 TIH 7” Casing Scrapper + Brush and scrap casing from 9345 ft – 9375 ft (May 18: 2019
@12:00)
 TIH 15 Joints 3-1/2” Kill string with PX-plug installed at X-landing nipple (May 20, 2019
@16:30)

5.0 H E ADS -U P L I ST
Expro Slickline
 Standard slickline unit and toolstring

SLB Completion
 1 ea 3-1/2” HLN with WRSV installed
 7 ea 3-1/2” SPM with dummy installed
 1 ea 7”x 3-1/2” packer
 1 ea 3-1/2” SSD (Up to open)
 1 ea 3-1/2” X-landing nipple

Baker Hughes
 2-1/8” mud motor + accessories
 2.75” mill bit
Page 4 of 17

Schlumberger-Private
Elnusa HWU—225K
 HWU-225 unit
 Twin BOP’s
 345 joints 1-1/4” macc pipe
 FOSV for 3-1/2” tubing
 Safety valve for 1-1/4” macc pipe

Elnusa Fluid Services


 Filtration unit
 Completion brine (3% KCl with Filtered Sea Water)
 Hi-vis and Safe Link (for losses)

FMC Wellhead
 Tubing hanger and x-mas tree + accessories
 Running/pulling tools

Penajam Supply Base


 310 Joints, 3-1/2” TMK tubing, 9.2#, N-80
 5-3/4” Bell guide / Lip guide

Page 5 of 17

Schlumberger-Private
6.0 W E L L C O N T R O L
6.1 W E L L C O N T R O L S A F EG U A R D S DURING N/D X-M AS T RE E AND R/U HWU BOP
 Kill well with FSW + 3% KCl completion brine and confirm no pressure in annulus.
 Install and verify 2 independent barriers in tubing:
o BPV
o PX-plug and prong
 Install and verify 2 independent barriers in annulus:
o Tubing Hanger
o Hydrostatic
 Keep monitoring the well closely and be ready for handling well control during N/D X-Mas Tree
and R/U BOP. One pump must be continuously running to fill up annulus.

6.2 W E L L C O N T R O L DURING TOH AND TIH C O MP L E T IO N


 Maintain well full of completion brine at all times
6.3 W E L L C O N T R O L S A F EG U A R D S DURING R/D HWU BOP AND N/U X-M AS T R E E
 Confirm no pressure in tubing and annulus.
 Install and verify 2 independent barriers in tubing:
o BPV
o PX Plug and Prong
 Install and verify 2 independent barriers in annulus:
o Tubing Hanger
o Hydrostatic
o 4” Baker Seal assembly
o 7” Baker ZXP packer
 Keep monitoring the well closely and be ready for handling well control during R/D BOP and
N/U X-Mas Tree. One pump running to fill up annulus.
6.4 W E L L C O N T R O L S A F EG U A R D S DURING N/U T W IN BOP AT W INDO W B ASK E T

 PX plug and prong


 Blind rams
6.5 M AXIM U M A N T I C I P A T E S U R F ACE P RE SSURE
 MASP from formation: 2,492 psi (assuming full column of gas with 0.1 psi/ft gas gradient)
 Maximum bullhead pressure: 1,801 psi (FG 0.62 psi/ft at at 10,118 ft TVD/10,615 ft MD)
 Maximum pressure test: 4000 psi (tubing pressure test)

Page 6 of 17

Schlumberger-Private
6.6 F L UID L O SS
(Refer to PHKT Loss Circulation SOP / PHKT_D&C_ TKI_003/2019 section III.4 for Major
Workovers)
 Maximum allowable fluid loss: 20 bbls/hr (Discuss with WO Superintendent/Completion
Engineer for further step).
 FSW + 3% KCl completion brine should be used to fill up the well when loss circulation
occurred.
 If losses still occurred, evaluate fluid density and reduce if practical.
 HEC polymer/fluid losses pill to be ready on location

6.7 B ARRIE R T A B L E
(Refer to PHKT Well Barrier Design SOP /PHKT_D&C_ TKI_021/2019)
Operation Barriers
Internal : N/A
External :
Cased Hole Slickline operation
 Wireline lubricator and BOP
 Completion fluid hydrostatic
Internal :
 BPV
 PX-plug and prong
N/D X-Mas Tree and R/U HWU BOP
External :
 Tubing hanger
 Hydrostatic
Internal :
 FOSV
 Completion Fluid Hydrostatic
TOH/TIH Completion string or macc pipe
External :
 BOP
 Completion Fluid Hydrostatic
Internal :
 BPV
 PX Plug and Prong
R/D HWU BOP and N/U X-Mas Tree
External :
 Tubing hanger
 Hydrostatic

Page 7 of 17

Schlumberger-Private
6.8 C ASING AND T U B I N G P R E SSURE T E ST P L AN
(Refer to PHKT Casing & Tubing Design SOP / PHKT_D&C_TKI_016/2019 & Well Barrier
Design SOP / PHKT_D&C_TKI_021/2019)
 Casing Pressure Test
o 1,500 psi
o Duration : 30 minutes
o Acceptance Criteria: Decrease from test pressure (30 minutes test) shall not exceed 10% of
test pressure and shall have a decreasing rate of change.
 Tubing Pressure Test
o Test Pressure: 4000 psi
o Duration: 30 minutes
o Acceptance Criteria: Decrease from test pressure (30 minutes test) shall not exceed 10% of
test pressure and shall have a decreasing rate of change.

6.9 M ACC P I P E D A T A

Page 8 of 17

Schlumberger-Private
7.0 P RO CE D U R E
7.1 W E L L PREPARATION PRIOR N/D X-M AS T RE E
1. Notify Production Department of the program commencement. Complete platform audit
checklist to identify platform condition.
2. Hold PJSM on location between Workover Site Manager, Production Supervisor and Business
Partners. Review work program, JSA and ensure following critical issues are discussed:
 Well control
 All lifting gear inspected and have proper certification
 Lifting plan discussed including Roles and Responsibility for each personnel assigned
 Barge craned inspected and have proper certification
 Competent Crane operator
 Ensure all equipment to be lifted are still below Safe Working Load (SWL) of crane and
lifting gear
 Perform heavy lift inspection
 Limit number of personnel around lifting operation and emphasize of line of fire during PJSM
 Scaffolding to be installed and certified
 All personnel working at height to use full body harness and practice 100% tied-off
 Emphasize on Stop Work Authority if in doubt or on any uncertain/abnormal condition
 Proper PPE to be used all the time
3. Check and record tubing pressure and casing pressure. Report the pressures in the morning
report.
4. Perform tubing-hanger cavity test 3000 psi with hydraulic oil (using hand pump) for 15 minutes.
Decrease from test pressure (15 minutes test) shall not exceed 10% of test pressure and shall
have a decreasing rate of change. Record cavity test on chart and report the result to Completion
Engineer/Workover Superintendent. Bleed off pressure.
5. M/U surface line to 3-1/2” x 9-5/8” annulus. Pressure test surface line to 300 psi low pressure
and 2000 psi high pressure Hold each test for 5 minutes. Ensure pressure stabilize (flat line) and
no visible leaks. WSM to verify the integrity of pressure test
6. Bullhead annulus with FSW completion brine. Maximum pumping pressure 1,801 psi. Bleed off
pressure to 0 psi thru gas buster

Contingency if PX-plug leaking at kill string


- M/U pump in tee and surface line. Line up 2” surface line from Elnusa pump manifold to
pump in tee. Pressure test surface line 300 psi low pressure and 3500 psi high pressure Hold
each test for 5 minutes. Ensure pressure stabilize (flat line) and no visible leaks. WSM to
verify the integrity of pressure test. Bleed off tubing and annulus pressure to 0 and observe
well
- R/U Slickline, pressure test PCE 300 psi low pressure and 2000 psi high pressure. Hold each
test for 5 minutes. Ensure pressure stabilize (flat line) and no visible leaks. WSM to verify
integrity of pressure test. Perform the following steps (Update slickline reports are attached)
- RIH and retrieve WRSV from HLN at 433 ft. Note: WRSV must be inspected and redressed
once at surface (Potentially performed by Production Team)
Page 9 of 17

Schlumberger-Private
- Bullhead down tubing at 1.5 times tubing volume ft with FSW completion brine. Maximum
bullhead pressure 1,801 psi. Observe tubing and bleed off pressure to 0 psi thru gas buster
- Circulate out hole clean with FSW completion brine until fluid clean at surface
- R/D Slickline
7. Install BPV manually as per TECHNIPFMC procedure.

7.2 N/D X-M A S T R E E AND R/U HWU-225


8. Keep pump running at the annulus and closely monitor annulus pressure at all time during N/D
X-Mas Tree and R/U BOP.
9. N/D FMC X-Mas Tree. Limit maximum crane tension to 5T during N/D tree process to avoid
connector snap out. Check condition of tubing hanger.
10. Install tubing-hanger test plug and control line plug.
11. N/U BOP & 11" Riser. Perform BOP as per Initial Pressure Test below (this step to be
performed stump test on barge):
a) VBR : 300/5000 psi
b) BR : 300/5000 psi
c) Annular Preventer : 300/3500 psi
d) Riser Connection : 3000 psi
If the operation is still on going on the same well 21 days after the Initial Pressure Test above,
then perform BOP Subsequent Test(s) below:
a) VBR : 300/2500 psi
b) BR : 300/2500 psi
c) Annular Preventer : 300/2500 psi
12. R/U HWU-225 & function test system as per Elnusa Procedure.
13. Retrieve tubing-hanger test plug and BPV as per TECHNIPFMC procedure. Ensure no gas
trapped below BPV.

7.3 P UL L O U T K I L L S T R I N G
14. M/U TECHNIPFMC tubing hanger Retrieving Tool. RIH and M/U landing joint.
15. Hold PJSM with all involved personnel prior retrieving completion. Review work program, JSA
and ensure following critical issues are discussed:
 Well control: keep filling the well thru annulus with FSW completion brine at 0.5 BPM or at
lowest pump rate during POOH completion
 Perform trip drill with all crew involved prior TOH
 Limit the number of personnel on work basket during TOH completion
 Plug control line prior POOH completion
 Install strip rubber and put hole cover to prevent drop object into the well
16. Clear window basket from non-essential personnel. Untighten tubing hanger hold down screw.
Keep pumping the tubing with FSW completion brine at lowest pump rate. Pull out seal
assembly from packer bore with maximum pull 165 Klbs (80% of yield brand new pipe of 3-

Page 10 of 17

Schlumberger-Private
1/2” TSB tubing) until completion string free. Record normal pick-up weight and continue
picking up string 10 ft. Confirm well stable before continuing POOH.
Notes:
 Monitor trip tank at all times.
 Immediately stop operation, shut-in the well and inform Workover Superintendent and
Completion Engineer if seen anomaly at the surface
 Inform Workover Superintendent and Completion Engineer if completion string is
unable to be free with maximum ~165 Klbs.
17. L/D FMC tubing hanger to top deck. Perform and visual check and prepare for re-run
18. Continue POOH existing completion.

7.4 TIH N E W C O MP L E T I O N
19. Hold PJSM with all involved personnel prior RIH Lower Completion. Review work program,
JSA and ensure following critical issues are discussed:
 Well control method to be used for killing well in case swabbing/kick observed
 Potential pinch points during make-up
 Ensure all JSA and work permits are prepared well in advance of the operations. SLB and
BHI to provide JSA and obtain approval from WSM prior RIH Upper Completion.
 Schlumberger and WSM to agree on final space-out.
 Ensure proper placement to avoid inefficiency during RIH upper completion.
 Final running tally to be review and approved by Completion Engineer, Workover
Superintendent and SLB Completion Field Service Manager prior RIH Upper Completion.

Prior to PU the first BHA, make sure to do the following critical check:
 Schlumberger tool specialist, Elnusa and PHKT representatives to measure all
components and prepare BHA schematic including depths, OD’s and ID’s, ensure
all equipment can be RIH inside 9-5/8” casing 47 ppf and 7” casing 29 ppf.
 Drift all tubular prior to TIH
 Perform well control drill.
 Verify fluid loss rate and correct fill-up/displacement
 Check tubing hanger control line port
 Apply the torque value requirements for all premium connections
 Any major change to the approved Standard Completion Program should be
discussed with the Completion Engineer and WSM prior to completion string
running

20. Make up completion string jewelry and seal assembly as per attached proposed well schematic.
No safety factor applied for below specification
TUBING WEIGHT GRADE CONNECTIO BURST COLLAPSE MAX. PULL
SIZE N TYPE 1000’S
INCHES #/FT. PSI PSI LB.
3-1/2” 9.2 L-80 TSB 10,160 10,540 207
3-1/2” 9.2 L-80 TMK UP PF 10,160 10,540 207

Page 11 of 17

Schlumberger-Private
COUPLING DIMENSIONS & MAKE UP TORQUE
CONN COUPLI TORQUE TORQUE DRIFT CONN O.D. CONN I.D.
TYPE NGLENG MIN OPTIMUM
TH
INCHES FT-LB FT-LB INCHES INCHES INCHES
3-1/2-TSB 8.228 3400 3780 2.867 3.937 2.969
3-1/2-TMK 6.238 2700 2900 2.867 4.252 2.953

21. M/U and RIH 3-1/2” 9.2# TSB/TMK UP tubing, completion jewelries and Bell Nipple as per
tally approved by Completion Engineer and SLB Completion Supervisor in town

Notes:
 PX Plug and Prong already installed at X-landing nipple and tested to 3,000 psi
 Keep filling up the well thru annulus with FSW completion brine at 0.5 BPM or at lowest
pump rate during TIH completion
 WSM to confirm the tubing inspection result from PSB
 Monitor make-up torque closely during tubing connection

Pressure test plan:

Page 12 of 17

Schlumberger-Private
- Pressure test tubing integrity#1: M/U and TIH Bell Nipple, 1 joint tubing, X-landing
nipple, 1 joint tubing, 7”x3-1/2” bluepack packer, 1 joint tubing, SSD (in closed
position), 1 joint tubing. Pressure test PX-plug against 3-1/2” tubing, 7”x3-1/2” blue
pack packer and 3-1/2” SSD (in close position) at 500 psi. After test complete, R/U
slickline and retrieve PX-plug and prong from X-landing nipple.
 Pressure test tubing integrity#2:
- Set PX-plug and prong at SSD nipple. Pressure test PX-plug and prong against
tubing to 4,000 psi
22. Resume TIH 3-1/2”, 9.2# completion string with bell nipple and 7”x3-1/2” bluepak packer.
Note:
- Perform tubing test integrity every 15 joints at 4,000 psi
- Check tubing weight regularly
- Running speed as per SLB recommendation
- Run slowly for bluepak packer accessing 9-5/8”x7” packer
- Monitor well pressure closely
23. Make up 3-1/2” Hydraulic Landing Nipple with WRSV already installed.
24. Cut ¼” control line. Make up the control line to hydraulic landing nipple port and pressure test
line integrity to 5000 psi. Function test the safety valve 3 times and record return volumes.
Keep pressure 5000 psi in control line while TIH.
25. Resume TIH 3-1/2” 9.2# as per tally.
26. Tag slowly tubing cut at 9,421 ft and verify with set down weight 10 klbs. Mark pipe and
verify the tubing cut depth.
27. Space out and M/U Tubing hanger on landing joint and TIH same to window.. Bleed off
control line pressure to 0. Cut ¼” control line (ensure give enough wrap of control line 3-5
round below of tubing hanger), connect the excess line from spooling unit to top of THRT,
flush the tubing hanger port to remove debris. Make up control line downhole side to tubing
hanger port below the hanger. Pressure test line integrity to 5000 psi. Function test safety valve
3 times and record return volumes. Maintain pressure 5000psi while RIH the hanger.
28. Drain riser and BOP stack prior landing hanger.
29. RIH tubing hanger to landing shoulder.
30. Close Annular (ensure low closing pressure as control line passing the BOP to prevent
crushing the control line). Pressure test backside seals and packer 500 psi for 15 minutes
(ensure seals integrity prior final landing, slight drop pressure might be observed as control
line passing annular seals). Open annular.
31. Slowly pull out with overpull max 10 klbs.
32. R/U Slickline, pressure test PCE to 300 psi low pressure and 3,000 psi high pressure Hold each
test for 5 minutes. Ensure pressure stabilize (flat line) and no visible leaks. WSM to verify
integrity of pressure test.
- Retrieve WRSV from Hydraulic Landing Nipple
- RIH and retrieve PX-lug and prong from SSD Landing nipple
- RIH 2.6” IB to tag Top of fish. POH.
Contingency plan If tubing cut is inaccessible,
1. Rotate completion string to make good alignment to access tubing cut
Page 13 of 17

Schlumberger-Private
2. Run Swedging tool to access Top of fish or
3. Tappered milling tool should be run by 1-1/4” macc pipe and mud motor
- R/D slikcline
7.5 S E T 7” X -3-1/2”B L U E P A C K P ACK E R

33. Displace annulus with FSW + 3% KCl + corrosion inhibitor


34. RIH and set PX plug and prong at X-landing nipple. Pressure up tubing and set 7”x3-1/2”
bluepak packer as SLB upper completion procedure
35. Pressure test backside against packer to 300/1,500 psi for 30 minutes on charts
7.6 N/U T W I N BOP S AND RUN M IL L ING TO O L

36. N/U 3-1/2” Safety valve 5K + twin BOP on Window basket. Pressure test twin BOP against
PX plug to 3,000 psi
37. Retrieve PX prong and plug body from HLN
38. R/D Slickline

Ensure to check the following prior RIH mac pipe:


 FOSV (in full open position) and the key to operate are available at the window basket
 Required crossovers for the tubulars to be ran are at the workbasket
 Pump operator to monitor the well via trip tank at all time during RIH and POOH mac pipe
 Review and perform well control drill with both day and night shift crew
 Rabbit all mac pipe and ensure mac pipe clean before RIH
 Perform PJSM discussing well control issue and personnel R&R during sand clean out
 Perform Stump Test for twin BOP

39. R/ M/U and function test 2.75” milling BHA at surface as per Baker’s SOP. (Milling BHA is
advised by Baker Specialists and approved by WO Superintendent).

Pump Rate 0.5 0.75 1 1.2 1.75


(bpm)
Pressure (psi)

40. TIH with 2.75” Baker Milling BHA (Junk Mill) as per attached BHA on 1-1/4” Mac pipe while
keeping the hole full with FSW completion brine.
Note :
- Monitor 3-1/2” x 9-5/8” annulus at all times during RIH & POOH mac pipe. Record &
report casing pressure on DMR
- Record the neutral weight and the slack off weight at predetermined increments while
running in hole to target depth.
- Run in hole at controlled speed and slow down through completion accessories. Limit RIH
Speed 20 fpm
- Perform function test motor every 20 joints
41. At 9,400 ft, performed function test as follows:

Pump Rate 0.5 0.75 1 1.2 1.75


(bpm)

Page 14 of 17

Schlumberger-Private
Pressure (psi)

42. Continue TIH and tag top of fish at 9,425 ft, check P/U, S/O (Record in Morning Report).
43. Start pumping with FSW + Hivis brine, adjust pump rate/ pressure until good return observed
at surface as per Baker thru tubing specialists. Mill out fish at 9421 ft MD. Watch for fish drop
indication and motor stall
Note:
- Monitor 3-1/2” x 9-5/8” annulus at all times during TIH & TOH mac pipe. Record & report
casing pressure on Morning Report
- Inform town if metal / debris/return not observed at surface
- FSW Hi-Vis brine recipe: FSW + 0.8 gal/bbl HEC liquid. Target viscosity: 40 cp
(equivalent to 63 sec/quartz)
- Safe lube to be ready on board in case found high pick-up weight on high deviation part.
- Reciprocate every 10 feet to ensure the tubing is clean from debris and no overpull
achieved. Pump Hi Vis to ensure cutting in return is clear.
- Set down between 1000 and 3000 lbs depending on the bottom hole assembly’s limitations
- Minimize connection time
- Inform workover superintendent/completion engineer if no milling progress.
- Discuss well control method and personnel R&R during PJSM prior Milling out job
- Always monitor trip tank for losses. Inform workover superintendent/completion engineer if
loss circulation occurs during Milling out then perform the Loss Circulation Contingency
step.
- If kick observed, shut-in well as per Elnusa shut-in procedure. Record mac pipe pressure,
SITP, SICP and inform Workover Superintendent. Circulate out influx and kill the well
- If anomaly observed during Milling, inform workover superintendent/ completion engineer
first before performing any circulation to bring influx out.

44. Push down fish to ±10,600 ft (proposed for 2.5” MRBP depth) with maximum 3000 lbs sit
down weight.
45. TOH mill BHA to surface and keep hole full
46. R/U slickline. Pressure test lubricator at 300/2500 psi. RIH and 2.72” TGC to bottom.
7.7 N/D T W I N BOP S , R/D HWU-225 AND N/U X-M AS T RE E
47. Ensure 3-1/2” x 9-5/8” annulus full with completion brine. Put the annulus on choke and
closely monitor annulus pressure at all time during N/D X-Mas Tree and R/U BOP. Ensure
tubing and casing pressure is stable at 0 psi.
48. Set BPV as per TECHNIPFMC procedure, N/D twin BOPs, R/D HWU-225 and N/D BOP.
49. N/U FMC X-mast tree
50. Pressure test the tubing bonnet from the tubing hanger adapter cavity test port to 3000 psi for
15 min to test the connection between the tubing bonnet with the wellhead. Decrease from test
pressure (15 minutes test) shall not exceed 10% of test pressure and shall have a decreasing
rate of change.
51. Install wing valve, choke body, and production flow line.
52. Retrieve BPV.
53. Pressure test body tree against wing valve to 300/3,000 psi against PX-Plug and test flow line
to 600 psi.

Page 15 of 17

Schlumberger-Private
54. R/U Slickline, pressure test PCE to 300 psi low pressure and 2000 psi high pressure Hold each
test for 5 minutes. Ensure pressure stabilize (flat line) and no visible leaks. WSM to verify
integrity of pressure test. Perform the following job:
a) Pull Prong and PX Plug body from X-Landing Nipple
b) Set WRSSV at Hydraulic Landing Nipple. Perform function test as per SLB procedure.
c) R/D Slickline
55. Suspend operation for Slickline (GLRA) and Mast Unit Operation.