0% found this document useful (0 votes)
571 views10 pages

AIFF NCE Construction Civil Works and Artificial Turf SECTION 8 Bill of Quantities 28.10.2019

The document is a bill of quantities for road and drain work projects containing 10 line items describing work such as excavation, filling, concrete work, and road surfacing. The quantities, units, rates and totals are provided for each work item. In total, it provides a detailed cost estimate for completing the road and drain construction works.

Uploaded by

Ibrahim Dawud
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
571 views10 pages

AIFF NCE Construction Civil Works and Artificial Turf SECTION 8 Bill of Quantities 28.10.2019

The document is a bill of quantities for road and drain work projects containing 10 line items describing work such as excavation, filling, concrete work, and road surfacing. The quantities, units, rates and totals are provided for each work item. In total, it provides a detailed cost estimate for completing the road and drain construction works.

Uploaded by

Ibrahim Dawud
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

AIFF ABSTRACT-ROAD WORK CDPL,MUMBAI

BILL OF QUANTITIES FOR ROAD WORKS


SL RATE AMOUNT IN INR
DESCRIPTION OF WORK QTY UNIT
NO

Supplying & filling with excavated earth earth


1 3,600.00 Cum
brought from outside

Excavation for roadway in soil by mechanical means


including cutting and pushing the earth to site of
embankement upto a distance of 100 metres
2 (average lead 50 metres), including trimming 2,025.00 Cum
bottom and side slopes in accordance with
requirements of lines, grades and cross sections.

Preparation and consolidation of sub grade with


power road roller of 8 to 12 tonne capacity after
excavating earth to an average of 22.5 cm depth,
dressing to camber and consolidating with road
3 roller including making good the undulations etc. 4,500.00 Sqm
and re-rolling the sub grade and disposal of surplus
earth with lead upto 50 metres.

Supplying, Stacking & spreading moorum 500mm


thick back filling for pitching including packing with
smaller stones and consolidation with power roller
4 4,500.00 Sqm
including spreading , watering and consolidation of
binding material etc.
AIFF ABSTRACT-ROAD WORK CDPL,MUMBAI

SL RATE AMOUNT IN INR


DESCRIPTION OF WORK QTY UNIT
NO

Construction of granular sub-base by providing


close graded Material conforming to specifications,
mixing in a mechanical mix plant at OMC, carriage
of mixed material by tippers to work site, for all
leads & lifts, spreading in uniform layers of
specified thickness with motor grader on prepared
5 surface and compacting with vibratory power roller 800.00 Cum
to achieve the desired density, complete as per
specifications and directions of Engineer-in-Charge.-
With material conforming to Grade-I (size range 75
mm to 0.075 mm) having CBR Value-30

Providing, laying, spreading and compacting graded


stone aggregate (size range 53 mm to 0.075 mm )
to wet mix macadam (WMM) specification including
premixing the material with water at OMC in
mechanical mix plant, carriage of mixed material by
tipper to site, for all leads & lifts, laying in uniform
6 layers with mechanical paver finisher in sub- base / 800.00 Cum
base course on well prepared surface and
compacting with vibratory roller of 8 to 10 tonne
capacity to achieve the desired density, complete as
per specifications and directions of Engineer-in-
Charge.-2 lAYERS
AIFF ABSTRACT-ROAD WORK CDPL,MUMBAI

SL RATE AMOUNT IN INR


DESCRIPTION OF WORK QTY UNIT
NO

Providing and laying bituminous macadam using


crushed stone aggregates of specified grading
premixed with bituminous binder,transported to site
by tippers,laid over a previously prepared surface
with paver finisher equiped with electronic sensor to
the required grade, level and alignment and rolling
7 with smooth wheeled, vibratory and tandem rollers 300.00 Cum
as per specificaton and density, complete as per
specifications and directions of Engg-in Charge.
50 to 100mm average compacted thickness with
bitumen of grade [email protected]% (percentage by
weight of total mix) prepared in Drum type Hot Mix
Plant of 60-90 TPH capacity

Providing and laying seal coat over prepared


surface of road with bitumen heated in bitumen
boiler fitted with the spray set spraying
using 98 kg of bitumen of grade VG - 10 and
8 blinding surface with 0.90 cum of stone aggregate 4,500.00 Sqmt
of 6.7 mm size (Passing 11.2 mm
sieve and retained on 2.36 mm sieve) per 100 sqm
of road surface, including rolling and finishing with
power road roller all complete.
AIFF ABSTRACT-ROAD WORK CDPL,MUMBAI

SL RATE AMOUNT IN INR


DESCRIPTION OF WORK QTY UNIT
NO

Providing and laying at or near ground level factory


made kerb stone of M-25 grade cement concrete in
position to the required line, level and curvature,
jointed with CM 1:3, including making joints with or
without grooves (thickness of joints except at sharp
9 curve shall not to more than 5mm), including 560.00 Rmt
making drainage opening wherever required
complete etc. as per direction of Engineer-in-
charge)(Length of finished kerb edging shall be
meaured for payment)(Precast CC kerb stone shall
be approved by Engineer in charge)

Providing and applying thermoplastic reflective


paint of any colour or compound for line
markinging, 3 mm thick of pigment as per MORTH
10 83.00 Sqmt
specification no. 803.4 (rate of application of
compound @ 8 kg/Sqm) etc complete. (Approved
by Engineer in Charge)
TOTAL COST
AIFF ABSTRACT-DRAIN WORK CDPL,MUMBAI

BILL OF QUANTITIES FOR STORM WATER DRAIN WORK


SL
DESCRIPTION OF ITEMS QTY UNIT RATE AMOUNT IN INR
No

Earth work in excavation by mechanical means


(Hydraulic excavator) / manual means over areas
(not exceeding 1.5 m in width as well as 10 sqm
1 on plan) including disposal of excavated earth,
lead upto 50m and lift upto 1.5m, disposed earth
to be levelled and neatly dressed.

All kinds of soil 3190 cum

Filling available excavated earth (excluding rock) 2166 cum


in trenches, plinth, sides of foundations etc. in
layers not exceeding 20cm in depth,
2 consolidating each eposited layer by ramming
and watering, lead up to 50 m and lift upto 1.5
m.

Loading and unloading of excavated earth. 1025 cum


(Placing tipper at loading point, loading with
3 front end loader, dumping, turning for return
trip, excluding time for haulage and return trip)
upto a lead upto 10 kms

Supplying and filling in plinth under floors, 350 Cum


4 including watering, ramming, consolidating and
dressing complete.Moorum/Hard Copra
AIFF ABSTRACT-DRAIN WORK CDPL,MUMBAI

SL
DESCRIPTION OF ITEMS QTY UNIT RATE AMOUNT IN INR
No

Providing and laying in position cement concrete


of specified grade excluding the cost of
5
centering and shuttering - All works upto Plinth
Level
1:4:8 (1 Cement : 4 coarse sand : 8 graded stone 134 cum
5a
aggregate 40mm nominal size
1:2:4 (1 cement : 2 coarse sand : 4 graded stone 87 cum
5b aggregate 20 mm nominal size)-Coping Work
AIFF ABSTRACT-DRAIN WORK CDPL,MUMBAI

SL
DESCRIPTION OF ITEMS QTY UNIT RATE AMOUNT IN INR
No

Providing and laying in position ready mixed M-


25 grade concrete for reinforced cement
concrete work, using cement content as per
approved design mix, manufactured in fully
automatic batching plant and transported to site
of work in transit mixer for all leads, having
continuous agitated mixer, manufactured as per
mix design of speicified grade for reinforced
cement concrete work, including pumping of
RMC form transit mixer to site of laying,
6 excluding the cost of centering, shuttering
finishing and reinforcement, including cost of
admixtures in recommended proportions as per
IS: 9103 to accelerate / retard setting of concrete,
improve workability without impairing strength
and durability as per direction of Engineer-in-
Charge.
(Note: Cement content conisdered in this item is
@ 330 kg/cum. Excess/Less cement used as per
design mix is payable/recoverable separately).

All works upto plinth level 552.00 cum

Steel reinforcement for R.C.C. work including


straightening, cutting, bending, placing in
7
position and binding all complete upto plinth
level.
AIFF ABSTRACT-DRAIN WORK CDPL,MUMBAI

SL
DESCRIPTION OF ITEMS QTY UNIT RATE AMOUNT IN INR
No

Thermo-Mechanically Treated bars 46920 kg

Centering and shuttering including strutting, 4176 Sqmt


8 propping etc. and removal of form work for
:Foundations, footings, bases for columns

15 mm cement plaster finished with a floating


9
coat of neat cement of mix:
1:3 (1 cement : 3 coarse sand) 508 sqm

Structural steel work in single section, fixed with


or without connecting plate, including cutting,
10 hoisting, fixing in position and applying a 32964 kg
priming coat of approved steel primer all
complete.-Hot Galvanised Welding material

Providing 50 mm dia CPVC pipe for perforation


12 150.00 RM
in Drain Cover

Providing and laying non-pressure NP2 class


(light duty) RCC pipes with collars jointed with
13 stiff mixture of cement mortar in the proportion
of 1:2 (1 cement : 2 find sand) including testing
of joints ect complete:

250 mm dia RCC Pipe 160.00 RM


AIFF ABSTRACT-DRAIN WORK CDPL,MUMBAI

SL
DESCRIPTION OF ITEMS QTY UNIT RATE AMOUNT IN INR
No

TOTAL COST ₹ 4.00


(III) INSTALLATION OF ARTIFICIAL TURF
SL
DESCRIPTION OF ITEMS QTY UNIT RATE AMOUNT IN INR
No
1 Artificial Football Pitch (Size 110mx 73.25m)
Supplying & filling with excavated earth 11480 cum
a
brought from outside
Design, supply and lay a FIFA certified (Quality) 7488 Sqm
artificial pitch complete with all necessary
b excavation, suitable sub-base, irrigation system
and sub-soil drainage complete with backing
layer, infill materials and white lines

NOTE:

Bidders to specify the type and thickness of


i sub-base and any sub-soil drainage included in
their pricing

Bidders are to submit themethod of installation


and their product specifications with regards to
ii
the type and length of grass, the backing layer
and infill materials
Allow for the cost to obtain FIFA certification
iii
for the installed artificial turf

TOTAL CARRIED TO SUMMARY OF COST