06 - Project Schedule Management
06 - Project Schedule Management
Engr. Saleh Elgebaly- PMP Course 6th Edition – 00966-500800794 – 002-01004040731 – [email protected]
PROJECT SCHEDULE MANAGEMENT إدارة الجدول الزمني للمشروع
1 Activity list
2 Activity attributes
3 Milestone list
Duration estimates
Basis of estimates
Schedule baseline
Project schedule
Critical path method
The project management team selects a scheduling When possible, the detailed project schedule should
method, such as Critical Path or an agile approach. remain flexible throughout the project to adjust for
knowledge gained, increased understanding of the
Then, the project-specific data, such as the activities, risk, and value-added activities.
planned dates, durations, resources, dependencies, and
constraints, are entered into a scheduling tool to create a
schedule model for the project.
Prepared by : Saleh Elgebaly PMP®, PMI- RMP® ,PgMP® , P3O®
PROJECT SCHEDULE MANAGEMENT إدارة الجدول الزمني للمشروع
TRENDS AND EMERGING PRACTICES IN PROJECT SCHEDULE MANAGEMENT االتجاهات والممارسات الناشئة في إدارة الجدول الزمني للمشروع
TRENDS
On-demand schedulingpsum
is based on the theory-of constraints and pull-based scheduling
concepts from lean manufacturing to limit a team’s work in progress
in order to balance demand against the team’s delivery throughput.
Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and
controlling the project schedule.
هي العملية التي تحدد السياسات واإلجراءات والوثائق المستخدمة في تخطيط الجدول الزمني للمشروع وتطويره وإدارته وتنفيذه ومراقبته
It Provides guidance and direction on how the project schedule will be managed throughout the project.
توفر اإلرشاد والتوجيه بشأن كيفية إدارة الجدول الزمني للمشروع على مدار
Input
Outputs
PROJECT CHARTER
01 Defines the summary milestone schedule that will influence the management of the project schedule.
EXPERT JUDGMENT
MEETINGS
Participants at these meetings may
include the project manager, the
project sponsor, selected project team
members, selected stakeholders,
DATA ANALYSIS anyone with responsibility for
Alternatives analysis can include schedule planning or execution, and
determining which schedule others as needed.
methodology to use, or how to combine
various methods on the project.
OUTPUTS
مع المشتريات أو الموارد البشرية
Project schedule
model Organizational Control thresholds
SCHEDULE MANAGEMENT PLAN development Level of accuracy procedures links
Reporting formats
Activity list
Activity attributes
DEFINE ACTIVITIES
Milestone list
Change requests
Identifying and documenting the specific actions to be performed to produce the project deliverables.
.تحديد األنشطة هي عملية تحديد وتوثيق إجراءات معينة تُنفَّذ كي يتم إنتاج مخرجات المشروع
it decomposes work packages into schedule activities that provide a basis for estimating, scheduling,
executing, monitoring, and controlling the project work.
. ومراقبته والتحكم فيه، وتنفيذه، وجدولته،سا لتقييم عمل المشروع
ً هي تجزئة مجموعات العمل إلى أنشطة للجدول الزمني توفر أسا
Tools &
Input
Techniques Outputs
03 01
ORGANIZATIONAL PROCESS ASSETS
EXPERT JUDGMENT
DECOMPOSITION التجزئة
Is a technique used for Dividing and Subdividing the project scope and project
deliverables into smaller, more manageable parts.
Each work package within the WBS is decomposed into the activities required to
produce the work package deliverables.
Involving team members in the decomposition can lead to better and more accurate results.
MEETINGS
Meetings may be face-to-face, virtual, formal, or informal.
Meetings may be held with team members or subject matter experts to define the activities
needed to complete the work.
MILESTONE LIST
Milestone is a significant point or event in a
project.
Indicates whether the milestone is mandatory,
such as those required by contract, or PROJECT MANAGEMENT PLAN UPDATES
optional, such as those based on historical Schedule baseline
information. Cost baseline
Milestones have Zero duration because they
represent a significant point or event.
CHANGE REQUESTS
Prepared by : Saleh Elgebaly PMP®, PMI- RMP® ,PgMP® , P3O®
6.2 DEFINE ACTIVITIES تحديد األنشطة
SEQUENCE ACTIVITIES
Computer-driven - Project management information system ( PMIS ).
Manual process – ideal for smaller projects and larger projects in the early
days, manual sequencing be preferred.
Blended approach – combination of manual and computer
Tools &
Input
Techniques Outputs
Every activity except the first and last should be connected to at least one predecessor and at least one successor
activity with an appropriate logical relationship.
Logical relationships should be designed to create a realistic project schedule. using lead or lag time between
activities.
performed by using project management software or by using manual or automated techniques.
The Sequence Activities converting the project activities from a list to a diagram to act as a first step to publish the
schedule baseline.
Prepared by : Saleh Elgebaly PMP®, PMI- RMP® ,PgMP® , P3O®
6.3 SEQUENCE ACTIVITIES تسلسل األنشطة
..تحدد التسلسل المنطقي للعمل للحصول على أكبر قدر من الكفاءة في ضوء جميع قيود المشروع
Two activities can have two logical relationships at the same time (for example, SS and FF).
Multiple relationships between the same activities are not recommended, so a decision has to be
made to select the relationship with the highest impact.
Discretionary dependencies
Sometimes referred to as preferred logic, preferential logic, or Internal dependencies
soft logic.
Established based on knowledge of best practices within a
Involve a precedence relationship between project
particular application area activities and are generally inside the project team’s
During construction, the electrical work should start after control.
finishing the plumbing work. For example, if the team cannot test a machine until
This order is not mandatory and both activities may occur at the they assemble it, there is an internal mandatory
same time (in parallel), but performing the activities in dependency.
sequential order reduces the overall project risk.
Prepared by : Saleh Elgebaly PMP®, PMI- RMP® ,PgMP® , P3O®
6.3 SEQUENCE ACTIVITIES تسلسل األنشطة
A lead : is the amount of time a successor activity can be advanced with respect to a predecessor activity.
( Starting the activity before completing its predecessor )
) فترة السبق هي مقدار الفترة الزمنية التي بها يمكن تقديم نشاط الحق بالنسبة لنشاط سابق(بدء النشاط قبل انهاء النشاط السايق له
On a project to construct a new office building, the landscaping could be scheduled to start 2 weeks prior to the
scheduled punch list completion
Leads are used in limited circumstances to advance a successor activity with respect to the predecessor activity
وتستخدم فترات السبق في ظروف محدودة لتقديم موعد نشاط الحق بالنسبة لنشاط سابق
A lag: is the amount of time a successor activity will be delayed with respect to a predecessor activity.
هي مقدار الوقت الذي بواسطته سيتم تأخير نشاط الحق فيما يخص نشاط سابق
Waiting time between activities ) ( عبارة عن ازمنة انتظار بين النشاطين المتتاليين
A technical writing team may begin editing the draft of a large document 15 days after they begin writing it.
LEAD = - LAG
Lags are used in limited circumstances where processes require a set period of time to elapse between the
predecessors and successors without work or resource impact.
وتستخدم فترات التأخير في ظروف محدودة حيث تتطلب العمليات أن تمضي فترة محددة من الوقت بين األنشطة
.السابقة والالحقة بال عمل أو تأثير للموارد
Prepared by : Saleh Elgebaly PMP®, PMI- RMP® ,PgMP® , P3O®
6.3 SEQUENCE ACTIVITIES تسلسل األنشطة
Is a graphical representation of the logical relationships, also referred to as dependencies, among the project
schedule activities.
بين أنشطة الجدول الزمني للمشروع- ويشار إليها كاعتماديات أيضا- مخطط شبكة الجدول الزمني للمشروع هو عبارة عن عرض رسومي للعالقات المنطقية
Estimating the number of work periods needed to complete individual activities with estimated resources.
.تقدير مدد النشاط هي عملية تقدير عدد فترات العمل الالزمة إلكمال األنشطة المنفردة باستخدام الموارد التي تم تقديرها
فإن إضافة الكثير من الموارد إلى النشاط قد يؤدي، وفي نقطة ما، ألنه من الممكن ازدياد المدة بسبب المخاطر،غالبًا ال ينخفض الزمن إلى النصف إذا تم زيادة الموارد إلى الضعف
.إلى زيادة المدة بسبب نقل المعرفة ومنحنى التعلم والتنسيق اإلضافي وغيرها من العوامل المرتبطة
The project manager also needs to be aware of Student Syndrome—or procrastination— when people start to apply
themselves only at the last possible moment before the deadline, and Parkinson’s Law where work expands to fill
the time available for its completion.
PROJECT DOCUMENTS
1. Activity attributes :
2. Activity list.
3. Assumption log.
4. Lessons learned register.
5. Milestone list.
6. Project team assignments. ORGANIZATIONAL PROCESS ASSETS
7.
8.
Resource breakdown structure.
Resource calendars.
INPUTS
9. Resource requirements.
10. Risk register.
02 - ANALOGOUS ESTIMATING
MEETINGS- 08 08 02 Estimating the duration or cost of an activity or
a project using Historical data from a similar
activity or project.
01 Used when there is a limited amount of detailed
information about the project.
Less costly and less time-consuming than other
techniques, but it is also less accurate.
DECISION MAKING- 07 07 03
03 - PARAMETRIC ESTIMATING
Calculate cost or duration based on historical
05 data and project parameters.
DATA ANALYSIS- 06
Reserve analysis 04 - THREE-POINT ESTIMATING
06 04 The accuracy of single-point duration estimates may
be improved by considering estimation uncertainty
and risk.
BOTTOM-UP ESTIMATING - 05
tE = (tO + tM + tP) / 3.
A method of estimating project duration or cost by aggregating the
estimates of the lower level components of the WBS.
Prepared by : Saleh Elgebaly PMP®, PMI- RMP® ,PgMP® , P3O®
6.4 ESTIMATE ACTIVITY DURATIONS تقدير مدد األنشطة
6.4.2.7 DECISION MAKING صنع القرار
One variation of the voting method that is often used in agile-based projects is called
the fist of five (also called fist to five).
The project manager asks the team to show their level of support for a decision :
By holding up a closed fist (indicating no support).
Up to five fingers (indicating full support).
If a team member holds up fewer than three fingers, the team member is given the
opportunity to discuss any objections with the team.
The project manager continues the fist-of-five process until the team achieves consensus
(everyone holds up three or more fingers) or agrees to move on to the next decision.
Duration estimates are quantitative assessments of the likely number of time periods that are required to
complete an activity, a phase, or a project.
تقديرات المدة هي تقييمات كمية للعدد المحتمل من الفترات الزمنية المطلوبة إلكمال نشاط أو مرحلة أو مشروع
A range of 2 weeks ± 2 days, which indicates that the activity will take at least 8 days and not more than 12
(assuming a 5-day work week).
A 15% probability of exceeding 3 weeks, which indicates a high probability—85%—that the activity will take 3 weeks or less.
The amount and type of additional details supporting the duration estimate vary by application area.
analysing activity sequences, durations, resource requirements, and schedule constraints to create a
schedule model for project execution and monitoring and controlling.
وضع الجدول الزمني هي عملية تحليل تسلسل األنشطة وفتراتها الزمنية ومتطلبات الموارد والقيود على الجدول الزمني إلنشاء نموذج الجدول
.الزمني لتنفيذ المشروع ومراقبته والتحكم فيه
The key benefit of this process is that
it generates a schedule model with planned dates for completing project activities.
أنها تصدر نموذج للجدول الزمني بتواريخ مخططة الستكمال أنشطة المشروع
Tools &
Techniques Outputs
Developing an acceptable project schedule is an iterative process. يعتبر وضع جدول زمني مقبول للمشروع عملية تكرارية
The schedule model is used to determine the planned start and finish dates for project activities and
milestones based on the best available information.
Schedule development can require the review and revision of duration estimates, resource estimates, and
schedule reserves to establish an approved project schedule that can serve as a baseline to track progress.
Key steps include defining the project milestones, identifying and sequencing activities, and estimating durations.
Once the activity start and finish dates have been determined, it is common to have the project staff assigned
to the activities review their assigned activities.
The staff confirms that the start and finish dates present No conflict with resource calendars or assigned
activities on other projects or tasks and thus are still valid.
PROJECT DOCUMENTS
Activity attributes Project schedule network diagrams.
Activity list Activity list
Assumption log Project team assignments.
Basis of estimates. Resource calendars.
Duration estimates Resource requirements.
Lessons learned. Risk register.
Milestone list.
ORGANIZATIONAL PROCESS ASSETS
AGREEMENTS
Vendors may have an input to the project
schedule as they develop the details of how INPUTS
they will perform the project work to meet
contractual commitments.
TOOLS AND TECHNIQUES SCHEDULE NETWORK ANALYSIS تحليل شبكة الجدول الزمني
Is the overarching technique used to generate the project schedule model.
This schedule network analysis technique calculates the early start, early finish, late start, and late finish
dates for all activities without regard for any resource limitations by performing a forward and backward pass
analysis through the schedule network
The critical path is the sequence of activities that represents the longest path through a project, which determines
the shortest possible project duration.
D
Activity
(Days)
Dependency
Critical Path Method (Example)
A 5 Start
B 4 Start
0 5 5 5 3 8 8 9 17
C 3 Start
A D G
D 3 A 0 0 5 6 1 9 9 1 18
E 6 A, B
F 4 C 0 18
0 4 4 5 6 11 11 7 18
G 9 D
Start B E H End
H 7 D, E 1 1 5 5 0 11 11 0 18
Consider all relationships areFS=0 0 18
Data analysis
Agile release planning also determines the number of iterations or sprints in the release, and allows the product owner and team
to decide how much needs to be developed and how long it will take to have a releasable product based on business goals,
dependencies, and impediments.
Schedule compression Techniques are used to shorten or accelerate the schedule duration without reducing the project scope
in order to meet schedule constraints, imposed dates, or other schedule objectives.
Crashing
A technique used to shorten the schedule duration for the least incremental cost by adding
resources.
Examples of crashing include approving overtime, bringing in additional resources, or paying to
expedite delivery to activities on the critical path.
Crashing works only for activities on the critical path where additional resources will shorten the
activity’s duration.
Crashing does not always produce a viable alternative and may result in increased risk and/or cost.
Fast tracking
Technique in which activities or phases normally done in sequence are performed in Parallel for at least
a portion of their duration.
An example is constructing the foundation for a building before completing all of the architectural
drawings.
Fast tracking may result in rework and increased risk.
Fast tracking only works when activities can be overlapped to shorten the project duration on the
critical path.
Using leads in case of schedule acceleration usually increases coordination efforts between the
activities concerned and increases quality risk.
Fast tracking may also increase project costs.
Include scheduling software that expedites the process of building a schedule model by generating start and
finish dates based on the inputs of activities, network diagrams, resources, and activity durations.
Is the Approved version of a schedule model that can be changed only through formal change control
procedures and is used as a basis for Comparison to actual results.
During monitoring and controlling, the approved baseline dates are Compared to the actual start and
finish dates to determine if Variances have occurred.
PROJECT SCHEDULE
يعتبر الجدول الزمني للمشروع مخرج ألحد نماذج الجدول الزمني التي توضح األنشطة المرتبطة مع ما تم التخطيط له من تواريخ ومدد
عندئذ، إذا تم تخطيط الموارد في مرحلة مبكرة. وكحد أدنى يتضمن الجدول تاريخ بداية وتاريخ نهاية مخطط لكل نشاط.ومعالم وموارد
يظل الجدول الزمني للمشروع جدول مبدئي حتى يتم التصديق على تعيين الموارد وحتى يتم تحديد تواريخ البدء واالنتهاء
Barcharts
• Also known as Gantt charts, bar charts
PROJECT SCHEDULE
يعتبر الجدول الزمني للمشروع مخرج ألحد نماذج الجدول الزمني التي توضح
.األنشطة المرتبطة مع ما تم التخطيط له من تواريخ ومدد ومعالم وموارد
Although a project schedule model can be presented in tabular form, it is more often presented graphically, using one
or more of the following formats:
1- Milestone charts
Only identify the scheduled start or completion of major deliverables and key external interfaces
تحدد فقط بداية الجدول الزمني أو استكمال التسليمات الرئيسية والواجهات الخارجية الرئيسية
2- Bar charts
Also known as Gantt charts, bar charts represent schedule information where activities are listed on the vertical
axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to
start and finish dates.
PROJECT CALENDARS
A project calendar identifies Working days and Shifts that are available for scheduled activities.
CHANGE REQUESTS
Modifications to the project scope or project schedule may result in change requests to the scope baseline, and/or
other components of the project management plan.
Preventive actions may include recommended changes to eliminate or reduce the probability of negative schedule
variances.
.إن اإلجراءات الوقائية يمكن أن تتضمن بعض التغيرات الموصى بها الستبعاد أو تقليل إمكانية حدوث أي تباين سلبي في الجدول الزمني
Is the process of monitoring the status of the project to update the project schedule and managing changes to the
schedule baseline.
.التحكم بالجدول الزمني هي عملية مراقبة حالة المشروع من أجل تحديث الجدول الزمني للمشروع وإدارة التغييرات التي تطرأ على الخط المرجعي للجدول الزمني
the schedule baseline is maintained throughout the project. .هي الحفاظ على الخط المرجعي للجدول الزمني على مدار المشروع
َ وتُؤد
َّى هذه العملية على مدار المشروع
Tools &
Input
Techniques Outputs
Updating the schedule model requires knowing the actual performance to date.
يتطلب تحديث نموذج الجدول الزمني معرفة األداء الفعلي حتى تاريخه
When work is being contracted, regular and milestone status updates from contractors and suppliers are a
means of ensuring the work is progressing as agreed upon to ensure the schedule is under control.
تعتبر تحديثات الحالة المنتظمة والخاصة بالمعالم من المقاولين والموردين وسائل لضمان تقدم العمل حسب المتفق عليه للتأكد،حينما يتم التعاقد للعمل
من السيطرة على الجدول الزمني
Scheduled status reviews and walkthroughs should be done to ensure the contractor reports are accurate and complete.
.يجب إجراء مراجعات الحالة والفحوص المجدولة لضمان صحة واكتمال تقارير المقاول
Trend Analysis
Examines project performance over Variance analysis
Performance reviews time to determine whether performance
Measure, Compare, and Analyse schedule is improving or deteriorating. looks at variances in planned versus
performance Against the schedule baseline actual start and finish dates, planned
such as actual start and finish dates, percent versus actual durations, and variances
complete, and remaining duration for work in float.
in progress.
Outputs
WORK PERFORMANCE INFORMATION
Includes information on how the project work is performing compared to the schedule baseline.
Variances in the start and finish dates and the durations can be calculated at the work package level
and control account level. For projects using earned value analysis, the (SV) and (SPI) are
documented for inclusion in work performance reports