2002 Report Evaluating The Use of A Fire Fighting Helicopter in The Netherlands 1
2002 Report Evaluating The Use of A Fire Fighting Helicopter in The Netherlands 1
Author
Astrid Scholtens
Translated by
Erica Peters
Cliff Sear
2
EVALUATION OF FIRE FIGHTING HELICOPTER
Preface
The Netherlands Institute for Fire Service and Disaster Management
(Nibra) provides a key source of expertise, developing and sharing
knowledge in both fire service operations and disaster management.
Evaluation projects in both areas form an important part of the
activities of the Nibra research team.
3
4
EVALUATION OF FIRE FIGHTING HELICOPTER
Table of contents
Abbreviations 06
1 Introduction 07
5 Technical evaluation 31
6 Overall evaluation 35
ATTACHMENTS
Attachment 3 Participants 73
Footnotes 77
5
Abbreviations
The following abbreviations will be used in the report:
6
EVALUATION OF FIRE FIGHTING HELICOPTER
1 Introduction
In 1997 an innovative way of fighting fires was devised. This involved
equipping a helicopter with an experimental extinguishing system1
(IFEX-system2, developed in 1994) and provided a new way to fight
fires in high-rise or complicated locations. Having been equipped,
the helicopter was technically fit for fighting fires but had yet to be
operationally tested.
By the end of 1997 the Chief Fire Officer of the Maarssen Fire
Brigade took the initiative to set up a pilot project for the fire
fighting helicopter. The objective of the fire fighting helicopter was
“to provide support to the fire service when dealing with fires in
high-rise buildings or fires in locations which are difficult to access”
(see protocol attachment 1, section B.7).
The pilot project was unique as it was the first to assess this
combination of equipment in operational situations. Many
participants were involved in the project providing financial
resources, specific expertise, equipment and by creating support for
the practical benefits of the helicopter.
By the end of 1999, which was later than originally planned, nine of
the representatives above signed an agreement to co-operate in the
pilot project. In the agreement they formally declared their
commitment to take part in the project that became known as the
‘Fire Fighting Helicopter Netherlands’. The pilot project
commenced on 3 April 2000 and was concluded on 3 October
2001.
7
The Netherlands Institute for Fire Service and Disaster Management
(Nibra) evaluated the pilot project and has presented the resulting
conclusions in this report. This evaluation sets out to establish
whether the use of a fire fighting helicopter is an effective way to
support fighting fires in high-rise buildings and whether it could form
a useful addition to fire fighting equipment in the future.
It has to be emphasized that research has been done the fire fighting
helicopter concept as a whole. That is to say the combination of the
helicopter and the IFEX-system. The operation of the IFEX-system
on its own has not been a part of the research carried out by Nibra.
Therefore an opinion has not been given regarding the system in
this evaluation.
8
EVALUATION OF FIRE FIGHTING HELICOPTER
The participants and others were aware before the project began
that the fire fighting helicopter would not always be able to provide
effective support. The IFEX-system is based on the cooling and
smothering effect of water vapour and this system has proved to be
more efficient in a confined space than in the open air (see
attachment 1, section B.1 en B.6) these circumstances would not
always exist.
‘Designated’ attacks
In this evaluation a ‘designated attack’ is an attack that meets the
objective of the pilot project. Namely the fire fighting helicopter had
to support the fire service during (suppressive) fire fighting in high-
rise buildings or fires which were difficult to access. Only designated
attacks are of importance when determining whether its operational
use has been successful. The decision whether to introduce the fire
fighting helicopter should be based on the objectives of the pilot
project. If the fire fighting helicopter proves to be successful for
different reasons, the project group will have to determine whether
9
the benefits identified make use of the fire fighting helicopter
desirable.
The project group may gain valuable information from attacks which
do not meet the criteria or are unsuccessful.
10
EVALUATION OF FIRE FIGHTING HELICOPTER
3 Outline of the
evaluation
Questionnaires
Two different questionnaires were designed for the evaluation.
After each attack the questionnaires were sent to the Fire Officer
requesting the helicopter and the Pilot and Operator of the
National Police Aviation Authority (PLD)5. At the commencement
of the project the questionnaires were sent to the National Police
Aviation Authority and several Fire Officers for comment. The
demonstration of the fire fighting helicopter in Nederhorst den Berg
(see section 4.1) was used by Nibra to validate the questionnaires
which, after minor amendments, were ready for use at the first
operational deployment on 12 May 2000.
The five main topics for the fire service and the National Police
Aviation Authority (PLD) in the questionnaires were:
• Alarm, mobilization and deployment of the helicopter
• Type, location and severity of the fire at the time of the request
and during the attack
• Communication, coaching and provision of information
• Use of the helicopter (e.g. influence of the ‘down-wash’ – that is
the draught caused by the rotors)
• Opinions regarding the use of the helicopter in general
11
results of their evaluations in the Nibra questionnaires. In addition
to the questionnaires Nibra personnel interviewed the pilots, in
some cases, after the attack.
Attendance at demonstrations
A number of Nibra researchers attended demonstrations and tests
with the fire fighting helicopter in Nederhorst den Berg on 2 May
2000 and in Amsterdam on 18 October 2001 amongst others. By
attending the demonstrations the researchers gained a clear
understanding of operation of the fire fighting helicopter and
practical procedures used.
Video recording
During some attacks video-recordings were made and footage has
been used for the evaluation.
12
EVALUATION OF FIRE FIGHTING HELICOPTER
4 Evaluation of each
attack
In this chapter, divided into sections, the most important
conclusions for each attack are provided. The conclusions are based
on the questionnaires completed by the Fire Officer, Pilot and
Operator, additional interviews with the people involved and
available video-recordings.
13
Date Location Designated Description of the Activities of the
attack fire helicopter
2 May Nederhorst den Yes Fire in cabin in yacht on Blussing van de
2000 Berg (exercise) the ‘Spiegelglas’ brandhaard
12 May Purmerend No Fire in warehouse Test of penetrating
2000 containing paper (status ability
of the fire at time of
attack: smouldering)
12 May Leusderheide No Bush/heath fire (status Damping down
2000 (no open at time of attack: Fire
fire) out on arr.)
03 May Utrecht No Fire in high-rise building None
2001 (no attack for
safety reasons)
Five ‘designated’ attacks were carried out during the pilot project
but only one of them was not simulated.
14
EVALUATION OF FIRE FIGHTING HELICOPTER
The fire fighting helicopter was already on its way when a request
was made by the Fire Brigade. After six shots the down-wash of the
helicopter caused the stern mooring to snap. Shortly after this the
second mooring snapped allowing the burning vessel to drift in the
direction of the observers. A fire boat, present in case of
emergency, quickly extinguished the fire producing large quantities
of smoke.
Main conclusions
• ‘Designated’ attack?
The fire fighting helicopter supported the fire service during an
attack on a fire that was difficult to access in the suppression phase.
The criteria of the pilot project were met and the attack can be
regarded as ‘designated’.
15
mainly melted away and the back of the yacht was open. However,
the fire took place in a reasonably confined space.
However, the Helicopter pilot pointed out that it was not useful for
the IC to direct the shots carried out by the Operator during the
attack.
The Helicopter pilot was of the opinion that the IC on the ground
did not have a view of the location or the fire that could assist the
Pilot or Operator. The Pilot suggested that the assessment was best
left to the Pilot and Operator in the cockpit to decide how and
where shots should be applied. The system is fitted with a camera
and display for the Operator to see were the shots had to be fired
and the Pilot is too pre-occupied during the attack to communicate
with people other than the Operator. (Nevertheless, before the
attack the IC should brief the Pilot about the attack strategy, see
section 4.6.)
After the project was finished Helicopter pilots were asked if they
shared this opinion. Their response was that they did. This would
mean that the attack strategy has to be adjusted to avoid false
expectations on the part of Incident Commanders, who would
expect to direct operations themselves.
The shots were not powerful enough because of the low pressure
in the IFEX-system, this meant that the helicopter had to quickly
approach the target and to hover approximately 5 meters away. The
seat of the fire must be reached to extinguish the fire effectively.
According the specification of the IFEX-system the effective
16
EVALUATION OF FIRE FIGHTING HELICOPTER
Apart from the IFEX-system and the Helicopter crew there was still
some carrying capacity left for water/additives and fuel: 50% fuel,
200 litres of water and 25 litres of additives (see attachment 1, sub
section B.6.2). The limited amount of fuel had an effect on the flight
time. The helicopter could not be permitted to stay in the air any
longer than was strictly necessary (see also section 4.6).
At 6.40am a message was sent that the fire was under control. The
IC decided to make a second request for the fire fighting helicopter
to test the penetrating ability of the IFEX-system on the paper mass
(actually the Fire Brigade wanted to test the IFEX-system and not
the fire fighting helicopter). The PLD complied with this request
despite the fact that the attack would not meet the criteria of the
pilot project (no high-rise building or location with difficult access).
Also the circumstances for an optimum use of the IFEX-system
were not present (accessible location, enclosed fire). The reason
why the PLD complied with this request was that it would be an
opportunity to test the Operational tactics and procedures. There
was no emergency at the time the helicopter was requested and the
helicopter did not immediately turn out to the fire.
17
When the helicopter arrived at the scene the paper mass was still
smouldering. The mass was about 6 meters high with a surface of
approximately 40 meters by 70 meters.
The Fire Brigade allocated and prepared the landing zone where the
helicopter had to touch down after arrival. After arrival of the
helicopter the crew and the IC discussed the attack strategy and it
was decided to apply two shots with pure water, two with additives
(Coldfire) and two ‘double shots’ (this means that two shots from
both canons were applied at the same time).
Main conclusions
• ‘Designated’ attack?
The attack in Purmerend shows that the PLD adopted a flexible
approach regarding mobilization (see chapter 2). As it was clear that
the attack did not meet the criteria of the pilot project. There was
no fire in a high-rise building or on a location which was difficult to
access. Also there was no open fire still burning. The helicopter has
only been used to test the penetrating ability of the IFEX-system
and not to assist during the suppressive phase of a fire.
• Withdrawal of personnel
The IC pointed out that the use of the fire fighting helicopter in an
emergency situation in the future will have a negative effect on the
continuity of operations because of the need to withdraw personnel
when it is in use. This will slow down the operation.
• Publicity
The media were not very positive in the way they reported the
attack, omitting a few essential principles. It was not clear in the
news coverage that it was an exercise enabling the fire brigade to
test a few aspects of the fire fighting helicopter. It had been
established that this exercise was not a ‘designated’ attack according
to the aim of the pilot project. However, the media conveyed the
18
EVALUATION OF FIRE FIGHTING HELICOPTER
impression that the attack was real: “the helicopter was used to
speed up the extinguishing process.” This was a totally wrong
assumption (for example: “the test in the open air went all wrong”)
and was not viewed in the proper context. It is remarkable that the
press at the scene did not attempt to interview the participants.
• Additives
As will be discussed in relation to the attack at the Leusder Heath,
the use of additives proved to have a more positive effect compared
with pure water. Nevertheless, it was decided fairly shortly from
the start of the pilot project to stop carrying additives. As a whole,
the benefit of additives proved to be limited. It became clear that
the additive ‘Coldfire’ and also the ‘ox blood’ had a negative
influence on the effectiveness of the IFEX-tsystem (see chapter 5,
technical evaluation). In view of the fact that the balance between
the fuel, water supply and additives had an effect on the available
flight time it, was decided to stop carrying additives but more fuel
and water instead. After the third attack (the heath fire at the
Leusder Heath) the fire fighting helicopter no longer carried additives
(see attachment 1, B.6.2).
After a discussion between the IC from the Leusden Fire Brigade and
the Senior Fire Officer of the Amersfoort Fire Brigade, at 1718 hours
a request was made for the fire fighting helicopter. The request
19
asked for the fire fighting helicopter to locate the seats of the fire
and to extinguish them immediately. The Senior Fire Officer made
this request as it was difficult to gain access to the area, particularly
for heavy fire appliances. Also, there were no accessible water
supplies for fire appliances in the area. The PLD were informed at
the time of the request that there was forest/heath fire with a
surface of one kilometer square consisting of several seats. The
request was accepted by PLD.
When the fire fighting helicopter reached the location (at 1742hrs)
the indicated area turned out to be far smaller than reported. The
affected area was 150 by 150 meters. The “fire under control”
message had not been sent but the fire was quite manageable due to
natural features of the area having a positive effect. The fire was
surrounded on three sides by areas of sand causing a natural break
and preventing the fire from spreading. There fire itself was quite
small but produced large quantities of smoke.
Main conclusions
• ‘Designated’ attack?
Ultimately the fire fighting helicopter was not used according the
original request. The fire fighting helicopter did not support the Fire
Brigade during the suppressive attack (the request: “to immediately
extinguish the seats of the fire”) but only during the damping down
phase. Therefore, it is still not clear what contribution can be made
or restrictions apply during forest/heath fires or how to slow down
or prevent ‘crown burning’. This was not a ‘designated’ attack within
the scope of the pilot project. Despite the fact that useful
information was gained.
• Effectiveness IFEX-system
It is difficult to make comment with regard to the effectiveness of
the IFEX-system during the damping down phase. According to the
PLD all applied shots were successful, which meant that they
reached the trees. However, this was refuted by the IC. He found
that the shots did not reach the trees sufficiently. It is questionable
however if the IC was able to draw this conclusion considering the
distance fire personnel had to remain during the attack. The
preferred attack strategy (applying two shots at the same time)
caused a lot of smoke and the PLD was unable to establish the
effectiveness of the shots.
20
EVALUATION OF FIRE FIGHTING HELICOPTER
• Communication
At the request of the regional control room, radio communication
took place via channel 7 instead of channel 10 (this is not in
accordance with the Operational tactics and procedures). Initially
this led to problems. It must be established in the first instance that
communications take place via channel 10 and only switched to
another channel later at the scene if necessary.
During the attack it became clear that the PLD and the fire service
worked with different geographical co-ordinates when referring to
the landing zone. The PLD used the geographic co-ordinates while
the fire service worked with the so called ‘RDM co-ordinates’9. This
explains why the Helicopter pilot could not find the landing zone in
first instance. This confusion led to a ten minutes delay.
• Landing zone
In the first instance it is the fire service who decides the landing
zone11. In general it is the fire service who are at the scene first (and
initiated the fire fighting helicopter project). However, it is the
Helicopter pilot who eventually decides whether the landing zone is
acceptable or not.
The attack at the Leusder Heath and the attack in Purmerend (see
attachment 2, section B.2.2.) have shown that it is hard for the fire
service to decide where the landing zone should be and to prepare
the zone for the helicopter to land. The fire service is not familiar
with the manoeuvrability of the helicopter and the amount of space
required. Consequently, the first landing zone identified by the fire
service was declined by the Helicopter pilot as it was deemed to be
too small and had insufficient space for take-off which could lead to
damage.
21
4.4 Fire in office building Ballast Nedam
On 3 May 2001 – a year after the attack at the Leusder Heath, a
request for the fire fighting helicopter was made by the Utrecht Fire
Brigade. It concerned a fire in a Ballast Nedam office building under
construction (approximately 7 floors, 60 meters high) at the
‘Liebosch’ industrial estate. The seat of the fire was located in the
technical area in an extension on the roof.
The fire crew and the IC have a different opinion with regard to the
status of the fire at the time of the request. According to the IC it
was a severe fire, while the fire crew stated that it was a minor fire
already under control. The crew commander managed to reach the
fire via the roof. According to the fire crew the fire service wanted
to use the fire fighting helicopter regardless of the need, to enable
tests to be undertaken.
Ultimately the fire fighting helicopter was not used. The pilot
decided against the use of the helicopter at this incident because of
the presence of high tower cranes and loose building materials close
to the scene.
Main conclusions
The decision not to use the fire fighting helicopter for safety
reasons was an easy one to make. The fire service was able to
extinguish the fire from the roof, making the use of the fire fighting
helicopter unnecessary, there was no emergency. However, this
raises the following question: would the risks have been acceptable
if the fire service had not been able to extinguish the fire themselves
via the roof? In such circumstances the risks for the fire fighting
helicopter would have been the same.
Main conclusions
There are two important conclusions to be drawn. Firstly, the
attack can not be classified as a ‘designated’ attack. The fire was
already extinguished at the time of the attack and the use of the fire
fighting helicopter was not urgent.
22
EVALUATION OF FIRE FIGHTING HELICOPTER
fighting helicopter, but instead the PLD had initiated its use. This
demonstrates that is not automatically the fire service who
considers the possibility of using the helicopter. On the other hand
it is questionable if this was a fire where the fire fighting helicopter
should have been used. It was not clear from the information gained
from the completed questionnaires whether the fire was difficult to
access.
However, the PLD initiated the use of the fire fighting helicopter. At
approximately 1645 hours the PLD “Operations” spotted a
substantial plume of smoke. After gathering information at the
control room of the ‘Kennemerland’ police the PLD offered
assistance with the heat helicopter and fire fighting helicopter. The
PLD decided to prepare the helicopters for take off in case they
were required by the fire service. Thirty minutes after arrival of the
IC (approximately at 1700 hours) a formal request was made for
assistance of the fire fighting helicopter and at 1705 hours the
helicopter was ready for take off from the air base.
Main conclusions
The circumstances present at this incident were not ideal for
achieving the optimum use of the IFEX-system. The location was
hard to access as it was in a high-rise building, but at the same time
the fire was very ‘exposed’ (see also section 4.2). This meant that a
successful attack was difficult to achieve.
• Communications/instructions
There was very little communication between the Helicopter crew
and the IC. The IC had asked the crew (via a police officer) to start
the attack at the northern side of the building and to move from
there towards the southern side. According to the Helicopter crew
they were forced to follow these instructions as the fire service is in
charge. The Helicopter crew suggested that they had not been able
to discuss the attack method with the IC initially, due to the fact
that communication with the IC had not been established. This was
not without risk. The wind direction at the time of the attack would
make the fire move towards the northern side of the building and
according to the Helicopter crew was “too strong for the tail”. The
IC was discontent about the way the Helicopter crew had carried
out his instructions and was of the opinion that they had not done
what was required.
23
It has previously been established that the Helicopter crew does not
need instructions from the IC during an attack (see section 4.1).
However, the IC must brief the Helicopter crew regarding strategy
before the attack commences. Although the fire service is in charge
it is important that this is discussed and agreed with Helicopter
crew. The attack strategy or the fire fighting tactics may be obvious
for Fire Officers but they might not be possible for the Helicopter
crew to achieve. In addition, it became clear during earlier attacks
that the Helicopter crew has a better view of the fire, particularly
when it is difficult to access for the fire service, and consequently is
better informed than the IC present.
To exploit the full potential of the helicopter, achieve optimum fire
fighting efficiency and discuss the risks involved simultaneously, good
communications between the IC and Helicopter crew is absolutely
essential.
It is clear from the video footage that the fire crew did not make
any attempt to extinguish the fire while the fire fighting helicopter
was present at the scene. The fire service was pre-occupied with
the preparations. This would have been a good opportunity to
establish the added value of the helicopter against the objectives of
the pilot project despite the fact that this was an open fire. In the
Operational tactics and procedures ‘providing assistance’ is intended
to mean that the fire fighting helicopter will stabilize the fire,
allowing the fire service to extinguish it fully. This is not explained in
more detail in the Operational tactics and procedures. However,
according to the PLD this implicit assumption was communicated to
the fire service during the instruction days (see also attachment 1,
section B.7).
24
EVALUATION OF FIRE FIGHTING HELICOPTER
The fire crew received the order to withdraw from the roof and
building with disbelief. It was against their natural instincts to let to
allow somebody else to do the job and to be on the sideline.
Consequently the withdrawal took 15 minutes.
• ‘Designated’ attack?
It has to be emphasized that for various reasons, whether or not
deliberately, the fire fighting helicopter was not used to its full
capability during the attack.
The Fire Officer eventually decided to let the fire fighting helicopter
depart as the down-wash caused the fire to spread to the store
below. The fire fighting helicopter did not make a positive
contribution towards extinguishing the fire.
25
north western side, a farm. The barn was surrounded by farmland
which was impassable because of standing crops.
There was a severe blaze in the barn and the direction of the wind
(southerly, later veering south westerly) increased the risk of fire
spread through flying sparks to the farm.
In the first instance four fire appliances and an aerial platform were
mobilized to the fire later assisted by a further four appliances.
According to the IC it was difficult to gain access, and there was a
lack of open water to re-supply the appliances. A request for the
fire fighting helicopter was made early in the evening.
It took a long time for the fire fighting helicopter to arrive at the
scene, more than an hour after the request was made, and by this
time there was no longer an acute situation. This emergency was
further reduced by the changing wind direction (south west)
meaning that the farm was no longer directly at risk. The barn
eventually burned down completely.
Main conclusions
• ‘Designated’ attack?
The attack did not meet the aim of the pilot project. When the fire
fighting helicopter arrived at the scene (more than an hour after the
request was made) a message had been sent that the fire was under
control. The helicopter could not assist the fire service during the
suppressive phase of the fire. It was not, therefore, a ‘designated’
attack.
Also, the metal roof of the barn had collapsed making it virtually
impossible for the fire fighting helicopter to reach the seat of the
fire. After four shots it was decided to cease the attack.
26
EVALUATION OF FIRE FIGHTING HELICOPTER
The fire service control room initiated the request for the fire
fighting helicopter 30 minutes after arrival of the IC, who was also in
charge during the incident in Oterleek.
After discussion with the IC five shots were applied into the
opening in the roof which largely extinguished the fire. Subsequently
the Fire Brigade was able to damp the fire down.
Main conclusions
• ‘Designated’ attack?
This was the first attack during the pilot project where the fire
fighting helicopter supported the fire service during the suppressive
phase of the fire at a location with difficult to access. Because of the
nature of the fire and the circumstances (i.e. fire in a confined space)
the IFEX-system was used to its optimum.
27
Firstly, the IC pointed out that the effect would have been the same
(although later) without the support of the fire fighting helicopter. If
there had been a risk of further fire spread the added value of the
fire fighting helicopter could have been better demonstrated.
Secondly, it was not the Senior Fire Officer on scene who thought
of making a request for the fire fighting helicopter but the control
room of the fire service. The IC, who had received instruction in
the use of the helicopter, of all people, should be aware of a
possible contribution of the fire fighting helicopter could make in
such circumstances.
• Request
The request has not been made according to the agreed operational
procedure on two points. This did not have a negative influence on
the attack.
Firstly, it was not the IC who made the request for the fire fighting
helicopter but the control room.
28
EVALUATION OF FIRE FIGHTING HELICOPTER
General remarks:
• The location was rather difficult to access because of the high
trees on the approach route.
• The weather conditions were favourable, there was a
light/moderate breeze.
• The area was evacuated.
• The local residents were involved in the preparations for the
attack by the fire service.
• A water intake had taken place before the start of the exercise.
• Technically the IFEX-system did not work to its optimum.
There were problems with the filling of the canons.
• The distance between the fire fighting helicopter and the
building was approximately 10 meters (all exercises).
• Additives were not used.
• There was no effect on the fire caused by the down-wash. The
smoke however was blown away by the down-wash.
Main conclusions
First exercise
The first fire was reported as a minor blaze. It took the fire fighting
helicopter two shots to extinguish the fire shortly after it was lit. It
has to be said that the IFEX-system did not work well. The time
span between the two shots was approximately one minute.
It should be emphasized that this was not a realistic situation.
Normally, the fire fighting helicopter would not be able to arrive at
the scene so quickly after the outbreak of fire. The fire had not yet
fully developed in this exercise.
In the evaluation, the IC pointed out that the fire service would
have been able to extinguish the fire immediately by normal means.
Second exercise
The second fire was also reported as a ‘small blaze’ on two sides of
the residence. This fire was more developed than the fire during the
first exercise. The fire fighting helicopter applied seven shots of
which four shots were successful. This meant that four shots were
under sufficient pressure and hit the seat of the fire. After the
29
successful shots the intensity of the flames decreased immediately.
However this was only a short-lived effect.
After seven shots it was decided to cease the attack as there was no
visible positive effect (caused by technical problems amongst
others).
The IC, as well as the Helicopter crew, were of the opinion that the
attack did not have the desired effect. It was the fire service who
eventually extinguished the fire with a 38mm low pressure hose line.
Third exercise
The third fire was also reported as a ‘small blaze’. The fire fighting
helicopter was only allowed to attack the fire after it was well
developed. The Helicopter crew tried to apply a shot at the back of
the building but this turned out to be impossible because of the
large quantities of smoke produced.
After two shots the fire was no longer showing on the outside of
the building. Seven shots out of ten were sufficiently powerful to
reach the seat of the fire. The fire visibly decreased in size where
the shots were applied. The attack was ceased after it became clear
that the fire fighting helicopter could not control the fire any
further.
The IC and the Helicopter crew regarded the last two attacks as
not particularly successful during the suppressive phase of the fire.
According to the crew this was probably due to technical faults in
the IFEX-system.
30
EVALUATION OF FIRE FIGHTING HELICOPTER
5 Technical evaluation
The PLD has carried out a technical evaluation of the fire fighting
helicopter in addition to the Nibra evaluation. The PLD evaluation is
described in this chapter.
It can be concluded from the above that the system has had
sufficient operational use to draw up a well-founded technical
evaluation. The following conclusions will mainly reflect the
technical results. This part of the report highlights operational
considerations that will be of important to the technical conclusion,
although opinions have been formed with regard to the actual use of
the canon.
• First cause
The installation’s computer generated very little information
regarding its status. This could be partially improved by providing
more intensive training during the use of the machine.
• Second cause
The design and the construction of the system does not reflect the
requirements for use on a helicopter. The level of vibration was
such that the following problems occurred in use:
31
o Detached couplings, low pressure air system (25 bar).
o Detached couplings, water filling system.
o Cracked couplings near the water canon selector.
o Cracked cable on the compressor.
o Aluminum suspension to the front of the installation cracked.
o The barrel locking mechanism caused recurring problems.
Compressor - installation
The choice of the compressor on the installation is also far from
perfect. The use of a combustion engine (petrol) that is not visible
to the pilot or crew, with no warning indicators, does not fit in the
current philosophy of aviation authority requirements. Furthermore,
the inefficiency of the compressor is such that fully charging the air
tanks (300 bars) takes approximately 45 min – 1 hour. The capacity
needed to keep the large water tanks under pressure was also
significant and, as a consequence, the pressure decreased rapidly
with every shot applied. Because of the decreasing pressure, arming
the canons becomes less efficient.
“Snorkelling”
From an operational point of view “snorkelling” might be desirable.
However, in practice this may not be feasible. The tanks have to be
entirely de-pressurized. In view of the fact that it will take a lot of
time to re-charge the entire system, it is uncertain whether
“snorkelling” and the use of a compressor adds any value. Perhaps,
changing or refilling the pressure cylinders while the fire service is
filling the water tanks could be a solution. This would also yield a
considerable reduction in weight.
Additives
The use of additives did not prove to be very effective. It was
reported that an additive suitable for the IFEX-system would be
developed, but this was never achieved. The use of the additive
32
EVALUATION OF FIRE FIGHTING HELICOPTER
Conclusion
Technically, the installation must be upgraded to be suitable for use
in an aviation environment. There are too many technical
deficiencies which adversely influence the usability of the fire fighting
helicopter. The installation requires high maintenance. This could be
reduced by adopting a higher standard of quality during
manufacture. Increasing the quality level could also have a positive
effect on the durability (and corrosion resistance) of the entire
system. This, in combination with an increased carrying capacity
could also improve the helicopter’s usability and effectiveness.
33
34
EVALUATION OF FIRE FIGHTING HELICOPTER
'Designated attacks'
During the pilot project period (3 April 2000 until 3 October 2001)
a total of seven requests were made for the fire fighting helicopter.
Six of them were actually responded to. In addition, the helicopter
was used four times shortly before the project began to support an
exercise (2 April 2000) and at a further three exercises (18
October 2001) after the project had finished. The four mentioned
attacks are also incorporated in this evaluation (see also chapter 4).
This means that there were ten attacks in total (from 7 requests)
and all evaluations were used for this report.
35
During the pilot project the fire fighting helicopter was mainly used
to provide assistance, which was not an objective of the pilot
project. On three occasions the fire fighting helicopter was used for
damping down, which was not an emergency situation. Examples are
the attacks in Purmerend, at the Leusder Heath and the dune fire in
Wijk aan Zee. The fire fighting helicopter has also been used in fire
situations where it was known that the extinguishing capacity of the
IFEX would not achieve its optimum effect. (see also paragraph
‘IFEX-system: the circumstances’). Examples are the attacks at the
Leusder Heath, the fire in the roof of the VNU building and the dune
fire in Wijk aan Zee amongst others.
The fire fighting helicopter was used for the fires mentioned above
as the steering committee, as well as the project group, wanted the
helicopter to be as accessible as possible. This would motivate the
fire service and add to the requests for the helicopter enabling
sufficient attacks to be carried and data gathered. Further to the
two first attacks in Purmerend and at the Leusder Heath it was
pointed out in newsletter no. 2 (July 2000) that “exceptionally the
fire fighting helicopter could be used for different attacks as well if
the PLD regarded the attack concerned as a useful experience”. The
PLD has always been flexible with regard to requests for the fire
fighting helicopter.
Conclusion
It has to be concluded that in many occasions that fire fighting
helicopter was used for fires where it was clear beforehand that
the helicopter could not contribute to the suppression of the fire.
On a few occasions the attack did not meet the objective of the
pilot project and/or the right circumstances necessary for the IFEX-
system. This was confirmed during the operations (see chapter 4,
evaluation per attack). Consequently, the attacks received a
negative assessment, not just from the Fire Brigade, who were
involved in the attack, but also by the media.
36
EVALUATION OF FIRE FIGHTING HELICOPTER
Excluding Inclusief
training/exercises training/exercises
Requests 7 7 (17)
Attacks 6 10
'Designated' attacks 1 5
Conclusion
It can be concluded that the number of ‘designated’ attacks carried
was insufficient to give a thorough opinion regarding the
possibilities of the fire fighting helicopter providing support during
fire fighting.
Useful information was gained from the pilot project to amend and
improve the Operational tactics and procedures (and therefore the
use of the fire fighting helicopter). However, this will only be
relevant if it is decided to continue using the fire fighting helicopter
by a second pilot project or by using the helicopter on a structural
basis. Sufficient information may then be gained from the evaluations
of each attack to improve the Operational tactics and procedures.
37
• the shots have to be applied at short intervals of only a ‘few’
seconds.
(See also attachment 1, section B.6).
It was assumed that the effective distance between the object and
the IFEX-system (see also Operational tactics and procedures) was
a maximum of 50 meters. The attacks during the pilot projects
made clear that under the current circumstances this was not
correct. The average distance during the attacks was approximately
10 – 15 meters from the target. Considerable capacity was needed
to keep pressure on the water tanks and this happened at the
expense of the shots, which became less powerful. Under these
conditions the fire fighting helicopter had to apply shots from less
than 15 meters from the target and needless to say, this was not
without risk.
Conclusion
The IFEX-system is an essential part of the fire fighting helicopter.
A correctly operating IFEX-system is necessary before one can
arrive at an objective opinion about the capabilities of the fire
fighting helicopter.
38
EVALUATION OF FIRE FIGHTING HELICOPTER
about value of the fire fighting helicopter when assisting during fires.
Even so, the pilot project has provided sufficient information to
come to a sound conclusion with regard to the added value of the
fire fighting helicopter when assisting during fire fighting in high-rise
buildings or locations which are difficult to access.
It is essential that the shots are powerful enough to reach the seat
of the fire (see also attachment 1, section B.6). The seat of the fire
has to be accessible and consequently should not be shielded by
obstacles. This was proved during the fire in the barn in Oterleek.
For an optimum extinguishing effect, the fire has to take place in a
confined space but where the seat of the fire is accessible. Clearly,
these conditions are contradictory and as a result not commonly
encountered.
Conclusion
For the pilot project to be successful the fire has to meet the
following three conditions:
• the fire has to be small
• in a confined space
• the seat of the fire has to be accessible.
It would be extremely rare for all of these conditions to be met at
the same time.
39
took place during the pilot project. The purpose of the interviews
was to examine, in broad terms, the fire service’s view of the
helicopter formed by factors including media coverage. After all it is
the fire service who would make use of the helicopter and their
view could influence the project and therefore its future use.
The Fire fighters, who were selected at random, had never made a
request for the fire fighting helicopter themselves. Only one
indicated that he once thought about making a request for the
helicopter but eventually had decided against it. All the others had
the opinion that no incidents under their command had occurred
where the fire fighting helicopter could have been of value.
(As a result of the attacks during the pilot project it became clear
that withdrawal was not only regarded by the fire personnel as
unnatural but in a few occasions, was also irresponsible (see
evaluation of the attack VNU building Hoofddorp). It proved to be
irresponsible to let the fire service cease their activities while they
were trying to stop the fire from spreading. This has not happened
on a few occasions and is against the Operational tactics and
procedures (for example during the attacks in Oterleek, Akersloot and
Hoofddorp). ‘Withdrawal of fire personnel’ will require serious
consideration if it is decided to use the helicopter for fighting
structural fires in future.)
Conclusion
The fire service was one of the key participants in the project. Not
only because the fire fighting helicopter is meant to assist the fire
service, but also because the fire service has to make a request for
the helicopter. It can be concluded that the fire service18 for
various reasons, had only a moderate enthusiasm for extinguishing
fires by helicopter. Although it would be hard to prove, it can be
assumed that the negative attitude had an influence on the
40
EVALUATION OF FIRE FIGHTING HELICOPTER
The latter is actually hardly surprising. Since 1735, when the ‘fire
hose and branch’ was invented, the fire service has focused on
attacking fires from inside the building (offensive fire fighting), little
has changed since then. The advent of motorized vehicles and
breathing apparatus did not cause a fundamental change. The
principle is still the same: enter, locate the seat of the fire and
extinguish20 . This implies that innovative methods of extinguishing
fires, like the helicopter, will not be easy to implement. Especially
when the fire service, in general, has no faith in the idea.
41
This contrasts with the education, training and exercises the crew
of the PLD received. No less than 14 pilots and 8 Operators (who
operated the IFEX-system during the attacks) of the PLD received
distinctive and substantial training (see also attachment B.5).
The PLD was very involved in the pilot project, not only during the
project but also during the preparatory time. The PLD got closely
involved from the inception of the idea for a new extinguishing
method (1998). Throughout the pilot project the PLD has been very
constructive and enthusiastic. A few Fire Officers pointed out that
they had a lot of admiration and respect for the knowledge of the
Helicopter crew. Not only because they were able to skilfully
manoeuvre the helicopter but also because of their knowledge with
regard to fire fighting. It can be concluded that the PLD has done
everything within their power to make this pilot project a success.
Conclusion
It can be concluded that the fire service has not made many
requests for the fire fighting helicopter during the pilot project. The
most obvious reasons were the limited training and education given
and the fact that using the fire fighting helicopter deviates from the
‘normal’ routine method of operation.
Down-wash
During most of the attacks (‘designated’ or not) the down-wash of
the helicopter had a negative effect on extinguishing the fire. The
down-wash is the wind caused by the rotors during flight. On some
occasions the fire did not only flare up again, but the down-wash
also made the fire spread through the building.
Safety aspects
This sub section will briefly go into the risks encountered during the
flights with the fire fighting helicopter. The safety risks with regard
to the IFEX-system only are pointed out in the technical evaluation.
• Single-engine helicopter
The IFEX-system was prepared and certified in Canada for only one
type of helicopter, the single-engine Ecureuil AS-350 B2 (see also
attachment B.5). However, the PLD expressed an opinion that
42
EVALUATION OF FIRE FIGHTING HELICOPTER
another type of helicopter would have been more suitable for safety
reasons, namely the twin-engine Bölkow Bo-105. At the time of the
pilot project the PLD had the twin-engine Bo-105 in its fleet and
therefore this option was considered first. The fact that this
helicopter is equipped with two engines means that it can operate
above residential areas. If one engine fails it will be possible to make
a safe landing with the remaining engine. At the start of the pilot
project the possibility of equipping the Bölkow with the IFEX-
system was considered. However, it emerged that flying the Bölkow
helicopter equipped with the IFEX-system would also have
disadvantages (see attachment 1, section B.6.1). Therefore, it was
decided to fly with the Ecureuil during the pilot project as the
limited number of operations meant that the risks were deemed
acceptable by the PLD. Sufficient evaluation data could be gained
from the pilot project to produce a conclusion about the value of
the system as a part of an (unspecified) helicopter.
It has been stated that this research is only introductory and further
work will be necessary to come to a well-founded conclusion with
regard to the danger of turbulence around buildings. To conclude
that operations during the pilot project were carried out
dangerously close to buildings based on existing research would be
43
premature. However, it can be concluded that the risks could be
reduced if the IFEX-system operated effectively at the specified
range of 50 meters.
Conclusion
Flying with the fire fighting helicopter during the pilot project was
not without risks and this cannot be eliminated in operations
involving structural fires. Therefore, the key question is; does the
value added by the fire fighting helicopter in this type of operation
outweigh the risk?
Recap
As already stated there have not been enough ‘designated’ attacks
to come to a well-founded opinion about the added value of the fire
fighting helicopter during fire fighting in situations described in the
objective of the pilot project.
However, it has been proved that the fire fighting helicopter in its
current form has not been able to add significantly to operations in
high-rise buildings or locations with poor access. This conclusion is
based on the facts gained from the pilot project. A number of
attacks have not been successful and on a few occasions the fire
service has been of the opinion that the outcome would have been
the same if they had taken care of the fire themselves. A number of
reasons are apparent:
• The down-wash had a negative effect on fire fighting
• The Helicopter crew had to deal with technical faults in the
extinguishing system
• The circumstances were not ideal for optimum performance of
the IFEX-system.
44
EVALUATION OF FIRE FIGHTING HELICOPTER
In addition, the evaluation points out that the senior Fire Officers
interviewed were not inclined to make use of the fire fighting
helicopter. For a variety of reasons, they expressed a limited degree
of enthusiasm and this could not be changed during the pilot
project. The method of using the fire fighting helicopter deviates
from the ‘conventional’ method of fighting fires. The attitude shown
by fire service officers will have to change if the fire fighting
helicopter is to become a normal method of operation. This might
be achieved by providing the fire service with better information
and a fire fighting helicopter with an efficient and reliable
extinguishing system. Training and exercises would be necessary to
enable fire commanders to become accustomed to the helicopter
and to consider its use when under pressure in a crisis situation,
confident that the alternative tactics employed would be effective.
45
46
EVALUATION OF FIRE FIGHTING HELICOPTER
BIJLAGEN
47
48
EVALUATION OF FIRE FIGHTING HELICOPTER
Attachment 1 Background
B.1 The extinguishing effect of water
The fundamental principle of fire fighting is based on eliminating one
or more of the three elements essential for a fire to exist namely:
fuel, oxygen and heat. This is known as the Triangle of Fire.
49
B.2 The IFEX-system and the helicopter
The helicopter has been used in the Netherlands for emergency
work since the 1950’s. From that time on the Search and Rescue
Units (SAR) of the Air Force mobilized their helicopters for rescue
operations at sea and also for transporting patients from the West
Fresian Islands to the mainland. Additionally, “Trauma helicopters”
are an integral part of the Dutch Health Care System used for
mobilizing specialized medical teams to the scene of accidents,
where they can provide care beyond the capabilities of ambulance
personnel. While it is not intended to use this system to transport
patients by helicopter, this can be achieved if necessary.
By chance, Steur met the Maarssen Fire Brigade’s Chief Fire Officer
and explained the concept of the fire fighting helicopter. From that
moment on, the idea had found a breeding ground in the
Netherlands as a result of an increasing number of high-rise
buildings. The fire fighting helicopter provided a possible means for
assisting fire fighting in such locations.
50
EVALUATION OF FIRE FIGHTING HELICOPTER
By the end of 1997 the Chief Fire Officer of the Maarssen Fire
Brigade had approached industry, the business world and the Air
Force to assist in making his idea a reality. However, they were not
interested. As the police and fire service co-operate at the scene of
an incident, the Chief Fire Officer approached the PLD and KLPD
with the same request. The PLD was willing to co-operate which
meant that the fire service would lead the project and the PLD
would lend support.
As a result of this visit to Canada the PLD stated that the idea of
using a fire fighting helicopter could be viable. The experimental
phase went on to prove that it was technically possible for the fire
fighting helicopter to become operational and the IFEX skid was
returned to its manufacturer in Germany. The PLD drew up a list of
alterations and improvements that needed to be carried out before
the start of the second phase.
51
sector (AMEV amongst others) and the RLD. A number of ‘training
targets’ were set on fire and these were attacked by the fire fighting
helicopter. This demonstration can be regarded as a success, despite
some technical faults concerning the pressure in the extinguishing
system.
In May 1998, preparations for the start of the pilot project were
made. The Mayor of Maarssen Chaired the Steering Committee.
This consisted of representatives of the Ministry of The Interior and
Kingdom Relations (BZK), CCRB, Nibra, AMEV and PLD. The
members were concerned that procedures were properly followed
in respect of finance and the preparation of contracts amongst
other issues. By the end of 1999 the participants, later than planned,
signed an agreement in which they formally declared their
commitment to take part in the project known as ‘Fire Fighting
Helicopter Netherlands’.
52
EVALUATION OF FIRE FIGHTING HELICOPTER
Training syllabus:
53
Fire Officers, based in the regions, gave training to a wider group of
ICs at various fire brigade locations, a total of 241 Fire Officers
received instruction.
In section B.3 it was explained that since the end of 1997, the PLD
was closely involved in the preparation of the pilot project. The PLD
did not only play an important role in this phase, but also made an
enormous commitment by offering its entire ‘flying platform’ for the
duration of the pilot project. This meant that the helicopter, pilots,
Operators and engineers for the maintenance of the IFEX-system
were all available on stand-by. This required a great deal of effort
and the PLD fulfilled a tremendously important role during the
entire project.
Despite the fact that the PLD only facilitated, no less than 14 pilots,
8 Operators (who operated the IFEX-system during an attack) and
engineers of the PLD underwent special, modular training. This
consisted of theoretical and practical parts all of which were
assessed.
54
EVALUATION OF FIRE FIGHTING HELICOPTER
During the pilot project the helicopter was based at Schiphol Airport.
This allowed the helicopter to arrive at the scene of an incident in
the Randstad between 10-30 minutes30 after take-off. The Ecureuil
AS-350 B2 received an exemption for the duration of the pilot
project allowing it to operate at lower levels and closer to
residential areas if necessary to enable training or an actual
extinguishing attack.
55
A water tank can contain a maximum of 155 litres of water and
each canon has a capacity of 18 litres (18 litres of water will be
released per shot). The compressed air cylinder is charged to a
pressure of 300 bars and this enables an operating pressure in the
canon of 25 bars. According to the specifications the maximum total
weight (without external load) of the installation is 280 kg.
During an attack the Operator can direct the shots using a colour
camera/monitor and the system is actuated by an automatic firing
mechanism. The canons can be depressed to a maximum of 90o.
When the Operator activates the system, by pulling the trigger, the
water will leave the canon at a velocity of approximately 120 meters
per second. The shot of water will reach the seat of the fire with
56
EVALUATION OF FIRE FIGHTING HELICOPTER
One shot of water (18 litres) has a cooling surface of 1,000 square
meters and creates a ‘steam blanket’ of approximately 1,700 litres.
The steam interrupts the oxygen supply and consequently the fire
will smother the fire (see also section B.1). The next shot should be
applied when the ‘steam blanket’ has evaporated, which will take a
few seconds. The system specification suggests that the canon can
be refilled in 6-7 seconds32 and the maximum effective range is 50
metres33.
A critical part of the operating theory is that the shot has to reach
the seat of the fire. If this is not achieved the system will not be
effective. In practice, this is difficult and will be challenging for an
Operator in a fire fighting helicopter, trying to reach the seat of the
fire via an open window in a high-rise building (an objective of the
pilot project).
An important point to note is that the penetrating ability of the heli-
IFEX-system is almost non-existent. After the open fire is damped
down the seat will continue to smoulder at a high temperature,
water applied at this stage will immediately be converted into steam.
The heli-IFEX-system will hardly have any effect34 at this point as the
water particles will be converted directly into steam and cooling of
the seat itself will not take place. A solid jet will be required to
penetrate the core. In theory this means that the fire fighting
helicopter will only be able to bring the fire under control, but the
fire service, using a solid jet, will have to finally extinguish the fire.
The fire fighting helicopter will therefore only be used for support
(as outlined in the objective of the pilot project).
Configuration
Apart from the fixed weight of the IFEX-system and the two crew,
more weight can be added in terms of water, additives and fuel. It
was decided to opt for the following configuration:
• 50% fuel (as it is harder to obtain fuel than water) 216 kg Jet A1
kerosene.
• 200 litres of water (100 litres of water per tank – both tanks
half full). Each shot will take 18 litres of water so effectively 10
shots can be applied (during re/filling approximately 20 litres of
water will be wasted). After 10 shots the amount of fuel will be
reduced significantly. This means that the canons can be refilled
up to 100% in most cases.
• 25% litres of additive, carried in 2 containers.
This configuration was later amended. It turned out that the fire
service did not require any additives (see section 4.2) and the IFEX-
skid was 70 kg heavier than the certificate of airworthiness
indicated. Therefore it was decided not to carry additives. Also, the
percentage of fuel was reduced to 45% and the amount of water to
180 litres.
57
B.7 The Operational tactics and procedures
During one of the demonstrations the operational and strategic
tactics were designed and agreed. The operational and strategic
tactics will be outlined below to provide an understanding of the use
of the fire fighting helicopter.
1 Aim
The aim of the fire fighting helicopter is to support the (regional)
fire services in the Netherlands during fire fighting in high-rise
buildings and on locations where access is difficult.
2 Availability
The duration of the pilot project was 18 months (3 April 2000 – 3
October 2001) or 15 attacks. In principle the fire fighting helicopter
was available for 7 days per week with the following restrictions.
• Initially the fire fighting helicopter was only available during
daylight.
• One helicopter was available during the pilot project.
• Weather circumstances can affect the ability to deploy. The
PLD makes the final decision.
• Based on availability and on the priorities of the PLD.
58
EVALUATION OF FIRE FIGHTING HELICOPTER
For an effective and safe use of the fire fighting helicopter the
trained IC has to be able to establish that:
• the burning object is reachable within a radius of 50 meters, the
maximum distance for the effective use of the water canon
• there is no substantial risk of explosion
• there is no danger of hazardous emissions when the fire has to
be approached by the fire fighting helicopter in to wind.
59
OPS notifies the Helicopter pilot and the Operator during their
daily briefing that operations for the fire service can be carried out.
60
EVALUATION OF FIRE FIGHTING HELICOPTER
12 Evaluation
• Each attack carried out by the fire fighting helicopter will be
evaluated. For this purpose the trained IC, the Helicopter pilot
and Operator will complete an evaluation form directly after the
operation. Completed forms have to be sent to Nibra. If
necessary Nibra will approach the people involved for an
interview.
• In the light of the evaluation report, the PLD Chief of
‘Helicopter’ Operations will personally debrief the PLD-
personnel.
• The evaluation report may lead to an amendment of procedures
during the trial period.
61
62
EVALUATION OF FIRE FIGHTING HELICOPTER
63
(Continuation of training on the ‘Spiegelplas’ at Nederhorst den Berg)
Effect of the helicopter The fire flared up again mainly caused by the down-wash of
on the fire the helicopter.
Reason for withdrawal Water supply had been used and the down-wash caused
helicopter the stern mooring to snap. This made the yacht turn and
extinguishing the fire became almost impossible
View of the Fire Brigade After the training Nibra researchers asked a number of
on the attack fire fighters involved for their opinion on the attack. In
general the Brigade found it quite incomprehensible that
the fire fighting helicopter had not been able to extinguish
a minor fire. It was agreed that the fire fighting helicopter
could be useful for cooling purposes. The helicopter will
never be able to extinguish the fire.
View PLD on the attack The fire diminished as a result of the attack. There were
also a few restrictions/limitations:
• The loading speed of the canons was too slow and
the loading time therefore too long
• The reach was too small (9 metres) caused by the
low pressure in the system
• Balance between fuel (endurance/weight) and the
water supply was a restriction
B.2.2 Test attack during fire in a paper warehouse, Purmerend, 12 May 2000
Attack No ‘designated’ attack
The circumstances did not meet the criteria of the pilot
project: there was no open fire (no emergency). The
attack has to be regarded as an experiment requested by
Fire Brigade.
Reason for request The Fire Brigade wanted to test the penetrating ability of
the IFEX canon on a thick layer of smouldering paper.
The PLD wanted to check the Operational tactics and
procedures during a practical exercise.
Time of arrival of IC at A second IC was employed for the attack with the
the scene of the incident helicopter
Time helicopter 0640 hrs
requested by IC
Status of fire at the time Fire under control
the request was made
Time helicopter took off 0821 hrs
from Schiphol Airport
Time of arrival at the 0830 hrs
scene – helicopter
Time of departure from 0949 hrs
the scene – helicopter
Status of the fire at the Smouldering fire in paper mass after a fire in a warehouse.
time the helicopter Message ‘Fire under control’ was sent
carried out the attack
Weather circumstances Light cloud, no precipitation and bright. Wind speed 10
knots (18 km/ph)
Attack strategy Shots were only applied from one position (at the top,
from the side, in one corner of the paper mass). The shots
were applied from hover position
Distance between 5 – 10 meters
helicopter and object(s)
Number of applied shots • Two with pure water
(according to the • Two with additives (Coldfire)
Operator) • Two double shots (Coldfire)
64
EVALUATION OF FIRE FIGHTING HELICOPTER
65
(Continuation of forest/heath fire at the Leusder Heath)
Time of departure from 1850 hrs
the scene – helicopter
Status of the fire at the Large forest/heath fire with various seats. It was reported
time the helicopter to the PLD that the surface concerned was one square
carried out the attack kilometer.
Weather circumstances Clear with a with speed of 10 knots (18 km/ph)
Attack strategy The IC was picked up at the scene of the incident to make
a reconnaissance flight in the effected area (this took 5
minutes). It was decided that the helicopter would keep
tree tops wet as a preventive measure (this took
approximately 15 minutes in total). Two attack methods
were applied: hovering and slowly taxiing above the trees
Distance between Hover: 10 meters
helicopter and object(s) Slow taxi speed: 5 – 10 meters
Number of applied shots 12 shots which included ‘runs’. That is to say that two
(according to the shots were applied rapidly after each other
Operator)
Number of successful 12 shots (that is to say the shots hit the top of the trees)
shots (according to the
Operator)
Intervals between the Two shots were applied rapidly after each other and the
shots interval between the 1st and 2nd shot was 5 - 10 seconds,
between the 2nd and 3rd shot 20 – 30 seconds, etc.
Landing (zone) Three landings were made: to pick up and take back the IC
and one for water intake. In the first instance the landing
zone was allocated by the Fire Brigade at the edge of the
heath. This caused the following difficulties:
• The fire service and PLD worked with different co-
ordinates (respectively the ‘RDM’ co-ordinates35and
geographical co-ordinates) which made it hard for the
Helicopter pilot to find the location. This caused a
delay of approximately 10 minutes
• The fire fighting helicopter was not able to touch
down as there were too many trees in the
surrounding area
66
EVALUATION OF FIRE FIGHTING HELICOPTER
67
(Continuation of dune fire near Wijk aan Zee)
Number of successful 5 (the amount of smoke created by the initial down-wash,
shots (according to the visibly decreased)
Operator)
Intervals between the 30 seconds
shots
Landing (zone) The helicopter landed for discussions with the IC. This
took place without any difficulties
Water intake n.a.
Communication between Before fire fighting there was a brief discussion. This was
IC and the Helicopter sufficient considering the agreed attack strategy
crew
Effect of the IFEX-system The smoke decreased visibly
on the fire
Effect of the helicopter The smoke increased caused by the down-wash
on the fire
Reason for withdrawal This was agreed before the attack
helicopter
View of the Fire Brigade -
on the attack
View PLD on the attack -
B.2.5 Attack on the fire at the VNU building in Hoofddorp – 9 July 2001
Attack Real attack, but not ‘designated’ (see attachment 5.6)
Reason for request The fire on the roof was hard to access
Time of arrival IC at the 1630 hrs
scene of the incident
Time helicopter 1700 hrs (at 1645hrs the PLD initiated preparations to get
requested by IC everything ready for the helicopter to take off)
Time helicopter took off 1705 hrs
from Schiphol Airport
Time of arrival at the 1708 hrs
scene – helicopter
Time of departure from 1800 hrs
the scene – helicopter
Status of the fire at the Severe blaze (according to the report of the fire service36)
time the helicopter
carried out the attack
Weather circumstances No significant cloud, no precipitation and good light. Wind
speed is unknown but there was a strong wind. The
buildings nearby caused a lot of mechanical turbulence.
Attack strategy At the request of the IC the attack was started at the
northern side of the building and moved from there
towards the southern side.
Distance between 10 – 15 meters
helicopter and object(s)
Number of applied shots 8 – 10
(according to the The first shot was applied at 1749hrs. The IC needed 25
Operator) minutes to decided whether the use of the helicopter was
actually necessary. After that, it took at least another 15
minutes for withdrawal of the fire service personnel and
other emergency services personnel.
Number of successful All shots were fairly powerful with an extinguishing effect
shots (according to the
Operator)
Intervals between the 30 – 45 seconds
shots
Landing (zone) No landing was been made
68
EVALUATION OF FIRE FIGHTING HELICOPTER
Helicopter crew:
The communication via channel 10 was difficult during the
initial alarm37 phase and during the fire fighting. The
communication improved when switched over to the
control room of the police. The direction by the IC was
minimal. It was indicated when (1749hrs) and how
(northern side) the helicopter could start with its
operation and when it had to cease again.
Effect of the IFEX-system Where the shots were applied the fire extinguished
on the fire reduced but flared up again shortly after
Effect of the helicopter The down-wash of the helicopter caused the fire to spread
on the fire through wall cavities to the stores below
Reason for withdrawal • The negative effect of the down-wash (caused the fire
helicopter to spread through wall cavities to the stores below)
• Successful result had not been achieved
View of the Fire Brigade • The helicopter had a negative influence on the fire:
on the attack the fire flared up again and spread to the store below
• The final result was nil benefit
• The actual attacks of the helicopter took too much
time
View PLD on the attack • According to the PLD the northern side
(leeward/sheltered side) was not a good place to start
the attack. The wind would just make the fire spread
fire in that direction. Nevertheless the PLD reported
to have acted upon the advice of the IC
• The use of an additive had a positive effect
• As the helicopter was used unnecessary the attack
did not result in a positive contribution
69
(Continuation of fire in barn, Oterleek)
Weather circumstances A beautiful summer evening
Wind force 3 – 4
Attack strategy Unknown
Distance between 10 – 15 meters
helicopter and object(s)
Number of applied shots 4
(according to the
Operator)
Number of successful 0 (that is to say that the shots did not reach the seat of
shots (according to the the fire as the metal roof was collapsed but mainly still
Operator) intact)
Intervals between the 1 minute
shots
Landing (zone) The helicopter touched down as the Helicopter crew had
to discuss the strategy.
Water intake n.a.
Instruction and It was reported that the communication during the attack
communication between was satisfactory
IC and the Helicopter
crew
Effect of the IFEX-system Nill
on the fire
Effect of the helicopter The down-wash caused a lot of small burning particles in
on the fire the air which increased the risk of fire spread and also re-
ignition.
Reason for withdrawal
helicopter It was not possible for the helicopter to extinguish the fire
and was also not assisting.
View of the Fire Brigade • It took long before the helicopter arrived
on the attack • The attack was perfect/excellent. This type of fire is
less suitable for extinguishing by a helicopter
equipped with an IFEX-system
• There was a lot of respect for the expertise and skills
of the Helicopter crew
View PLD on the attack • The extinguishing operation had no effect at all on the
fire.
70
EVALUATION OF FIRE FIGHTING HELICOPTER
1. IC and the control 1. As the control room initiated the request for the fire
room fighting helicopter the communication was in first
instance not clear
2. Communications went well. As the IC gave a few
2. IC and Helicopter correcting instructions after the first shot the
crew following shots were direct hits
Effect of the IFEX-system The flames were largely extinguished
on the fire
Effect of the helicopter By the chosen attack strategy (taxiing) there was hardly
on the fire any negative influence caused by the down-wash
Reason for withdrawal • The flames were largely extinguished
helicopter • Dusk falling
View of the Fire Brigade • The helicopter arrived fairly quickly at the scene
on the attack (compared with the attack on 3 August)
• The attack could not have been better. However, it
was pointed out that the attack would have been
more effective if extinguished via the hole in the
outer wall instead of from above
• Without the use of the helicopter the same result
would have been achieved, although more slowly
• The fire service were complimentary about the
expertise and the skills of the Helicopter crew
View PLD on the attack • For a better result the request should have been
made earlier
71
72
EVALUATION OF FIRE FIGHTING HELICOPTER
Attachment 3 Participants
In this attachment, an overview is given of the organizations who
made an important contribution to the project ‘Fire fighting
helicopter in the Netherlands.’
The Royal Navy Training Institute made the facilities at the School
of the NBCD, in Den Helder, available for further training in the use
of the fire fighting helicopter and additional instruction for Fire
Officers.
73
agreement, took responsibility for creating a positive image within
the regional fire brigades.
74
EVALUATION OF FIRE FIGHTING HELICOPTER
75
76
EVALUATION OF FIRE FIGHTING HELICOPTER
Footnotes
1
In this evaluation report this combination will be called ‘fire fighting
helicopter’
2
See attachment 1, section B.6
3
This is also based on the fact that the penetrating ability of the IFEX-
system is very limited. To extinguish the glowing seat of a fire (the flames
are almost out) a powerful solid jet is required. When the fire fighting
helicopter has stabilized the fire, the fire service will always have to damp
down (with a solid jet). The fire fighting helicopter can only be used to
assist during fire fighting operations (see also attachment 1, section B.6).
4
The Flight Commander of the PLD decides whether a request from the
fire service to use the helicopter can be accepted or not (see Operational
tactics and procedures, attachment 1, section B.7).
5
The questionnaires were completed under supervision of the Flight
Commander.
6
The reason was that the fire fighting helicopter had to be available within
the agreed response time.
7
In Canada the so-called heli-IFEX-system was adapted for only one type of
helicopter, the one-engine Ecureuil AS-350 B2. To fly with a single-engine
aircraft is not entirely without risk. A different type of helicopter would be
more suitable, namely the twin-engine Bölkow Bo-105. The fact that this
helicopter has two engines means that it can operate with less risk over
residential areas. For the pilot project the capabilities of the Bölkow were
considered equipped with IFEX-system. However, to fly with the Bölkow
equipped with the IFEX-system would have had various disadvantages
(compared with the Ecureuil, see attachment 1, section B.6.2). Eventually it
was decided to use the Ecureuil during the pilot project. The reduction of
risk was mainly achieved by a number of safeguards:
• A flight was only permitted for an actual (or expected) IFEX-attack
over built-up/residential areas. It was not allowed to prolong the
attack if this was not necessary.
• No more than 15 attacks will be carried out during the entire trial
period.
• The approach route had to be chosen so that the risks were reduced
to an absolute minimum.
8
The effect of the down-wash on a fire in a confined space is very limited.
Restriction of the down-wash can also be achieved by approaching the fire
at ‘slow taxi speed’ (see also section 4.1).
9
The system ‘Rijks Driehoeks Meting (RDM)’ (co-ordinate system) is only
applicable in the Netherlands. The ‘RDM grid’ is also known as ‘TOP grid’.
The ‘TOP grid’ is very simple to use and therefore the disaster relief
organization in the Netherlands decided to use this system.
10
It has to be stressed that this information is extracted from the
questionnaire completed by the IC. The PLD pointed out that the attack
was evaluated with the fire service. The fact that the PLD ignored the IC’s
instruction/directions was not discussed according to the PLD.
77
11
The method required for the fire service to create a landing zone is not
explained in the Operational tactics and procedures. However, this did
come up during the training session for the fire service (see attachment 1,
section B.5). It was pointed out that a landing zone has to be at least 25 by
25 meters, free from obstacles, emergency workers and other people and
also the landing zone has to be cordoned.
12
The PLD reported that it was a moderate fire.
13
In first instance the exercises would take place on 13 September but as a
mark of respect after the terrorist attacks in the USA on 11 September the
exercises were postponed to 18 October.
14
In the Bijlmermeer a large number of flats were due to be demolished to
improve the area and to create more variation between high-rise and low-
rise buildings. It is hoped that this will improve the living environment. The
housing association was prepared to provide one of the blocks of flats (due
for demolition) for exercise purposes.
15
As a consequence the evaluation forms completed by the people
involved were very brief.
16
This is also based on the fact that the penetrating ability of the IFEX-
system is very limited. To extinguish the glowing seat of a fire
(of which the flames are mainly put out) a powerful, solid jet is required.
When the fire fighting helicopter has stabilized the fire, the fire service will
always have to damp down (with a solid jet). The fire fighting helicopter
can only be used to assist during an fire fighting operation.
17
The training and exercises are not included in the requests.
18
Based on the interviews held.
19
Crew Commanders and IC’s are intended here.
20
Extracted from: “En steekende de Spuitpyp door de deur” by E. Oomes
(Nibra essay prize 1999).
21
One of the main pieces of research in this field is the theory of the
‘Recognition-Primed Decisions (RPD), developed by R. Klein. Klein has
done research from 1985 onwards to investigate the way professionals
take decisions in stressful situations and under time pressure.
22
This philosophy was implemented in the ‘Leidraad Oefenen’ (training
guide) for the fire service.
23
However, the Fire Officers were kept informed on a regular basis during
the pilot project via news letters.
24
According to the manufacturer: “the smaller the size of the water
droplets, the greater their absorption capacity.”
25
According to the manufacturer: “the higher the droplet velocity, the
greater the amount of water that reaches the base of the fire.”
26
The Cougar and the Chinook.
78
EVALUATION OF FIRE FIGHTING HELICOPTER
27
They were: the Chief Pilot -Helicopters, a Quality Insurance Inspector
(specialized in aviation techniques) and a maintenance/operational
Helicopter pilot.
28
For example the ‘load factor’, knowledge of the system, description of
the system, safety criteria with regard to the pressure cylinders that are
part of the IFEX-system (for example decreasing the air pressure in case of
a crash).
29
To use the helicopter in combination with the IFEX-skid an ‘optional’
certificate was required. The Canadian Aviation Authority provided a
temporary certificate. At that time they were trying to obtain a full
‘Supplementary Type Certificate’ (a certificate of airworthiness).
30
During the trial period the IFEX-system was mounted under the
helicopter and was therefore operationally available on stand by.
31
The mist particles shot from a distance of 4 metres will be approximately
100 microns, those shot from 6 metres will be 5 microns in size (research
The Fire Research Station in London).
32
The attacks proved that this was not feasible.
33
The attacks proved that the effective distance is not presently 50 meters,
but somewhere in the region of 10 to 15 meters.
34
This was also confirmed after the attack in Purmerend.
35
RDM co-ordinates = ’Rijks Driehoeks Meting – grid (only applicable in
the Netherlands).
36
The PLD reported a moderate fire. Considering the equipment used by
the fire service (2 appliances and an aerial platform) this suggests a
moderate fire.
37
During alarming, mobilization and take off, all happened at the same time,
the PLD tried to contact the IC. This proved to be difficult.
38
According to the PLD’s report this was ‘approximately 2110 hrs – 2115
hrs).
79