Carpentry Framing Skills Guide
Carpentry Framing Skills Guide
Sector: CONSTRUCTION
Qualification Title: CARPENTRY NC II
Unit of Competency: INSTALL FRAMING WORKS
Module Title: INSTALLING FRAMING WORKS
Technical Education and Skills Development Authority
Jacobo Z. Gonzales Memorial School of Arts and
Trades San Antonio, Biñan City
Remember to:
Work through all the information and complete the activities in each section.
Read information sheets and complete the self-check. Suggested references
are included to supplement the materials provided in this module.
Most probably your trainer will also be your supervisor or manager. He/she is
there to support you and show you the correct way to do things.
You will be given plenty of opportunity to ask questions and practice on the
job. Make sure you practice your new skills during regular work shifts. This way you
will improve both your speed and memory and also your confidence.
Use the Self-checks, Operation Sheets or Job Sheets at the end of each
section to test your own progress.
When you feel confident that you have had sufficient practice, ask your
Trainer to evaluate you. The results of your assessment will be recorded in your
Progress Chart and Accomplishment Chart.
UNIT OF COMPETENCY : INSTALL FRAMING WORKS
PREREQUISITE :
CONTENTS:
Characteristics of common Philippine Lumber
Material Specifications
Types and Parts of a Frame Constructions
ASSESSMENT CRITERIA
1. Plans and details are correctly interpreted according to job requirements
2. Appropriate materials, tools and equipment are selected and prepared
consistent with job requirements
3. Materials are re-checked and properly staged according to job requirements
4. Defective materials are reported to immediate supervisor following standard
operating procedures
5. Unexpected situations are responded to in line with work place requirement
6. Housekeeping is performed according to safety regulations
7. Appropriate PPE is selected according to job requirements
CONDITIONS:
You must be provided with the following:
1. WORKPLACE LOCATION • Personal Protective
2. TOOLS AND EQUIPMENT Equipment
Claw Hammer • Portable Circular Saw
Pencil/Marking pen • Plan and working drawings
Pull-Push Rule • Lumber
Nylon String • Nails
Steel Square • Plywood
Try-square
Hand Saw
Chalk Line
Manuals
3. TRAINING MATERIALS Related References
Leaning Packages
Bond paper
Ball pens
ASSESSMENT METHOD
Portfolio
Learning Experience
PREPARE APPROPRIATE MATERIALS, TOOLS AND EQUIPMENT FOR
INSTALLING FRAMING WORKS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the TYPES and
CHARACTERISTICS of COMMON PHILIPPINE LUMBER
DUNGON
GUIJO
IPIL
KATMON
LANITE
MAYAPIS
MOLAVE
RED LAUAN
TANGUILE
YAKAL
2. 2. 2.
3. 3. 3.
4.
ANSWER KEY 5.1-1
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the TYPES,
STANDARD SIZES, and USES of LUMBER for CONSTRUCTION CARPENTRY.
A. Lumber
Lumber varies greatly in structural characteristics. A carpenter must learn
about lumber so that he can choose the most suitable material for each job.
1. Grades
Lumber, as it comes from the sawmill, is divided into three main classes: yard
lumber, structural material and factory and shop lumber. It is classified on the
basis of quality. The carpenter must choose a quality that is suitable for the intended
purpose. At the same time, he must exercise economy by not choosing a better (and
therefore more expensive) grade than is required.
Lumber is subdivided into classifications of select lumber and common
lumber.
Select Lumber - Select lumber is of good appearance and finishing. It is
identified by the following grade names for comparison of quality:
o Grade A is suitable for natural finishes and is practically clear.
o Grade B is suitable for natural finishes, is of high quality, and is generally
clear.
o Grade C is suitable for high-quality paint finishes.
o Grade D is suitable for paint finishes between high-finishing grades and
common grades and has somewhat the nature of both.
Common Lumber - Common lumber is suitable for general construction and
utility purposes. It is identified by the following grade names for comparison of
quality:
o No. 1 common is suitable for use without waste, it is sound and tight
knotted, and it may be considered watertight lumber.
o No. 2 common is less restricted in quality than No. 1, but of the same
general quality. It is used for framing, sheathing, and other structural forms
where the stress or strain is not too great.
o No. 3 common permits some waste, and it is lower in quality than No. 2. It
is used for such rough work as footing, guardrails, and rough flooring.
2. Uses of Lumber
a. Frames. Building frames are the wood forms constructed to support the
finished members of a structure. These include posts, girders (beams), scabs,
joists, subfloors, sole plates, girts, knee braces, top plates, and rafters. No. 2
common lumber is used for framing. Heavy frame components, such as
beams and girders, are made by combining several pieces of framing
material.
b. Walls. The exterior wall of a frame structure usually has three layers:
sheathing, building paper, and siding. Sheathing and siding lumber are
normally grade No. 2 common softwood, which is with solid knots, no voids.
Siding is either vertically or horizontally applied. Theater construction may limit
available material to lap siding for both horizontal and vertical surfaces. For
local procurement, there are several types of drop and bevel siding, which is
applied horizontally.
3. Sizes
Lumber is usually sawed into standard dimensions (length, width, and
thickness). This allows uniformity in planning structures and in ordering materials.
Table 1 lists the common widths and thicknesses of wood in rough and in dressed
dimensions in the US. Standards have been established for dimension differences
between the quoted size of lumber and its standard sizes when dressed.
Quoted size refers to dimensions prior to surfacing. These dimension
differences must be taken into consideration. A good example of the dimension
difference is the common 2 x 4. As shown in Table 1, the familiar quoted size 2 x 4 is
the rough or nominal dimension, but the actual dressed size is 1 1/2 x 3 1/2 inches.
Lumber is sawn in standard sizes used for light framing.
Thickness: 1, 2, and 4 inches.
Width: 2, 4, 6, 8, 10, and 12 inches.
Length: 8, 10, 12, 14, 16, 18, and 20 feet.
The actual dimensions of dressed lumber are less than the sewn dimensions
because of drying and planing (or finishing). For the relative difference between
sewn (standard or nominal) dimensions and actual sizes of construction lumber, see
Table 2-1.
MULTIPLE CHOICE: Read the statement carefully. Choose the letter of the correct
answer. Write the letter of your choice on the space provided.
ANSWER KEY 5.1-2
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
1.
INFORMATION SHEET NO. 5.1-3
TYPES AND PARTS OF FRAME CONSTRUCTION
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the Different
TYPES and PARTS A OF FRAME CONSTRUCTION
PLATFORM FRAME
In platform-frame construction, first
floor joists are completely covered with
sub-flooring to form a platform upon
which exterior walls and interior partitions
are erected. This is the type of
construction most generally used in home
building. Platform construction is easy to
erect. It provides a work surface at each
floor level and is readily adapted to
various methods of prefabrication. In
platform systems it is common practice to
assemble wall framing on the floor and tilt
the entire unit into place.
BALLOON FRAME
In balloon-frame construction,
exterior wall studs continue through
the first and second stories. First floor
joists and exterior wall studs both bear
on the anchored sill. Second-floor
joists bear on a minimum 1x4-inch
ribbon strip, which has been let-in to
the inside edges of exterior wall studs.
COMBINATION FRAME
A modification of the old
braced frame which was of heavy
timbers with every joint mortised
and tenoned. The modification
consists of lighter timbers and
less mortising and pinning to save
material and labor.
MULTIPLE CHOICE: Read the statement carefully. Choose the letter of the correct
answer. Write the letter of your choice on the space provided.
ANSWER KEY 5.1-3
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
2.
LEARNING OUTCOME NO. 2 Lay-out/erect and assemble post and
girts
CONTENTS:
Post
Girts and Girders
Load Conditions and Structural System Response
ASSESSMENT CRITERIA
1. Posts and girts are laid-out, marked and cut according to working drawings
and specifications with tolerance of 3mm on all measurements,
plumbness, and levelness
2. Posts are erected vertically based on plans and specifications with
tolerance of + 3mm on all measurements
3. Girts and girders are attached to the posts horizontally according to plans
and specifications
4. Unexpected situations are responded to in line with work place requirement
5. Housekeeping is performed according to safety regulations
6. Appropriate PPE is used according to job requirements
CONDITIONS:
You must be provided with the following:
1. WORKPLACE LOCATION • Personal Protective
2. TOOLS AND EQUIPMENT Equipment
Claw Hammer • Portable Circular Saw
Pencil/Marking pen • Plan and working drawings
Pull-Push Rule • Lumber
Nylon String • Nails
Steel Square • Plywood
Try-square
Hand Saw
Chalk Line
Manuals
3. TRAINING MATERIALS Related References
Leaning Packages
Bond paper
Ball pens
ASSESSMENT METHOD
Portfolio
Learning Experience
LAY-OUT/ERECT AND ASSEMBLE POST AND GIRTS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the TYPES OF
WOOD POST and METHODS OF PLUMBING POST.
Wood posts may be solid, built-up, or spaced. In selecting a wood post, the
following should be considered: lumber species, structural grade, modulus of
elasticity, and allowable compressive, bending and shear stress value permitted for
the intended use. In addition, attention must be paid to the precise loading conditions
and the types of connections used.
Wood posts are loaded axially in compression. Failure can result in crushing
of wood fibers if the maximum unit stress exceeds the allowable unit stress in
compression parallel to the grain. The load capacity of the post is also determined by
its slenderness ratio. As the slenderness ratio of a post increases, a post can fail
from buckling.
After the corner post, T-post, and intermediate wall studs have been nailed to
the plates or girts, the walls must be plumbed and straightened so that the
permanent braces and rafters may be installed. This is done by using a level or
plumb bob and a chalkline.
Plumbing Posts
There are two methods for plumbing posts.
Method 1: To plumb a corner with a plumb bob
1. To plumb a corner with a plumb bob, first attach to the bob a string long
enough to extend to or below the bottom of the post.
2. Lay a rule on top of the post so that 2 inches of the rule extends over the
post on the side to be plumbed.
3. Then hang the bob-line over the rule so that the line is 2 inches from the
post and extends to the bottom of it.
4. With another rule, measure the distance from the post to the center of the line
at the bottom of the post; if it does not measure 2 inches, the post is not
plumb.
5. Move the post
inward or outward
until distance from
the post to the
center of the line is
exactly 2 inches.
Then nail the
temporarily brace
in place.
6. Repeat this
procedure to the
other face of the
post. The post is
then plum. This
process is carried
out to the
remaining post of
the building.
Method 2: An alternate method of plumbing a post
1. Attach the string of the plumb bob securely at the top of the post to be
plumbed, making sure that the string is long enough to allow the plumb bob to
hung near the bottom of the post.
2. Use two blocks of wood identical in thickness as gage blocks.
3. Tack one block near the top of the post between the plumb bob string and the
post (gage block No. 1).
4. Inserting the second block between the plumb bob string and the bottom of
the post (gage block No. 2) .
5. If the entire face of the second block makes contact with the string, the post is
plumb.
SELF- CHECK NO. 5.2-1
Check your mastery in the erecting and plumbing the posts by completing the
tasks below.
Arrange in order the steps of plumbing a corner post by writing the number
on the space provided.
Move the post inward or outward until distance from the post
to the center of the line is exactly 2 inches. Then nail the
temporarily brace in place.
Then hang the bob-line over the rule so that the line is 2
inches from the post and extends to the bottom of it.
With another rule, measure the distance from the post to the
center of the line at the bottom of the post; if it does not
measure 2 inches, the post is not plumb.
Repeat this procedure to the other face of the post. The post
is then plum. This process is carried out to the remaining post
of the building.
ANSWER KEY 5.2-1
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
2 Lay a rule on top of the post so that 2 inches of the rule extends over
the post on the side to be plumbed.
1 To plumb a corner with a plumb bob, first attach to the bob a string
long enough to extend to or below the bottom of the post.
5 Move the post inward or outward until distance from the post to the
center of the line is exactly 2 inches. Then nail the temporarily brace in
place.
3 Then hang the bob-line over the rule so that the line is 2 inches from
the post and extends to the bottom of it.
4 With another rule, measure the distance from the post to the center of
the line at the bottom of the post; if it does not measure 2 inches, the
post is not plumb.
6 Repeat this procedure to the other face of the post. The post is then
plum. This process is carried out to the remaining post of the building.
Steps/Procedure:
CRITERIA YES NO
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the PARTS OF A
FRAMED HOUSE.
The decision to
use one girder over
another is a function of
cost, availability, span
and loading conditions,
clearance or head-
room requirements,
and ease of
construction.
Girders in
residential construction
are usually one of the
following types as
illustrated.
Girders carry a large part of the building weight. They must be rigid and properly
supported at the foundation walls and on the columns. They must be installed
properly to support joists. The ends of wood girders should bear at least 4 inches on
posts.
SIZE REQUIREMENTS
Carpenters should understand the effect of length, width, and depth on the
strength of wood girders before attempting to determine their size.
Principles that govern the size of a girder are the:
• Distance between girder posts
• Girder load area
• Total floor load on the girder per square foot
• Load on the girder per linear foot
• Total load on the girder
• Material to be used
• Wood moisture content and types of wood used, since some woods are
stronger than others
Built-up girder
details
A girder should be just large enough to support an ordinary load. Any size
larger than that wastes material. For greater carrying capacity, it is better to increase
a girder's depth (within limits) than its
width. When the depth of a girder is
doubled (the width of lumber, such as 2 x
8 or 2 x 6), the safe load increases four
times. For example, a girder 3 inches
wide and 12 inches deep will carry four
times as much weight as a girder 3
inches wide and 6 inches deep.
MULTIPLE CHOICE: Read the statement carefully. Choose the letter of the correct
answer. Write the letter of your choice on the space provided.
ANSWER KEY 5.2-2
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
3.
INFORMATION SHEET NO. 5.2-3
LOAD CONDITIONS AND STRUCTURAL SYSTEM RESPONSE
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the TYPES OF
BUILDING LOADS.
Building loads can be divided into two types based on the orientation of the
structural actions or forces that they induce:
Vertical Loads Horizontal (Lateral) Loads
• Dead (gravity)
• Wind
• Live (gravity)
• Seismic (horizontal ground motion)
• Snow (gravity)
• Flood (static and dynamic hydraulic
• Wind (uplift on roof)
forces)
• Seismic and wind (overturning) • Soil (active lateral pressure)
• Seismic (vertical ground motion)
Gravity loads act in the same direction as gravity (i.e., downward or vertically)
and include dead, live, and snow loads. They are generally static in nature and
usually considered a uniformly distributed or concentrated load.
A buildings structure weight is called the dead load. The dead load per square
foot of floor area is carried directly or indirectly to the girder by bearing partitions.
The weight of furniture, persons, and other movable loads, not actually a part of
the building but still carried by the girder, is called the live load.
Snow on the roof is considered part of the live load.
Wind uplift forces are generated by negative (suction) pressures acting in an
outward direction from the surface of the roof in response to the aerodynamics of
wind flowing over and around the building.
Vertical forces are also created by overturning reactions due to wind and
seismic lateral loads acting on the overall building and its lateral force resisting
systems. Earthquakes also produce vertical ground motions or accelerations
which increase the effect of gravity loads.
The primary loads that produce lateral forces on buildings are attributable to
forces associated with wind, seismic ground motion, floods, and soil. Wind and
seismic lateral loads apply to the entire building. Lateral forces from wind are
generated by positive wind pressures on the windward face of the building and by
negative pressures on the leeward face of the building, creating a combined push-
and-pull effect.
LEARNING OUTCOME NO. 3
Lay-out/install floor joists
CONTENTS:
Floor Joist
Standard Size of Floor Opening
ASSESSMENT CRITERIA
1. Floor joists are set out, cut and fixed, and laterally supported at + 3mm on
all measurements and levelness in accordance with working drawings and
specifications
2. Joists are trimmed for openings and fixed with fastenings according to the
requirements of the working drawings and specifications
3. Unexpected situations are responded to in line with work place requirement
4. Housekeeping is performed according to safety regulations
5. Appropriate PPE is used according to job requirements
CONDITIONS:
You must be provided with the following:
1. WORKPLACE LOCATION • Personal Protective
2. TOOLS AND EQUIPMENT Equipment
Claw Hammer • Portable Circular Saw
Pencil/Marking pen • Plan and working drawings
Pull-Push Rule • Lumber
Nylon String • Nails
Steel Square • Plywood
Try-square
Hand Saw
Chalk Line
Manuals
3. TRAINING MATERIALS Related References
Leaning Packages
Bond paper
Ball pens
ASSESSMENT METHOD
Portfolio
Learning Experience
LAY-OUT/INSTALL FLOOR JOISTS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the PARTS OF
A FLOOR SYSTEM and STEPS IN LAYING OUT A PLATFORM FLOOR
ASSEMBLY.
The wood floor framing system consists of the common floor joists, cross
bridging, solid bridging, and others.
After the foundation is completed and the concrete or mortar has been
properly set up, assembly of the floor system can begin.
The construction of a platform floor assembly is normally done in the
sequence shown below:
MULTIPLE CHOICE: Read the statement carefully. Choose the letter of the correct
answer. Write the letter of your choice on the space provided .
Figure 1
ANSWER KEY 5.3-1
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
1. A
2. C
3. B
4. D
5. B
INFORMATION SHEET NO. 5.3-2
FLOOR OPENINGS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the PARTS OF A
FLOOR OPENING and PROCEDURES IN FRAMING.
Headers, trimmers and tail joists form the framing for floor openings.
Trimmers and headers are doubled when the header span exceeds 4 feet. Headers
more than 6 feet in length are supported at the ends by joist hangers or framing
anchors unless they are bearing on a partition, beam or wall. Tail joists which exceed
12 feet in length are supported on framing anchors or on ledger strips not less than
nominal 2x2 inches.
Headers run at right angles to the direction of the joists and are doubled. Trimmers
run parallel to the joists and are actually doubled joists.
Joists are framed to the headers where the headers form the opening frame at right
angles to the joists.
These shorter joists, framed to the headers are called tail beams, tail joists, or
header joists.
The number of headers and trimmers required at any opening depends upon the
shape of the opening, whether it is a simple rectangle or contains additional angles ; upon
the direction in which the opening runs in relation to the direction in which the joists run ; and
upon the position of the opening in relation to partitions or walls.
A typical procedure for framing an opening like the one shown is given below:
IDENTIFICATION: Identify the different parts of floor opening by writing your answer
beside the numbers
ANSWER KEY 5.3-2
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
LEARNING OUTCOME NO. 4
Lay-out/install wall studs
CONTENTS:
Components of a Wall
Measuring and Cutting Studs
ASSESSMENT CRITERIA
1. Wall studs are identified, measured and cut based on working drawings and
specifications with tolerance of + 3mm maximum on all measurements
2. Horizontal studs are laid–out and installed based on working drawings and
specifications with tolerance of + 3mm maximum on all measurements
3. Unexpected situations are dealt with according to company rules and
regulations
4. Appropriate PPE are used according to OSHC regulations
5. Housekeeping is performed according to safety standards and regulations
CONDITIONS:
You must be provided with the following:
1. WORKPLACE LOCATION • Personal Protective
2. TOOLS AND EQUIPMENT Equipment
Claw Hammer • Portable Circular Saw
Pencil/Marking pen • Plan and working drawings
Pull-Push Rule • Lumber
Nylon String • Nails
Steel Square • Plywood
Try-square
Hand Saw
Chalk Line
Manuals
3. TRAINING MATERIALS Related References
Leaning Packages
Bond paper
Ball pens
ASSESSMENT METHOD
Portfolio
Learning Experience
LAY-OUT/INSTALL WALL STUDS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to IDENTIFY the
COMPONENTS OF A WALL .
A. Components of a Wall
The figure below identifies the structural members of a wood frame wall. Each
of the members shown on the illustration is then described. You will need to know
these terms as you proceed through this module.
• Blocking (spacer)A wood block used as a filler piece and support between
framing members.
• Cripple stud—In wall framing, a short framing stud that fills the space
between a header and a top plate or between the sill and the soleplate.
• Double top plate—A plate made of two members to provide better stiffening
of a wall. It is also used for connecting splices, corners, and partitions that are
at right angles (perpendicular) to the wall.
• Header—A horizontal structural member that supports the load over an
opening such as a door or window.
• King stud—The full-length stud next to the trimmer stud in a wall opening.
• Partition—A wall that subdivides space within a building. A bearing partition
or wall is one that supports the floors and roof directly above in addition to its
own weight.
• Rough opening—An opening in the framing formed by framing members,
usually for a window or door.
• Rough sill—The lower framing member attached to the top of the lower
cripple studs to form the base of a rough opening for a window.
• Soleplate—The lowest horizontal member of a wall or partition to which the
studs are nailed. It rests on the rough floor.
• Stud—The main vertical framing member in a wall or partition.
• Top plate—The upper horizontal framing member of a wall used to carry the
roof trusses or rafters.
• Trimmer stud—The vertical framing member that forms the sides of rough
openings for doors and windows. It provides stiffening for the frame and
supports the weight of the header.
Step 1. Mark the locations of the soleplates by measuring in the width of the
soleplate (e.g., 3½") from the outside edge of the sill on each corner. Snap a
chalkline to mark the soleplate location, then repeat this for each wall.
Step 2. The top plate and soleplate are laid out together. Start by placing the
soleplate as indicated by the chalkline and
tacking it in place. Lay the top plate against
the soleplate so that the location of framing
members can be transferred from the
soleplate to the top plate. Also tack the top
plate. Tacking prevents the plates from
moving, which would make the critical layout
lines inaccurate.
CRITERIA YES NO
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the HOW TO
MEASURE AND CUT STUDS
CRITERIA YES NO
1. Did I cut/trim the needed materials (lumber)
according to dimension as specified in the house
plan?
2. Is the assembled wall in according to the house plan
and specifications of ± 3 mm on all measurements,
plumbness,, levelness and squareness?
Step 1. If the sheathing was installed with the wall laying down, or if the wall is
very long, it will probably be too heavy to be lifted into place by the
framing crew. In that case, use a crane or the special lifting jacks made
for that purpose . Use cleats to prevent the wall
from sliding.
Step 4. As the walls are erected, straighten the walls and nail temporary interior
bracing in place.
Assessment Method:
Portfolio
Demonstration
PERFORMANCE CRITERIA CHECKLIST
OPERATION SHEET NO. 5.4-2b
CRITERIA YES NO
Step 1. Plumb one corner post with a level or a plumb bob. Nail temporary braces
to hold the post in place. Repeat this procedure for all corner posts.
Step 2. Fasten a chalk line to the outside of one corner post at the top and stretch
the line to the corner post at
the opposite end of the
building. Then fasten the line
to this post.
Step 3. Place a 3/4-inch block under
each end of the line for
clearance.
Step 4. Place temporary braces at
intervals small enough to
hold the wall straight.
Step 5. Nail the brace when the wall
is far enough away from the
line to permit a 3/4-inch
block to slide between the
line and the plate.
CRITERIA YES NO
1. Is the erected wall in according to the house plan and
specifications of ± 3 mm on all measurements,
plumbness, levelness and squareness?
2. Did I use appropriate personal protective equipment
in laying out the wall?
CONTENTS:
Types of Roof Designs
Roof Frames
Parts of a Roof
Tension and Compression of Truss
ASSESSMENT CRITERIA
1. Types of roof and other components are fabricated, laid-out and installed
according to working drawings and specifications with tolerance of + 3mm
on all measurements, plumbness, levelness and squareness
2. Roof components are installed according to working drawings and
specifications
3. Unexpected situations are responded to in line with work place requirement
4. Housekeeping is performed according to safety regulations
5. Appropriate PPE is used according to job requirements and OHS
specifications
CONDITIONS:
You must be provided with the following:
1. WORKPLACE LOCATION • Personal Protective
2. TOOLS AND EQUIPMENT Equipment
Claw Hammer • Portable Circular Saw
Pencil/Marking pen • Plan and working drawings
Pull-Push Rule • Lumber
Nylon String • Nails
Steel Square • Plywood
Try-square
Hand Saw
Chalk Line
Manuals
3. TRAINING MATERIALS Related References
Leaning Packages
Bond paper
Ball pens
ASSESSMENT METHOD
Portfolio
Learning Experience
Lay-out/fabricate/install roof frames
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the Different
TYPES OF ROOF DESIGNS.
1. Shed Roof, Lean-to Roof or Pent Roof - a roof shape having only one
sloping plane.
2. Gable Roof or Pitch Roof - a roof having a single slope on each side of a
central ridge; usually with a gable at one or both ends.
3. Hip Roof or Hip and Valley Roof – a roof which slopes upward from all four
sides of a building, requiring a hip rafter at each corner.
4. Pyramidal Roof - a hipped roof that usually has four to six sloping surfaces,
terminating in a peak.
5. Pavilion Roof - a roof hipped equally on all sides, so as to have a
pyramidal form; a pyramidal hipped roof.
6. Gambrel Roof - a roof which has two pitches on each side (U.S.); in
Great Britain called a Mansard Roof
7. Sawtooth Roof - is a development of the shed roof made into a series of
lean-to roofs covering one building. This is commonly used in factories
where extra light is required through the clerestories formed in the vertical
portion of the roof.
8. Butterfly Roof - is a two shed roof where the slopes meet at the center of
the building.
9. Dome - is a hemispherical form of roof usually found in observatories.
10. Conical Roof or Sphere - is a steep roof of circular section that tapers
uniformly from the circular base to a central point. - is a steep roof of
circular section that tapers uniformly from the circular base to a central
point.
SELF- CHECK NO. 5.5-1
Check your mastery in the different types of roof design by completing the
tasks below.
IDENTIFICATION: Identify the types of roof design in the illustration. Write your
answer on the space provided.
1. 2.
3. 4.
5.
ANSWER KEY 5.5-1
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
1. Gable roof
2. Hip roof
3. Cross gable roof
4. Gambrel roof
5. Shed
INFORMATION SHEET NO. 5.5-2
ROOF FRAMES
LEARNING OBJECTIVE:
Upon completing this section, you should be able to IDENTIFY the PARTS
OF ROOF FRAMES
1. Common rafters - These are framing members that extend at right angles
from the plate line to the roof ridge. They are called common rafters because
they are common to all types of roofs and are used as the basis for laying
out other types of rafters.
2. Hip rafters - These are roof members that extend diagonally from the corner
of the plate to the ridge.
3. Valley rafters - These rafters extend from the plate to the ridge along the
lines where two roofs intersect.
4. Jack rafters - These are a common rafter. The three kinds of jack rafter are:
• Hip jack, which extends from the plate to the hip rafter.
• Valley jack, which extends from the ridge of the valley rafter.
• Cripple jack, which is placed between a hip rafter and a valley rafter.
The cripple jack rafter is also part of a common rafter, but it touches
neither the ridge of the roof nor the rafter plate.
SELF- CHECK NO. 5.5-2
Check your mastery in identifying the different parts of roof frames by
completing the tasks below.
IDENTIFICATION: Look at the illustration below. Identify the parts of the roof frames
by writing your answer on the space provided.
1.
2.
3.
4.
5.
6.
7.
8.
ANSWER KEY 5.5-2
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
1. Hip rafter
2. Ridge or Ridge board
3. Valley jack rafter
4. Common rafter
5. Hip jack rafter
6. Valley rafter
7. Overhang
8. Plate
INFORMATION SHEET NO. 5.5-3
PARTS OF A ROOF TRUSS
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the PARTS OF A
ROOF TRUSS.
Roof trusses incorporate rafters (top chords) and ceiling joists (bottom
chords) into a structural frame fabricated from 2-inch-thick dimension lumber, usually
2x4s or 2x6s. A combination of web members are positioned between the top and
bottom chords, usually in triangular arrangements that form a rigid framework.
Roof trusses are able to span the entire width of a home without interior
support walls, allowing complete freedom in partitioning interior living space.
IDENTIFICATION: Look at the illustration below. Identify the parts of the roof frames
by writing your answer on the space provided.
1.
2.
3.
4.
5.
ANSWER KEY 5.5-3
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
1. Slope
2. Rafter
3. Bottom Chord
4. Splice
5. Web
OPERATION SHEET NO. 5.5-3
Title:
Layout Truss
Performance Objective: Given the necessary materials, you should be
able to layout truss
Supplies and Materials: Working Drawing/ Plan
Lumber, fasteners
Tools and Equipment: • circular saw • folding rule
• hand saw • try square
• hammer • measuring rods
• wrecking bar
Steps/Procedure:
Step 1. Get the material to a level spot of ground where work benches will be
almost level.
Step 2. Obtain from the blueprints the measurement of all pieces to be used in the
truss.
Step 3. Lay out the length on the different sizes of timber and cut them accurately.
Step 4. After all lengths are cut, lay them in their correct position to form a truss.
Step 5. Nail them together temporarily.
Step 6. Lay out the location of all holes to be bored. Recheck the measurements
for accuracy.
Step 7. Bore holes to the size called for on the print. Use a brace and bit or the
woodborer that accompanies the air compressor. Bore holes perpendicular to the
face of the timber.
Truss Layout
Assessment Method:
Portfolio
Demonstration
PERFORMANCE CRITERIA CHECKLIST
OPERATION SHEET NO. 5.5-3
CRITERIA YES NO
LEARNING OBJECTIVE:
Upon completing this section, you should be able to KNOW the TENSION
AND COMPRESSION OF A TRUSS
All trusses in a roof structure are designed for the worst possible combination
of dead, live and wind loads. The individual truss members are designed to restrain
the corresponding forces i.e., tension or compression, or a combination of bending
with either the tension or compression force.
a. Tension (pulling). With this type of force the member being pulled or subjected
to a tension force is said to be “in tension”. The ability of a member to
restrain tension forces depends on the material strength of the member and
its cross-sectional area.
In view A, the ends of the two top chords (A-B and A-C) are being pushed
together(compressed). The bottom chord prevents the lower ends (B and C) of the
top chords from pushing out; therefore, the bottom chord is in a pulling-apart
state(tension). Because the lower ends of the top chords cannot pull apart, the peak
of the truss (A) cannot
drop down.
In view B, the
long webs are secured
to the peak of the truss
(A) and also fastened to
the bottom chord at
points D and E. This
gives the bottom chord
support along the
outside wall span. The
weight of the bottom
chord has a pulling-
apart effect (tension) on
the long webs.
In view C, the short webs run from the intermediate points F and G of the top
chord to points D and E of the bottom chord. Their purpose is to provide support to
the top chord. This exerts a downward, pushing-together force (compression) on
the short web.
In view D, you can see that the overall design of the truss roof transfers
the entire load (roof weight, snow load, wind load, and so forth) down through the
outside walls to the foundation. Web members must be fastened at certain
points along the top and bottom chords in order to handle the stress and weight
placed upon the truss.
1.
2.
3.
4.
5.
ANSWER KEY 5.5-4
Check your answer with the answer key below. If you fail to get it right, refer
back to corresponding resources until you make it perfect.
1. C
2. C
3. T
4. T
5. C
LEARNING OUTCOME NO. 6 Lay-out/install ceiling joist
CONTENTS:
Ceiling Joist
ASSESSMENT CRITERIA
1. Ceiling joists are identified, measured, and cut according to working
drawings and specifications with tolerance of + 3 mm on all measurements,
levelness and squareness
2. Ceiling joists are laid-out and installed according to working drawings and
specifications with tolerance of + 3 mm on all measurements, levelness and
squareness
CONDITIONS:
You must be provided with the following:
1. WORKPLACE LOCATION • Personal Protective
2. TOOLS AND EQUIPMENT Equipment
Claw Hammer • Portable Circular Saw
Pencil/Marking pen • Plan and working drawings
Pull-Push Rule • Lumber
Nylon String • Nails
Steel Square • Plywood
Try-square
Hand Saw
Chalk Line
Manuals
3. TRAINING MATERIALS Related References
Leaning Packages
Bond paper
Ball pens
ASSESSMENT METHOD
Portfolio
Learning Experience
Lay-out/install ceiling joist
LEARNING OBJECTIVE:
Upon completing this section, you should be able to Identify the PARTS of
CEILING FRAMES and Know how to INSTALL it.
1. Ceiling joist - one of several small beams to which the ceiling of a room is
attached. They are mortised into the sides of the binding joists, nailed to
the underside of these joists, suspended from them by straps.
2. Binding joist or binder - a beam which supports the common joists of a
wood floor above and the ceiling joists below; commonly joins two
vertical posts.
3. Plate joist - a horizontal board which connects and terminates the ceiling
joists. It provides the line and rigidity at the ends of the joists and connects
the suspended ceiling to the walls.
4. Ceiling strap - a strip of wood, nailed to the underside of floor joists or
rafters, from which a ceiling is suspended or fastened.