WORK CENTER
SCHEDULING
Chapter Twenty-Two
McGraw-Hill/Irwin Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved.
Learning Objectives
LO22-1: Explain work center scheduling.
LO22-2: Analyze scheduling problems using priority
rules and more specialized techniques.
LO22-3: Apply scheduling techniques to the
manufacturing shop floor.
LO22-4: Analyze employee schedules in the service
sector.
22-2
Manufacturing Execution Systems
Manufacturing execution system (MES): an information
system that schedules, dispatches, tracks, monitors, and
controls production
Real-time linkage to:
MRP
Product and process planning
Systems that extend beyond the factory
Service execution system (SES): an information system that
links schedules, dispatches, tracks, monitors, and controls the
customer’s encounters with the service organization
22-3
The Nature and Importance of
Work Centers
Work center: an area in which production resources
are organized and work is completed
May be a single machine, a group of machines, or an
area where work is done
Can be organized according to function, product in a
flow, or group technology
Jobs need to be routed between functionally
organized work centers to complete the work
22-4
Loading
Infinite loading: work is assigned to a work center
based on what is needed
No consideration to capacity
Finite loading: schedules each resource using the
setup and run time required for each order
Determines exactly what will be done by each resource
at every moment during the day
22-5
Scheduling
Forward scheduling: the system takes an order and
schedules each operation that must be completed
forward in time
Can tell the earliest date an order can be completed
Backward scheduling: starts with due date and
schedules the required operations in reverse
sequence
Can tell when an order must be started in order to be
done by a specific date
22-6
Limitations
Machine-limited process: equipment is the critical
resource that is scheduled
Labor-limited process: people are the key resource
that is scheduled
Most actual processes are either labor limited or
machine limited but not both
22-7
Types of Manufacturing Processes and
Scheduling Approaches
22-8
Typical Scheduling and Control
Functions
1. Allocating orders, equipment, and
personnel
2. Determining the sequence of order
performance
3. Initiating performance of the scheduled
work
4. Shop-floor control
22-9
Objectives of Work-Center Scheduling
1. Meet due dates
2. Minimize lead time
3. Minimize setup time or cost
4. Minimize work-in-process inventory
5. Maximize machine utilization
22-10
Job Sequencing
Sequencing: the process of determining the job
order on machines or work centers
Also known as priority sequencing
Priority rules: the rules used in obtaining a job
sequence
Can be simple or complex
Can use one or more pieces of information
Common rules shown on next slide
22-11
Priority Rules for Job Sequencing
22-12
Standard Measures of Schedule
Performance
1. Meeting due dates
2. Minimizing the flow time
3. Minimizing work-in-process inventory
4. Minimizing idle time
22-13
Example 22.1: n Jobs on One Machine
22-14
Example 22.1: FCFS and SOT Rules
22-15
Example 22.1: EDD and LCFS Rules
22-16
Example 22.1: Random and STR Rules
22-17
Comparison of Priority Rules
22-18
Scheduling n Jobs on Two Machines
Two or more jobs must be processed on two
machines in a common sequence.
Wish to minimize the flow time from the beginning
of the first job to the finish of the last job.
Use Johnson’s rule.
22-19
Steps to Johnson’s Rule
1. List the operation time for each job.
2. Select the shortest operation time.
3. If the shortest time is on the first machine, do first.
If the shortest time is on the second machine, do the
job last.
For ties, do first.
4. Repeat steps 2-3 for each remaining job.
22-20
Example 22.2: n Jobs on Two Machines
22-21
Example 22.2: Scheduling Jobs
22-22
Example 22.2: Optimal Schedule of
Jobs Using Johnson’s Rule
22-23
Scheduling a Set Number of Jobs on
the Same Number of Machines
Some work centers have enough machines to start all the
jobs.
Here the issue is the particular assignment of individual
jobs to individual machines.
Assignment method: a special case of the transportation
method of linear programming.
1. There are n things to be distributed to n destinations.
2. Each thing assigned to one and only one destination.
3. Only one criterion can be used.
22-24
Example 22.3: Assignment Method
Assignment Matrix Showing Machine Processing Costs for Each Job
22-25
Example 22.3: Step 1– Row Reduction
22-26
Example 22.3: Step 2 – Column
Reduction
22-27
Example 22.3: Step 3 – Apply Line
Test
22-28
Example 22.3: Step 4 – Additional
Reduction
22-29
Example 22.3: Optimal Solution
22-30
Example 22.3: Optimal Assignment
and Their Costs
Job I to Machine E $3
Job II to Machine B 4
Job III to Machine C 2
Job IV to Machine D 5
Job V to Machine A 3
Total Cost $17
22-31
Shop-Floor Control: Major Functions
1. Assigning priority of each shop order
2. Maintaining WIP quantity information
3. Conveying shop-order status information to the
office
4. Providing actual output data for capacity control
purposes
5. Providing quantity by location by shop order for
WIP inventory and accounting
6. Providing measurement of efficiency, utilization,
and productivity
22-32
Gantt Chart
22-33
Tools of Shop-Floor Control
1. The daily dispatch list
2. Various status and exception reports
a. Anticipated delay report
b. Scrap report
c. Rework report
d. Performance summary reports
e. Shortage list
3. An input/output control report
22-34
Some Basic Tools of Shop-Floor Control
22-35
Shop Capacity Control Load Flow
22-36
Principles of Work Center Scheduling
1. There is a direct equivalence between work flow and cash
flow.
2. The effectiveness of any job shop should be measured by
speed of flow through the shop.
3. Schedule jobs as a string, with process steps back-to-back.
4. A job once started should not be interrupted.
5. Speed of flow is most efficiently achieved by focusing on
bottleneck work centers and jobs.
22-37
Principles of Job Shop Scheduling
(continued)
6. Reschedule every day.
7. Obtain feedback each day on jobs that are not completed
at each work center.
8. Match work center input information to what the worker
can actually do.
9. When improving output, look for incompatibility between
engineering design and process execution.
10. Certainty of standards, routings, and so forth is not
possible, but always work toward achieving it.
22-38
Personnel Scheduling in Services
Scheduling consecutive days off
Scheduling daily work times
Scheduling hourly work times
22-39
Software for Employee Scheduling
ScheduleSource Inc. of Broomfield, Colorado, offers an integrated
suite of tools for workforce management named TeamWork.
At the heart of TeamWork is a customizable and automated
employee scheduling system. The benefits of TeamWork software
include features such as
Web based
Optimized schedules
Zero conflict scheduling
Time and attendance recordkeeping
E-mail notifications
Audit trail
Advanced reporting
Accessibility from anywhere any time
22-40
Steps for the Software
Step 1: Define labor requirements.
Step 2: Establish employee availability.
Step 3: Assign employees to particular skill sets and
rank an employee’s skill set level from 1 to 10 (1
being novice, 5 being average, and 10 being
superlative).
Step 4: The TeamWork software automatically
builds a schedule.
22-41
TSA and ScheduleSource Software
ScheduleSource customers include
The Transportation Security Administration (TSA) has
successfully implemented ScheduleSource Software to
generate schedules for more than 44,000 federal
airport security personnel at 429 airports.
More than 30,000,000 individual shifts were scheduled
in the airport security deployment.
22-42