Disbursement Voucher: DPWH-Sorsogon 1st DEO
Disbursement Voucher: DPWH-Sorsogon 1st DEO
Address MANILA
Responsibility
Particulars MFO/PAP Amount
Center
185,839.05 185,839.05
B. Accounting Entry:
Account Title UACS Code Debit Credit
Signature Signature
Printed
IVAN MAR D. MANAOIS Printed Name IGNACIO T. ODIAMAN
Name
Accountant III District Engineer
Position Position
Head, Accounting Unit/Authorized Representative Agency Head/Authorized Representative
Date Date
E. Receipt of Payment JEV No.
Check/ Date : Bank Name & Account Number:
ADA No. :
Date : Printed Name: Date
Signature :
Official Receipt No. & Date/Other Documents
34300000 32995197.71
5145000 4,949,279.66
1880231.3428 3688698.130598
1808466.79
1303057
1715000
411943
4454351.694
765653.56
4949279.66
494927.97
Appendix 32
Responsibility
Particulars MFO/PAP Amount
Center
185,839.05
B. Accounting Entry:
Account Title UACS Code Debit Credit
Signature Signature
Printed
IVAN MAR D. MANAOIS Printed Name IGNACIO T. ODIAMAN
Name
Accountant III District Engineer
Position Position
Head, Accounting Unit/Authorized Representative Agency Head/Authorized Representative
Date Date
E. Receipt of Payment JEV No.
Check/ Date : Bank Name & Account Number:
ADA No. :
Date : Printed Name: Date
Signature :
Official Receipt No. & Date/Other Documents
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
BACKGROUND INFORMATION
Contract ID : 17FK0007
EXECUTIVE SUMMARY
:
PRISCILLA B. JEBULAN
Project Engineer
PLS. CAPITALIZE
X PERIOD COVERED OF BILLING
ALL DETAILS
EXCEPT FOR DATE
(FORMAT)
If there is suspension order or revised contract date put the revised contract end date
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
BILLING SUMMARY
Contract ID : 17FK0007
PAYMENT BREAKDOWN :
PREVIOUS COST OF THIS
DESCRIPTION CONTRACT COST
BILLING BILLING
- - -
PRISCILLA B. JEBULAN
Project Engineer
REMARKS : Completed (100.00%)
January 10, 2018
Date
BALANCE
if projects in one package is 2 or more, list all projects with corresponding contract
- X
amount per project
-
PLS. CAPITALIZE
ALL DETAILS
EXCEPT FOR DATE
- (FORMAT)
JEBULAN
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
PRISCILLA B. JEBULAN
Project Engineer
PRISCILLA B. JEBULAN
Project Engineer
PROJECT ID : 17FK0007
Certified by:
PRISCILLA B. JEBULAN
Project Engineer
Noted:
IGNACIO T. ODIAMAN
District Engineer
X DATE
X if necessary
X if necessary
X if necessary
X if necessary
X NO. OF DAYS ELAPSED TO DATE
ND FOUND CORRECT
ECOMMENDED:
ND RECOMMENDED
FOR PAYMENT:
IGNACIO T. ODIAMAN
District Engineer
al Progress: 100.00%
iry Date : January 4, 2018 if there is revised contract date put the revised end date
or (-) : 0.00%
Republic of the Philippines
Department of Public Works and Highways
Sorsogon First District Engineering Office
Guinaljon, Sorsogon City
CERTIFICATION
This is to certify further that all requirements and supporting papers, pursuant to Department Order NO.
55, series of 1988, have been complied with, reviewed and found to be in order.
IGNACIO T. ODIAMAN
DPWH District Engineer
Sorsogon 1st DEO Guinlajon, Sorsogon City
Sir:
ALFREDO J. TAN
Contractor
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
Sir:
In connection with the letter request for inspection of 100.00% work accomplished by AL NIÑO
CONSTRUCTION AND SUPPLY , may we request from your good office a representative to
conduct a joint inspection with the Inspectorate Group of this Office in connection with the
implementation of 17FK0007 - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION
STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF MILAGROSA RIVER
CONTROL, CASTILLA, SORSOGON
IGNACIO T. ODIAMAN
District Engineer
AFFIDAVIT
I, ALFREDO J. TAN of legal age, Filipino, and presently residing at LEGAZPI after having duly sworn
to in accordance with the law, depose and say;
2. That I have already paid my employees and laborers of their salaries and wages in connection with
the prosecution of the above named projects;
3. That all the sand and gravel used by us in the prosecution of the aforementioned project was supplied
to us at site by private haulers and concessionaires;
4. That all the taxes due the government in connection with the above mentioned project have been
paid by our firm;
5. That I am executing this affidavit to establish the fact that I am not responsible for the payment of
the said sand and gravel tax required by the Minister of Finance under the local Tax Regulation No.
4-75, dated November 17, 1975 and implemented by the Department of Public Works and Highways
under Memo No. 65, dated November 24, 1975;
6. That I further certify that I did not promise any official or employee of the Department of gift or
money to secure claim for this 100.00 % of work accomplished in the above-mentioned project.
IN WITNESS WHEREOF, I hereunto affix my signature this 10 th day of January at SORSOGON CITY.
ALFREDO J. TAN
Proprietor
Notary Public
Doc. No.
Page No.
Book No.
Series of 20
X NAME AND ADDRESS
X PROJECT DESCRIPTION
X PERCENTAGE OF ACCOMPLISHMENT
X DATE
X PROPRIETOR
X DATE
Republic of the Philippines
Department of Public Works and Highways
Sorsogon First District Engineering Office
Guinaljon, Sorsogon City
CERTIFICATION
This is to certify that AL NIÑO CONSTRUCTION AND SUPPLY has submitted final and completed as
staked plans in connection with CONTRACT ID 17FK0007 - CONSTRUCTION / MAINTENANCE OF FLOOD
MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF MILAGROSA RIVER CONTROL,
CASTILLA, SORSOGON
PRISCILLA B. JEBULAN
Project Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
CONTRACT ID : 17FK0007
LIMITS :
LOCATION :
This is to certify that as of January 11, 2018 no written complaints have been filed in this Office on unpaid labor or
unpaid materials and on equipment lease or rental filed against the contractor AL NIÑO CONSTRUCTION AND SUPPLY
This certification is issued to the Contractor as a requirement in connection with their request for final payment of 100%
work accomplished for the implementation of 17FK0007 - CONSTRUCTION / MAINTENANCE OF FLOOD
MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF MILAGROSA RIVER
CONTROL, CASTILLA, SORSOGON
PRISCILLA B. JEBULAN
Project Engineer
EQUIPMENT
STRUCTURES AND
VER CONTROL,
X LOCATION
X
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
This is to certify that AL NIÑO CONSTRUCTION AND SUPPLY did not use/lease/rent any government equipment in
connection with CONTRACT ID 17FK0007 - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION
STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF MILAGROSA RIVER CONTROL, CASTILLA,
SORSOGON and has no financial obligations and the like relative to the above mentioned project.
Issued upon request this 10th day of January, 2018 for the payment of the above-mentioned project.
PRISCILLA B. JEBULAN
Project Engineer
x
X
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
FINDINGS
Recommendations:
X DATE OF INSPECTION
X Recommendations
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
FINDINGS :
We, the undersigned members of the Inspectorate Team, conducted a joint inspection of the above stated project and found the
same to be satisfactorily completed on March 10, 2019 in accordance with the Plans and Specifications of the Contract.
X CHANGE THE DATE IF THERE ARE DEFECTS NOTED IN THE 1ST COMPLETION INSPECTION
PROVIDE HERE A NARRATIVE REPORT OF THE INSPECTORATE TEAM'S
FINDINGS. ATTACH THE TEAM'S PREVIOUS COMPLETION INSPECTION
REPORT, INDICATING DEFECTS/DEFICIENCIES OBSERVED BY THE
INSPECTORATE TEAM AND REPAIR WORKS DONE BY THE CONTRACTOR.
X IF THE FIRST COMPLETION INSPECTION REPORT (NO.1) SHOWS
DEFECTS/DEFICIENCIES, INCLURE HERE THE TEAM'S COMMENDATION
FOR THE CONTRACTOR AND THE DPWH CONSTRUCTION SUPERVISION
TEAM FOR THEIR EXEMPLARY PERFORMANCE
X DATE
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
"Annex B"
Project ID : 17FK0007
CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION
PROJECT NAME: : STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF
MILAGROSA RIVER CONTROL, CASTILLA, SORSOGON
LOCATION : Castilla, Sorsogon
CONTRACTOR : AL NIÑO CONSTRUCTION & SUPPLY
We, the undersigned members of the Inspectorate Team, conducted a joint inspection of the above stated
project and found the same to be satisfactorily completed on March 10, 2019 in accordance with the Plans
and Specifications of the Contract.
CERTIFICATION OF COMPLETION
This is to certify that the above stated project has been satisfactorily completed on March 10, 2019 in accordance
with the Plans and Specifications of the Contract based on the Final Completion Inspection Report of the Inspectorate
Team dated March 19, 2019.
This certification does not relieve the Contractor of his obligations and responsibilities in undertaking repair works
on any defect or failure that may occur in any section of the project during the one-year Defects Liability Period starting
from the date of completion as herein stated. Neither is he relieve of his obligations and responsibilities pursuant to the
provisions of R.A. 9184.
IGNACIO T. ODIAMAN
District Engineer
Conforme:
_______________________
ALFREDO J. TAN
Contractor
X CHANGE DATE IF THERE IS DEFECTS OR DEFICIENCIES NOTED IN THE 1ST COMPLETION
ATION STRUCTURES
AGROSA RIVER
Reference No.:
Date :
This is to certify that as per records of this office, AL NIÑO CONSTRUCTION AND SUPPLY, contractor of
17FK0007 - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE
SYSTEM - CONSTRUCTION OF MILAGROSA RIVER CONTROL, CASTILLA, SORSOGON, has no property
and/or money accountability with the Supply and Property in Administrative Division/Section, in connection with the
above-mentioned contract.
In order to be complete, similar clearance shall be obtained from the DPWH Implementing Office (IO) of the
above-mentioned project and from the Bureau of Equipment and/or Regional Equipment Services (RES) for whatever
accountabilities there might be under their respective jurisdictions.
RICO D. DESPUIG
Supply Officer II
LARRY B. REYES
Administrative Officer V
X CHANGE DATE IF THERE IS DEFECTS OR DEFICIENCIES NOTED IN THE 1ST COMPLETION INSPEC TION R
OMPLETION INSPEC TION REPORT
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
Contract ID : 17FK0007
1. EQUIPMENT RENTALS, SPARE PARTS AND MATERIALS ISSUED, SERVICES RENDERED ETC.
(Attach supporting papers if necessary)
(State the present condition of the equipment together with your comment and/or recommendation)
Submitted by:
PRISCILLA B. JEBULAN
Project Engineer
x ADD LOCATION
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
This is to certify that the construction works as specified below has been completed under direct supervision in
accordance with the plans, specifications and programs of work.
CONCURRED BY:
Submitted By:
This is to certify that I, has this date acknowledge and receive custody of the above-specified project in view of the
report of the District Inspectorate Team that same is satisfactorily completed in accordance with the plans, specifications and
program of work. I assume the responsibility of the structures for proper maintenance only
WITNESS
PRISCILLA B. JEBULAN
Project Engineer
APPROVED:
IGNACIO T. ODIAMAN
District Engineer
X NAME OF CONTRACTOR
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
What : CERTIFICATION
Re : Turn-over of Laboratory Equipment
Contract ID : 17FK0007
Contractor : AL NIÑO CONSTRUCTION & SUPPLY
This is to certify that the contract for the said project did not include any provisions for the purchase of
laboratory equipment.
PRISCILLA B. JEBULAN
Project Engineer
ULAN
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
What : CERTIFICATION
Re : Turn-over of Equipment Bought out of Project Funds
Contract ID : 17FK0007
Contractor : AL NIÑO CONSTRUCTION & SUPPLY
This is to certify that the contract for the said project did not include any provisions for the purchase of
office equipment, furniture, building, surveying instrument and service vehicle.
PRISCILLA B. JEBULAN
Project Engineer
ULAN
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
What : CERTIFICATION
Re : Approved Time Extension / Suspension and Resume Orders
Contract ID : 17FK0007
Contractor : AL NIÑO CONSTRUCTION & SUPPLY
This is to certify that the contract for the said project did not issue any Approved Time
Extensions/Suspension and Resume Order.
PRISCILLA B. JEBULAN
Project Engineer
ULAN
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sorsogon First District Engineering Office
Guinlajon, Sorsogon City
What : CERTIFICATION
Re : As Built Quantity / Final Change Order
Contract ID : 17FK0007
Contractor : AL NIÑO CONSTRUCTION & SUPPLY
This is to certify that the contract for the said project did not issue any As Built Quantity/Final Change
Order.
PRISCILLA B. JEBULAN
Project Engineer
ULAN
Republic of the Philippines
Department of Public Works and Highways
Sorsogon First District Engineering Office
Guinaljon, Sorsogon City
CERTIFICATION