Brick Chamber Rate Analysis

The document provides a rate analysis for the construction of brick masonry chambers of two different sizes, listing the materials, quantities, unit rates, and amounts for each item. It includes details on the number of bricks, cement, sand, and labor required. The total costs are calculated for each chamber size after adding the subtotals and contractor profit.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
7K views3 pages

Brick Chamber Rate Analysis

The document provides a rate analysis for the construction of brick masonry chambers of two different sizes, listing the materials, quantities, unit rates, and amounts for each item. It includes details on the number of bricks, cement, sand, and labor required. The total costs are calculated for each chamber size after adding the subtotals and contractor profit.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

RATE ANALYSIS

SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

CONSTRUCTION OF BRICK MASONRY CHAMBERS OF


SIZE 950 MM x 650 MM x 1000 MM ( INTERNAL
1 DIMENSIONS)
BRICKS
2 x 1.41 x 0.23 x 1.0 0.6486
2 x 0.65 x 0.23 x 1.0 0.299
Brick Work Qty per Chamber 0.9476
NO.OF BRICKS PER CU.M IS = 0.9476 x 450 = 426.42 Nos 427 5.5 2348.5

Cement Consumption per cu.M of Brick Work in CM 1:4


For 10 Cu.M 14 Bags . For 0.9476 Cu.M - 14 X 0.9476 /
10=1.32664 Bags 1.32664 350 464.324

Sand for brick work -For 10 Cu.m - 2.7 Cu.M of Sand.


Rate per Brass of Sand is Rs. 8500 /2.83 = 3003.534 per
Cu.M 0.255852 3000 767.556
Soling - 1.6 X 1.1 X 0.23 0.4048 1000 404.8
PCC - 1.6 X 1.1 X 0.1 0.176 4700 827.2
External Plastering - 2X 1.41X1.0+2X0.65X1.0=4.12 Sq.M 4.12

Internal Plastering - 2 X 0.65 X 1.0 +2X0.95X1.0 = 3.2 Sq.M 3.2

Cement Consumption per 7.32 Sq.M Plastering Work in


CM 1:4 For 100 Sq. Ft 73Kgs . For 7.32 Sq.M -
73*7.32*10.767/100 - 57.53 Kgs = 57.53/50=1.15 Bags Bags 1.15 360 414

Sand for 100 Sq. Ft Plastering area is 0.23 Cu.M. For


7.42 Sq.M =7.42*10.767=78.81 Sq.Ft . Sand for 78.81
Sq, Ft = 78.81*0.23/100=0.181 Cu.M Cu.M 0.181 3000 543
Labour
Mason Nos 1 750 750
Labour Nos 2 400 800
Sub Total in Rs. 7319.38
Add Contractor Profit @ 10% 731.938
Rate for Brick Chamber Construction 8051.318

SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

CONSTRUCTION OF BRICK MASONRY CHAMBERS OF


SIZE 450 MM x 450 MM x 1000 MM ( INTERNAL
1 DIMENSIONS)
BRICKS
2 x 0.91 x 0.23 x 1.0 0.4186
2 x 0.45 x 0.23 x 1.0 0.207
Brick Work Qty per Chamber 0.6256
NO.OF BRICKS PER CU.M IS = 0.6256 x 450 = 281.52 Nos 282 5.5 1551

Cement Consumption per cu.M of Brick Work in CM 1:4


For 10 Cu.M 14 Bags . For 0.6256 Cu.M - 14 X 0.6256 /
10=1.32664 Bags 0.87584 350 306.544

Sand for brick work -For 10 Cu.m - 2.7 Cu.M of Sand.


Rate per Brass of Sand is Rs. 8500 /2.83 = 3003.534 per
Cu.M 0.168912 3000 506.736
Soling - 1.11 X 1.11 X 0.23 0.2783 1000 278.3
PCC - 1.11 X 1.1 X 0.1 0.1221 4700 573.87
External Plastering - 2X 1.11X1.0+2X0.45X1.0=4.12 Sq.M 3.12

Internal Plastering - 2 X 0.45 X 1.0 +2X0.45X1.0 = 1.8 Sq.M 1.8

Cement Consumption per 7.32 Sq.M Plastering Work in


CM 1:4 For 100 Sq. Ft 73Kgs . For 7.32 Sq.M -
73*7.32*10.767/100 - 57.53 Kgs = 57.53/50=1.15 Bags Bags 1.15 360 414

Sand for 100 Sq. Ft Plastering area is 0.23 Cu.M. For


7.42 Sq.M =7.42*10.767=78.81 Sq.Ft . Sand for 78.81
Sq, Ft = 78.81*0.23/100=0.181 Cu.M Cu.M 0.181 3000 543
Labour
Mason Nos 1 750 750
Labour Nos 1 400 400
Sub Total in Rs. 5323.45
Add Contractor Profit @ 10% 532.345
Rate for Brick Chamber Construction 5855.795
3003.534

100 73
78.81444 57.53454 1.150691

0.181263

4.12
3.2