The document is a monthly safety audit checklist for contractors working on a construction project. It contains over 30 questions across 5 sections reviewing office procedures, site security, safety responsibilities, and any additional comments. For each "No" response, corrective actions are required to address safety issues and ensure compliance with regulations.

Uploaded by

Jamil Hossain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
130 views7 pages

Safety Audit CheckList

The document is a monthly safety audit checklist for contractors working on a construction project. It contains over 30 questions across 5 sections reviewing office procedures, site security, safety responsibilities, and any additional comments. For each "No" response, corrective actions are required to address safety issues and ensure compliance with regulations.

Uploaded by

Jamil Hossain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

CONTRACTORS MONTHLY SAFETY AUDIT CHECKLIST

Project Number: Project Name:


Phase:
Date Completed:

Contractor:

Safety Representative:

Total Employees:

Total Contractor employees:

Total subcontractor employees:

1.0 Current Status of Contract (Check appropriate activities)


Site clearing & grubbing Overhead mechanical/electrical

Excavation Interior finishes

Foundations Demolition

Structural frame Remodeling

Exterior enclosure Close out

Other:

2.0 Office Procedures

Yes No N/A Description

1. Safety & health poster posted.

2. Emergency telephone numbers posted.

3. First aid kit & supplies on job.

4. Copy of OSHA safety standard in the office.

5. Toolbox meeting reports issued, forwarded to Project Superintendent & filed.

6. Safety notices issued, forwarded to appropriate personnel and filed.

7. Received visit from OSHA this month.

8. Emergency stretcher located on job – near hoist or elevator.

9. Any first aid injuries reported were forwarded to Site Management.

10. OSHA Form 200 posted.

N/A = Not Applicable “NO” requires Corrective Action

3.0 Site Security & Warning Signs


Yes No N/A Description
1. Site secured with fence and gates. Gates closed and locked.

Corrective action:

2. Warning signs posted for general public.

Corrective action:

3. Overhead protection installed where any overhead work is taking place.

Corrective action:

4. Any exterior storage of flammable liquids:

a) At least 20 feet from all buildings

b) No smoking signs posted (signs should read Danger- Flammable)

c) Containers properly labeled

d) Spill containment in place

Corrective action:

5. All excavation are appropriately laid out and secured.

Corrective action:

6. All mobile equipment is locked when not in use.

Corrective action:

7. Occupied areas of the project are barricaded and warning signs posted.

Corrective action:

N/A = Not Applicable “NO” requires Corrective Action

4.0 Safety Responsibilities


Yes No N/A Description

1. Perimeter guard rails are installed properly for protection of all employees.

Corrective action:

2. All floor openings protected by guardrails or are covered, secured and marked.

Corrective action:

3. Temporary ladders properly installed to all levels, and secured at the top and the bottom.

Corrective action:

4. Operating rules posted in operator’s station (or equivalent), and all equipment safety inspected at
the start of the day.

Corrective action:

5. Adequate overhead protection for individuals working near hoisting areas.

Corrective action:

6. All hoist entrances guarded by barricades and/or conventional fall protection.

Corrective action:

7. Employees are wearing hard hats and all required personal protection equipment.

Corrective action:

8. Fire protection and emergency evacuation procedures are established.

Corrective action:

N/A = Not Applicable “NO” requires Corrective Action


4.0 Safety Responsibilities (Continued)

Yes No N/A Description

9. Fire extinguishers installed throughout the project and have been adequately inspected.

Corrective action:

10. Weekly toolbox meetings are taking place with field employees of contractors/subcontractors.

Corrective action:

11. Adequate toilet facilities are installed and are kept in a sanitary condition.

Corrective action:

12. Trash containers and regular disposal is provided.

Corrective action:

13. An adequate supply of portable water is available and clearly marked. Paper cups and trash
containers are also provided.

Corrective action:

14. Traffic control measures are used to protect crossing traffic and pedestrians.

Corrective action:

15. New employees processed through project orientation and have been instructed on specific safety
procedures.
Corrective action:

16. Excavations and trenches are sloped properly or braced.

Corrective action:

N/A = Not Applicable “NO” requires Corrective Action


4.0 Safety Responsibilities (Continued)

Yes No N/A Description


17. Perimeter guardrail systems installed at all floor edges and openings.

Corrective action:

18. Housekeeping is kept up to date.

Corrective action:

19. All flammable liquids are properly stored and handled.

Corrective action:

20. Gas cylinders are transported, used and/or stored properly.

Corrective action:

21. Temporary lighting is installed in areas where it is needed. Lighting is in good working condition.

Corrective action:

22. Temporary electrical systems are on ground fault systems.

Corrective action:

22a. Extension cords include ground fault protection and are in good condition.

Corrective action:

23. All cranes and/or rigging equipment are inspected daily before use.

Corrective action:

N/A = Not Applicable “NO” requires Corrective Action


4.0 Safety Responsibilities (Continued)

Yes No N/A Description

24. Mobile cranes are checked for stability, and outriggers properly blocked on stable ground.

Corrective action:

25. Counterweight swing areas are barricaded to prevent access to unaware workers.

Corrective action:

26. Crane operators are cautioned to stay an adequate distance from all overhead power lines.

Corrective action:

27. All welders are instructed in safe welding and cutting practices. Fire protection measures are taken
and fire extinguishers are available.

Corrective action:

28. Scaffolds are adequately erected. Scaffolds are equipped with ladders and base plates.

Corrective action:

29. Scaffolds or platforms are tightly planed for full width.

Corrective action:

30. All scaffolds or platforms are provided with a guard rail (2 x 4) or equivalent 42" high, midrail
(2x4) or equivalent and a toe board 4" high.

Corrective action:

31. Hanging or suspended scaffolds are checked daily. Safety harnesses and lifelines are used by
employees.
Corrective action:
N/A = Not Applicable “NO” requires Corrective Action

4.0 Safety Responsibilities (Continued)

Yes No N/A Description

32. All damaged or excessively worn equipment is tagged out or removed from service.

Corrective action:

33. Additional safety requirements implemented for this project.

Corrective action:

5.0 Additional Comments,

N/A = Not Applicable “NO” requires Corrective Action


cc: