This weekly progress report provides updates on the construction of a model secondary school in Oginibo, Delta State, Nigeria by Betagod Investment Limited. The report indicates that construction is 99% complete, with only testing, commissioning, snagging and handover remaining. Photos document completed works like landscaping, fencing, furniture installation and computer lab setup. The project is expected to be finished and handed over by July 31, 2019.

Uploaded by

Eze Nonso
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
79 views11 pages

SIte Report Week 113

This weekly progress report provides updates on the construction of a model secondary school in Oginibo, Delta State, Nigeria by Betagod Investment Limited. The report indicates that construction is 99% complete, with only testing, commissioning, snagging and handover remaining. Photos document completed works like landscaping, fencing, furniture installation and computer lab setup. The project is expected to be finished and handed over by July 31, 2019.

Uploaded by

Eze Nonso
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 11

CONSTRUCTION AND EQUIPPING OF

MODEL SECONDARY SCHOOL

OGINIBO, JEREMI CLAN, DELTA STATE


(Corporate Social Responsibility Project)

By
BETAGOD INVESTMENT LIMITED

WEEKLY PROGRESS REPORT NO. 113

Action Name Position Sign Date

Prepared by OKPE, Cletus PROJECT MANAGER

Approved by OLIGBI Joseph MANAGING DIRECTOR

Page 1 of 11
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 2 of 11 PROGRESS REPORT Date: 01/07/2020

1.0 Project Milestones

1.1 Project Commencement Date – 15/01/2018


1.2 Project Kick off meeting Date – 26/02/2018
1.3 New site hand over Date – 15/06/2018
1.4 Commencement of site office erection – 03/07/2018
1.5 Completed Ground floor block work 100% 21/02/2019
1.6 Completed top floor block work 100% 28/03/2019
1.7 Completed Roofing sheets installation 100% 09/05/2019

2.0 Weekly Progress Of Work

BGIL Dates: 01-July 2020 (Week 113)

Plan % Weekly 1.80


Actual % Weekly 1.80
Actual %Cumulative
99.00
2.1 Earn Values
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 3 of 11 PROGRESS REPORT Date: 01/07/2020

2.2 Activities Completed

2.2.1 Demobilized from Old site at Otu – Jeremi


2.2.2 Design drawings submitted for approval – completed
2.2.3 Contractor take-over of Oginibo site
2.2.4 Profiling and trenching
2.2.5 Substructure Completed
2.2.6 Completed Ground and Upper floor block work
2.2.7 Completed Aluminium Sheets Installations
2.2.8 Completed plastering
2.2.9 Completed Window Frames Installations
2.2.10 Completed Electrical Wiring Installations
2.2.11 Completed tiling works
2.2.12 Completed Door/window installations
2.2.13 Completed Electrical fittings Installation
2.2.14 Completed PVC and Suspended ceiling Installation
2.2.15 Completed Protector installations
2.2.16 Completed Floor finish (Terrazzo)
2.2.17 Completed Painting work

2.3 One week Look ahead

2.3.1 Carry out testing and power appliances


2.3.2 Carry out commissioning
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 4 of 11 PROGRESS REPORT Date: 01/07/2020

2.4 Weekly progress.

2.4.1 Completed fencing works


2.4.2 Completed Solar lighting Installation works
2.4.3 Completed furniture works
2.4.4 Completed Laboratory set up.
2.4.5 Completed landscaping

2.5 Milestone Progress

Description Percentage Completion


Selection of Engineering Consultant 100%
Scope of work and Tender Document Approval 100%
Selection of contractor via CFT & award 100%
Project Execution
Site preparation for mobilization 100%
Mobilization 100%
Sub structure 100%
Super structure 100%
Roofing 100%
Finishes 100%
External works / Plastering 100%
Painting 100%
Furniture & equipment & Laboratory 100%
Landscaping 100%
Fencing 100%
Solar Panel /Generator/Inverter 100%
Testing and commissioning 50%
Snagging and closure 90%
Demobilization & Handover 80%
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 5 of 11 PROGRESS REPORT Date: 01/07/2020

Updated POW -See attached updated POW

3.0 Project Finish date

3.1 Project Finish Date – 6 months from commencement/Site handover


3.2 New Project Finish Date – 31 July 2019, Site handover
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 6 of 11 PROGRESS REPORT Date: 01/07/2020

4.0 Work Progress Photograph


Borehole complete
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 7 of 11 PROGRESS REPORT Date: 01/07/2020

Landscaping completed
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 8 of 11 PROGRESS REPORT Date: 01/07/2020

Progress Photos Contd.

Furniture completed

Furniture completed
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 9 of 11 PROGRESS REPORT Date: 01/07/2020

Gate completed coml

Fence completed
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 10 of 11 PROGRESS REPORT Date: 01/07/2020

Computer Lab completed


WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 11 of 11 PROGRESS REPORT Date: 01/07/2020

Power connected