CONSTRUCTION AND EQUIPPING OF
MODEL SECONDARY SCHOOL
OGINIBO, JEREMI CLAN, DELTA STATE
(Corporate Social Responsibility Project)
By
BETAGOD INVESTMENT LIMITED
WEEKLY PROGRESS REPORT NO. 113
Action Name Position Sign Date
Prepared by OKPE, Cletus PROJECT MANAGER
Approved by OLIGBI Joseph MANAGING DIRECTOR
Page 1 of 11
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 2 of 11 PROGRESS REPORT Date: 01/07/2020
1.0 Project Milestones
1.1 Project Commencement Date – 15/01/2018
1.2 Project Kick off meeting Date – 26/02/2018
1.3 New site hand over Date – 15/06/2018
1.4 Commencement of site office erection – 03/07/2018
1.5 Completed Ground floor block work 100% 21/02/2019
1.6 Completed top floor block work 100% 28/03/2019
1.7 Completed Roofing sheets installation 100% 09/05/2019
2.0 Weekly Progress Of Work
BGIL Dates: 01-July 2020 (Week 113)
Plan % Weekly 1.80
Actual % Weekly 1.80
Actual %Cumulative
99.00
2.1 Earn Values
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 3 of 11 PROGRESS REPORT Date: 01/07/2020
2.2 Activities Completed
2.2.1 Demobilized from Old site at Otu – Jeremi
2.2.2 Design drawings submitted for approval – completed
2.2.3 Contractor take-over of Oginibo site
2.2.4 Profiling and trenching
2.2.5 Substructure Completed
2.2.6 Completed Ground and Upper floor block work
2.2.7 Completed Aluminium Sheets Installations
2.2.8 Completed plastering
2.2.9 Completed Window Frames Installations
2.2.10 Completed Electrical Wiring Installations
2.2.11 Completed tiling works
2.2.12 Completed Door/window installations
2.2.13 Completed Electrical fittings Installation
2.2.14 Completed PVC and Suspended ceiling Installation
2.2.15 Completed Protector installations
2.2.16 Completed Floor finish (Terrazzo)
2.2.17 Completed Painting work
2.3 One week Look ahead
2.3.1 Carry out testing and power appliances
2.3.2 Carry out commissioning
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 4 of 11 PROGRESS REPORT Date: 01/07/2020
2.4 Weekly progress.
2.4.1 Completed fencing works
2.4.2 Completed Solar lighting Installation works
2.4.3 Completed furniture works
2.4.4 Completed Laboratory set up.
2.4.5 Completed landscaping
2.5 Milestone Progress
Description Percentage Completion
Selection of Engineering Consultant 100%
Scope of work and Tender Document Approval 100%
Selection of contractor via CFT & award 100%
Project Execution
Site preparation for mobilization 100%
Mobilization 100%
Sub structure 100%
Super structure 100%
Roofing 100%
Finishes 100%
External works / Plastering 100%
Painting 100%
Furniture & equipment & Laboratory 100%
Landscaping 100%
Fencing 100%
Solar Panel /Generator/Inverter 100%
Testing and commissioning 50%
Snagging and closure 90%
Demobilization & Handover 80%
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 5 of 11 PROGRESS REPORT Date: 01/07/2020
Updated POW -See attached updated POW
3.0 Project Finish date
3.1 Project Finish Date – 6 months from commencement/Site handover
3.2 New Project Finish Date – 31 July 2019, Site handover
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 6 of 11 PROGRESS REPORT Date: 01/07/2020
4.0 Work Progress Photograph
Borehole complete
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 7 of 11 PROGRESS REPORT Date: 01/07/2020
Landscaping completed
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 8 of 11 PROGRESS REPORT Date: 01/07/2020
Progress Photos Contd.
Furniture completed
Furniture completed
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 9 of 11 PROGRESS REPORT Date: 01/07/2020
Gate completed coml
Fence completed
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 10 of 11 PROGRESS REPORT Date: 01/07/2020
Computer Lab completed
WEEK 113 BETAGOD INVESTMENT LIMITED Doc. BGIL/TUPNI/113/20918
No.
CONSTRUCTION AND EQUIPPING
OF MODEL SECONDARY SCHOOL.
OGINIBO, JEREMI CLAN, DELTA
STATE
Page 11 of 11 PROGRESS REPORT Date: 01/07/2020
Power connected