Chilled Water Piping Installation Method

The document is a method statement for installing and testing chilled water piping at the Burj Dubai residences project. It outlines the materials to be used, including black steel pipes and fabricated fittings. It describes the method for storing, preparing, and installing the piping through steps like lifting pipes with cranes, marking pipe routes, cutting pipes to length, preparing joints, and assembling piping sections. The piping will be installed in trenches and supported by fabricated steel structures, then pressure tested before being insulated.

Uploaded by

Alaa Anwer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
145 views10 pages

Chilled Water Piping Installation Method

The document is a method statement for installing and testing chilled water piping at the Burj Dubai residences project. It outlines the materials to be used, including black steel pipes and fabricated fittings. It describes the method for storing, preparing, and installing the piping through steps like lifting pipes with cranes, marking pipe routes, cutting pipes to length, preparing joints, and assembling piping sections. The piping will be installed in trenches and supported by fabricated steel structures, then pressure tested before being insulated.

Uploaded by

Alaa Anwer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 10

Burj Dubai – The Residences Nasa Multiplex

Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

Burj Dubai – The Residences

Design Consultant
Woods Bagot

MEP Consultant
Roberts & Partners

Revised as per
2 Consultant 04.07.04
Comments
Issued for
1 10.06.04
Approval
Issued for
0 08.06.04
Approval
ETA M&E ETA M&E NMX MACE

Rev. Description Date Prepared By Reviewed Approved Approved


By By By

Page 1 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

1.0 Scope :

1.1 This method statement applied to installation, pressure testing, joint insulation
of chilled water piping including and accessories.

2.0 Purpose :

2.1 Purpose of this method statement is to outline the method of storage, handling,
fabrication, installation, pressure testing, joint insulation and water piping
including fittings.

3.0 Material :

3.1 Pipes

ERW, black steel, SCH 40, Grade ‘B’

3.2 Fittings

Fabricated MI fittings, grooved ends.

3.3 Supporting Materials

Fabricated MS structured supports. (Sketch enclosed)

4.0 Method :

4.1 Storage :

4.1.1 All material while unloading shall not be dropped, but slowly lowered
to the ground with the help of mobile / tower crane.

4.1.2 For pipes, wooden supports shall be placed beneath at equal distance. If
stored on the floor.

4.1.3 Pipes shall be stacked on a flat surface with adequate supports.

4.1.4 End caps of pipes shall be in place until removed for installation.

Page 2 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

4.1.5 While stacking, it shall be ensured that pipes of bigger sizes are placed
below and smaller sizes on top.

4.1.6 All pipes shall be covered and shall not be exposed to direct sunlight.

4.1.7 Insulation material shall be segregated as per size, thickness for easy
retrieval, stores out of direct heat.

4.1.8 Manufacturers instructions for storage shall be followed for applicable


items.

4.2 Preparation :

4.2.1 Check and ensure all drawings used for installation are latest and
approved for construction.

4.2.2 Mark the pipe routing and support locations in the trench as per
approved drawings.

4.2.3 Check the co-ordination of piping layout with other services and decide
pipe route with minimum bends/offsets.

4.2.4 Check and ensure sufficient clearance around pipe for applying joint
insulation.

4.2.5 Fabricate the structural supports from MS angle / channels .

4.3 Installation :

4.3.1 Lift pipe with the help of mobile / tower crane and rope / chain and
kept on 40 Ft. trailer.

4.3.2 Shift drive trailer to the site.

4.3.3 Lift pipe with the help of tower crane rope / chain.

4.3.4 Unload at required position on the support and adjust the pipe.

4.3.5 Drill the holes in trench wall for fixing supports.

Page 3 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

4.3.6 Fix supports, as per sketch attached.

4.3.7 Lay full length of 12m long as it fits to the requirement.

4.3.8 For the shorter lengths requirement, measure the length as per site
condition.

4.3.9 Mark short length requirement on the pipe, remove the insulation
locally, cut the pipe with the help of gas cutting set, 200mm longer than
required then machine cut end of pipe to extract length.

4.3.10 Short pieces to be jointed by grooved ends will be square cut with
mechanical cutter.

4.3.11 Prepare the pipe ends according to the type of joints ie. welded joint /
grooved joints.

4.3.12 The end preparation shall be done at site workshop.

4.3.13 Welding / grooving as applicable shall be done as per fitting / coupling


manufactures recommendations. Refer attached copy of relevant pages
of Victaulic catalogue for groove preparation.

4.3.14 Shorter lengths of pipe that can be handled by machine (upto 2 Mtr)
may be grooved joint or welded joint. Larger length pipes shall have
one welded joint either side.

4.3.15 End preparations for welded joints shall be done as per approved
welding procedure. Method Statement M-017.

4.3.16 After the end preparation clean the pipe ends and ensure no material
and dust is left inside.

4.3.17 Depending on site conditions, assemble the piping into manageable


lengths on the floor. Using threaded, welded/groove coupled jointing as
applicable.

4.3.18 Qualified and approved welders shall be engaged for welding works.
Current certificates provided with M/S-M-017.

Page 4 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

4.3.19 Install the pipe spool at heights as per approved drawings in a neat and
tidy manner.

4.3.20 Align and level the piping as per approved drawings.

a. Pipes to be kept on the levelled (with the help of water column


tubes) supports.
b. Bring the pipe ends touching to each other.
c. Check the alignment with the help of sprite level / set square at the
four opposite point on the pipe periphery.
d. Adjust the alignment with help of slight knocking of hammer on the
pipe.
e. Repeat above procedure till sprit level / sequence give +15%
deflection.

4.3.21 Make provisions for installing drain and air vent points as per approved
drawings.

4.3.22 Fix the blind plugs / temporary valves on all drain, air vent.

4.3.23 Make temporary tapping provisions at multiple points for easy and
quick filling and draining of pressure testing water.

4.3.24 Ensure all joints are properly tightened.

4.3.25 Raise the “Work Inspection Request (WIR)” of piping installation by


NMX QA/QC and consultant. Obtain clearance for hydraulic pressure
testing.

4.4 Pressure Testing :

4.1 The chilled water piping shall be tested according to the system working
pressure and PN ratings of the pipes, pipe fitting and valves used in the
piping. Test pressure as follows :

Floor piping test pressure : 15 Bar


Risers (Low & High) and trench piping : 20 Bar

Page 5 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

4.2 The piping may be tested in sections or in total, depending on site


requirements.

4.3 Estimate the piping volume and make arrangement for required quality
of clean water.

4.4 Arrange for temporary piping / hose pipe connections for filling and
draining the water.

4.5 Fix the temporary valves at air vent / drain points and approved and
pressure gauges.(Calibration Certificates provided).

4.6 Fill the piping system with clean water.

4.7 Warning signs will be displayed while carrying out pressure testing,
barriers to be erected to exclude other workers.

4.8 During initial filling, employ sufficient man power to monitor the entire
length of the piping system for possible leakages.

4.9 If leakages are observed, arrest the leakage immediately. If leakages are
major, isolate the leaking portion with nearest isolating valve and / or
stop the water filling / drain down completely where tests are partial and
no values are installed.

4.10 Rectify the leakages and again fill the water.

4.11 Ensure no leakages throughout the entire piping system.

4.12 Observe for the leakages and pressurise the system using hydraulic test
pump.

4.13 During pressurisation observe the joints and entire piping system for
leakages.

4.14 Pressurise the system till pressure on the pressure gauge at lowest part of
the system indicates pressure.

4.15 Observe the pressure gauges readings for 8 hours and ensure there is no
drop in gauge pressure.

Page 6 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

4.16 Raise the “WIR” for witnessing the hydraulic pressure testing by NMX
QA/QC and consultant.

4.17 Obtain proceed with clearance for insulation only after satisfactory
pressure testing.

4.5 Joint Insulation

Field joint insulation procedure

Field joint insulation shall be applied after the preinsulated pipes are installed and
joined, either by welding or mechanically with mechanical couplings, and pressure-
tested per the project’s specifications. If the preinsulated piping system is supplied
with leak detection / location system, please refer to the leak detection installation
procedure prior to insulating the joints. Field insulation application at joints shall be
as follows:

4.51. Joint Preparation

Ensure that the joint was tested and leak-free. Clean the surface of the pipe
joint and remove any foreign material around the joint to be insulated. Make
sure the joint is clean and dry. Apply by brush, red-oxide primer to the
welded area and any scratched or damaged area.

4.5.2 Installation of G.I. sheet metal mould

4.5.3 Place the galvanized sheet metal mould/roll-up around the joint area. Ensure
that the length of the mould is centered and equally distributed at each of the
adjoining jacket pipe ends.

4.5.4 Locate the pouring hole and position on top of the joint.

4.5.5 Fasten the mould tightly with plastic straps or wires at three locations to
ensure tightness between the jacket and the mould.

4.5.6 To ensure a complete closure of the G.I. sheet metal mould, apply 4mm Dia
rivets every 2” distance along the G.I. overlapping ends.

Page 7 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

4.5.7 Seal both of the mould ends utilizing two wraps of mastic, duct or gray tape
of 2” width.

4.5.8 Pouring of PU foam chemicals

After the sheet metal mould is securely placed on the field joint to be
insulated, weigh the required amount of chemicals, Polyol & Isocyanate
(ISO), in separate cups. Please note that Polyol has a distinctive smell, with a
pale-to-dark yellow color; ISO is colored black. Both chemicals should not
be exposed to air-moisture or heat for long hours. Make sure the chemicals
containers are closed tightly after usage.

First, pour the Polyol (weighed in a cup) into the mixing cup/bucket. When
ready to mix, pour the ISO (weighted in a cup) into the mixing cup/bucket
with Polyol and using electric drill with mixer blade attached, mix the two
chemicals for 20 seconds. Make sure the chemicals are thoroughly mixed.
When the color of the mixture changes (from dark to pale yellow) or when
the mixture is starting to rise, pour immediately (as quickly as possible) the
mixture through the pouring hole of the mould. Allow few minutes for the
foam to rise, then, plug the pouring hole to refrain rising foam from coming
out of the hole.

4.5.9 Polyol and Isocyanate has to be kept in closed container until it is finally
poured in the mixing bucket.

4.5.10 Heat shrinkable sleeve will only be applied to the ends of the HDPE mould
for sealing.

4.5.11 Remove any excess foam at the mould seams and pouring hole. Clean the
surface of the sheet metal mould. Remove the plastic straps/wires.

4.5.12 Cut the shrink sleeve to the required length. Remove the plastic backing of
the shrink sleeve and place one end of the shrink sleeve on top of the mould
and wrap around the joint allowing some overlap at the top of the joint
(about 50mm for smaller pipe sizes to 150mm for larger pipe sizes). Ensure
that the width of the shrink sleeve is centered with the joint to be sealed,
completely covering the entire length of the mould.

4.5.13 The shrink sleeve should be loose when in place. This will compensate for
the shrinkage of the material when heated.

Page 8 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

4.5.14 Using the torch, pre-heat slightly the inner adhesive part of the closure patch.
Position the closure patch so that the patch is centered on the overlap along
the full width of the shrink sleeve.

4.5.15 With the torch, heat up the closure patch evenly. Do not overheat the closure
patch and with a gloved-hand, smoothen and tap lightly the closure patch to
ensure good bonding.

4.5.16 Start shrinking the sleeve from one end or from the middle and apply heat
circumferentially with the torch in brush-stroke motion until the shrink
sleeve is fully bonded on the joint. Do not overheat!

4.5.17 The sealing of the joint is completed when the melted adhesive is coming out
from the edges of the sleeves.

5.0 Inspection

5.1 “WIR” by NMX QA/QC and Consultant shall be raised for piping installation,
pressure testing, joint insulation and signed by Roberts & Partners.

5.2 Inspection shall be carried out as per installation checklist during installation, testing
and insulation stages by ETA QA/QC Dept.

5.3 The entire installation work shall be supervised by the supervisors/engineers.

6.0 Safety

6.1 Hot work permit will be obtained prior to the commencement of any hot works.

6.2 All safety precautions shall be followed as per established project safety plan and
procedure.

6.3 Warning signs shall be displayed while carrying out pressure testing.

6.4 Only experienced and skilled technicians shall be engaged for carrying out
installation and testing work.

Page 9 of 10

525028106.doc
Burj Dubai – The Residences Nasa Multiplex
Client :-
ETA
MEP Contractor
Emaar Properties (1804)
M&E Division
Method Statement Title Method Statement No.
Installation and testing of Chilled Water Piping ETA / MS / M – 002.A
(Pre-insulated) Rev. No. & Date:
‘2’ 04.07.2004

6.5 The people involved in the installation shall use PPE such as safety helmets, safety
shoes, helmets, gloves etc.

6.6 Safety office shall check and ensure that all safety precautions are followed.

6.7 Safety office shall check and ensure chat all scaffolding and ladders used at
site are having duly signed tags.

6.8 Fire extinguishers will be provided near to the hot work areas.

6.9 Welder screen for Arc Welding will be erected to protect against arc eye of other
persons.

6.10 Necessary precautions shall be taken for fumes which are flammable, toxic and
dangerous to humans.

7.0 References

7.1 “WIR” duly signed by ETA/NMX QA/QC and consultant for

i) Piping Installation
ii) Pressure Testing
iii) Insulation

8.0 Non Destructive Testing

See Method Statement M-018 (shall be submitted by specialist)