Lecture Notes w11
Lecture Notes w11
Mustafa Bağrıyanık
Prof.Dr.
Istanbul Technical University
Department of Electrical Engineering
Maslak, 34469, TURKEY
S V I*
S V .I
S 3.V .I*
P 3.V .I . cos
S P2 Q2
P V .I . cos
Q V .I . sin Q 3.V .I . sin
MV LV
Shunt reactor
compensation
Effect of shunt reactors
• Shunt reactors may be installed in the
following conditions:
– To compensate for overvoltages occurring at
substations served by long lines during low-
load periods, as a result of the line's
capacitance (Ferranti effect as voltage tip up)
– To compensate for leading power factors at
generating plants, resulting in lower transient
and steady-state stability limits
– To reduce open-circuit line charging kVA
requirements in extra high-voltage (EHV)
systems.
Synchronous compensators
Q’
q cos 0.8 36.87
1
q’
Q P tan q 100 tan36.87 75 kVAr P
S 100 j 75 kVA QC
PF of 0.95 requires q desired cos1 0.95 18.19
S new 100 j 75 Qcap
75 Qcap
tan18.19 75 Qcap 32.86
100
Qcap 42.14 kVAr
Tariff example
In Turkey, for residental customers whose power is less than 9 kW, the
power supply authority delivers reactive energy for free.
• The power rate which equals active energy divided by reactive
energy, should not be only under the penalty limits,
• Electrical energy delivery companies charge a (poor) power factor
penalty.
• Typically, penalties are assessed if power factor measured at the
meter is less than 95%.
REACTIVE POWER LIMITS IN TURKEY
• Referring to figure, to
increase the power
factor to 0.8 would need
41 913 kVAR.
• Therefore, the factory would be charged $0.3757 x
30 x 41 913 = $472 401.42 over a month period,
which could be avoided by increasing the power
factor to 0.8!
• This should be more than enough economic
justification to install power factor correction (PFC)
equipment.
• As a very rough approximation, the capital
investment for PFC equipment can be
taken as $250/kVAR on 11 kV.
• Therefore, to add -42 MVAR capacitive
would mean a capital investment of $10.5
million, which would be paid back in
approximately 22 months.
• Approving power factor also have added
benefits, like reduced active and reactive
losses due to the reduction in the
magnitude of currents flowing.
INSTALLING SHUNT CAPACITORS
Power Factor correction configurations
• Loads can be corrected individually, in groups, or centrally
• The choice of configuration must be considered from both
an economic and technical point of view
Example 1
4km A 6km B 3km C
///
10kV Qc
300kVA 460kW
cos=0.6(lagging) cos=0.8 (lagging)
Line reactance per unit length x=0.4Ω/km,
conductivity of the conductor ϰCu =56m/m·mm2
cross-sectional area of the conductor q=25mm2
a) Calculate the maximum vertical (longitudinal) voltage drop if the power
of the capacitor at B is zero, Qc =0.
b) Calculate the power of the capacitor Qc so that the voltage drop at C is
zero. (∆VC =0)
Load 1
Load 2
700kVA
500kVA
cos =0.8 (lagging)
cos =0.85 (lagging)
5km
(3x25 mm2 )
34.5/15kV
2600kVA
cos =0.707 (lagging)
conductivity of the conductor ϰCu =56m/m·mm2
A textile mill, with 400V supply voltage, has a maximum demand of 8MVA at
a power factor of 0.9 (lagging) with compensation in the daytime. Without
compensation capacitors, the mill operates at 0.6 (lagging) power factor. At
night, the mill operates at its quarter of maximum power. Calculate the
power factor at night when there is reactive power compensation.