The Case Study On Penang South - Island Reclamation (PSR) Megaproject
The Case Study On Penang South - Island Reclamation (PSR) Megaproject
Team members
CONTENTS
01 INTRODUCTION………4
02 CASE STUDY: PENANG SOUTH
ISLAND RECLAMATION (PSR)
MEGAPROJECT……….10
03 CURRENT MALAYSIAN
ENVIRONMENTAL LAWS AND
POLICIES ……………25
04 POTENTIALITIES AND
CONSTRAINTS OF THESE
LEGISLATIONS……….34
05 CONCLUSION &
WAY FORWARD………..38
INTRODUCTION
Malaysia is a signatory to the ASEAN Declaration on Environmental
Sustainability which, inter alia, declared to “promote conservation
and sustainable management of key ecosystems, including
forests, coastal and marine habitats and to increase the
cumulative forest cover in the ASEAN region by at least 10 million
hectares by 2020”.
Source: https://asean.org/?static_post=asean-declaration-on-environmental-sustainability
“Asia’s growth is tremendously dirty, polluting, damaging and
carbon intensive.” Sachs said the situation is no different in
Malaysia that while on the path of development, it is not
developing sustainably. He added that Malaysia has
remarkable bio and cultural diversity, but they are not being
adequately protected. (Jeffrey D. Sachs, 2012)
Penang was originally founded by Captain Francis Light when
he took possession of the land on behalf of East Indian Trading
Company on year 1786.
"The protective measures for the properties are adequate. Both towns exhibit a
generally acceptable state of conservation, although efforts are required to ensure
the conservation of shophouses. The management plans and structures are
adequate, and can be enhanced through the continuing conservation programs of
the State Party."
P
R
E
S
E
R
V
E
RAPID URBANISATION
INDUSTRALIZATION
FINANCIAL ADVANTAGES
CASE STUDY: PENANG SOUTH
ISLAND RECLAMATION (PSR)
MEGAPROJECT
Project owner and PDP
Penang State Government owned this project. The Project delivery partner (PDP) is
SRS CONSORTIUM which consists of GAMUDA, Ideal Property, and Loh Phoy
Yen Holdings. SRS manages the two mega projects, PSR and PTMP and the State
Government pays SRS a 6% fee based on the construction cost PSR (RM11billion
for reclamation works)
Penang Transport Master Plan (PTMP)
The PSR was to fund the RM46 billion Penang Transport Master Plan (PTMP). The
reclaimed islands will belong fully to State Government but most of the land will be
auctioned off to fund PTMP so the transport plan could be entirely self- funded
Tourism Destination
Targeting average tourism spending as well as new international
high-value destination products
Climate Action Life Below Water Life On Land Peace, Justice, and Partnerships
Strong Institutions
J. W. S. Zeng, 2020)
“a playground for city
planners and architects
to give their best design”
a mixed development
project.
THE CONCEPT
“urban mosaic”
It will provide residents with approximately 4.6 km of public beaches, 600
acres of parks, and a 25 km waterfront. The project is conceived as an
urban mosaic of three diverse islands with a clear focus on livability,
environmental sustainability, and social and economic inclusivity. The
three islands bring together mixed-use districts of 15,000 to 18,000
residents across 50 to 500 acres, and a continuous 50 to 100m buffer
around each district, establishing habitat connectivity and supporting edge
ecologies in reserves, parks, corridors and urban plazas.
“the channels”
Meanwhile, newly
established marine The phases of construction:
habitats support 1- active destinations include
biodiversity underwater a wave pool and
by providing spawning technology park;
grounds for native species, 2- a civic heart establishes
and recreational points and governance and research
hatcheries support the local institutions in the area;
communities along 3- a cultural coast builds upon the
Penang’s southern coast. heritage and vibrant creative
energy of Penang’s George Town
Then is continue with phase 2 of the development which is Sri Tanjung Pinang
2 (STP2) which are yet achieve their target completion date on 2019.
The proposed reclamation development (Left & Center photos) STP 1 in 1996
(Right photo) STP 1 in 2015
OTHERS RECLAMATION PROJECTS IN PENANG.
1 2 3 4 5 6
Administration Prohibition and Control Miscellaneous
of Pollution
03
Conservation of country’s unique and diverse cultural
and natural heritage with effective participation by all
Commitment and Accountability
7
sectors of society, and
8 Active Participation in the International Community
Environmental Impact Assessment (EIA)
The EIA was introduced in the EQA in 1986. It has now become an important part
of the environmental law scene.
All prescribed activities need to obtain EIA approval from the Director General of
Environment prior to the giving of approval by the relevant Federal or State
Government authority for the implementation of the project. The Approving
Authority is the Government Authority that has the task of deciding, whether or
not a project should proceed.
Due to the sensitivity of the project and polluting potential (significant impacts)
from the construction and/or operations, some of the prescribed activities have
been required to go through the Detailed EIA Procedures which involves public
participation.
STEP 03
A. H. Embong (2015)
Legislation insufficient
1
Not sufficient legislation governing the coastal zone and marine
area, and most of Environmental Laws and policy are an act that
Lack of enforcement
4
Lack of enforcement to ensure the legislation and
environmental management plan implemented as per
control the developments with minimal impacts to environment plan
and not to stop destruction to natural environment.
No SOP
no standard procedures that apply to criminal
environmental cases and the procedures are
2 Corruption
Corruption (or complacency) of our enforcement
officials and politicians
5
essentially the same with the normal criminal cases
Light sentences
3
the Malaysian courts were criticized for imposing light
sentences against environmental offenders and poor
Ecological complexity
6
The complexity of Malaysia’s ecology has also been a
challenge to ensure consistent monitoring of
judicial awareness in protecting our marine wildlife enforcement
against destruction of marine and water pollution
A. H. Embong (2015)
It is not a prerequisite to developmental projects.
01 The fact remains that projects do go on without the said approval as what happened in the case of Tenggara Gugusan Holidays Sdn Bhd v Public
Prosecutor a case regarding a resort project on the beach of Kampung Pulau Kerengga, Marang, Terengganu. Although the crux of the decision
was the definition of "any person"," the case was brought to court because the EIA report was completed after the
project itself was completed, thus making a mockery of the process as well as being in breach of the EQA.
There is a conflict of interest in the writing of the EIA report as the consultants who prepare the
02 report are hired by the development company.
The DOE has a list of consultants which they endorse, but a developer is free to choose his own. It does not take a large stretch of the imagination
to see that a consultant is highly unlikely going to prepare an unfavorable report for the very person who is paying him.
There are too many loopholes in the criteria of projects that require an ElA report.
03 For example housing projects only need an EIA report if they are over 50 hectares in size." All it takes is for a developer to break his project into
smaller lots and he can in that way circumvent the EIA requirement.
CONCLUSION & WAY FORWARD
list of references
S. Abdullah & H. K Loi (1992), Coastal Reclamation In Malaysia retrieved from https://www.water.gov.my
/jps/resources/auto%20download%20images/5844e2d67f042.pdf
Dr. Nik & Associates Sdn. Bhd (2017) , Environmental Impact Assessment 2nd Schedule Study for the
proposed Reclamation & dredging works for the penang south reclamation (PSR) retrieved from
http://anyflip.com/zxcu/zmtw
E. Teh (2019) What is the Penang South Reclamation (PSR)?, in A penang forum series, reclamation : a ticking
time bomb, retrieved from https://penangforum.files.wordpress.com/2019/09/what-is-the-penang-south-
reclamation-psr-1-2.pdf
S . Y Chee et all (2017) Land reclamation and artificial islands: Walking the tightrope between development
and conservation.
J. W. S. Zeng,(2020), Evaluating the Penang South Reclamation (PSR) Project According to the United
Nations’ Sustainable Development Goals retrieved from https://penanginstitute.org/publications/issues/
evaluating-the-penang-south-reclamation-psr-project-according-to-the-united-nations-sustainable-development-
goals/
S. Khoo (2020), Save Penang! Reject the 3-Islands Reclamation! retrieved from https://www.change.org/p
/prime-minister-of-malaysia-save-penang-reject-the-3-islands-reclamation?signed=true
N. Mohammad ( 2011), Environmental Law and Policy Practices in Malaysia: An Empirical Study
S.Loone (2017), EIA report on Penang reclamation projectfinally on display, retrieved from
https://www.malaysiakini.com/news/383384
list of references
A. Dermawan (2019), Penang details 72 DoE conditions for PSR project, The New Straits Times,
https://www.nst.com.my/news/nation/2019/07/504839/penang-details-72-doe-conditions-psr-project
https://www.malaysiakini.com/letters/496247
https://pg-mdc.com/main/
https://www.lonelyplanet.com/articles/biodivercity-malaysia
https://www.hmetro.com.my/mutakhir/2019/11/513817/bantahan-nelayan-aktivis-tolak-tambak-metrotv
Penang2030, A Family-Focused Green and Smart State that inspires the nation, first edition (2019)
www.penang2030.com