Method of Statement For Fire Fighting Works (Part-1)
Method of Statement For Fire Fighting Works (Part-1)
(Part-1)
Purpose:
This method describes the detailed procedure for installation and Testing of Wet Raiser Fire Protection System,
Pipes, Sprinkler, Fire Pumps, Valves and Fire Fighting Accessories as per the standard Practice and Codes.
Inspection of Materials:
Inspection of Pipe / Valve / Flanges:
Check Type of Material, Size of Material , Make of Material.
Chemicals such as paints, primer and thinner, check their expiration date before receiving.
Physical Damages Inspection:
In case of any damages observed during inspection, the concern report will be issued and Material shall
be returned to the supplier for replacement.
Installation Procedure:
(1) Pipe Hanger / Support Installations
Piping Route will be the as per most advantageous manner possible with respect to headroom, valve
access, opening and equipment clearance, and clearance for other work.
The Line layout should be verified from Site in charge.
After marking the pipe routes, the anchoring points will be drilled according to the required support
spacing as shown on the approved shop drawings.
Pipe Diameter (mm) Maximum Hanger Spacing (mm) Rod Size (mm)
25 2000 8
32 2500 8
40 2500 8
50 2500 8
65 2500 10
80 2500 10
100 * 2500 * 12 *
150 * 3000 * 16 *
200 * 3000 * 16 *
* As per Site Requirement Fabrication Support may be used.
Mark out the location of hanger thread rods for pipe installation as per the approved construction
drawing.
Fasteners and fully threaded rods shall be used for installing the pipe supports. The sizes of pipe
supports and installation shall be in accordance with manufacturer’s recommendations.
For Single pipes of size 100 mm and above, with the prior approval 50xx50xx6 mm MS Angle iron and
for Double Pipe 75x75x6mm with U Clamp with Fastener may be used for Supporting horizontal Pipe
from ceiling.
Drill the marked position for hangers and supports by using the drill bit of appropriate size.
Fix the unfix anchor at drilled position by gentle and uniformly hammering.
Fix the threaded rod of appropriate diameter and size & length in the anchor by twisting by turning.
After fixing the threaded rod, insert a washer of appropriate size in to the rod.
Finally fix the washer near to the slab by tightening a nut over it, this will improve the strength and load
bearing capacity of threaded rod.
For installing pipes vertically or horizontally inside the building standard pipe supports of reputed make
shall be used. Following supports shall be used.
Clevis Hangers or MS Chanel for horizontal supports to adjust varying heights.
The Pipe route should be min 500mm away from wall.
Supports will be arranged as near as possible to pipe joints and any change in direction.
Vertical Riser Support:
Risers shall be supported by pipe clamps or by hangers located on the horizontal connections within 24
inches (0.6 Meter) of the centerline of the riser.
Welding Electrodes:
Electrodes used for welding should comply with IS:814, 1991.
Generally all welding shall be performed using Shielded metal arc welding (SMAW) process using
cellulosed-coated electrode (E6013 type) for root run and subsequent passes
Storing of Welding Electrodes:
Welding electrodes shall be stored in indoors free from moisture.
Qualified and certified welders only shall do welding.
No welding shall be done if there is impingement of any rain, or high winds
Fabrication of Pipe (But Welding):
The welding of pipes in the field should comply with IS:816, 1969.
All pipes and fittings shall be cleaned of Dust, Mud from inside and outside before Welding.
All pipe, fittings shall be smooth, clean and free from blisters, loose mill scale, sand and dirt prior to the
installation.
1. Edge Preparation: Before welding, the ends shall be cleaned by wire brush, filing or grinding and
making “V” on edge of both pipe.
2. Welding of Root Run: Primary Welding shall be done by E6013, 2.5mm Welding Rod (90 to 90A, 18
to 25V) of approved make.
3. Chipping and Cleaning of Root Run: Each weld- Root run shall be thoroughly cleaned to remove the
slag, irregularities and any defects, before the next run is deposited.
4. Final Welding Run: Final Welding shall be done by E6013, 3.5mm Welding Rod (80 to 140A, 20 to
25V) of approved make.
5. Chipping and Cleaning of Final Run: Each Final weld shall be thoroughly cleaned to remove the slag,
irregularities and any defect
All lines shall be suitably supported so as to provide rigidity and avoid vibrations.
Proper lines and levels shall be maintained while installing exposed pipes.
All lines less than 50 mm NB size can be socket welded to matching rating fittings.
All lines above 50mm NB size shall be butts welded with full penetration welds.
All bolts, nuts and washers used shall be of GI.
Extra supports shall be provided at the bends and at heavy fittings like valves to avoid undue stress on
the pipes.
Open ends of piping shall be blocked as soon as the pipe is installed to avoid entrance of foreign matter.
Pipes must be of Heavy grade M.S. pipe conforming to IS 1239. The pipes, fittings and installation shall
be hydraulically tested to a pressure of 15 Kg/Sq.cm. or 1.5 times the working pressure whichever is
higher.
(4) Flanges:
Mild steel flanges shall be in accordance with Table – 17 of IS : 6392 i.e. “Plate Flanges for Welding”
and flange thickness shall be as under. Gasket thickness shall not be less than 3 mm.
Check the flange size and specification according to pump size and valve size,
Flange Details
Pipe Dia Flange Thickness No. of holes
200 mm. 24 mm. 12
150 mm and 125 mm 22 mm. 8
100 mm and 80 mm 20 mm. 8
65 mm. 18mm 4
40 mm and below. 16mm 4
All hardware items such as Nuts, Bolts, and Washers shall be of appropriate size.
Washers shall be used on both sides of the bolt.