Voli I I Cost Estimate
Voli I I Cost Estimate
RECAPITULATON SHEET
Abstract
PWD(NH)Div. Thane QTCPL
PREPARATION OF DETAILED PROJECT REPORT (DPR) FOR
REHABILITATION AND UP-GRADATION OF EXISTING ROAD
FROM KM 84.00 TO KM 101.00 OF MALSHEJ GHAT OF NH-
61 IN THE STATE OF MAHARASHTRA ON ENGINEERING,
PROCUREMENT & CONSTRUCTIONS (EPC) BASIS
CONTRACT. (DESIGN LENGTH – 15.29KM)
ABSTRACT SHEET
Cost Estimate
ABSTRACT
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
I Site Clearance
2 Excavation in Earthwork
Excavation in soil in hilly area by mechanical means including
2.01 cutting and trimming of side slopes and disposing of excavated Cum 27700.00 189.00 5235300.00
earth with all lifts and lead upto 1000 metres.
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
Excavation for catch / side water gutter in all sorts of soils to the
specified section including stacking the excavated stuff in a regular
7.01 Cum 24910.00 370.00 9216700.00
bund and disposing of unsuitable or excess stuff as directed all sorts
of soils.
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
10 Culverts
Dismantling of Structures (Dismantling of existing structures like
culverts, bridges, retaining walls and other structure comprising of
masonry, cement concrete, wood work, steel work, including T&P
10.01 Cum 297.00 813.00 241461.00
and scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres)
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
Providing & fixing Solar Powered Traffic Blinkers LED based 300
mm/200 mm dia signal head with In built blinker unit having
11.03 battery & battery charger unit with photo electric switch complete Nos 22.00 75000.00 1650000.00
as per technical specification clause 112 and as directed by the
Engineer.
PWD(NH)Div. Thane QTCPL
Cost Estimate
Sr. No. Item Description Unit Qty. Rate in Rs. Amount in Rs.
PWD(NH)Div. Thane QTCPL
PREPARATION OF DETAILED PROJECT REPORT (DPR) FOR
REHABILITATION AND UP-GRADATION OF EXISTING ROAD
FROM KM 84.00 TO KM 101.00 OF MALSHEJ GHAT OF NH-
61 IN THE STATE OF MAHARASHTRA ON ENGINEERING,
PROCUREMENT & CONSTRUCTIONS (EPC) BASIS
CONTRACT. (DESIGN LENGTH – 15.29KM)
MEASUREMENT SHEET
Rehabilitation and Up-gradation of Existing Road from Km.84.00 to
Km 101.00 of Malshej Ghat of NH- 61 in the state of Maharashtra on
Engineering, Procurement & Construction (EPC) Basis Contract.
(Length = 17.00 km)
Typical Cross Schedule
Chainage (m)
Sr.no. Length (m) C/s Type
From To.
1 83700 83800 100 TCS‐1a
2 83800 84500 700 TCS‐1a
3 84500 84594 94 TCS‐4a
4 84594 84667 73 TCS‐3a
5 84667 84800 133 TCS‐4a
6 85000 85270 270 TCS‐4a
7 85270 85294 24 TCS‐3a
8 85294 85337 43 TCS‐4a
9 85337 85411 74 TCS‐3a
10 85411 85572 161 TCS‐4a
11 85572 85602 30 TCS‐3a
12 85602 85947 345 TCS‐4a
13 85947 86025 78 TCS‐3a
14 86025 86261 236 TCS‐4a
15 86261 86538 277 TCS‐3a
16 86538 86649 111 TCS‐4a
17 86649 87184 535 TCS‐4a
18 87184 87205 21 TCS‐3a
19 87205 87238 33 TCS‐4a
20 87238 87331 93 TCS‐3a
21 87331 87360 29 TCS‐4a
22 87360 87619 259 TCS‐3a
23 87619 87681 62 TCS‐4a
24 87681 87738 57 TCS‐3a
25 87738 87857 119 TCS‐4a
26 87857 87906 49 TCS‐3a
27 87906 87923 17 TCS‐3a
28 87923 87978 55 TCS‐3a
29 87978 88015 37 TCS‐4a
30 88015 88079 64 TCS‐3a
31 88079 88232 153 TCS‐4a
32 88232 88295 63 TCS‐3a
33 88295 88442 147 TCS‐4a
34 88442 88500 58 TCS‐3a
35 88500 88717 217 TCS‐4a
36 88717 88742 25 TCS‐3a
37 88742 88891 149 TCS‐4a
38 88891 89028 137 TCS‐3a
39 89028 89458 430 TCS‐4a
40 89458 89520 62 TCS‐3a
41 89520 89600 80 TCS‐4a
42 89860 90000 140 TCS‐4a
43 90000 90750 750 TCS‐4b
44 91400 91517 117 TCS‐4b
45 92417 92624 207 TCS‐3a
46 92624 92862 238 TCS‐4a
47 92862 92893 31 TCS‐3a
48 92893 93070 177 TCS‐4a
49 93070 93095 25 TCS‐3a
50 93095 93630 535 TCS‐4a
Chainage (m)
Sr.no. Length (m) C/s Type
From To.
51 93630 93662 32 TCS‐3a
52 93662 93889 227 TCS‐4a
53 93889 93924 35 TCS‐3a
54 93924 93968 44 TCS‐4a
55 93968 94008 40 TCS‐3a
56 94008 94180 172 TCS‐4a
57 94180 94206 26 TCS‐3a
58 94206 94700 494 TCS‐4a
59 94700 94707 7 TCS‐4
60 94707 94991 284 TCS‐3
61 94991 95600 609 TCS‐4
62 95600 99880 4280 TCS‐1
63 99880 100280 400 TCS‐2
64 100280 100700 420 TCS‐4
65 100700 101000 300 TCS‐1
Total length in M 15290
Sr.No. Length in m
Typical Cross Section
extra 250 added for faning portion from Ch.
1 TCS‐1 4580 83.800 to Ch. 84.000
2 TCS‐1a 800
3 TCS‐2 400
4 TCS‐3 284
5 TCS‐3a 1912
6 TCS‐4 1036
7 TCS‐4a 5411
8 TCS‐4b 867
15290
Measurement Sheet
Rehabilitation and Up-gradation of Existing Road from Km.84.00 to Km 101.00 of Malshej Ghat of NH- 61 in the state of Maharashtra on Engineering,
Procurement & Construction (EPC) Basis Contract. (Length = 17.00 km)
MEASUREMENT SHEET
Sr.No. Item Description Unit Nos. L B D/H Qty Total Qty
Upgradation of Existing Road
1 Chapter 1. Site Clearance and Dismantling
Clearing and Grubbing Road Land .(Clearing and grubbing road
land including uprooting rank vegetation, grass, bushes, shrubs,
saplings and trees girth up to 300 mm, removal of stumps of trees
1.01 cut earlier and disposal of unserviceable materials and stacking of Hect
serviceable material to be used or auctioned up to a lead of 1000
metres including removal and disposal of top organic soil not
exceeding 150 mm in thickness.)
TCS 1 1 4580.00 2.60 1.19
TCS 1a 1 800.00 2.60 0.21
TCS 2 1 400.00 2.60 0.10
TCS 3 1 284.00 2.60 0.07
TCS 3a 1 1912.00 2.60 0.50
TCS 4 1 1036.00 2.60 0.27
TCS 4a 1 5411.00 2.60 1.41
TCS 4b 1 867.00 3.50 0.30
Total Qty 15290.00 4.05
NH PWD Div. Thane QTCPL
Measurement Sheet
NH PWD Div. Thane QTCPL
Measurement Sheet
for grade correction between Ch 98860 to Ch.100280 Cum 1 1420.00 15.00 3.50 74550.00
Excavation in Hard Rock (controlled blasting) with disposal
upto 1000 metres (Excavation for roadway in hard rock with
controlled blasting by drilling, blasting and breaking, trimming of
3.02 Cum
bottom and side slopes in accordance with requirements of lines,
grades and cross sections, loading and disposal of cut road with
in all lifts and leads upto 1000 metres )
Between Ch. 91900 to Ch. 92090 -Hillok side -Widening Cum 1 420.00 3.75 8.15 12836.25
for grade correction between Ch 98860 to Ch.100280 Cum 1 1420.00 15.00 4.50 95850.00
Considering 10% of total excavated qty = Cum 1 74550.00 10.00% assume 7455.00 7455.00
Excavation in Hard Rock (blasting prohibited) (Excavation for
roadway in hard rock (blasting prohibited) with rock breakers
including breaking rock, loading in tippers and disposal within all
3.03 Cum
lifts and lead upto 1000 metres, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections.)
Considering 20% of total excavated qty = Cum 1 74550.00 20.00% assume 14910.00 14910.00
NH PWD Div. Thane QTCPL
Measurement Sheet
NH PWD Div. Thane QTCPL
Measurement Sheet
NH PWD Div. Thane QTCPL
Measurement Sheet
NH PWD Div. Thane QTCPL
Measurement Sheet
NH PWD Div. Thane QTCPL
Retaining Wall
NH PWD Div. Thane QTCPL
Retaining Wall
Painting
For Breast Wall Sqm 1.00 1,150.00 1.40 1610 1610
NH PWD Div. Thane QTCPL
Junctions
JUNCTIONS
NH PWD Div. Thane QTCPL
Culvert
Rehabilitation and Up-gradation of Existing Road from Km.84.00 to Km 101.00 of Malshej Ghat of NH- 61 in the state of
Maharashtra on Engineering, Procurement & Construction (EPC) Basis Contract. (Length = 17.00 km)
BILL OF QUANTITIES
Pipe Pipe Box
Sr.No. Item Description Unit Culverts Culverts Culverts Total Qty
(Recons + (Widening
10 Culverts
Dismantling of Structures (Dismantling of existing structures like
culverts, bridges, retaining walls and other structure comprising of
masonry, cement concrete, wood work, steel work, including T&P
10.01 Cum 0.00 297.00 297.00
and scaffolding wherever necessary, sorting the dismantled material,
disposal of unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 metres)
Dismantling stone masonry in lime or cement mortar including
10.02 Cum 0.00 2217.60 255.00 2472.60
stacking the materils as directed with all leads, lifts etc.
Dismantling of existing RCC Hume Pipes of all diameters and
disposing the same at areas approved by Engineer in Charge with all
10.03 Rmt 495.00 495.00 990.00
leads and lifts. Pipes in sound conditions shall be re-used for
construction as directed by the Engineer in Charge.
Excavation in soil in hilly area by mechanical means including cutting
10.04 and trimming of side slopes and disposing of excavated earth with all Cum 712.80 712.80 52.00 1477.60
lifts and lead upto 1000 metres.
Excavation for roadway in ordinary rock by deploying a dozer, 80 HP
including cutting and pushing the cut earth to site of embankment
10.05 upto a distance of 100 metres ( average lead 50 metres ), trimming Cum 356.40 267.30 26.00 649.70
bottom and side slopes in accordance with the requirements of lines,
grades and cross sections.
Excavation in Hard Rock (controlled blasting) with disposal upto
1000 metres (Excavation for roadway in hard rock with controlled
blasting by drilling, blasting and breaking, trimming of bottom and
10.06 Cum 118.80 89.10 9.00 216.90
side slopes in accordance with requirements of lines, grades and cross
sections, loading and disposal of cut road with in all lifts and leads
upto 1000 metres )
10.07 PCC M15 Bedding Cum 429.00 858.00 155.00 1442.00
10.08 PCC M20 Cum 858.00 1716.00 220.15 2794.15
10.09 RCC M30 Conc Cum 425.00 425.00
10.10 NP4 Pipe 1200mm dia Rmt 495.00 330.00 825.00
10.11 Flexible apron Cum 285.12 285.12 302.20 872.44
10.12 Stone pitching Cum 1374.78 1374.78 2749.56
10.13 Filter media Cum 526.68 526.68 1053.36
10.14 Earth fill Cum 6275.94 6275.94 12551.88
10.15 RCC M20 Pillar for inscribing structure no. Cum 10.56 10.56 21.12
10.16 Steel MT 42.45 42.45
PWD(NH) QTCPL
Box Culvert
Box Culvert - Size - 1 Cell- 2x2m & 2 Cell -2x2m (Qty for 3 nos.)
Flexible Apron
U/S Cum 1 8.06 6.00 0.75 36.27
D/s Cum 1 8.06 3.00 0.75 18.14
NH PWD Div. Thane QTCPL
Pipe Culvert
9 NP4 Pipe 1200mm dia (For recons) Rmt 1 15.00 15.00 495.00
10 Flexible apron Cum 1 6.40 3.00 0.30 5.76 D/S flexible apron
1 6.40 1.50 0.30 2.88 U/S flexible apron
for Reconstruction and new culverts 8.64 285.12
NH PWD QTCPL
Pipe Culvert
Qty for
Sr.no. Item Unit Nos. L B D For 33 Nos. Remarks
one
12 Filter media
for Reconstruction and new culverts Cum 4 surface area 26.60 0.15 15.96 526.68
NH PWD QTCPL
Pipe Culvert
10 Flexible apron Cum 1 6.40 3.00 0.30 5.76 D/S flexible apron
1 6.40 1.50 0.30 2.88 U/S flexible apron
8.64
for widening of culverts at 33 locations 1 285.12
Total Qty= Cum 285.12
11 Stone pitching
Cum 4 surface area 34.72 0.30 41.66 3.14rs+3.14r*r
NH PWD QTCPL
Pipe Culvert
Qty for
Sr.no. Item Unit Nos. L B D For 33 Nos. Remarks
one
for widening of culverts at 33 locations 1 1374.78
Total Qty= 1374.78
12 Filter media
for Reconstruction and new culverts Cum 4 surface area 26.60 0.15 15.96
for widening of culverts at 33 locations 1 526.68
Total Qty= 526.68
NH PWD QTCPL
Traffic management during construction and Maintenance during construction
Item No. DESCRIPTION Unit No. Length Width Depth Quantity
LAND ACQUISITION
Rehabilitation and Upgradation of Exsiting Road from Km.84.00 to Km.101.00 of Malshej
Ghat of NH-61 in the State of Maharahstra on Engineering Procurement & Construction
(EPC) Basis Contract. (Length = 17.00Km)
9426000.00
Calculate the value of assest (building, tree, etc) attached to the land
under acquisition in terms of section 29 of the RFCTLARR Act, 2013.
37452000.00
Add the amount determined under step 2 & Step 3 then provide for
100% solatium on the amount so arrived.
558000.00
Calculate the amount of interest on Basic Market Value @ 12% in terms
of section 30(3) of the Act.
116250.00
Note:- The Land rates are considered from Ready Reckoner Rates of State Government
R/R Proposal
Extimated
Quantity approximately subject Replacement Valuation
Sr.No. Item final valuation by PWD Unit Rate for Amount in Rs. Remark
Valuation as Lakh
on 2019
Number Area Sq.Meter
I Structure
A Temporary Structure 6 150 Sqm 7500 11.25
B Permanent Structures 4 250 Sqm 25000 62.5
Abstract Sheet
Unit Rate
Sr. No Particular Unit No L W D/H Qty Amount in Rs Remark
in Rs.
3 Transporation from Factory to Site MT 1 1.00 0.942 0.006 0.0443682 847.76 37.61
10 H.O. Supervision Charges @1.3% on Net Material Cost+Erection Cost 1.30% 89704.43
(D) PROVISION OF WORK :- LT Line Road Crossing using UG cable BY HDD Bore
1 Providing HDD Bore (Size: 200 mm Dia) for Mtr 600 2400 1440000.00
TOTAL 1440000.00
Scrap Value Sheet
Technical Estimate for Shifting of HT/LT/DTC due to improvement in road boundary &
road widening for National Highway (NH-61) Sawarne Km. 84+000 to Malshej at Km.
101+000 in r/o Executive Engineer,National Highway Division, Thane in the state of
Maharashtra.
S.No Particular Unit Qty Rate Amount
11KV Work
1 Pole RSJ Nos 4 11311 45244
2 Pole PSC Nos 10 0 0
3 Disc Insulator with H/w Nos 24 0 0
4 Pin insulator Nos 42 0 0
5 11KV V Cross arm with clamp Nos 10 639 6390
6 11KV Top Fitting with Clamp Nos 10 123 1230
7 Cut Point Channel Set's 4 895.10 3580.4
8 Bracing Set Set's 4 233.1 932.4
9 ACSR Conductor 03 Mtrs 1500 17.8 26700
10 HT Guarding Cross arm Nos 2 548.42 1096.85
Total of 11KV work Dismantaling Amount 85173.6
LT Work
1 Pole PSC Nos 8 0 0
2 Pole RSJ Nos 2 5268 10536
3 AAC Ant Conductor Mtrs 960 23.47 22531.2
4 AAC Gant Conductor Mtrs 320 18.5 5920
5 Guarding Channel Nos 0 0 0
6 D Clamp Nos 0 0 0
7 Vertical Nos 0 0 0
8 Shackel Insulator Nos 30 0 0
9 Shackel H/W Nos 20 0 0
10 Sudries Transportation Nos 0 0 0
Total of LT work Dismantaling Amount 38987.2