Method Statement IFC 03.09.19
Method Statement IFC 03.09.19
19 SECOND ISSUE
0 05.07.19 FIRST ISSUE
Rev Date Description Checked Approved
CONTRACTOR : STERLING AND WILSON PVT. LTD & ELECTROMONTAJ SA. UJV
Title :
Method Statement
Consultant’s Comments:
No new comments
Page 1 of 1
PROJECT: 220kV RUSUMO-NYAKANAZI TRANSMISSION LINE.
CONTRACT NO: RUS-TZ/PA/001/2017-18/HQ/W/22
Comments Received on: 18th July 2019
Document Title: Method Statement, Rev 0 - APPROVED EXCEPT AS NOTED
Title: REPLY TO CONSULTANTS COMMENTS
For Civil Works, after foundation excavation there shall be site soil
Included in Rev 01 – Method Statement of Civil Work, refer point
classification comparing with the laboratory test results for the
5E 1st para.
1 final type of foundation decision. This shall be done in the
presence of Contractor, Consultant/Client and there should be
forms for them to sign.
If the foundation is excavated deeper than necessary, the level Included in Rev 01 – Method Statement of Civil Work, refer point
2 shall be brought up to the required level by blinding concrete 5F.
Material used for backfilling shall be inspected by Consultant/Client Included in Rev 01 – Method Statement of Civil Work, refer point
3 before use. Imported material shall be used for backfilling when 5N.
incurring unsuitable material during excavation.
STRINGING; 5. ACTIVITIES The same will be produced at the beginning of stringing activity.
- Contractor shall submit to the Employer for approval a
fully detailed stringing schedule stating the following Sag Tension chart will be submitted & get approved prior to start of
indications as per employer requirement: stringing activity.
- The locations of conductor and earth wire drums and
pullers
- The proposed position of mid-span joints,
9 - The maximum tensions to be used during running out of
pilot wires, conductor, earthwire and OPGW
- The sag of each span and the stringing chart
- The crossing of roads, rivers
- The crossing and proximity of overhead lines (with their
definitive outage requests) or railroad
- Protection of important crossings
__________________________________________________________________________
A : General Direction: Included
The following should be added to bullet number five (5): The
additional loads imposed on specific support during conductor
stringing by the use of temporary guys shall be calculated and
submitted to the Employer for appraisal prior to conductor
stringing commencing.
In the same time please correct the Header of chapter "Civil Work" Corrected
__________________________________________________________________________
STERLING and WILSON METHOD DO C No .: SW-T&D-MS-SURVEY-001
RE V No .: 0 1
PVT LTD.
STATEMENT DA T E: 1 9 .0 7 .2 0 1 9
1. PURPOSE:
To establish Methodology on Survey work for construction of 220kV Rusumo-
Nyakanazi Transmission Line. This procedure establishes description and guidelines
for works performed during Survey Work.
It explains the duties of each worker, machinery used and methodology based on
international standards.
2. SCOPE:
Survey is the first and most important activity in the construction of Transmission Line.
The main objective of the survey is to establish the best possible shortest route in a
good terrain for the construction of transmission line. Survey works can be divided as
further:
• Preliminary Survey & Selection of Route
• Approvals & Clearances for the Line Route
• Detailed Survey
• Profile Plotting & Tower Spotting
• Check Survey & Location Marking
3. REFERENCE:
• Sterling and Wilson project plan
• Sterling and Wilson Health & Safety Plan
• Contract / Design Specification
• Approved Technical Data Sheets
• Approved Drawings
• Equipment must be in good condition and all safety devices functional and
active during all the time.
• Tools must be in good shape and not damaged or modified.
• Visitors or vendors must have permission to get in on site, they must attend a
brief about the HSE rules and sign the attendance sheet.
• Housekeeping and clean working area.
5. PRELIMINARY SURVEY & SELECTION OF ROUTE:
The initial route maps/topographical maps shall be obtained from concerned
authorities to have a fair idea about the route, terrain, angle points etc. Preliminary
Survey can be carried out with the help of GPS.
The preliminary route alignment shall be plotted on Topographical Maps to the scale
of 1 cm = 0.5km (1: 50,000).
All topographical details including Power Lines, Railway lines, rivers, canals, roads,
houses, orchard, mineral bearing/ mining area etc. on either side of the proposed
route alignment of transmission lines shall be drawn to scale.
• Alignment shall be plotted on the Map with NORTH being clearly indicated on
each drawing.
• Latitude and Longitude shall also be properly marked.
• For the convenience of handling, the width and length of the drawings shall be
restricted to convenient sizes with 30 mm overlaps between the sheets. The
match line shall be clearly shown on these sheets.
• The coordinates of the angle points and the section length between angle
points shall be noted down from the top sheets and it shall form the basis for
the walk-over survey to finalize the route alignment.
The following aspects should be considered before finalization of the route alignment.
• The line corridor selected is short and straight as far as practicable.
• From the point of view of ease of construction, the line should be close to the
roadway.
• The number of angle tower should be minimum.
• Cost of securing & clearing right of way, making access roads and time required
for these works is minimum.
• The line should be as far away as possible from telecommunication lines and
should not run parallel and close to these.
• Crossing with roads and railway lines should be minimum and preferably at
right angles.
• Difficult and unsafe approaches should be avoided.
• The lines should be away from buildings containing explosives, bulk storage oil
tanks and oil and gas pipe lines.
• The line route should be suitable for catering to future load developments
without major modifications.
6. APPROVALS & CLEARANCES FOR THE LINE ROUTE:
Each angle point location shall be shown in the top sheet with details of nearby
permanent landmarks, such as specific tree(s), house, tube-wells, churches, electric
pole/tower, telephone pole/tower, canal, roads, highways, railway lines etc. The
relative distance of land marks from the angle points and their coordinates should also
be given.
The Schedule of Angle points is to be submitted and brief description of the terrain
between the angle points and the distance should also be given.
Information regarding infrastructural facilities available along the route alignment like
access to roads, railway stations, construction material sources, fuel availability etc.
near proposed route shall be furnished in the preliminary survey report.
In case the route alignment encounters areas like forests, developed
industrial/residential zones which are unavoidable, the same shall be clearly marked
on the route alignment topographic sheets specifying the details like their
coordinates, boundary limits etc.
Some portions of the line may require clearance from various authorities. We should
indicate the portion of line so affected, the nature of clearance required and the name
of concerned organization such as local bodies, municipalities, telephone lines, inland
Navigation, Irrigation Department, Electricity Boards and Zonal Railways, Divisional
Forest Authorities, Defense area, Water and Gas Pipe line etc.
The contractor shall mentioned road crossings, telephone & power line crossings, river
crossings, human settlements if any nearby, HV & LT line crossings etc. so that these
data will help to spot the tower at proper locations. When the line passes through hilly
terrains, possible places for locating the towers shall be recorded in the survey field
books.
At all angle point location concrete block shall be buried to a depth of at least 300mm.
Identification Details shall be prominently marked/painted on the block.
Directional beacons at 30 to 50 m from angle point shall have to be provided for both
the directions.
During the survey, if not enough side clearance is found then side clearance survey
shall be conducted and submitted to Client/Consultant with recommendation for the
solution of problem.
If the difference in levels be too high, the chart may be broken up according to
requirement. A 300mm overlap shall be shown on each following sheet. The profile
shall progress from left to right. If the natural ground has a cross slope equal to or
greater than 1:10, an additional longitudinal profile will be surveyed parallel to the
route at 10m from the axis of the line, it will be plotted as dotted line on the main
longitudinal profile drawing. Detailed cross sections are to be made at critical location
like river crossing and other location as directed by Client/Consultant.
Sag template chart shall be prepared based on the data provided in the specification
and the tower design.
With the help of PLS – CADD or similar software with proper input of all data as per
the specification and approved designs, tower locations shall be spotted. While
locating the towers on the profile sheet, the following shall be taken into
consideration. Span, Body / Leg Extension, road & power line crossing, clearance from
ground, buildings trees etc.
The profile sheets, duly spotted, along with preliminary schedules indicating type of
towers, wind span, weight span, angle of deviation, river or road crossing, tower body
extensions and other details shall be submitted.
After approval of the profile by the Client/Consultant, process to obtain NOC from various
concerned authorities shall be taken up. In case of any deviations proposed from
authorities, the same shall be made as per the instructions of client and final approval
shall be obtained. After obtaining of NOC only other site activities shall commence.
10. CHECK SURVEY & LOCATION MARKING:
With the help of profile drawings and tower schedule, all tower locations shall be
spotted physically at site and re-checked to confirm that pole positions are in
conformity with the profiles.
The location shall be pegged and marked clearly with provisional tower numbers.
In case any variations/problems are encountered, the same shall be recorded and
brought to the notice of Client immediately and the tower location shall be shifted
accordingly.
Any corrections done at site shall be incorporated in the revised profile drawings.
When the transmission line passes over hilly and mountainous terrain and unequal
legs of towers or benching at tower location envisaged, cross diagonal profile and plan
essential for the selection of individual leg extension and benching quantities.
The leveling instrument shall be set at the center peg fixed at the tower location. With
the use of leveling staff/prism, levels are measured along the diagonal at every one
meter near each pit (tower legs). Normally, five readings shall be taken (1 reading at
center of pit and 2 readings in either side of the pit).
The reduced levels shall be calculated using these readings. These levels shall be
plotted on graph which indicates the cross section of the ground along the diagonal of
the pit. The same shall be reviewed and accordingly suitable leg extensions required
for the towers will be finalized.
Degree of Residual
Risk Degree of Risk Person
Sl. Hazard and /or Occuring of responsible
Activity Who Effected Result Control Measure(s)
Risk rating
Risk rating
Probability
Probability
Severity
Severity
No. risk for control
measure(s)
PROBABILITY SEVERITY
1. Very Unlikely Almost no, Has not occurred before 1. Very Light No loss of work time, can only be eliminated immediately, requiring first aid.
2. Slight Rarely occur, very few, Only abnormal Situation 2. Light No loss of working days, out patient treatment withot permanent effect.
3. Feasible Possible but not common 3. Medium Slight Injury, in patient treatment.
4. Likely Often, Has before, will again 4. serious Serious injury, long term therapy, occupational disease.
5. Very Likely Occurs frequently and under normal operating Conditions 5. Very Serious Death, Permanent disability.
SEVERITY
5. Very
RESULT ACTION PROBABILITY 1. Very Light 2. Light 3. Medium 4. serious
Serious
The work must not be started or ongoing activity must be stopped immediately till
Intolerable Risk 1. Very
the defined risk is reduced. Although the activities carried out are not possible to 1 2 3 4 5
(25) Unlikely
reduce the risk, activity must be avoided.
The work must not be started or ongoing activity must be stopped immediately till
High Risk the defined risk is reduced. The risk relates to continue to work, emergency
2. Slight 2 4 6 8 10
(15,16,20) measures to be takenand as a result of these measuresshould be decided to
continuethe activity.
Midium Risks The activities should be started for reducing the defined risks. The reduction
3. Feasible 3 6 9 12 15
(8, 9, 10, 12) measures of risk may take more time.
The identified risks may not be necessary to eliminate additional control
Acceptable Risks
processes. However these controls should be continued and maintained existing 4. Likely 4 8 12 16 20
(2, 3, 4, 5, 6)
controls be inspected.
Unimportant Planning and control processes carried out to eliminate the risk of identified 5. Very
5 10 15 20 25
Risks (1) activities may not need to keep records. Likely
SEQUENCE OF JOB STEPS POTENTIAL ACCIDENTS OR HAZARDS RECOMMENDED SAFE JOB PROCEDURE
All workers and site supervisors must attend the Tool Box Talk in the
All workers must identify the risks in every step of the works.
morning before work start.
All the required measures must be taken to prevent any accident or incident
PREPARED BY:
All workers must identify the potential Hazards.
Tool Box Talk before on site according to HSE Plan.
STERLING and WILSON
activity starts. All workers and supervisors must read and understand the Tool Box Talk and
then to sign up the attendance list.
Wild Life such as venomous snake, rodents, dogs etc. Anti venoms available on site.
Sliding or falling of workers due to steep area. First Aid Kit will be available on site in each work place.
Clear all vegetation and shrubs away from the working area.
Survey Works
Stay away from dogs, snakes, rodents etc. and don’t touch them.
Keep secure distance at least 2m away from edge of excavation or cliff.
METHOD
APPROVED BY:
Project Director (Sanjay Khanna)
DO C No .: SW-T&D-MS-SURVEY-001
METHOD DOC No .: SW -T & D -M S -B U SH - 0 0 2
RE V No .: 0 1
STATEMENT DA T E: 2 0 .0 7 .1 9
1. PURPOSE:
To establish Methodology on Bush clearing work for construction of 220kV Rusumo-
Nyakanazi Transmission Line. This procedure establishes description and guidelines
for works performed during Bush clearing Work.
It explains the duties of each worker, machinery used and methodology based on
international standards.
2. SCOPE:
Removal of trees and scrub along the Right of Way (ROW) as per specification and to
ensure that no vegetation shall exceed their permissible limit in the ROW.
3. REFERENCE:
• Sterling and Wilson project plan
• Sterling and Wilson Health & Safety Plan
• Contract / Design Specification
• Approved Technical Data Sheets
• Approved Drawings
• Cutting of trees, shrubs, bushes, etc. in the right of way is to be got done as
shown in the drawing above. All trees, shrubs, bushes, etc. which infringe on
the clearances are to be cut.
• Beyond tree clearing strip, trees will be cut where necessary to guarantee a
minimum safety distance of 4.5m between the conductors and the ends of
the branches.
• Beyond the tree clearing strip, any trees whose mature height +2m is equal
to the distance between the foot of the tree and the vertical plane through
the closest conductor shall be cut down.
• Trees or bushes growing inside or very close to the legs of towers shall be
cut/removed.
• Cutting and removal of stumps of trees after removing the branches, with
tree branches and trunks being cut into 1.5m lengths and sacked on the edge
of the right of way.
6. EQUIPMENTS / TOOLS EMPLOYED:
1. Vehicles
2. Chainsaw
3. Hand tools
4. Backhoe Loader/ Dozer
PREPARED BY:
Sl. Hazard and /or Occuring of responsible
Activity Who Effected Result Control Measure(s)
No. risk for control
measure(s)
Risk rating
Risk rating
Probability
Probability
Check machine before use. Supervisor,
Bush
Operation of hand Site Engineer,
1 Blisters & Cuts Clearing 5 3 15 High risk Wear proper PPE. 3 3 9
held Machine HSE, Const.
Team
Manager
Careful while stacking of branches.
APPROVED BY:
Project Director (Sanjay Khanna)
DOC No .: SW -T & D -M S -B U SH - 0 0 2
PROBABILITY SEVERITY
1. Very Unlikely Almost no, Has not occurred before 1. Very Light No loss of work time, can only be eliminated immediately, requiring first aid.
2. Slight Rarely occur, very few, Only abnormal Situation 2. Light No loss of working days, out patient treatment withot permanent effect.
3. Feasible Possible but not common 3. Medium Slight Injury, in patient treatment.
PREPARED BY:
4. Likely Often, Has before, will again 4. serious Serious injury, long term therapy, occupational disease.
5. Very Likely Occurs frequently and under normal operating Conditions 5. Very Serious Death, Permanent disability.
continuethe activity.
STATEMENT
Midium Risks The activities should be started for reducing the defined risks. The reduction
3. Feasible 3 6 9 12 15
(8, 9, 10, 12) measures of risk may take more time.
BUSH CLEARING
APPROVED BY:
Project Director (Sanjay Khanna)
DOC No .: SW -T & D -M S -B U SH - 0 0 2
SEQUENCE OF JOB STEPS POTENTIAL ACCIDENTS OR HAZARDS RECOMMENDED SAFE JOB PROCEDURE
All workers and site supervisors must attend the Tool Box Talk in the
All workers must identify the risks in every step of the works.
PREPARED BY:
morning before work start.
All the required measures must be taken to prevent any accident or incident
All workers must identify the potential Hazards.
Tool Box Talk before on site according to HSE Plan.
any activity.
Blisters and Cuts Check condition of the machine before use, change the faulty parts.
Check the sourrounding area which may cause trouble, clear the working
Falling of Tree
area, check the shape of the tree, wind direction.
An audible warning must be given when the tree is ready to fall.
METHOD
leaned on the tree to be felled next. Such trees add extra stress in the tree to
Bush Clearing
BUSH CLEARING
be felled next and can cause a sharp jump of the tree. Therefore the tree to
be felled must not support other already felled trees.
Poisonous insects and reptiles, Plants, Hidden Stones Anti venoms available on site.
First Aid Kit will be available on site in each work place.
Page 8 of 8
RE V No .: 0 1
DA T E: 2 0 .0 7 .1 9
APPROVED BY:
Project Director (Sanjay Khanna)
DOC No .: SW -T & D -M S -B U SH - 0 0 2
METHOD DO C No .: SW-T&D-MS-AR-003
RE V No .: 0 0
STATEMENT DA T E: 0 1 .0 7 .1 9
1. PURPOSE:
To establish Methodology on Access road work for construction of 220kV Rusumo-
Nyakanazi Transmission Line. This procedure establishes description and guidelines
for works performed during Access road Work.
It explains the duties of each worker, machinery used, and methodology based on
international standards.
2. SCOPE:
To construct and maintain access road wherever necessary with consideration to
environmental condition and safety practices.
3. REFERENCE:
• Sterling and Wilson project plan
• Sterling and Wilson Health & Safety Plan
• Contract / Design Specification
• Approved Technical Data Sheets
• Approved Drawings
a. After completion of check survey, a detailed joint study of existing roads will be
carried out. After the study a proposal shall be submitted to client/consultant for
access road required for the construction.
b. Client/consultant will obtain the right of access to the existing roads and shall
provide the same to make use of it.
c. Access from one tower to another shall preferably be by straight line track running
alongside the power line or transversal access tracks that can be used to reach the
various points of the line quickly from the existing main roads.
d. General characteristics of the tracks will be as follows.
• Track width as per site condition for movement of vehicle.
• Accessible by an all-terrain vehicle even in the rainy season.
e. While constructing access road following basic principles shall be followed,
• Levelling and proper drainage must be done where required. Existing
drainage systems shall not be blocked or altered in any way unless agreed
upon by the client/consultant. Wherever required cutting and filling must
be done to maintain the levelling of access roads.
f. No access for a period of 24 hours is permitted on any un-tarred road following a
single downpour of more than 20mm.
g. No vehicle traffic shall be allowed in wetlands. Only existing roads through such
wetlands will be used with the approval of Client/consultant and Relevant bodies.
No equipment shall be used which may cause irreparable damage to wetlands.
6. EQUIPMENTS / TOOLS EMPLOYED:
1. Vehicles
2. Backhoe Loader/ Dozer/ Shovel
3. Compactor
4. Grader
PREPARED BY:
Medium Site Engineer,
1 House Keeping Fuel or chemical All workers 4 3 12 immediately removed to a safe place and 3 3 9
Risk HSE, Const.
substances. stored in closed containers for safe disposal
Manager
till to be removed from the site to a safer
area.
METHOD
STATEMENT
ACCESS ROAD
Page 5 of 7
RE V No .: 0 0
DA T E: 0 1 .0 7 .1 9
APPROVED BY:
DO C No .: SW-T&D-MS-AR-003
PREPARED BY:
2. Slight Rarely occur, very few, Only abnormal Situation 2. Light No loss of working days, out patient treatment withot permanent effect.
3. Feasible Possible but not common 3. Medium Slight Injury, in patient treatment.
The work must not be started or ongoing activity must be stopped immediately till
STATEMENT
High Risk the defined risk is reduced. The risk relates to continue to work, emergency
ACCESS ROAD
2. Slight 2 4 6 8 10
(15,16,20) measures to be takenand as a result of these measuresshould be decided to
continuethe activity.
Midium Risks The activities should be started for reducing the defined risks. The reduction
3. Feasible 3 6 9 12 15
(8, 9, 10, 12) measures of risk may take more time.
The identified risks may not be necessary to eliminate additional control
Acceptable Risks
processes. However these controls should be continued and maintained existing 4. Likely 4 8 12 16 20
Page 6 of 7
(2, 3, 4, 5, 6)
controls be inspected.
RE V No .: 0 0
Unimportant Planning and control processes carried out to eliminate the risk of identified 5. Very
DA T E: 0 1 .0 7 .1 9
5 10 15 20 25
Risks (1) activities may not need to keep records. Likely
APPROVED BY:
DO C No .: SW-T&D-MS-AR-003
PREPARED BY:
activity starts. All workers and supervisors must read and understand the Tool Box Talk and
then to sign up the attendance list.
If any other personnel comes in site must read and sign the JHA before starts
House Keeping Spills incident such as Oil, Fuel or chemical substances. that they are roadworthy and no oil leaks are present. Spill trays will be
available on each vehicle.
METHOD
STATEMENT
ACCESS ROAD
Page 7 of 7
RE V No .: 0 0
DA T E: 0 1 .0 7 .1 9
APPROVED BY:
DO C No .: SW-T&D-MS-AR-003
1. PURPOSE:
To establish Methodology on Civil work for construction of 220kV Rusumo-
Nyakanazi Transmission Line. This procedure establishes description and guidelines
for works performed during Civil Work.
It explains the duties of each worker, machinery used and methodology based on
international standards.
2. SCOPE:
The scope of this procedure is to detail the process of Civil works including
Excavation, Foundation installation, concreting and backfilling operation.
3. REFERENCE:
• Sterling and Wilson project plan
• Sterling and Wilson Health & Safety Plan
• Contract / Design Specification
• Approved Technical Data Sheets
• Approved Drawings
5 CM
10.0300
3.0000
4.0000 LEG D
S2+ 12+0 0.2322
LEG B 477.9642
S2+ 12+1 477.66
476.9632
F ill
0.1512 Excavation Excavation
Benchmark
3.0000
Excavation C oncrete
Backfill
3.0000
Backfill C oncrete
Lean C oncrete
0.1000
Lean C oncrete
0.1000
5.4900 5.3700
10.0300
2.0000
LEG C
S2+ 12-1 478.96
4.0000 F ill
F ill 0.1002
477.66
LEG A
476.96 S2+ 12+1
F ill Benchmark 3.0000
C oncrete
Backfill
Excavation
8
Lean C oncrete
3.0000 0.1000
Backfill C oncrete
5.4900 5.2500
C. Excavation:
While excavating, the earth is cut vertically / tapered / in steps as per the soil
conditions at site to avoid any kind of mishap caused by collapsing of the pit sides
during excavation and foundation work.
The excavated earth is to be kept at a sufficient distance so that it does not create
any burden on the sides of excavated earth pits and reenters into the pit in case
of rain.
During excavation in sandy soil or water bearing strata, and particularly in black
cotton soil where there is every likelihood of collapsing of the sides of the pits,
Hard
Clay
Very dense
A
Sand 400 1800 >30 300 250 300 250
Soft Rock
Firm Clay
B 200 1600 10-20 250 200 150 100
Dense Sand
Stiff Clay
Loose to
C 100 1600 5-10 - 100 - 00
compact Sand
Soft Clay
D
Loose Sand 50 1400 3-5 - 00 - 00
Unfrac-
E tured Rock >1000 2000 - 450 - - -
E. Types of Foundation:
Suitable types of foundations shall be designed for each soil class and tower type.
Final type of soil classification for each location will be concluded after comparing
actual excavated soil strata and soil classification proposed in the soil investigation
report in the presence of Contractor, Consultant/Client. The same should be
documented. The type of the foundation to be casted at any location depends
upon the type of soil, sub – soil water level and the presence of surface water.
While classifying foundations, the worst conditions are to be considered and not
necessarily the conditions prevailing at the time of inspection.
The foundations will be chosen among the following types,
• Pad & Chimney type with undercut for soil type A - This is used at locations
where decomposed or fissured rock gravel, kankar, limestone, laterite or
any other soil of similar nature is met. Wet fissured rock foundation is
adopted in case of fissured rock locations where water table is met at 1.5
meter or more below ground level. A separate foundation design shall be
used if water level is encountered at less than 1.5 meter below ground
level.
G. Stub Setting:
It is imperative stubs are set accurately and within the permissible tolerances to
ensure erection may proceed without inducing stresses in tower members. All
setting dimensions (back to back, diagonals and levels) shall be measured using
steel measuring tapes.
The dimensions of the setting of stub will be checked at the following stages,
• When the stub is first positioned before the reinforcement is placed.
• When the base concrete is done and completed.
• After the chimney concrete is done.
• After back filling is completed.
Stub setting can be done in following ways,
• Using Template:
A stub setting template is a specific tool for a type, design & make of tower.
It is a light rigid steel framework and is used to hold the tower stubs at the
correct alignment and slope during the concreting work. The template is
adjustable type which can suit the standard tower as well as towers with
standard extensions.
After the excavation is completed, the sides of the template are assembled
and placed on the four sides of the location. The sides are then connected,
taking into consideration the type of tower (normal or with extension) to
be erected, to form the shape of the template with the four corners located
in the excavated pits.
The template is lifted and placed on jacks. Eight jacks are used, two for each
corner of the template. The jacks are supported on sleepers which are
placed across the pits so that the load of the template is distributed away
from the excavated pits. The lengths of the sides and diagonals of the
template are measured. These are compared with those given in the
drawing and corrected as required.
Plumb lines, one in the transverse direction and the other in the
longitudinal direction, are drawn from the peg markings given for the
location.
The template is centered on the location with the help of the plumb lines.
The template is levelled and the height of the base of the template above
ground level is kept as given in the drawing.
The lengths of the sides and diagonals of the template are finally checked
and corrected if required. The levelling of the template is also checked and
corrected.
The stubs are then fixed on the legs of the template. The distance between
the end of the stub and the base of the pit is checked with reference to the
foundation drawing.
H. Reinforcement Placement:
Reinforcement steel shall be of grade 60 with a minimum elastic limit of 400mpa.
The numbers, lengths, diameters, forms and positions of all reinforcing bars shall
be in accordance with approved drawings. All reinforcement shall be fabricated in
the store yards and transported to site. During placement the following shall be
adhered to,
• All reinforcement shall be cleaned of foreign material (rust, oil, grease,
mud, etc.) prior to placement.
• The spacing between the bars and from ground or form box is as per the
foundation drawing.
• All reinforcement bars are to be secured using binding wires of 18-gauge
soft iron wire.
• Sufficient precast rings or distance blocks shall be used between the
reinforcement and the bottom and sides of the excavations to ensure the
• The steel reinforcement bars shall be held in place by means of link stirrups
and annealed iron spacers to prevent them from moving when placing the
concrete.
I. Form Work:
Form boxes of the shape, size and dimensions for the individual type and make of
tower as per approved foundation design and drawing are to be used.
Adequate quantity of form boxes for all types of towers, particularly suspension
towers, shall be got fabricated so that work can be carried out at many locations
and the desired progress can be achieved.
Form boxes are made from M. S. Sheets having adequate thickness to be rigid
during the placing of the concrete. To avoid honeycombs in the concrete, the form
boxes shall be sufficiently tightened to prevent cement slurry from coming out. All
form work shall be checked for cleanliness and oiled before use and shall be
capable of removal without undue disturbance to the concrete.
All the materials such as fine and coarse aggregates, water, and
cement required for concrete will be inspected for use prior to
commencement.
Prior to commencement of concreting activities, the following shall
be available on site.
Concrete Mixers - in good working order
Vibrators
Water - required quantity
Fine Aggregate -required quantity
Coarse Aggregate -required quantity
Cement -required quantity
Protection for the same
Aggregate measuring boxes, Mixing Sheets, water measuring
container
Test cube molds / Slump cone
Concrete chutes / slides / elephant trunks
De-watering pumps (if necessary for the site).
All materials employed for the concrete shall be from approved
sources only.
All bags of cement shall be stored on site in a correct and proper
manner; they shall be protected from rain and surface water.
Aggregates shall be placed on ground clear of the vegetation. Fine
and coarse aggregate stacks shall be kept physically separated
The concrete mixer shall be placed in such a location so that the
transport distance of the concrete to the foundation is minimized.
The mix quantities shall always be strictly in accordance with the
approved design mix quantities.
All aggregates shall be measured by volume employing suitable
batch boxes of approved dimensions shall be made and used for
the measurement of coarse and fine aggregates. A suitable
container for the measurement of water shall also be used. The
boxes shall not be overfilled. After filling the box, the contents shall
be flush with the top edges of the box sides to ensure the correct
quantity in each box.
The aggregates together with the cement and water shall be added
to the mixer and mixed as long as is necessary to ensure a
homogeneous and workable mix.
Concrete cubes shall be taken for testing.
Proper care will be taken to transfer the concrete from the mixer to
the pit to avoid segregation of the constituent materials. The
following shall be adhered to,
The maximum free-fall height shall not be more than 1m. To
ensure these chutes shall be employed.
Pad concrete shall initially be placed.
After and during pouring the concrete shall be continuously
vibrated by means of vibrators to ensure proper compaction.
Vibration shall not be used as a means of repositioning the
placed concrete.
K. Testing of Concrete:
There are two types of testing of concrete used for foundations works. One is
Slump Test used for testing fresh concrete, and the other one is Compressive
Strength measured from Compression testing of concrete cubes.
• Slump Test
A slump in a truncated cone 300 mm high and of standard dimensions shall
be between 50 and 90 mm, corresponding to a stiff plastic consistency.
The concrete sample should not be taken from the first or last section of
the pour.
Tools needed to perform these tests are as follow,
A bucket or wheel barrow
Wooden board / Polythene sheet or similar
Tamping rod or vibrating poker
Slump cone
Pen or marker to identify the samples
Mound releasing agent and brush
Scoop
Trowel/Concrete float
Tape Measure/Steel Rule
Damp cloth
After the top layer has been compacted, Remove spilled concrete from the
base plate/surface. Remove the cone from concrete by raising it carefully
in vertical direction.
Once the slump test procedure is carried out, if the slump of the concrete
is not within consistency class then concrete can be adjusted by applying
additive to the concrete in consultation with client/consultant.
Before the concrete is scooped into the molds, the molds must be lightly
coated in a mold release agent. When using a 150mm mold, the concrete
sample is scooped into the mold in 3 equal layers (50mm) and compacted
between each layer manually by compacting rod.
The test cubes (specimens) shall be marked clearly and indelibly, without
damaging the specimen.
The test specimens will be left in the mold for at least 16 hours, but no
longer than 3days, protected against shock, vibration and dehydration.
After removal from the mold, the test specimens will be cured till
immediately before testing, in water.
The cubes are tested on the face perpendicular to the casting face. The
compression machine exerts a constant progressing force on the cubes till
they fail. The reading at failure is the maximum compressive strength of
the concrete.
The form works will be carefully removed a minimum of 24 hours after casting.
The exposed surfaces of the concrete will be checked for any imperfections i.e.
honeycombing, etc. Local repairs to the concrete surfaces shall only be permitted
with the approval client/consultant.
Repairs for honeycombing shall comprise applying a skin of concrete surrounding
the area of appearance of honey comb and a rough plastering and a finish coat will
be done.
M. Curing:
Immediately after the removal of formwork all concrete exposed surfaces shall be
protected by the application of jute covers or suitable materials which shall be
kept moist during the entire curing period.
Curing shall be continuous for a minimum of 14 days after removal of the form box
or until back filling commences.
N. Back Filling:
Back-filling of the excavation shall not commence until the foundation have been
inspected and approved by client/consultant.
O. Painting:
All concrete foundations shall be treated with a bituminous or equivalent coating
to resist acid attack. The thickness of the coating shall be at least 2 mm thick.
The surface to be covered shall be perfectly clean.
The coating shall be applied only ay the end of the curing period to ensure that
concrete surface is completely dry.
P. Tower Grounding:
During the setting out of stub the basic earthing device shall be installed in
accordance with the approved drawings.
When the backfilling has finished the electrical resistance will be measured and
recorded, if it doesn’t reach a value of 10 Ω, should be reinforced and the
measurement should be repeated.
Close to the Substation the first and last five towers including dead end towers
shall have the earth resistance of 5 Ω or less.
Q. Site Cleanup & Erosion Control:
After completion of all foundation and earthing activities the site shall be cleaned
of all surplus excavated material and construction material.
The work site shall be reinstated, wherever possible to original ground contours.
The site shall be checked to ensure that the foundation is not exposed to the
possible erosion problems from either natural surface water drainage or that
resulting from the construction activities.
If erosion control measures are deemed necessary a proposal shall be submitted
to client for approval giving the following information.
How the rain water run-off is to be allowed for and delivered from and around the
foundation.
How exposed ground surfaces are to be protected against weathering and the
possibility of erosion the depth and details of the foundation with note of the
presence of fill material. If there is a possibility of slippage precaution shall be
taken in this respect.
6. EROSION CONTROL WORK
• Existing drifts and bridges may be used at the consent of the landowner.
However, such structures must be examined for strength and durability before
being used.
• Methods of erosion control for river stream, donga etc.
Erosion control barriers
Silt screen facing
Sand bag sediment barrier
Water diversion berms
Re vegetation – all the disturbed area along the servitude will be re-
vegetated.
• The erosion control is to be done, based on site conditions, by employing any
or a combination of the following three methods which are best suited for the
site conditions.
Benching.
Protection against cutting of soil by flow of water.
Revetment.
A. Benching:
This method is generally used if the soil is gently sloping and there
is no significant difference in the levels of the soil around the
foundation. The soil at the higher level is cut and spread in the
lower level so that the soil near the foundation becomes level.
C. REVETMENT:
• The inside of the revetment is filled with earth up to the reference ground
level. The earth is rammed to compaction in layers of 150 mm.
• The pointing of the face of the stone masonry wall is done using 1:6 cement
mortar.
PREPARED BY:
No. risk for control
measure(s)
Severity
Severity
Risk rating
Risk rating
Probability
Probability
Visual control by the operator before starting
1 5 5 25 2 5 10
Foundation underground facilities workers e Risk detail information of these facilities. HSE, Const.
Manager
use warning signs.
APPROVED BY:
DO C No .: SW-T&D-MS-FDN-004
PREPARED BY:
No. risk for control
measure(s)
Severity
Severity
Risk rating
Risk rating
Probability
Probability
Installation of
CIVIL WORK
9 Protruding nails All workers 4 4 16 High Risk proper place. 2 4 8 Engineer, HSE,
Shuttering
Wear Proper PPE Const. Manager
APPROVED BY:
DO C No .: SW-T&D-MS-FDN-004
PREPARED BY:
Activity Who Effected Result Control Measure(s)
No. risk for control
measure(s)
Severity
Severity
Risk rating
Risk rating
Probability
Probability
APPROVED BY:
DO C No .: SW-T&D-MS-FDN-004
PREPARED BY:
No. ris k for control
meas ure(s )
Severity
Severity
Risk rating
Risk rating
Probability
Probability
APPROVED BY:
DO C No .: SW-T&D-MS-FDN-004
PREPARED BY:
3. Feasible Possible but not common 3. Medium Slight Injury, in patient treatment.
4. Likely Often, Has before, will again 4. serious Serious injury, long term therapy, occupational disease.
High Risk the defined risk is reduced. The risk relates to continue to work, emergency
2. Slight 2 4 6 8 10
STATEMENT
continuethe activity.
Midium Risks The activities should be started for reducing the defined risks. The reduction
3. Feasible 3 6 9 12 15
(8, 9, 10, 12) measures of risk may take more time.
The identified risks may not be necessary to eliminate additional control
Acceptable Risks
processes. However these controls should be continued and maintained existing 4. Likely 4 8 12 16 20
(2, 3, 4, 5, 6)
controls be inspected.
Unimportant Planning and control processes carried out to eliminate the risk of identified 5. Very
Page 32 of 35
RE V No .: 0 1
5 10 15 20 25
Risks (1) activities may not need to keep records. Likely
DA T E: 2 0 .0 7 .1 9
APPROVED BY:
DO C No .: SW-T&D-MS-FDN-004
PREPARED BY:
morning before work start.
All the required measures must be taken to prevent any accident or incident
All workers must identify the potential Hazards.
Tool Box Talk before on site according to HSE Plan.
activity starts. All workers and supervisors must read and understand the Tool Box Talk and
facilities.
Slope sliding during excavation All the excavation workmust be done according to design.
Slope slips from heavy rain condition Slope supports and shore supports.
Excavation of Foundation
Improper machinery and tools. Only trained workers.
All the excavated area must be barricade at least 2m from edge of excavation
Falling at height.
STATEMENT
CIVIL WORK
APPROVED BY:
DO C No .: SW-T&D-MS-FDN-004
PREPARED BY:
Materials falling from height Wear Proper PPE
Stub Fixing Bad wheather condition Store material and tools in proper place at least 1m from excavation edge.
Shuttering Installation
Hand and Eye Injury Ensure all nails are removed and stored at proper place.
Tools must be checked before put in use.
Use proper ladders.
Working at Height Only trained workers.
Injury due to sharp Edge Wear Proper PPE
Form Box installation and Collapse of Form Box Before using inspect form box properly, ensure no sharp edge.
Page 34 of 35
De installation.
RE V No .: 0 1
APPROVED BY:
DO C No .: SW-T&D-MS-FDN-004
PREPARED BY:
Wear Proper PPE
additives.
Traffic Management. Traffic management by site workers.
APPROVED BY:
DO C No .: SW-T&D-MS-FDN-004
1. PURPOSE:
To establish Methodology on Tower Erection work for construction of 220kV
Rusumo- Nyakanazi Transmission Line. This procedure establishes description and
guidelines for works performed during Tower Erection Work.
It explains the duties of each worker, machinery used and methodology based on
international standards.
2. SCOPE:
The scope of this procedure is to detail the process of Tower Erection works
including Ground assembly, Tower erection and tightening operation.
3. REFERENCE:
• Sterling and Wilson project plan
• Sterling and Wilson Health & Safety Plan
• Contract / Design Specification
• Approved Technical Data Sheets
• Approved Drawings
5. ACTIVITIES:
Before Tower erection commences the Contractor shall submit to the Project
Manager, drawings and relevant design calculations of all the proposed tower erection
intended for use.
The following are the sequence of works that are involved in Tower erection works,
• General
• Material Transport and Handling
• Tower Erection
• Final Tightening
• Fixing of Accessories
• Verticality Check of Erected Towers
A. General:
The towers shall be erected on the foundations not less than 28 days after
concreting or till such time that the concrete has acquired sufficient strength.
Deviation can be made by a specific waiver given by the employer.
Construction Material used e.g. Structural steel members; Fasteners etc. shall
conform to the requirements of Project Specifications.
The tower will be erected as per the Approved Drawings and tower schedule.
Tower will be fitted with all accessories including step bolts tightened.
When erecting structures near energized lines, care shall be taken to ground these
un-energized structures before any worker come in contact with them.
B. Material Transport and Handling:
Boom truck, small truck, pick-up will be used for material transportation. Special
care should be considered for handling and packing to prevent any damage.
Forklift, Crane or boom truck will be used to load and unload materials.
In the store and at site, tower shall be placed over wooden/concrete blocks to
avoid direct contact with ground.
The tower members shall not be dragged over the ground surfaces.
Any foreign material that may tend to adhere permanently to the structures shall
be removed.
Due care shall be taken to ensure no damages are caused to the galvanization of
tower parts during loading, transporting and unloading.
C. Tower Erection:
There are three main methods of erection of steel transmission towers which are
described as below:
a) Built up method or Piecemeal method.
• This method is most commonly used for the erection due to the
following advantages,
Tower materials can be supplied to site in knocked down condition,
i.e., in pieces which facilitates easier and cheaper transportation.
It does not require any heavy machinery such as cranes, etc.
Tower erection activity can be done in any kind of terrain and
throughout most of the year.
Availability of workmen at cheaper rates.
• This method consists of erecting the towers member by member. The
tower members are first set out and kept on the ground serially
according to erection sequence to avoid time loss due to searching for
them as and when required.
STEP - 1
• The cross bracings of the first section, which may be assembled on the
ground, are raised one by one as a unit and bolted to the already
erected corner leg angles. The first section of the tower thus built and
horizontal struts (belt members), if any, are bolted in position.
STEP – 2 STEP - 3
STEP – 4 STEP – 5
• Cross – arms are assembled on the ground, the bird guards and
hangers for suspension towers are fitted on the cross – arms.
• A rope is passed through a pulley fixed on the tower peak. The cross –
arms are raised up with this rope and fixed to the main body of the
tower.
• For heavier towers, a small boom is rigged on one of the tower legs
for hoisting purposes.
STEP – 6
b) Section method.
• The major sections of the tower are assembled on the ground and the
same are erected as units. Either a mobile crane or a derrick / gin pole
is used.
• Care shall be taken so that no stacked tower members/assembled
tower parts should block the access road and free movement of crane.
• Prior to tower assembly, the space requirements for the crane shall
be discussed and finalized with the crane operator so that the
assembled panels of tower shall be stacked accordingly to avoid space
constraints/blockage during tower erection.
• The two opposite sides of the tower section of the tower are
assembled on the ground. Each assembled side is then lifted clear of
the ground with the Crane and is lowered into position on bolts to
stubs or anchor bolts. One side is held in place with props or rope
guys while the other side is being erected. The two opposite sides are
then laced together with cross members and bracings / diagonals, and
the assembled section is lined up and made square to the line.
• The first face of the second section is raised. After the two opposite
faces are raised, the bracings on the other two sides are fitted and
bolted up.
• The last lift raises the top of the towers. After the tower top is placed
and all side bracings have been bolted up, all the guy are removed.
• Prior to tower assembly, the space requirements for the crane shall be
discussed and finalized with the crane operator so that the assembled
panels of tower shall be stacked accordingly to avoid space
constraints/blockage during tower erection.
• For this method of erection, a level piece of ground close to the
footing is chosen for the tower assembly. On slopping ground,
however, elaborate packing of the low side is essential before
assembly commences.
• The complete tower is assembled in a horizontal position on even
ground. The tower is assembled along the direction of the line to
allow the cross arms to be fitted.
• After the assembly is complete, the tower is picked up from the
ground with the help of a crane and carried to its location and set on
its foundation.
D. Final Tightening:
All empty holes are to be filled in with nut and bolt of appropriate size and a
spring washer.
All nuts shall be tightened properly using correct size spanners. Before tightening
it should be ensured that filler washers and plates are placed in relevant gaps
between members, bolts of proper size and length are inserted and one spring
washer is inserted under each nut. In case of step bolts, spring washer shall be
placed under the outer nut.
The tightening shall be carried on progressively from the top downwards, care
being taken that all bolts at every level are tightened simultaneously and up to
an approved torque. It is advisable to employ four persons, each covering one leg
and the face to his right.
12 40 60
16 80 100
20 140 180
24 280 320
The threads of bolts shall project outside the nuts by one to two threads and
shall be punched at three positions on the top inner periphery of the nut and
bolt to ensure that the nuts are not loosened in the course of time.
If during tightening, a nut is found to be slipping or running over the bolt threads,
the bolt together with the nut shall be changed outright.
E. Fixing of Accessories:
The supports for the anti – climbing device are fitted on the main corner legs of all
the towers. The anti – climbing devices (Flats with edges cut to a sharp point) are
installed after the stringing work has been completed.
Number plate, phase plate, danger plates, anti-climbing devises will be fixed after
completion of stringing work to avoid damages and inconvenience at the time of
stringing work.
F. Verticality Check of Erected Towers:
The finally erected tower shall be truly vertical after erection and no straining is
permitted to bring it in alignment.
The verticality of the tower is checked using a theodolite placed away from the
tower but in the longitudinal and transverse center lines of the tower.
All towers shall be vertical within a tolerance at the tower top as per specification
after conductors and earth-wires have been clamped in.
• Longitudinal deviation: less than 50 cm.
• Transversal deviation with respect to the line axis: (D/500 + 5 cm), where
D is the distance in meters from the point considered to the closest angle
point.
• Vertical deviation: 3 mm per meter, with a maximum tolerance of 20 cm.
• After erection and review, the verticality deviation of a support must not
exceed 50 mm, regard- less of the height of the support.
Severity
Severity
Risk rating
Risk rating
Probability
Probability
PREPARED BY:
Accident due to movement
Qualified and trained operators only.
of Crane/ Fork lift.
Improper loading or
Safe loading of vehicles on the load capacity.
unloading
condition.
Only trained and qualified pers onnel
DA T E: 0 2 .0 7 .1 9
Lifting operation with Drivers , Ins pect and determine whether a rope or Supervisor, Site
6 boom trauck/ Crane/ Lifting equipment failure Operators , 4 5 20 High Ris k other piece of lifting equipment is damaged 2 5 10 Engineer, HSE,
Fork Lift All workers . or not fit for purpos e Const. Manager
Periodic maintenance of equipment.
APPROVED BY:
Project Director (Sanjay Khanna)
DO C No .: SW -T & D - MS -E RE - 0 0 5
Degree of Res i dua l
Ri s k Degree of Ri s k
Pers on
Sl . Ha za rd a nd /or Occuri ng of res pons i bl e
Acti vi ty Who Effected Res ul t Control Mea s ure(s )
No. ri s k for control
mea s ure(s )
Severity
Severity
Risk rating
Risk rating
Probability
Probability
Onl y tra i ned a nd qua l i fi ed opera tors
PREPARED BY:
Li fti ng opera ti on wi th Col l a ps e of the l oa d due to Dri vers , Opera tors s houl d be a bl e to determi ne the Supervisor, Site
7 boom tra uck/ Cra ne/ i mproper l oopi ng of Opera tors , 4 5 20 Hi gh Ri s k wei ght, center of gra vi ty a nd cha ra cteri s ti cs of 2 5 10 Engineer, HSE,
Fork Li ft Sl i ng/Rope Al l workers . the l oa d. Const. Manager
Vi s ua l i ns pecti on of rope/s l i ng before put i n
Const. Manager
condi ti on
Vi s ua l check of the tool s before s ta rti ng work
Supervi s or,
Remove a l l da ma ged tool s . Si te Engi neer,
11 Worki ng a t Hei ght Improper type of tool s Al l Workers 5 4 20 Hi gh Ri s k 3 4 12
Us e proper tool s HSE, Cons t.
Ma na ger
Wea r Proper PPE
Immedi a tel y cl ea n up us i ng i nert s a nd or
other s ui ta bl e ma teri a l s .
Page 16 of 19
Supervi s or,
RE V No .: 0 0
APPROVED BY:
Project Director (Sanjay Khanna)
DO C No .: SW -T & D - MS -E RE - 0 0 5
PROBABILITY SEVERITY
1. Very Unlikely Almost no, Has not occurred before 1. Very Light No loss of work time, can only be eliminated immediately, requiring first aid.
PREPARED BY:
2. Slight Rarely occur, very few, Only abnormal Situation 2. Light No loss of working days, out patient treatment withot permanent effect.
3. Feasible Possible but not common 3. Medium Slight Injury, in patient treatment.
The work must not be started or ongoing activity must be stopped immediately till
STATEMENT
High Risk the defined risk is reduced. The risk relates to continue to work, emergency
2. Slight 2 4 6 8 10
(15,16,20) measures to be takenand as a result of these measuresshould be decided to
TOWER ERECTION
continuethe activity.
Midium Risks The activities should be started for reducing the defined risks. The reduction
3. Feasible 3 6 9 12 15
(8, 9, 10, 12) measures of risk may take more time.
The identified risks may not be necessary to eliminate additional control
Acceptable Risks
processes. However these controls should be continued and maintained existing 4. Likely 4 8 12 16 20
(2, 3, 4, 5, 6)
Page 17 of 19
controls be inspected.
RE V No .: 0 0
Unimportant Planning and control processes carried out to eliminate the risk of identified 5. Very
DA T E: 0 2 .0 7 .1 9
5 10 15 20 25
Risks (1) activities may not need to keep records. Likely
APPROVED BY:
Project Director (Sanjay Khanna)
DO C No .: SW -T & D - MS -E RE - 0 0 5
SEQUENCE OF JOB STEPS POTENTIAL ACCIDENTS OR HAZARDS RECOMMENDED SAFE JOB PROCEDURE
All workers and site supervisors must attend the Tool Box Talk in the
All workers must identify the risks in every step of the works.
morning before work start.
All the required measures must be taken to prevent any accident or incident
All workers must identify the potential Hazards.
Tool Box Talk before
PREPARED BY:
on site according to HSE Plan.
activity starts. All workers and supervisors must read and understand the Tool Box Talk and
then to sign up the attendance list.
If any other personnel comes in site must read and sign the JHA before starts
Overhead power lines and cables. Visual control by the operator before starting work
Inspect and determine whether a rope or other piece of lifting equipment is
Lifting equipment failure
TOWER ERECTION
APPROVED BY:
Project Director (Sanjay Khanna)
DO C No .: SW -T & D - MS -E RE - 0 0 5
SEQUENCE OF JOB STEPS POTENTIAL ACCIDENTS OR HAZARDS RECOMMENDED SAFE JOB PROCEDURE
Falling from height due to slips & trips Only trained and qualified workers will participate at this activities.
Worker who will work at height must use safety harness and other fall
PREPARED BY:
arrester equipments like vertical lifeline or fall arrest block.
Falling from height due to physical fatigue Workers will not work for a long time at height
Don’t smoke, eat, drink or use the phone during working at height.
All equipment must be proper for the work that will be used.
TOWER ERECTION
Page 19 of 19
RE V No .: 0 0
DA T E: 0 2 .0 7 .1 9
APPROVED BY:
Project Director (Sanjay Khanna)
DO C No .: SW -T & D - MS -E RE - 0 0 5
METHOD DO C No .: SW-T&D-MS-STG-006
RE V No .: 0 1
STATEMENT DA T E: 1 9 .0 7 .1 9
STRINGING Page 1 of 40
STRINGING Page 2 of 40
1. PURPOSE:
To establish Methodology on Stringing work for construction of 220kV Rusumo-
Nyakanazi Transmission Line. This procedure establishes description and guidelines
for works performed during Stringing Work.
It explains the duties of each worker, machinery used and methodology based on
international standards.
2. SCOPE:
The scope of this procedure is to detail the process of Stringing works including
Conductor Stringing, Earthwire (GSW & OPGW) Stringing.
3. REFERENCE:
• Sterling and Wilson project plan
• Sterling and Wilson Health & Safety Plan
• Contract / Design Specification
• Approved Technical Data Sheets
• Approved Drawings
STRINGING Page 3 of 40
STRINGING Page 4 of 40
STRINGING Page 5 of 40
Stay Length
Cross Arm
Height - H
1.5H
• The stay pits are excavated to a minimum depth of 2.0 meters. Normally,
an anchor in the form of a piece of steel joist or rail of length 1.8 meters
with a steel lead fixed on it is placed in this pit and the pit is backfilled
tightly with the excavated earth or borrowed earth. For loose sand and wet
black cotton soil conditions, a piece of steel joist or a sleeper (for greater
width) of length 2.3 meters should be used for the anchor. The length of
the steel lead is about 4.25 meters and its other end projects out of the
ground. A trench, sloping at an angle of approximately 30 degrees to the
horizontal, is dug from the base of the pit to the ground level for this lead.
• Steel stay wires are fixed on the cross arms / peaks using D – shackles and
pulled up to the stay pit. They are connected to the stay lead from the pit
through a turnbuckle using bulldog clamps. The turnbuckle is then
tightened to a tension sufficient to balance the load which will be imposed
on the cross arms / peak(s) when stringing is carried out on the other side
of the tower.
• In case the conductor of the next / previous section has been payed out
and rough sagged (at approximately 50% working tension) on the tower on
which final sagging is to be done, providing of stays is also not necessary.
This method is to be used only after ensuring that this kind of one end
loading is permissible as per the tower foundation design and adequate
clearance from power lines is available in the rough sagged section. This
method is normally used for 400 kV lines.
• Requirement and availability of hardware fittings and accessories shall be
confirmed prior to the commencement of stringing for that section.
• Sizes of accessories and certain stringing tools shall be checked for
compatibility with conductor diameter.
• The stringing section shall be selected and studied in detail for any road
crossing, power line crossing to ascertain need of any special arrangements
like scaffolding and to plan accordingly. Also, necessary protection for the
STRINGING Page 6 of 40
STRINGING Page 7 of 40
STRINGING Page 8 of 40
• All compression joints should be carefully made and record of initial and
final lengths of the joints is to be maintained.
• Over stressing causing damage to towers should be avoided. Care should
be exercised not to over tension the conductor.
STRINGING Page 9 of 40
• The sequence of paying out shall be from top to downwards, i.e., the
earthwire shall be payed out first.
• Earthwire drums are mounted on a turn table at the start of the section.
The turn table is provided with a suitable braking device to prevent over
running and backlash and to avoid damages to or lose running out and
kinking of the earthwire.
• The locations of the earthwire drums depend on the section length, length
of earthwire on each drum and site conditions. They can be located either
at suitable intermediate tower(s) (normally one drum length away) and /
or at the other end of the section.
• Earthwire drum battens should be removed just prior to moving drums on
to drum stands / turntable. Drums should be transported and positioned
at site on stands / turntable with the least possible amount of rolling.
• A tractor is employed to pull the earthwire. The end of the earthwire is
tightened in a come – along clamp (bolted type or automatic) and attached
to the tractor. Care should be taken during paying out to ensure that the
earthwire does not get damaged by being dragged over stones, etc.
Ground rollers of sufficient height should be used when paying out over
rocky terrain so that the earthwire does not touch the ground.
• The earthwire shall be continuously observed for loose or broken strands
or any other damage. These coils are to be removed carefully and repair
sleeve / mid span joint is to be provided as required.
• The earthwire is pulled / payed out to a distance beyond the first tower.
This distance is roughly a little more than double the height of the tower
peak. The extra length of earthwire is pulled back, taken to the tower peak,
passed through the earthwire roller / running block and brought down the
other side of the tower. The earthwire is then pulled by the tractor towards
the next location.
• This procedure is continued / followed for the subsequent towers till the
end of the section or the drum length is reached, whichever is earlier.
• If the section length is more than one drum length. Then the next earthwire
drum is taken up for paying out. The process is continued till the paying out
of earthwire for the complete section is completed.
• The mid span joints for earthwire are provided as required. All joints shall
be made at least 30 metres away from the towers. No joints shall be made
in tension spans or in the first span near an angle tower. No joint shall be
STRINGING Page 10 of 40
used in any span crossing other major power lines. Earthwire joints shall
be made in the manner prescribed by the manufacturer so that they do not
crack or get damaged in the stringing operations.
• The earthwire is compressed in the dead end hardware at the section point
where sagging will not be done.
• If the ends of the earth wire are damaged, the damaged parts are cut off
after the steel strands are tied up with at least two rounds of binding wire.
• The steel tube is then slipped on to the steel strands and compressed to
the specified load and dimensions.
• Any sharp edges or burrs remaining after compressing the steel tube are
filed off to give a smooth finish.
• The vibration dampers are then fixed on the earth wire at the distance
specified for the size of the earth wire.
• The earth wire and tension hardware are hoisted up and fixed on the peak
/ earth wire cross arm of the tower.
• The earthwire of the complete section is then pulled at the other end of
the section where sagging is to be done. This is called rough sagging and
the earthwire is pulled such that there is no slack and it is well clear of the
ground and power lines in the intermediate spans of the section.
• After being rough sagged as above, the earthwire is tied to the stay or
anchor provided for it till it is finally sagged / tensioned.
D. Paying Out of Earthwire (OPGW):
• OPGW pulling is performed by tension stringing method. For that pilot wire
paying out is necessary. For OPGW pulling 10mm/12mm pilot wire used.
Special clamps like Wedge clamps are used to hold the OPGW.
• Pilot wire paying out method for OPGW is very much like the pilot paying
out for conductor which is described below.
• To pass the pilot wire through aerial roller which shall connected to the
desired place through D Shackle, 12mm PP rope shall be used.
• Pilot wire shall be paid out from tensioner machine point to puller machine
point, with the help of tractor.
• The locations of the OPGW drums depend on the OPGW drum schedule
which is finalized after final approval of profiles.
STRINGING Page 11 of 40
STRINGING Page 12 of 40
Insulators having any hair cracks or chipping or any other defect shall not
be used. They shall be replaced and immediately be destroyed to avoid
unintentional re-use.
• Prior to installation, Insulators shall be cleaned in a manner that will not
spoil, injure or scratch the surface of the insulator, but in no case, shall any
oil be used for the purpose. All cotter pins shall be checked for correct
positioning and freedom from defects. All bolts, nuts and cotter pins shall
be installed to facilitate easy inspection and live line maintenance work.
• The hardware shall be assembled as per the manufacturer’s drawing and
their upper and lower parts are connected to the corresponding sides of
the insulator string. Arcing horns are fitted on the hardware. These shall be
placed in the line direction on suspension string assemblies, and facing
upwards / vertically on tension insulator string assemblies. The part of the
hardware which is used for clamping the conductor shall not be fitted at
this stage. The security clips in the insulators and the hardware shall be
properly opened.
• Three Sheave Running Block shall be fitted to the bottom of insulator
string in case of suspension towers and to the tower cross arms in case of
tension towers.
• The minimum radius of the Running Block at the base of the groove shall
be more than 1.1 times the radius of the conductor or earth-wire. The
depth of groove shall be a minimum of 25% greater than the diameter of
the conductor. The sheave diameter measure at the bottom of the groove
shall be more than 20 times the outside diameter of the conductor or
earth-wire. The groove shall be wide enough for the passage of
compression joints. The running block must be wide enough to able to
pass the head board through it.
STRINGING Page 13 of 40
STRINGING Page 14 of 40
ground. One end of the rope is firmly tied below the 3rd or 4th insulator.
The complete string with the Running block fixed at its end, is lifted by
pulling the rope, through another pulley / snatch block attached to one of
the tower legs, by hands or by means of a tractor. After reaching the top
the string is attached to the suspension hanger and is released slowly to
hang free.
• Paying out of pilot wire shall be started after the completion of hoisting
aerial rollers for the stringing section.
• Temporary stay wire arrangements shall be provided for the angle Towers
as per requirement at both ends before paying out pilot wire.
STRINGING Page 15 of 40
• The pilot wire shall have the same lay direction as that of conductor to
prevent twisting during stringing.
• The pilot wire shall be checked for any possible damage of the strands.
Any damage found shall be attended properly before shifting to site.
• Required number of pilot wire drums for the stringing reach shall be
transported to site through trucks. The loading and unloading of the same
shall be done with the help of crane/fork lift to avoid possible damage.
• Using the above, pilot wire shall be paid out from tensioner machine
point to puller machine point, with the help of tractors/pay loader.
G. Conductor Stringing:
• Multi – conductor lines are generally strung with the help of tension
stringing equipment. In this method, the conductor is kept under tension
during the paying out process. This method keeps the conductor clear of
the ground and obstacles which might cause conductor surface damage.
• After paying out of pilot wire, it is then used to pull the conductors from
the reel stands using specially designed tensioners and pullers. While
running out the conductors, care should be taken such that the
conductors do not touch and rub against the ground or objects which
could cause scratches or damage to the strands. The conductor shall not
be over – strained during pulling. The conductor drum is jacked up on a
steel shaft on a drum jack. The conductor shall be run out of the drums
from the top to avoid damage due to chafing.
STRINGING Page 16 of 40
• The distance of the puller, tensioner and intermediate anchor sites from
towers should be selected so that the towers are not overloaded. A
minimum pulling line slope of three horizontal to one vertical from the
tower to the site is to be provided. It is also necessary that the puller be
positioned so that the pilot wire enters the machine at the smallest
horizontal angle thereby minimizing the possibility of damaging it. When
a bull wheel type puller is employed, the reel winder to recover the pilot
wire is located at the pulling site. The pilot line winder is located at the
tensioner site.
• The arrangement of the tensioner and reel stands should be such that the
lateral angle between the conductor as it approaches the bull wheel and
the plane of rotation of the wheel is not large enough to cause the
conductor to rub on the sides of the groove. Bird – caging problems in
large conductors can be eliminated by using a maximum fleet angle of 1.5
degree from the plane normal to the conductor reel axis and a back
tension of approximately 4500 N. Problems of bird – caging is normally
more acute in the case of large conductors having three or more
aluminum layers.
STRINGING Page 17 of 40
site. All equipment, conductors, anchors and structures within the work
area must be bonded together and connected to the ground source.
• Pilot wires are pulled in under tension. The pilot wire is connected to a
single conductor through swivel link, or to bundle conductors through
swivel links and a running board.
STRINGING Page 18 of 40
the pulling end might exceed the tension at the tensioner by a significant
amount. Difference in tension is caused by the length of conductor
strung, number and performance of travelers, differences in elevation of
supporting towers, etc.
• When a bull wheel type puller is utilized, the pilot wire is recovered
during the pulling operation on a separate piece of equipment. A reel
winder is placed behind the puller in an arrangement similar to the reel
stand at the tension site.
STRINGING Page 19 of 40
particularly ensured that metal bands are installed and wrapped with
tape over both the open ends of the grip to prevent it from accidentally
coming off and dropping the conductor. If the ends are not banded and
taped, the grips may slip off when passing through the tensioner. The
paying out operation is then continued.
• When the ends of the conductors from the old and new drums come out
of the wheels of the tensioner, the paying out operation is stopped for
jointing the conductors. Any of the two methods given below are
employed for providing slack or loose length in the two conductors for
jointing the ends of the two conductors.
a) Come along clamps are fitted on the two conductors and these
are pulled together using tensioning equipment such as turn
buckle or pull lift. The ends of the conductors thus become loose.
b) A come along clamp is fitted on the conductor under tension in
the paying out and connected to an anchor or stay using a wire
rope sling. The conductor is held on this anchor or stay. The
conductor end from the tensioner is released so that sufficient
loose length is available.
The wire sock is removed. The ends of the two conductors are jointed
together with a mid span joint. The joint is covered with a joint protector
so that it is not damaged when passing through rollers / travellers. The
tension in the conductor(s) is released and the paying out operation is
then continued. The joint protectors are removed after paying out has
been completed.
• The conductors, joints and clamps shall be installed in such a manner that
there is no bird caging, over tensioning of individual wires or layers or
other deformation or damage to the conductors. Clamps or hauling
devices should, under erection conditions, allow no relative movement of
strands or layers of the conductors.
• Steel wire rope is passed through a pulley fixed on the tower cross arm.
One end is connected to the conductor and the other end to a pulling
arrangement on the other side of the tower. This wire rope is pulled till
STRINGING Page 20 of 40
• If the ends of the conductors are damaged, the damaged parts are cut off
after the aluminium strands are tied up with at least two rounds of
binding wire. The depth of the hollow tube of the steel portion of the
hardware is measured. A mark, which is at a distance equal to this
measured length plus a length equal to the elongation of the steel tube
during compression, is made on conductor from its cut end.
• The aluminium strands of the conductor, after being tied up with at least
two rounds of binding wire near this mark, are cut at this mark while
ensuring that the steel strands are not scratched. The steel strands are
tied up with at least two rounds of binding wire after the aluminium
strands are cut off.
• The aluminium tube is then pulled back over the steel tube. The holes in
the aluminium tube are sealed with plugs. The aluminium tube is then
compressed to the specified load and dimensions except the portion
between the holes which is marked as ‘uncompressed zone’. The portion
of the aluminium tube over the compressed part of the steel tube is not
to be compressed. The compression is started from the insulator string
end of the aluminium tube, skipping the ‘uncompressed zone’, and then
worked towards the end of the aluminium tube.
• The conductor is fitted to the relevant insulator string & hardware. The
vibration dampers are then fixed on the conductor at the distance
specified for the size of the conductor.
STRINGING Page 21 of 40
• The conductor and tension hardware are hoisted up and fixed on the
cross arm of the tower.
• The conductor of the complete section is then pulled at the section end
where sagging is to be done. This is called rough sagging and the
conductor is pulled such that there is no slack and it is well clear of the
ground and power lines in the intermediate spans of the section.
• After being rough sagged as above, the conductor is tied to the stay or
anchor provided for it till it is finally sagged / tensioned.
STRINGING Page 22 of 40
one repair sleeve per conductor should normally not be permitted in any
one span.
• The surface of the conductor or earth wire where the repair sleeve is to be
provided is cleaned with fine emery paper. The open end of the repair
sleeve is fitted on the conductor or earth wire to cover the portion in need
of repair. The cover of the repair sleeve is slid into place. The repair sleeve
is then compressed to the required load.
• Any sharp edges or burrs remaining after compressing the repair sleeve are
filed off to give a smooth finish.
• If the ends of the conductors are damaged, the damaged parts are cut off
after the aluminium strands are tied up with at least two rounds of binding
wire.
• The aluminium tube portion of the mid span joint is slipped on to one of
the conductors.
• A mark is made on the conductors at a distance from their open ends which
is equal to half the length of the steel tube portion plus its elongation
during compression. The conductor strands are tied up near this mark with
two rounds of binding wire. The aluminium strands are cut at these marks
to expose the steel core, taking care not to nick the steel strands. The steel
strands are tied up with at least two rounds of binding wire as the
aluminium strands are cut off.
• The two ends of the steel core of the conductors are inserted into the steel
tube of the mid span joint making sure that the ends are at the center of
the steel tube, i.e., equal lengths of the steel cores of both the conductors
remain outside the tube. The steel tube is then compressed, beginning
from the center and then first one side and then the other side, to the
specified load and dimensions. Any sharp edges or burrs remaining after
compressing the steel tube are filed off to give a smooth finish. Grease is
applied on the compressed tube.
• The aluminium strands of the conductor are cleaned, particularly in the
case of old and blackened conductors. The aluminium tube is slipped over
the steel joint taking care to ensure that the center of the tube is in the
center of the joint. This can be done by marking both the conductors, from
STRINGING Page 23 of 40
the center of the steel joint, at a distance equal to half the length of the
aluminium tube.
• The holes in the aluminium tube are plugged with aluminium plugs. The
aluminium tube is then compressed to the specified load and dimensions
except the portion between the holes which is marked as ‘uncompressed
zone’. The portion of the aluminium tube over the compressed part of the
steel tube is not to be compressed. The compression is started from the
end of the ‘uncompressed zone’ and then worked towards the end of the
aluminium tube.
• Any sharp edges or burrs remaining after compressing the aluminium
portion are filed off to give a smooth finish.
• The mid span joints are provided on earthwire in the same manner as the
steel portion of the conductors.
J. Final Sagging:
• After being rough sagged, the conductor / earth wire shall not be allowed
to hang in the stringing blocks for more than 96 hours before being pulled
to the specified sag.
• The pulley arrangement is used with steel wire rope of adequate size &
strength as per load requirement. The finally erected tower shall be truly
vertical after erection and no straining is permitted to bring it in alignment.
• A come along clamp is fitted on each rough sagged conductor at a
distance from the tower on which the final sagging is being carried out.
The come along clamp is then connected to the pulley arrangement
which is being used for final sagging through a steel wire rope which is
generally referred to as “lead”. The length of this lead is such that, after
final sag, the come along clamp remains far enough from the tower so
that the loose portion of the conductor on the tower side can be pulled
up to the cross arm for measurement. The different methods employed
for final sagging are described below.
SINGLE CONDUCTOR:
• In Sagging winch and a 4 way + 4 way pulley arrangement, a single steel
wire rope (lead) is connected to the come along clamp on the conductor.
The other end of this lead is connected to the one end of the pulley
system. The other end of the pulley system is connected to the tower
cross arm.
STRINGING Page 24 of 40
• The pulling rope of the pulley system above is brought down through
single way pulleys installed on the cross arm and on the tower leg at cross
arm level. The pulling rope is attached to a tractor through a pulley on the
tower leg near ground level. The tractor pulls the pulling rope till the
required sag and tension of the conductor are reached.
• Another way of employing the above method is the same except that,
instead of using a tractor, a sagging winch is used for final sagging.
Initially, the pulling rope is attached to a tractor through a pulley on the
tower leg near ground level and the tractor pulls the pulling rope till
about 80% of the required tension is attained. The rope is then
transferred to the sagging winch which is installed on the tower leg near
ground level. The sagging winch is then operated to pull the conductor to
the required sag and tension.
• The sag tension chart furnishing the details of sag at different temperature
at various spans shall be used at site.
• Sag board and sag scope (eyesight and target method) shall be used to
determine the final sag level. Preferably the span that is nearest to
equivalent spans shall be identified as sag span to measure the sag. Sag
board shall be installed to the Towers at the required height as per the
approved sag tension chart and the conductor temperature measured by
an accurate thermometer during sagging operation.
STRINGING Page 25 of 40
• The final sag level shall be checked in one or more spans according to the
section length.
• When the sag matches with the sag value as per the sag tension chart, the
tightening of conductor shall be stopped.
TWIN CONDUCTORS:
• For twin conductors, one steel wire rope lead is passed through an
equalizing pulley, of diameter equal to the sub – conductor spacing, and its
ends are connected to both the come along clamps on the conductors. This
is done so that the tension on both the conductors remains the same. The
equalizing pulley is connected to one end of the pulley system. The other
end of the pulley system is connected to the tower cross arm. Then final
sag is done as mentioned above.
STRINGING Page 26 of 40
STRINGING Page 27 of 40
up with at least two rounds of binding wire, are cut at this new mark while
ensuring that the steel strands are not scratched. The steel strands are tied
up with at least two rounds of binding wire after the aluminium strands are
cut off.
• The depth of the hollow tube of the steel portion of the hardware is
measured. A mark is made on the steel strands, from the cut end of the
aluminium strands of the conductor, which is at a distance equal to the
measured length plus a length equal to the elongation of the steel tube
during compression. The steel strands are tied up with at least two rounds
of binding wire on both ends of the mark and cut.
• The aluminium tube is first slipped on to the conductor keeping the jumper
end on the tower side. The steel tube is then slipped on to the steel strands
and compressed to the specified load and dimensions. Any sharp edges or
burrs remaining after compressing the steel portion are filed off to give a
smooth finish. Grease is applied over the compressed steel tube. The
aluminium tube is pulled back over the steel tube. The holes in the
aluminium tube are sealed with plugs. The aluminium tube is then
compressed to the specified load and dimensions except the portion
between the holes which is marked as ‘uncompressed zone’. The portion
of the aluminium tube over the compressed part of the steel tube is not to
be compressed. The compression is started from the insulator string end
of the aluminium tube, skipping the ‘uncompressed zone’, and then
worked towards the end of the aluminium tube.
• Any sharp edges or burrs remaining after compressing the aluminium
portion are filed off to give a smooth finish.
• The vibration dampers are then fixed on the conductor at the distance
specified for the size of the conductor.
L. Dead Ending of Conductor:
• After the earthwire has been pulled to the required sag and tension, the
loose earthwire is pulled up to the peak / earth wire cross arm using a sisal/
propylene rope passing through a pulley fitted on the peak / earth wire
cross arm. A mark is made on the earthwire corresponding to the anchoring
point on the peak / earth wire cross arm. This mark (M1) indicates the
length of the earthwire from the come – along clamp to the anchoring
point on the tower peak / earth wire cross arm. The earthwire is brought
back to the ground.
STRINGING Page 28 of 40
• The length (L1) of the tension hardware assembly is measured from its
anchoring point to the end of the steel tube of the hardware. The depth
(L2) of the hollow portion of the steel tube of the hardware is measured.
This length (L2) is deducted from the length (L1) of the earthwire tension
hardware assembly giving a length L3 = L1 – L2. The distance of the mark
(M1) from the anchoring point on the tower is re – marked by reducing it
by the length L3. The earthwire, after being tied up with at least two rounds
of binding wire, is cut at this new mark.
• A mark is made on the steel strands from the cut end which is at a distance
equal to the measured length plus a length equal to the elongation of the
steel tube during compression.
• The steel tube is then slipped on to the steel strands and compressed to
the specified load and dimensions. The compression is started from the
tower end of the steel tube, and then worked towards its end.
• Any sharp edges or burrs remaining after compressing the joint are filed
off to give a smooth finish.
• The vibration dampers are then fixed on the earthwire at the distance
specified for the size of the earthwire.
• The rope which was used to measure the length of the earthwire is tied to
the earthwire. The complete hardware and earthwire are pulled up
towards the peak with this rope. A slight over tension is given on the
earthwire to facilitate the fixing of the tension hardware.
• The end of the tension hardware is anchored to the tower peak. The
tension in the pulley system is then slowly released. If the other end of the
tower has already been strung, then the tension in the stay is also reduced
while releasing the tension in the pulley system. The tensioning
arrangement is thereafter removed and shifted to the cross arm.
• The earth bond is connected between the tension hardware and the leg of
the tower on which hole is provided for it.
M. CLIPPING IN / CLAMPING OF CONDUCTORS:
STRINGING Page 29 of 40
or a set of two – way & three – way pulleys with rope suspended from the
tower cross arm is used for this purpose. The hook used for lifting the
conductor should not mark any notch on the conductor or cause severe
bends. In case of conductors of the top and middle cross arms, these can
be brought down to the middle and bottom cross arms respectively. In case
of bundle conductors, the multiple conductors may be lifted
simultaneously by using a yoke arrangement attached to the lifting hook.
• The armour rods are first fitted on the conductor after matching the
centers marked on the conductor and the armour rods. The conductor is
then placed in its permanent suspension clamps and tightened.
• When clipping is being done, care must be exercised to ascertain that the
conductors are grounded prior to clipping even though the lines being
clipped are not attached to any electrical source. A local ground / earthing
is provided on the conductor at the location of work.
• After tightening the suspension clamps on the conductor, the conductor is
again raised and the clamp is fitted in the suspension insulator string.
• The vibration dampers are then fixed on the conductor at the distance
specified for the size of the conductor.
N. CLIPPING IN / CLAMPING OF EARTHWIRE:
• A small derrick is fitted on the tower peak and a pulley and rope are fixed
on it. The rope is tied to the earthwire and the earthwire is lifted off the
roller. The earthwire is fitted in the clamp of the suspension hardware. The
clamp is tightened and then fitted on the hardware.
• The vibration dampers are then fixed on the earthwire at the distance
specified for the size of the earthwire.
• The earth bond is connected between the suspension hardware and the
leg of the tower on which hole is provided for it.
O. INSTALLATION OF SPACER DAMPERS:
STRINGING Page 30 of 40
• The jumpers at the section and angle towers shall be formed to parabolic
shape taking into consideration the natural curve of the conductor formed
due to its winding on the drum. The length of the jumper should be cut so
that the jumper drop is as per drawing to meet the minimum clearance
requirements. Pilot suspension insulator string should be used, if provided
in the design of large angle towers or if found necessary otherwise, to
restrict the jumper swings to the design values.
• The required length of jumper shall be cut and compressed in jumper cones
on the ground.
• The jumpers shall then be lifted with the help of pulleys and PP ropes and
attached to the tension clamps on either side of the Tower.
• Portable earths shall be installed on all phases during jumpering to avoid
induction.
• Clearance between jumpers and the tower steel work is to be checked
during erection and before handing over the line.
STRINGING Page 31 of 40
STRINGING Page 32 of 40
PREPARED BY:
No. risk for control
measure(s)
Severity
Severity
Risk rating
Risk rating
Probability
Probability
Accident due to movement
Drivers,
STRINGING
Transportation of Workers,
2 Overturn of vehicles 4 5 20 High Risk 2 5 10 Engineer, HSE,
materials Pedestrians Safe loading of vehicles on the load capacity Const. Manager
Intolerabl monitored.
5 boom trauck/ Crane/ Bad weather condition Operators, 5 5 25 2 5 10 Engineer, HSE,
e Risk Work must be stopped during bad weather Const. Manager
Fork Lift All workers.
condition.
Only trained and qualified personnel
APPROVED BY:
Lifting operation with Drivers, Inspect and determine whether a rope or Supervisor, Site
6 boom trauck/ Crane/ Lifting equipment failure Operators, 4 5 20 High Risk other piece of lifting equipment is damaged 2 5 10 Engineer, HSE,
Const. Manager
DO C No .: SW-T&D-MS-STG-006
Severity
Severity
Risk rating
Risk rating
Probability
Probability
PREPARED BY:
Only trained and qualified operators
Lifting operation with Collaps e of the load due to Drivers , Operators s hould be able to determine the Supervisor, Site
7 boom trauck/ Crane/ improper looping of Operators , 4 5 20 High Ris k weight, center of gravity and characteris tics of 2 5 10 Engineer, HSE,
Fork Lift Sling/Rope All workers . the load. Const. Manager
Supervisor, Site
Intolerabl height.
STRINGING
9 Working at Height Object falling from height All Workers 5 5 25 2 5 10 Engineer, HSE,
STATEMENT
APPROVED BY:
Manager
Periodically Ins pection of Puller and
Tens ioner
DO C No .: SW-T&D-MS-STG-006
Severity
Severity
Risk rating
Risk rating
Probability
Probability
PREPARED BY:
Using certified equipments
Puller/Tensioner must be visually and
mechanical periodically inspected before
Supervisor,
used them from authorized operator.
Supervisor,
Wear Proper PPE
Stringing and Sagging Failure of tools like pulley, Operator, Site Engineer,
15 4 4 16 High Risk 3 4 12
activity wire rope, PP rope, Socks etc. Workers Communication will be with hand radio HSE, Const.
Make sure no one should stand under the Manager
line during stringinig activity
Exclusive trained personnel (Basic Harness
Awareness)
Switch off existing overhead power lines and
earthing in both Substation by authorized
person
Earth Conductor, GSW and OPGW during
Page 35 of 40
RE V No .: 0 1
stringing Supervisor,
Intersection and nearest
Stringing and Sagging Operator, Site Engineer,
16 with existing over head 4 5 20 High Risk Wear Proper PPE 2 5 10
DA T E: 1 9 .0 7 .1 9
APPROVED BY:
Exclusive trained personnel (Basic Harness
Awareness)
DO C No .: SW-T&D-MS-STG-006
Severity
Severity
PREPARED BY:
Risk rating
Risk rating
Probability
Probability
Use proper Scaffolding/ Crane/ Boom truck to
pass the pilot wire/ conductor/ opgw/ GSW
18 House Keeping Fuel or chemical All Workers 4 3 12 immediately removed to a safe place and 3 3 9
STRINGING
APPROVED BY:
DO C No .: SW-T&D-MS-STG-006
PREPARED BY:
4. Likely Often, Has before, will again 4. serious Serious injury, long term therapy, occupational disease.
5. Very Likely Occurs frequently and under normal operating Conditions 5. Very Serious Death, Permanent disability.
High Risk the defined risk is reduced. The risk relates to continue to work, emergency
STRINGING
2. Slight 2 4 6 8 10
STATEMENT
Unimportant Planning and control processes carried out to eliminate the risk of identified 5. Very
5 10 15 20 25
DA T E: 1 9 .0 7 .1 9
APPROVED BY:
DO C No .: SW-T&D-MS-STG-006
PREPARED BY:
Tool Box Talk before on site according to HSE Plan.
activity starts. All workers and supervisors must read and understand the Tool Box Talk and
then to sign up the attendance list.
STRINGING
Overhead power lines and cables. Visual control by the operator before starting work
Inspect and determine whether a rope or other piece of lifting equipment is
Lifting equipment failure
damaged or not fit for purpose.
Lifting operation Periodic maintenance of equipment.
Weather condition shall be regularly monitored & the work must be stopped
Bad weather condition
during bad weather condition.
When wind velocities are above 40 km/h, the rated load and boom lengths
Page 38 of 40
APPROVED BY:
DO C No .: SW-T&D-MS-STG-006
PREPARED BY:
Falling from height due to negligence of workers. Don’t smoke, eat, drink or use the phone during working at height.
Do not throw tools to each other.
Failure of tools like pulley, wire rope, PP rope, Socks etc. All tools to be checked if are in good condition before installing
METHOD
Intersection and nearest with existing over head power lines Switch off existing overhead power lines and earthing in both Substation by a
Use proper Scaffolding/ Crane/ Boom truck to pass the pilot wire/ conductor/
Crossing National highways, Railways
opgw/ GSW with guaranteed safe elevation.
APPROVED BY:
DO C No .: SW-T&D-MS-STG-006
PREPARED BY:
Visual control by the operator before starting work
TSE Machine Periodically Inspection of Puller and Tensioner
STRINGING
STATEMENT
Page 40 of 40
RE V No .: 0 1
DA T E: 1 9 .0 7 .1 9
APPROVED BY:
DO C No .: SW-T&D-MS-STG-006