GE Healthcare: Proteus XR/F ST Final Study
GE Healthcare: Proteus XR/F ST Final Study
----
B 18/Sep/2020 Initial release per PIM revision 11
A 27/Jan/2020 Initial release per PIM revision 10 ----
REV DATE MODIFICATIONS
01 - C1 - Cover Sheet 10 - S3 - Structural Details ----
02 - C2 - Disclaimer - Site Readiness 11 - M1 - HVAC - Environment
03 - A1 - General Notes
04 - A2 - Equipment Layout
12 - E1 - Electrical Notes GE Healthcare ----
13 - E2 - Electrical Layout ----
05 - A3 - Equipment Details (1) 14 - E3 - Electrical Elevations
06 - A4 - Equipment Details (2) 15 - E4 - Power Requirements
07 - A5 - Delivery
08 - S1 - Structural Notes
16 - E5 - Interconnections PROTEUS XR/F ST
09 - S2 - Structural Layout FINAL STUDY
Drawn by Verified by Concession S.O. (GON) PIM Manual Rev
A mandatory component of this drawing set is the GE Healthcare Pre Installation manual. Failure to reference the Pre Installation manual will result in
incomplete documentation required for site design and preparation.
Pre Installation documents for GE Healthcare products can be accessed on the web at: www.gehealthcare.com/siteplanning RET REK - ---- 1913363 11
GE does not take responsibility for any damages resulting from changes on drawings made by others. Errors may occur by not referring to the complete Format Scale File Name Date Sheet
set of final issue drawing. GE cannot accept responsibility for any damage due to the partial use of GE final issue drawings, however caused. All
dimensions are in millimeters unless otherwise specified. Do not scale from printed pdf files. GE accepts no responsibility or liability for defective work
due to scaling from these drawings. A3 1/4"=1'-0" EN-RAD-TYP-PROTEUS XRF-ST.DWG 04/Jun/2021 01/16
DISCLAIMER GLOBAL SITE READINESS CHECKLIST (DI)
DOC1809666 Rev. 7
GENERAL SPECIFICATIONS Site Ready Checks at Installation
EHS Site Requirements
· GE is not responsible for the installation of developers and associated equipment, lighting, cassette trays and Overall access route to the scan room free from obstruction / high hazards.
protective screens or derivatives not mentioned in the order.
Enough space to store tools, equipment, parts, install waste and the general area free from obstruction and trip hazards.
· The final study contains recommendations for the location of GE equipment and associated devices, electrical
wiring and room arrangements. When preparing the study, every effort has been made to consider every Enough necessary facilities for the GE employees available.
aspect of the actual equipment expected to be installed. No 3rd parties working in the area that may affect the safety of the installation activity.
· The layout of the equipment offered by GE, the dimensions given for the premises, the details provided for Area free from any chemical, gas, dust, welding fume exposure and has painting been completed and dry.
the pre-installation work and electrical power supply are given according to the information noted during All emergency routes identified, signed and clear from obstruction.
on-site study and the wishes expressed by the customer. Accessible single source lockable panel that LOTO can be applied to for GE equipment installation (MDP and/or PDU).
· The room dimensions used to create the equipment layout may originate from a previous layout and may not There are no other conditions or hazards that you have observed or have been made aware of by the customer or contractors on site.
be accurate as they may not have been verified on site. GE cannot take any responsibility for errors due to
Required for Mechanical Install start
lack of information.
· Dimensions apply to finished surfaces of the room. Room dimensions, including ceiling height, for all Exam, Equipment/Technical & Control rooms meets GE specifications.
· Actual configuration may differ from options presented in some typical views or tables. Ceiling support structure, if indicated on the GE drawing, is in the correct location and at the correct height according to the Original
· If this set of final drawings has been approved by the customer, any subsequent modification of the site must Equipment Manufacturer specifications.
be subject to further investigation by GE about the feasibility of installing the equipment. Any reservations Levelness and spacing has been measured, and is ready for the installation of any GE supplied components.
must be noted. Overhead support Structure (unistrut) has been confirmed with customer/contractor to meet required GE provided criteria.
· The equipment layout indicates the placement and interconnection of the indicated equipment components. Finished ceiling is installed. If applicable ceiling tiles installed per PMI discretion.
There may be local requirements that could impact the placement of these components. It remains the
Floor levelness/flatness is measured and within tolerance, and there are no visible defects per GEHC specifications.
customer's responsibility to ensure that the site and final equipment placement complies with all applicable
local requirements. Entry door threshold meets PIM requirement.
· All work required to install GE equipment must be carried out in compliance with the building regulations and Rooms that will contain equipment, including staging areas if applicable, are construction debris free. Precautions must be taken to prevent
the safety standards of legal force in the country concerned. debris from entering rooms containing equipment.
· These drawings are not to be used for actual construction purposes. The company cannot take responsibility Cable ways (floor/wall/ceiling/Access Flooring) are available for installation of GE cables are of correct length and diameter.
for any damage resulting therefrom.
Cable ways routes per GE Final drawings and cable access openings areas installed at a time determined by GEHC PM. Surface floor duct can
be installed at time of system installation.
CUSTOMER RESPONSIBILITIES
Adequate room illumination installed and working.
· It is the responsibility of the customer to prepare the site in accordance with the specifications stated in the Customer supplied countertops where GE equipment will be installed are in place.
final study. A detailed site readiness checklist is provided by GE. It is the responsibility of the customer to Required for Calibration Start
ensure all requirements are fulfilled and that the site conforms to all specifications defined in the checklist and HVAC systems Installed, and the site meets minimum environmental operational system requirements.
final study. The GE Project Manager of Installation (PMI) will work in cooperation with the customer to follow System power & grounding (PDB/MDP) is available as per GE specifications.
up and ensure that actions in the checklist are complete, and if necessary, will aid in the rescheduling of the System power & grounding (PDB/MDP) is installed at point of final connection and ready to use. Lock Out Tag Out is available.
delivery and installation date.
PMI to confirm all feeder wires and breaker are size appropriately. EPO installed if needed.
· Prior to installation, a structrual engineer of record must ensure that the floor and ceiling is designed in such a
PMI to confirm with electrician all power and signal cables are well terminated ensuring there are no loose connections.
way that the loads of the installed system can be securely borne and transferred. The layout of additional
structural elements, dimensioning and the selection of appropriate installation methods are the sole Network outlets installed.
responsibility of the structural engineer. Execution of load bearing structures supporting equipment on the Computer network available and working.
ceiling, floor or walls are the customer's responsibility. Lead doors and windows complete or scheduled to be installed. If applicable, radiation protection (shielding) finished & radioprotection
regulatory approval for installation obtained.
RADIO-PROTECTION Note: The details shown here are only an extract from DOC1809666. For the complete document please contact your PMI.
· Suitable radiological protection must be determined by a qualified radiological physicist in conformation with
local regulations. GE does not take responsibility for the specification or provision of radio-protection.
THE UNDERSIGNED, HEREBY CERTIFIES THAT I HAVE READ AND APPROVED THE PLANS IN THIS DOCUMENT.
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 C2 - Disclaimer - Site Readiness 02/16
CUSTOMER SITE READINESS REQUIREMENTS ENVIRONMENTAL SPECIFICATIONS
· Any deviation from these drawings must be communicated in writing to and reviewed by your local GE MAGNETIC INTERFERENCE
healthcare installation project manager prior to making changes.
To guarantee specified imaging performance:
· Make arrangements for any rigging, special handling, or facility modifications that must be made to deliver X-ray tubes and control console equipment must be located in ambient static field of less than 10 gauss.
the equipment to the installation site. If desired, your local GE healthcare installation project manager can Digital flat panel must be located in ambient static magnetic fields of less than 1 gauss.
supply a reference list of rigging contractors.
To guarantee data integrity:
· New construction requires the following; System electronics must be located in ambient static magnetic fields of less than 10 gauss.
1. Secure area for equipment,
2. Power for drills and other test equipment, To obtain specified geometric linearity:
3. Capability for image analysis, Operators console equipment must be located in ambient static magnetic fields of less than 10 gauss.
4. Restrooms.
· Provide for refuse removal and disposal (e.g. crates, cartons, packing)
· For CT, MR, PET/CT, and SPECT systems it is required to minimize vibrations within the scan room. It is the
customer's responsibility to contract a vibration consultant/engineer to implement site design modifications
to meet the GE vibration specification. Refer to the system preinstallation manual for vibration specifications.
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 A1 - General Notes 03/16
LEGEND
A GE Supplied D Available from GE
B GE Supplied/contractor installed E Equipment existing in room
C Customer/contractor supplied and installed * Item to be reinstalled from another site
MAX MAX
HEAT WEIGHT HEAT WEIGHT
BY ITEM DESCRIPTION OUTPUT (lbs) OUTPUT (kg)
(btu) (W)
A 1 Fixed Table 423 330 123 149
A 2 Wall Stand - 320 - 145
A 3 Tube Stand 450 493 132 223
A 4 Generator 542 209 160 94
A 5 Aero DR Interface Unit 112 25 33 11
A 6 Access Point 112 2.2 33 0.9
A 7 CS7 Control Console 1774 37 520 16
14'-8"
PC Interface Box (mount above
4'-1" A 8 counter top) - 1 - 0.45
C 12
corridor width
C 13 Counter top for equipment- provide grommeted openings as required to route cables
RAD ROOM
C 14 Control wall to ceiling with lead glass viewing window
3 6
Exam room height
15'-5"
6'-9"
13 1.8M [72"] SID Below table top to wall bucky
"
10
10 1'-
CONTROL ROOM
7'-7"
180°
180°
[30 in]
770
[22 in]
[22 in]
[91 in]
548
548
2318
[75 in]
1900
[16 in]
400
605 605
[37 in]
[24 in] [24 in]
950.6
1295 530
[51 in] [21 in]
FRONT SIDE
FRONT SIDE
1000 1000
[5 in]
[.17 in]
115
[18 in]
4.4 [39 in] [39 in]
460
12.8
°
[18 in]
[.5 in]
[3 in]
90
457
90
[32 in]
89
825
°
[5 in]
115
90
°
90
°
[17 in]
450 2200 450 605 605
434
[18 in] [87 in] [18 in] [24 in] [24 in]
SCALE 1:20 PLAN CG weight 144 kg (319 lb) Center of gravity PLAN
SCALE 1:50 CG - weight 237 kg (521 lb) Center of gravity
657
[27.2 in]
[25.9 in]
[61.2 in]
690
[88 in]
[85.2 in]
1555
2235
2165
[74.8 in]
1900
[66.57 in]
1691
[14.2 in]
360
[11.6 in]
1.8
294.6
[.07 in]
712
[28 in]
PLAN
[13.6 in]
Mi
n1
345
LL [6 53 - 592 592
WA OOR in - M
10 ax 2 [23.3 in] [23.3 in]
FL 4 8 ]
.7 i 73
n]
381 2 in
8 FRONT PLAN
[15 in] (2) 15 mm [0.59 in] [9.
SIDE Center of gravity FRONT diameter Floor Drilling SCALE 1:25
Holes for M8 (5/16 in) Bolts
Center of gravity SCALE 1:10
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 A3 - Equipment Details (1) 05/16
75KVA SINGLE PHASE STEP-UP TRANSFORMER
533 51
[21 in] [2 in]
(TYP.)
[14 in]
355
[24 in]
609
[38 in]
965 Ground lug Cable access
(each side)
65
[2.56 in]
546 482
[21 in] [19 in]
FRONT SIDE
660
[26 in]
[25 in]
635
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 A4 - Equipment Details (2) 06/16
DELIVERY
150 150
[5.9] [5.9]
F A: INSTALL AREA:
G F F G D Minimum space required to utilize
the tube stand dollies
[7.9]
200
500 500
[19.7] [19.7] B: SERVICE AREA:
G Minimum area to allow you to draw
A
2158
[85]
F: OPERATION AREA:
Ventilation required 150 mm [5.9"].
Note: if the WS is on the right side, area B will be on the left side G: SERVICE AREA:
Service area required when generator
is anchored in seismic zones.
SCALE 1:50
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 A5 - Delivery 07/16
STRUCTURAL NOTES
· Methods of support for the steelwork that will permit attachment to structural steel or through bolts in
concrete construction should be favored. Do not use concrete or masonry anchors in direct tension.
· All units that are wall mounted or wall supported are to be provided with supports where necessary. Wall
supports are to be supplied and installed by the customer or his contractors. See plan for suggested locations.
· Control walls shall be constructed to minimum 2130mm (7'-0") high.
· Dimensions are to finished surfaces of room.
· Customers contractor must provide all penetrations in post tension floors.
· Customers contractor must provide and install any non-standard anchoring. Documents for standard
anchoring methods are included with GE equipment drawings for geographic areas that require such
documentation.
· Customers contractor must provide and install hardware for "through the floor" anchoring and/or any bracing
under access floors. This contractor must also provide floor drilling that cannot be completed because of an
obstruction encountered while drilling by the GE installer such as rebar etc.
· It is the customer's responsibility to perform any floor or wall penetrations that may be required. The
customer is also responsible for ensuring that no subsurface utilities (e.g., electrical or any other form of
wiring, conduits, piping, duct work or structural supports (i.e. post tension cables or rebar) will interfere or
come in contact with subsurface penetration operations (e.g. drilling and installation of anchors/screws)
performed during the installation process. To ensure worker safety, GE installers will perform surface
penetration operations only after the customer's validation and completion of the "GE surface penetration
permit".
· Different anchor types are used to install the components of the system. Refer to Structural Requirements
Section(s) of the Pre-Installation Manual for each anchor requirement.
· Refer to the Structural Requirements Section for the required minimum embedment.
· The ground surface must be flat and leveled, maximum tolerance for leveling is ±1.5 mm per 1 m (0.2 in per 10
ft). If the tolerances are not met by using the spacers provided, a grout pad shipped with the system is to be
used by the contractor to meet this specification. The maximum pad thickness is 6.3 mm (0.25 in).
[4 in]
100
The typical equipment positions shown ensure the
1000 mm [40 in] SID below the table top. The tube
1100
[43 in] stand install dolly clearances and surface
horizontal wall duct on the back wall are taken
200 into account. Site the system according to the
[8 in] dimensions on the Equipment Layout.
[45.5 in]
[37 in]
*1156
950
[36.4 in]
[28 in]
*926
720
190 75
1000 187 153 120
2260
[39 in]
[ ]
7 in
7 in
[6 in]
[ ]
3 in
5 in
[89 in]
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 S1 - Structural Notes 08/16
ITEM DESCRIPTION
4'-1"
1'-9"
0'-9"
0'-10"
0'-10"
2'-6"
2
3'-9"
EQUIPMENT ROOM
4
7'-11"
1'-0"
CONTROL ROOM
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG 1/4"=1'-0" Rev B Date 04/Jun/2021 S2 - Structural Layout 09/16
ST TUBE STAND BASEPLATE ST TABLE BASEPLATE
1295
[51 in]
1240
[49 in]
620 620
40 480 480 480 480 [24 in] [24 in]
[1 in]
[11 in]
273
[9 in]
224
[14 in]
[21 in]
355
537
[17 in]
[18 in]
434
460
[7 in]
184
[5 in]
131
[1 in]
1185
13
[47 in]
2000
[79 in]
[9.8 in]
[3.9 in]
248
100
100
[3.9 in]
30
[1.2 in]
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 S3 - Structural Details 10/16
TEMPERATURE AND HUMIDITY SPECIFICATIONS
IN-USE CONDITIONS
EXAM ROOM CONTROL ROOM
Min Max Min Max
Temperature
10°C (50°F) 40°C (104°F) T.B.D. T.B.D.
Relative humidity (1) 30% to 75% T.B.D.
W BTU/h W (In Use) BTU/h (In Use)
Heat output
523.6 1784.8 97.3 332.5
Exam room heat output assumes a working cycle of one [1] patient every two [2] minutes during one [1] hour.
The optional docking station can be sited in the exam room or the control room. It adds 70.3 W (240 BTU/h) to the heat load.
STORAGE CONDITIONS
Temperature 5°C to 60°C (41°F to 140°F)
Relative humidity (1) 20% to 90%
Material should not be stored for more than 90 days.
(1) non-condensing
AIR RENEWAL
According to local standards.
NOTE
In case of using air conditioning systems that have a risk of water leakage it is recommended not to install it above electric equipment or to
take measures to protect the equipment from dropping water.
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 M1 - HVAC - Environment 11/16
CONNECTIVITY REQUIREMENTS ELECTRICAL NOTES
Broadband Connections are necessary during the installation process and going forward to ensure full support
from the Engineering Teams for the customers system. Maximum performance and availability for the customers 1. All wires specified shall be copper stranded, flexible, thermo-plastic, color coded, cut 10 foot long at outlet
system is maintained and closely monitored during the lifetime of the system. Proactive and reactive maintenance boxes, duct termination points or stubbed conduit ends. All conductors, power, signal and ground, must be
is available utilising the wide range of digital tools using the connectivity solutions listed below: run in a conduit or duct system. Electrical contractor shall ring out and tag all wires at both ends. Wire runs
must be continuous copper stranded and free from splices.
· Site-to-Site VPN/GE Solution 1.1. Aluminum or solid wires are not allowed.
2. Wire sizes given are for use of equipment. Larger sizes may be required by local codes.
· Site-to-Site VPN/Customer Solution 3. It is recommended that all wires be color coded, as required in accordance with national and local electrical
codes.
· Connection through Dedicated Service Network 4. Conduit sizes shall be verified by the architect, electrical engineer or contractor, in accordance with local or
national codes.
· Internet Access - connectivity for InSite 2.0 5. Convenience outlets are not illustrated. Their number and location are to be specified by others. Locate at
least one convenience outlet close to the system control, the power distritbution unit and one on each wall of
The requirements for these connectivity solutions are explained in the broadband solutions catalogue (separate the procedure room. Use hospital approved outlet or equivalent.
document). 6. General room illumination is not illustrated. Caution should be taken to avoid excessive heat from overhead
spotlights. Damage can occur to ceiling mounting components and wiring if high wattage bulbs are used.
For all installations, make sure you have at least one (1) RJ45 dedicated to connect the new equipment on the LAN. Recommend low wattage bulbs no higher than 75 watts and use dimmer controls (except MR). Do not mount
lights directly above areas where ceiling mounted accessories will be parked.
7. Routing of cable ductwork, conduits, etc., must run direct as possible otherwise may result in the need for
greater than standard cable lengths (refer to the interconnection diagram for maximum usable lengths point
to point).
8. Conduit turns to have large, sweeping bends with minimum radius in accordance with national and local
electrical codes.
9. A special grounding system is required in all procedure rooms by some national and local codes. It is
recommended in areas where patients might be examined or treated under present, future, or emergency
conditions. Consult the governing electrical code and confer with appropriate customer administrative
personnel to determine the areas requiring this type of grounding system.
10. The maximum point to point distances illustrated on this drawing must not be exceeded.
11. Physical connection of primary power to GE equipment is to be made by customers electrical contractor with
the supervision of a GE representative. The GE representative would be required to identify the physical
connection location, and insure proper handling of GE equipment.
12. GEHC conducts power audits to verify quality of power being delivered to the system. The customer's
electrical contractor is required to be available to support this activity.
· All junction boxes, conduit, duct, duct dividers, switches, circuit breakers, cable tray, etc., are to be supplied
and installed by customers electrical contractor.
· Conduit and duct runs shall have sweep radius bends
· Conduits and duct above ceiling or below finished floor must be installed as near to ceiling or floor as possible
to reduce run length.
· Ceiling mounted junction boxes illustrated on this plan must be installed flush with finished ceiling.
· All ductwork must meet the following requirements:
1.Ductwork shall be metal with dividers and have removable, accessible covers.
2.Ductwork shall be certified/rated for electrical power purposes.
3.Ductwork shall be electrically and mechanically bonded together in an approved manner.
4.PVC as a substitute must be used in accordance with all local and national codes.
· All openings in raceway and access flooring are to be cut out and finished off with grommet material by the
customers contractor.
· General contractor to insert pull cords for all cable run conduits between the equipment room and the
operators control room.
· 10 foot pigtails at all junction points.
· Grounding is critical to equipment function and patient safety. Site must conform to wiring specifications
shown on this plan.
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 E1 - Electrical Notes 12/16
FLOOR AND ELECTRICAL LAYOUT
ITEM DESCRIPTION
1 Main disconnect panel
2 4" x 2" surface floor duct with minimum 1 divider
3 10" x 3 1/2" surface wall duct with minimum 2 dividers
4 Box above ceiling size per local code
5 1" conduit above ceiling
6 2 1/2" conduit above ceiling
7 Flush box, size per local code [Access Point]
8 6" x 6" x 4" box [Console]
5'-0"
3
A Surface wall duct
7'-11"
1'-2" 1'-3"
3 8 D
2
1
3
CONTROL ROOM
2'-11"
7'-9"
11'-2" 5 6
From To Size
Qty
(Bubble # / Item) (Bubble # / Item) In. mm
Generator 1 As Req'd As Req'd
1 Main Disconnect Panel
System Emergency Off 1 1/2 16
Warning Light 1 1/2 13
Warning Light Controller Generator 1 1/2 13
120-V 1Ø Power 1 As Req'd As Req'd
Door Interlock Switch Generator 1 1/2 16
4 Aero DR interface unit 7 Access Point 1 1 25
75kVA Transformer Facility Power As Req'd As Req'd
75kVA Transformer 1 Main Disconnect Panel 1 As Req'd As Req'd
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG 1/4"=1'-0" Rev B Date 04/Jun/2021 E2 - Electrical Layout 13/16
4
+ 8'-6" + 8'-6"
T.B.D.
3
3 3
± 0'-0" ± 0'-0"
1'-0"
1'-0"
A B
1'-0"
+ 8'-6" + 8'-6" + 8'-6"
1 7
8
5'-0"
3 2
1'-0"
1'-6"
± 0'-0" ± 0'-0" ± 0'-0"
C D E
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG 1/4"=1'-0" Rev B Date 04/Jun/2021 E3 - Electrical Elevations 14/16
POWER REQUIREMENTS POWER DISTRIBUTION
· Neutral must be terminated inside the main disconnect panel (MDP) and not at any GE cabinet.
· The section of the supply cable should be calculated in accordance with its length and the maximum TBL 115/208/
permissible voltage drops. Refer to Feeder Table. 230/240V
SUPPLY CHARACTERISTICS Main Disconnect Panel (MDP)
For GEN supply (1 phase) feeder and Refer to table 2. Also available from GE:
· Power input must be separated from any others which may generate transients (elevators, air conditioning, ground wire size Refer to Table 1 E4502TA (208V with TRAN)
E4502TB (230-240V)
radiology rooms equipped with high speed film changers...)
· All equipment (lighting, power outlets, etc...) installed with GE system components must be powered L1 3 x 1.5 mm² GEN
230/240V
separately. [16AWG]
24V 24V
GROUND SYSTEM
3 x 1.5 mm² 3 x 1.5 mm² 3 x 1.5 mm² 3 x 1.5 mm² 8 x 1.5 mm²
· The grounding conductor will be of same size as the feeder. This ground will run from the MDP back to facility
[16AWG] [16AWG] [16AWG] [16AWG] [16AWG]
power source/main grounding point and always travel in the same conduit with the feeders and neutral.
· Grounding is critical to equipment function and patient safety. Site must conform to wiring specifications
shown on this plan. DLK SEO SEO L Y
CABLES
If applicable 1 included If applicable If applicable If applicable
· Power and cable installation must comply with the distribution diagram attached. with GE MDP
· All wiring must be THHN or TFFN stranded copper thermoplastic 600 volt or equivalent insulation. Aluminum
or solid wires are not allowed. Cable color codes must comply with standards for electrical installation. LEGEND TABLE 1: MINIMUM WIRE SIZE - FACILITY TRANSFORMER TO MDP
· General contractor to insert pull cords in all GE supplied cable run conduits. 1.5 m (5') pigtails at all junction DLK Door interlock switch
MIN. FEEDER WIRE SIZE, MINIMUM FEEDER WIRE LENGTH - ft (m)
points. GEN Generator cabinet AWG OR MCM (mm²)/VAC 50 (15) 100 (30) 150 (45) 200 (60)
L System ON light - 24V -
208 VAC/GROUND 1 (50) 3/0 (95) N/A N/A
Located near access doors
230/240 VAC/GROUND 2 (35) 2/0 (70) 4/0 (95) N/A
L1 X-Ray ON light - Located near
GENERAL NOTES
access doors
Calculations based on nominal voltage.
SEO Emergency OFF, near access Recommended feeder sizes from distribution transformer to the power cabinet.
doors Neutral must be terminated inside the Main Disconnect Panel (MDP) and not at any GE
cabinet
TBL Elevating table (this cable is In all cases qualified personnel must verify that the feeder (at the point of take-off) and
not supplied, or used, with the the run to the X-Ray system meet all the requirements stated in the PIM
ST fixed table) Grounding conductor will run from the equipment back to the power source/main
TRAN 75kVA step-up transformer grounding point and always travel in the same conduit with the feeders
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 E4 - Power Requirements 15/16
TYPICAL CABLE MANAGEMENT INTERCONNECTIONS
EXAM ROOM
DUCT ON THE FLOOR WALL DUCT X-RAY
GENERATOR
CABINET
Customer supplied
9.5m (31.2')
TABLE
NOT TO SCALE
X-RAY TUBE
SUPPORT
CONTROL ROOM
17.6m (57.7')
PC INTERFACE
BOX
OPERATOR
CONSOLE
Typical PROTEUS XR/F ST EN-RAD-TYP-PROTEUS XRF-ST.DWG Rev B Date 04/Jun/2021 E5 - Interconnections 16/16