Polystorm Technical Guide
Polystorm Technical Guide
Uniclass EPIC
L2172 B524
CI/SfB
(52.5) X
May 2011
1
Contents
Water Management
Solutions Contents
Modular Cell Systems Section Page
This document describes the products from Polypipe Water Management Design Protocol 4 30 - 49
Solutions for implementing a stormwater management system that
meets the requirements for Sustainable Drainage Systems (SUDS). Installation 5 50 - 63
• Forms for specifying your requirements for Catchpits and Stormcheck chambers
2 3
Index - pages
Products 2 14 - 23
Modular cell system overview 2.1 16 - 17
Polystorm Lite 2.2 18 - 19
Section 1 - provides an overview of SUDS. Polystorm 2.3 20 - 21
Polystorm hybrid construction 2.4 22 - 23
Section 2 - provides guidance on drainage design and Testing & Certification 3 24 - 29
helps you select which product to use for managing a Testing and certification 3.1 26 - 27
Summary of test results 3.2 28 - 29
site's stormwater run-off. Design Protocol 4 30 - 49
Detail design protocol 4.1 32 - 35
Section 3 - provides testing and certification information. Distributed loads 4.2 36
Lateral loading calculation example 4.3 37 - 38
Section 4 & 5 - describe design protocol, installation Maximum burial depths 4.4 39
Special measures 4.5 40
and maintenance. Hydraulic design 4.6 41
Hydrological rainfall 4.7 42 - 43
Section 6 - provides information on associated products. Soakaway design 4.8 44 - 47
General layouts 4.9 48 - 49
Section 7 - shows project solutions. Installation 5 50 - 63
Health and safety 5.1 52 - 55
Section 8 - company overview. Connections 5.2 56 - 57
Ventilation 5.3 58 - 60
Typical installation procedure - soakaway 5.4 61 - 62
Maintenance 5.5 63
Associated Products 6 64 - 73
Stormcheck 6.1 66 - 67
Storm-X4 6.2 68 - 71
Fabrications 6.3 72 - 73
Project Solutions 7 74 - 79
Polystorm case studies 7.1 76
Polystorm Lite case study 7.2 77
Hybrid solutions case study 7.3 78 - 79
The Company 8 80 - 91
Manufacture 8.1 82 - 83
Innovation, research & development 8.2 84 - 85
Health, safety & environmental policies 8.3 86 - 87
Sustainability 8.4 88 - 89
Support information 8.5 90 - 91
4 5
Index - illustrations & tables
Description Section Table Illustrations* Page Description Section Table Illustrations* Page
Products Installation
Polystorm Lite - technical specification overview 2 1 18 Impermeable geomembrane properties 5 17 53
Polystorm Lite cell dimensions 2 Figure 1 18 Clip connectors 5 *Figure 31 54
Polystorm Lite - product codes and pack quantities 2 2 19 Shear connectors 5 *Figure 32 54
Polystorm Lite maximum burial depths 2 Figure 2 19 Location of points for clips and shears 5 *Figure 33 54
Polystorm technical specification overview 2 3 20 Shear connector installation 5 *Figure 34 55
Polystorm cell dimensions 2 Figure 3 20 Clip connector installation 5 *Figure 35 55
Polystorm - product codes and pack quantities 2 4 21 160/110mm Invert level reducer 5 *Figure 36 56
Polystorm maximum burial depths 2 Figure 4 21 160mm diameter adaptor 5 *Figure 37 56
Polystorm Lite burial depths 2 Figure 5 22 Polystorm cell 160mm diameter knock out 5 *Figure 38 56
Polystorm burial depths 2 Figure 6 22 Fabricated Polystorm cell allowing 225mm diameter
5 *Figure 39 56
Hybrid solution burial depths 2 Figure 7 23 pipe connection
Fabricated Polystorm cell allowing 300mm diameter
Testing & Certification 5 *Figure 40 56
pipe connection
Compression test rig 3 Figure 8 26
Typical Polystorm 450mm inlet manifold detail 5 *Figure 41 57
Unit axis; direction of applied load 3 Figure 9 27
Typical Polystorm 450mm inlet manifold detail 5 *Figure 42 57
Position of load platens; point load resistance 3 *Figure 10 27
Typical Polystorm manifold detail 5 *Figure 43 57
Creep test rig 3 Figure 11 27
Typical Polystorm 600mm inlet manifold detail 5 *Figure 44 57
Dimensions of Polystorm Lite cell 3 Figure 12 28
Vertical vent pipe with cowl 5 *Figure 45 58
Dimensions of Polystorm cell 3 Figure 13 28
Horizontal vent pipe 5 *Figure 46 58
Technical data of Polystorm Lite and Polystorm cells 3 5 29
Permeable geotextile properties 5 18 61
Design Protocol Silt trap 5 Figure 47 63
Structural design 4 Figure 14 32
Associated Products
Partial material factors of safety: Polystorm Lite & Polystorm 4 6 34
Manual bypass design 6 Figure 48 67
Partial factors of safety for applied loads 4 7 35
Auto bypass design 6 Figure 49 67
Distributed loads - design against collapse 4 Figure 15 36
Capabilities of Storm-X4 to reduce chemical pollutants 6 19 71
Lateral loading - load from wheels 4 Figure 16 37
Lateral loading - from earth, water pressure and surcharge
4 Figure 17 37
above cell
Lateral loading - design against floatation 4 Figure 18 38
Polystorm Lite - maximum depth of installation 4 8 39
Polystorm - maximum depth of installation 4 9 39 * Please note:
Polystorm & Polystorm Lite - minimum cover levels 4 10 39 Illustrations shown within this
Reducing lateral pressure - building out layers 4 Figure 19 40
publication are available as
Reducing lateral pressure - using reinforced soil backfill 4 Figure 20 40
downloadable CAD drawings from
Reducing lateral pressure - mass concrete backfill 4 Figure 21 40 Seating
Rings
Pre-cast Concrete
Concrete
www.polypipewms.co.uk
94.20m Surround
Cover Slab
1.0 Overview
Polypipe Water Management Solutions
Overview
Part of the overall Polypipe Civils business, the Polypipe Water Management
Solutions (WMS) team includes some of the most talented Civil Engineers and Contents
Water Management Specialists within the industry to provide dedicated knowledge, Page
support and technical expertise for a wide range of sustainable drainage systems SUDS best practise & legislation 1.1 10 - 11
(SUDS) and water management projects. Drainage design - planning, cost effective techniques,
1.2 12 - 13
site evaluation, adoption and future maintenance
Today, the concept of sustainable water management is a major driver in the UK construction
industry. Planning Policy Statement 25 (PPS25) requires local planning authorities to institute policies
that enforce, wherever possible, the use of Sustainable Drainage Systems or SUDS. Combine this
with the Floods and Water Management Act and it becomes obvious that specifying the correct
8 9
Overview 1.1
Sustainable drainage systems are an alternative to the traditional approach of 1.1.3 The Code for Sustainable Homes
The Building Regulations also provide guidance on the construction of rainwater Polypipe WMS
collecting stormwater in pipes and discharging it into treatment works or harvesting systems for the first time. The newly published Guidance Document provide the developer,
entitled ‘The Code for Sustainable Homes’ indicates the Government’s intentions both large and small, with
watercourses. SUDS best practice limits the flow of rainwater which runs off a site
to further drive developers towards building sustainable homes. flexible value engineered
or is piped away, protects local watercourses from the contamination carried in As well as covering energy efficiency, water usage and waste, the Code also
solutions which cater for
almost any site conditions
proposes a minimum standard for surface water management. This minimum
surface run-off, encourages natural groundwater recharge (where appropriate) and restraints.
standard will require peak run-off rates or annual run-off volumes of surface
and reduces the likelihood of downstream flooding. water to be no more than the original conditions of the site.
(c) a sewer.
SUDS best practice limits the flow of rainwater which runs off a site or
is piped away, protects local watercourses from contamination carried in
surface run-off, encourages natural groundwater recharge (where
appropriate) and reduces the likelihood of downstream flooding.
10 11
Overview 1.2
Step 3 Substitute • Covers all types of flooding the Environment Agency to adopt a strategic overview role for all forms of flood
risk, including groundwater and surface water.
• Flooding considered at all stages of the planning process
Step 4 Control
• Risk-based sequential approach 1.2.6 Adoption and future maintenance
Step 5 Mitigate • Safe development of sustainable communities In the early stages of design, consideration should be given to the arrangements
for adoption and future maintenance of the system. This is likely to influence the
Step 4 requires planners to use SUDS
design just as much as technical considerations. For private, or non-adopted systems,
as a form of control for surface water.
maintenance will be the responsibility of the owner and future developments may
1.2.2 Planning
be affected by covenants. For systems serving more than one residential property
Planning authorities will set a limit to the rate of stormwater flow from a site via
it is recommended that maintenance should be the responsibility of a publicly
sewers as a condition of planning consent. In recognition of this, Local Planners
accountable body, which will often necessitate the payment of a commuted sum
increasingly state that all applications should, in the first instance, aim to
or a legal agreement, possibly backed by the deposit of a financial bond.
incorporate SUDS into development proposals. SUDS are also considered suitable
The adopting organisation should approve the design before construction.
for mitigating adverse impacts and supporting water conservation objectives.
12 13
Products 2.0
weather patterns. The flooding witnessed during recent years is a clear indication Contents
that climate change is causing more frequent and extreme weather events and Page
innovative solutions are required to cope with increased pressure on our existing Polystorm modular cell system overview 2.1 16 - 17
Polystorm 2.3 20 - 21
Planning Policy Statement 25 - Development and flood risk
Polystorm hybrid construction 2.4 22 - 23
Planning Policy Statement 25 (PPS25) sets out Government policy on
development and flood risk. Its aim is to ensure that flood risk is taken into
account at all stages in the planning process to avoid inappropriate
development in areas at risk of flooding and to direct development away from
areas of highest risk. Where new development is exceptionally necessary in
such areas, policy aims to make it safe, without increasing flood risk elsewhere
and where possible, reducing flood risk overall.
Planning Policy Statement 25: Development and Flood Risk (PPS25), published in June 2008.
14 15
Products 2.1
releases the water within set discharge limits (attenuation) or, Polystorm Lite Polystorm
where soil conditions allow, be wrapped in a permeable geotextile
and slowly release the water back into the surrounding soil (soakaway).
• Light weight yet robust: Excellent Health and Safety non-loaded applications
and installation benefits
• Polystorm is designed for use in
Shear connector
• Easy to handle: Unique rounded corners for ease of light trafficked and loaded For connecting cells
handling and reduces likelihood of punctures to membranes applications together vertically
• Cost effective: Especially when used as a hybrid, value The Polystorm Technical Manual is available
engineered system
to download at:
• Recyclable: 100% recyclable at the end of its useful life www.polypipewms.co.uk/downloads
16 17
Products 2.2
0.5m
Polystorm Lite
Technical specification overview Ridgidrain flange adaptor - 150mm PSMFA150 1 Note: Minimum cover and burial depths
Designed for use may vary depending on load and ground
Unit type Polystorm Lite EN1401 flange adaptor - 160mm PSMFA160 1
in landscaped, conditions. Please contact Polypipe WMS
for further information. All grades of
pedestrian or Product code PSM2* Basic silt trap PSMST160 1
Polystorm units may be used in situations
other non-loaded Dimensions 1m x 0.5m x 0.4m high Advanced silt trap - 15 litres/sec PSMSTA160/15 1 outside of those recommended above,
applications with Total volume 0.2m per cube Mini silt trap for Polystorm Lite PSMST110 1
through the use of the appropriate
protective measures designed to reduce
a load bearing the imposed loading on the proposed
Unit weight 7kgs** Cover & frame (round) UG501 1
capacity of: Polystorm structures.
Cube storage volume 0.19m³ (190 litres) Cover & frame (square) UG502 1
20 tonnes Surface area 55% perforated 450mm silt trap lid & frame UG512 1
Compressive strength Maximum 20 tonnes per sq metre 460mm lockable plastic cover & frame UG511 1
* Each unit includes 4 clips and 2 shear connectors. Please note that brick bond connector may be Chamber riser section ICDR1 1
required at additional cost.
Silt trap sealing ring UG488 1
** Pallet weight dependent upon order quantity and transport type.
*** In weak clay soil conditions the maximum burial depth is 1.5 metres. Polystorm Lite should not Table 2
be installed below the water table.
Table 1
18 19
Products 2.3
2.3 Polystorm
0.5m
0.6m
min Polystorm features individual modular cells that can be built up
to form a load-bearing tank structure of any shape or size to
receive rainwater collected from the gutter system or surface
drains ready to release within a set discharge limit. Polystorm
0.4m 3.1m has a 40 tonne per square metre compressive strength and is
ideally suited for light trafficked and loaded applications.
Polystorm can be used for both attenuation and soakaway
Polystorm
Clips PSMCLIP 60
Technical specification overview EN1401 flange adaptor - 110mm PSMFA110 1 Note: Minimum cover and burial depths
Designed for use may vary depending on load and ground
Ridgidrain flange adaptor - 150mm PSMFA150 1
in trafficked and Unit type Polystorm conditions. Please contact Polypipe WMS
for further information. All grades of
loaded applications Product code PSM1* EN1401 flange adaptor - 160mm PSMFA160 1
Polystorm units may be used in situations
with a load bearing Dimensions 1m x 0.5m x 0.4m high Basic silt trap PSMST160 1 outside of those recommended above,
Cube storage volume 0.19m³ (190 litres) Cover & frame (square) UG502 1
Surface area 48% perforated 450mm silt trap lid & frame UG512 1
Compressive strength Maximum 40 tonnes per sq metre 460mm lockable plastic cover & frame UG511 1
Maximum burial depth 3.7 metres*** Polypropylene cover & frame ICDC1 1
* Each unit includes 4 clips and 2 shear connectors. Please note that brick bond connector may be Chamber riser section ICDR1 1
required at additional cost.
Silt trap sealing ring UG488 1
** Pallet weight dependent upon order quantity and transport type.
*** In weak clay soil conditions the maximum burial depth is reduced, please consult Polypipe WMS Table 4
Technical Team on 01509 615100.
Table 3
20 21
Products 2.4
The following illustrations indicate maximum burial depths for Hybrid Solution
Polystorm Lite and Polystorm modular cell systems.
VALUE ENGINEERED STRUCTURES
Pedestrian
0.5m min
1.99m
3.2m
0.5m 0.6m
min min
2.49m*
1.99m 3.7m*
3.1m
Figure 7
Figure 5
22 23
Testing and certification 3.0
and where possible, are covered by third party certification. Our manufacturing Contents
processes are also accredited to ISO 9001:2008. There are two quality control
Page
labs in operation 12 hours a day. Testing and certification 3.1 26 - 27
24 25
Testing and certification 3.1
As a manufacturer of plastic below-ground water management products, Polypipe 3.1.2 Test protocol Polystorm cell; direction of applied load and platen
location
Laboratory testing to determine the structural performance
WMS invests heavily in British Board of Agrément (BBA) approval and is a supporter of the Polystorm cells has followed the protocol agreed
y-axis
500mm
with the British Board of Agrément (BBA). Direct loading
of the criteria used to assess each product. By achieving BBA approval, Polypipe WMS
tests were carried out on single cells. Individual cells were
can pass on to our customers confidence in the performance of all our products. load tested until failure (i.e. the point at which they could
400mm
not sustain further load).
perform in-line with our claims when installed in accordance with the BBA certificate.
26 27
Testing and certification 3.2
Weight (kg) 7 9
(1) = Applied load (2) = At up to 20 years @ 20°C @ 127kN/m2 load (Polystorm) (3) = Time in hours
(2) = At up to 20 years @ 20°C @ 54kN/m2 load (Polystorm Lite)
1.0m * Maximum burial depth dependant upon soil conditions, see page 39 for further details.
Table 5
3.2.2 Durability
Figure 12 Dimensions of Polystorm Lite cell
When installed in accordance with Polypipe WMS recommendations, the
0.5m
design life of Polystorm Lite and Polystorm cells exceeds 50 years. Please refer
to BBA certificate.
1.0m
28 29
Design protocol 4.0
Design protocol
Contents
Page
Polypipe WMS provide a full in-house design facility. Upon consultation our team Special measures 4.5 40
of designers and technical advisors will guide you as to the best solution for your Hydraulic design 4.6 41
30 31
Design protocol 4.1
4.1 Detail design protocol 4.1.2 Limit state design, 4.1.3 Industry standards,
4.1.1 Structural design 4.1.4 Factors of safety
4.1.1 Structural design 4.1.2 Limit state design 4.1.3 Industry standards
When designing plastic geocellular structure for soakaway or attenuation tanks care has to be taken to ensure In the design of any load carrying system, there needs to There are currently no design standards or guides specific
the finished system is safe to carry the loads they will be subject to. The diagram below outlines a safe route to be factors of safety to allow for any variation in either to generic modular plastic stormwater tanks, with each
the design and installation of Polystorm modular stormwater tanks. the applied load or cellular unit strength. Limit state manufacturer within the marketplace providing their
design does not use a single overall factor of safety; the own guidelines that tend to be specific to their own cells.
method looks at ‘limit states’ and applies partial factors However, a generic design method has been developed
Applied loads Partial factors of safety of safety to the various design parameters depending on that can be applied to most types of cells, using basic
• Distributed • On material properties the consequences of the limit state being exceeded. In structural design theory and relevant British Standards. In
• Concentrated • On loads the case of Polystorm drainage tanks the two limit states particular the loading on plastic tanks may be considered
• Traffic • Follow BPF and to be considered are: to be the same as a buried concrete or steel tank and so
• Backfill CIRIA guidance the loads and partial factors of safety for loads have been
• Stockpiles
• Ultimate limit state (ULS)
taken from the following:
This is when the strength of the cell is exceeded
• Earth pressure
by the applied loads and the tank collapses. This is 1. British Standards Institution (1997). British Standard
• Construction traffic
obviously serious and the partial factors of safety BS8110, Part 1: 1997; Structural use of concrete:
• Cranes
used in this assessment are chosen to ensure there Code of practice for design and construction. BSI
• Uplift
is a negligible risk of a collapse occurring.
2. British Standards Institution (1996). British Standard
• Serviceability limit state (SLS) BS 6399: Part 1: 1996: British Standard Loadings for
This considers the operational behaviour of a tank Buildings. Part 1 Code of Practice for dead and
Analysis
to ensure that the installation remains serviceable. imposed loads. BSI
Laboratory testing • Failure
For the structural calculations this means that
• Ultimate compressive • Deflection (movement The only available guidance relating to plastic materials
deflections are not excessive and do not cause
strength at yield under load) in similar situations to buried cellular tanks is that
damage to overlying surfaces (such as asphalt) or
• Deflection parameters • Creep for plastic geosynthetics in soil strengthening and
cause a significant reduction in the storage volume of
• Creep • Flotation reinforcement. The information in the following British
the tank. The Polystorm Lite cell is recommended for
Figure 14 Standard has been used as a guide to the choice of
use in landscaped areas, where deflections would
partial material factors used for the design:
have a negligible effect. SLS would therefore not play
a significant role in Polystorm Lite structural design. 1. British Standards Institution (1995). British Standard
Listed below are the four main reasons for failure of the system:
BS8006: 1995; Code of practice for strengthened/
1 Structural failure or collapse - when the structure cannot support the reinforced soils and other fills. BSI
applied loads.
2 Excessive deflection or movement when vehicles passing over the tank 4.1.4 Factors of safety
cause movement and the surface above may crack or displace.
To ensure that the risk of exceeding the limit states is
3 Creep - excessive movement or loss of strength over a period of time minimal, factors of safety are applied to the cellular unit’s
which can occur under a constant load. ultimate compressive strength and to any applied loads;
these are known as partial factors of safety.
4 Flotation: Constructing a tank below the groundwater table can
create uplift.
32 33
Design protocol 4.1
4.1.5 Material factors ƒm12 4.1.6 Applied loads and load factors
The ultimate compressive strength of the Polystorm cells This is applied to take account of the extrapolation of creep Loads that may be imposed on a cellular storage structure such as Polystorm,
has been obtained from laboratory testing on samples. test data. It is also used in the case of the Polystorm cells to can be broken down into the following types:
To take account of other factors such as variations due to allow for the absence of fatigue testing. A suggested value
manufacturing processes, variability and uncertainties in of ƒm12 is given by Ingoldv = Log (td/tt) where td = design
• Dead Loads
Permanent loads applied to the cells, including the weight of backfill
material strength (e.g. due to extrapolation of data), life, tt is duration of creep test. This gives a value for the ULS,
material placed over the top and lateral (horizontal) earth and water
damage during installation and environmental effects, with a design life of 20 years, of ƒm12 = 1.9. Although the
pressure loads acting on the side of the system.
a design strength is derived by dividing the cell’s cells will be under compressive loads and appear to fail in
characteristic strength by a material partial factor of compression at the internal columns, they are complex • Live Loads
safety (ƒm), appropriate to the material and limit state. structures. Some of the elements will be acting in tension Loads due to pedestrian, vehicle and construction traffic that are not
There is no guidance on the choice of material factors and when polypropylene is subject to creep under long term permanent. Traffic wheel loads are normally given as static loads, with
for plastic storage tanks. tensile loads it can lose strength over time. Therefore the a factor applied to allow for dynamic effects (a moving wheel will impose
values taken from reinforced earth applications are more force on the ground than a static one).
Partial material factors of safety: considered reasonable. For serviceability, which is not so
A design load is obtained by applying a partial factor of safety to the estimated
Polystorm Lite & Polystorm critical, a value of 1.25 is adopted.
characteristic load. This allows for unforeseen variations of loading and also the
Limit state ƒm severity of the consequences of the limit state occurring. The loads on cellular
Ultimate limit state 2.75
ƒm21 units will be similar to loads applied in the design of structures using rigid
Serviceability limit state 1.5 This is applied to take account of damage during installation. materials such as concrete and therefore the partial safety factors for loads that
The Polystorm cells are robust and not particularly susceptible are appropriate to the design of plastic storage systems are taken from British
Table 6
to damage and therefore, in the absence of specific damaged Standard BS 8110.
The partial factor ƒm is made up of several components:
strength testing, a factor of 1.1 for the ULS and 1.0 for the
SLS has been used.
ƒm11 Partial factors of safety for applied loads
This is applied to the characteristic strength of Polystorm.
ƒm22 Imposed vertical Imposed earth Imposed
It covers possible reductions in strength from the control Limit state dead load pressure dead load live load
This is applied to take account of environmental ƒm ƒm ƒm
test specimens and inaccuracies in the assessment of the
conditions. The polypropylene used in the manufacture
resistance of a structural element resulting from Ultimate
of the Polystorm units is resistant to all contaminants that are 1.40 1.40 1.60
modelling errors. For tightly controlled Polystorm limit state
naturally found in soil and rainwater. No specific test results
production ƒm11 would normally be between 1.05 and
are available and so a value of ƒm22 for both ULS and SLS of Serviceability
1.1. Because a limited number of compression tests have
1.1 has been adopted; which is the minimum value limit state 1.0 1.0 1.0
been undertaken on the Polystorm cells in addition to (Polystorm only)
recommended for reinforced earth applications by Ingoldv.
this property not being measured as part of the quality
With the total value of ƒm = ƒm11 x ƒm12 x ƒm21 x ƒm21 Table 7
control program, a conservative value has been adopted.
Compression tests were undertaken at points judged by Therefore, for the following limit state, ƒm will equate to: Thermal expansion of the cells will be negligible because temperature variations
inspection to be the weakest however the cell is a that are likely to occur in the ground should not be significant. These loads are
Ultimate limit state: Serviceability limit state:
complex three dimensional structure, therefore an therefore not considered in this design.
1.2 x 1.9 x 1.1 x 1.1 = 2.75 1.1 x 1.25 x 1.0 x 1.1 = 1.5
allowance must be made for this. In view of the
The use of conservative factors also allows for synergistic
preceding factors and the conservative choice of design
effects (i.e. the combined effect of construction damage,
parameters already undertaken, a value of ƒm11= 1.20
environmental effects and lower than expected cell strength)
has been adopted for the ULS and 1.1 for the SLS. This
that may result in a greater combined effect than the three
can be reviewed if the compressive strength is measured
factors acting individually. These factors are only applicable
as part of the manufacturing quality control procedure.
for temperate climate conditions such as in the UK. Although
the strength of polypropylene varies with temperature, this
will not be significant for installation in the UK where the
temperature in the ground (at the typical depth of
installation) remains between 0°C and 20°C with a mean
value of around 10°C.
34 35
Design protocol 4.2/4.3
Table 8
Table 9
Polystorm Lite & Polystorm - minimum cover levels ( to top of cells) (m)
Field
Live load conditions Light trafficking (Polystorm only)
(Polystorm Lite & Polystorm)
Car park with vehicle mass Car park with occasional
<2500kg vehicle mass >2500kg
Table 10
Please note that the maximum burial depths above are based on the partial factors of safety derived during consultation
with the British Board of Agrément (BBA) prior to the publication of CIRIA C680. The BBA has used higher partial factors
of safety than CIRIA C680. For further information of the design method detailed in CIRIA C680 please contact our
4.5.1 Special measures 4.6.1 Hydraulic design Polystorm can be used to provide attenuation, long term
Hydraulic design calculations provide the storage volume storage and can be designed into systems that provide
The earth pressure at the design depth for the tank may exceed the lateral strength of Polystorm Lite and
required on any particular site that is required to reduce interception storage (e.g. soakaways or below swales or
Polystorm cells (once it has been factored down). If this is the case there are a number of solutions:
the speed, frequency and volume of rainfall run-off into infiltration basins). The SUDS manual also requires
1. Redesign the drainage system to make the invert of the tank shallower.
rivers or sewers. The required volume depends on the site treatment of pollution in run-off and Polystorm can help
2. Place the cells in a stepped configurations where the tank gets wider from the base to the top (Figure 19).
location, the size of the area being drained, the soil these treatment systems work more effectively by
3. Reinforce the lower part of the backfill with geogrids (Figure 20).
infiltration rate (for soakaways) or allowable discharge controlling the flow of water through them (for example by
4. Use mass concrete backfill in the lower part of the backfill (Figure 21).
rate (for attenuations systems). providing attenuation storage upstream of a wetland). The
exact design requirements for any site should be agreed
Reducing lateral pressure on a Polystorm Tank The design of SUDS should follow the requirements in
with the Environment Agency.
the CIRIA Report C 697 The SUDS Manual.
This identifies three types of storage that are required:
4.6.2 Design of attenuation storage
• Interception storage - this is not actually storage -
The volume of Polystorm required for attenuation storage
the aim is to reduce the frequency of run-off and
Fill needs to is typically calculated using drainage design software
be very compact prevent run-off from sites for rainfall events up to
based on the Wallingford Procedure. The volume of
to avoid settlement 5mm in order to simulate the behaviour of
whch can cause temporary run-off storage required is shown in Figure 22
crushing on edge greenfield catchments more closely. This is achieved
and is simply the difference between the volume of
of boxes using infiltration or source control methods where
Build out layers to reduce 45°
run-off that enters the tank during a design storm and the
pressure on lower layer evapotranspiration can reduce the volume of run-off.
volume of water that is allowed to flow out in the same
Figure 19 • Attenuation storage - used to reduce the peak period (which is governed by the discharge rate allowed
discharge rate from a site (i.e. how fast water flows by the regulators). In this way Polystorm can be used to
off the site) and is used to store excess water where limit the peak rate of run-off from a site (usually to the
the rate of discharge is limited to greenfield run-off greenfield run-off rate). The calculations are completed
Maximum rates (or other agreed rate). It is designed to operate
allowable for a range of return periods and durations.
depth for a range of annual probabilities (typically 1 in
Maximum
allowable
depth
Soil backfill
= –
Figure 21
40 41
Design protocol 4.7
0.2 335 500 665 discharge criteria for the different storage volumes.
This factor is allowed for in the design table. 1475mm² car park and other areas surround material
100mm bed
Therefore the total impermeable area = 2675m²
Figure 24
42 43
Typical Silt Trap
Design protocol 4.8
• The test hole should be typically 0.3m-1m wide and 1m-3m long
(make a record of the test hole dimensions)
1-3m
1.5m 1.0m
Approx Figure 26
1.0m
1.125m 100%
75%
1.5-2.5m
25% 0.375m
Maximum
Figure 25
• Contact the Polypipe WMS technical support team and advise them of the
1.5-2.5m
dimensions of the test hole and lowest timed result (in minutes) Maximum
• Polypipe WMS will take this data and estimate the soakaway size required
44 45
Design protocol 4.8
10) allows a storage volume equal to the area to be drained multiplied by 10mm 8 6.08 14.4 8.0 12.16 16.0 16.0 24.32 19.2 32.0
for areas up to 25m². Beyond this size, design should be carried out in accordance 10 7.60 17.6 10.0 15.20 19.2 20.0 30.40 22.4 40.0
with BS EN 752-4 : 1998 or BRE Digest 365. BS EN 752-4 : 1998 suggests a storage
100 76.00 161.6 100.0 152.00 163.2 200.0 304.00 166.4 400.0
volume equal to 20mm multiplied by the area to be drained.
Table 15
1 0.19 (2)
19.0
Concrete Ring conversion
2 0.38 (2)
25.0
Depth of
3 0.57 28.5 (3) 900 1050 1200 1300 1500 1800
soakaway
4 0.76 (3)
38.0 0.25 1 2 2 2 3 4
5 0.95 (3)
47.5 0.50 2 3 4 4 5 7
6 1.14 (3)
57.0 0.75 3 4 5 6 8 11
Table 13 1.00 4 5 7 8 10 14
(1) When doubt exists over suitability of ground for infiltration permeability 1.25 5 6 8 10 12 17
(2) In accordance with Approved Document H3 (refer to 1.1 page 10). 1.75 7 9 11 14 17 24
2.00 7 10 13 16 20 27
(3) In accordance with BS EN 752-4 : 1998, Clause NG 2.4.
2.25 8 10 13 16 20 29
2.50 8 11 14 18 22 31
When the BRE or CIRIA approach is used, the design volumes and areas for
trench or cuboid type installations can be found from Tables 14 and 15. 2.75 9 12 16 20 24 34
3.00 11 14 18 21 28 41
Volumetric data per linear metre for one cell (0.5m) wide Table 16
trench configuration
Number of Storage volume Side areas Base area
cells high (m3) (m2) (m2)
Table 14
46 47
Design protocol 4.9
150mm Ø Ridgidrain
Ridgidrain Ridgidrain
pipe pipe
Figure 27
Example of offline solution
Seating
Rings Concrete
Pre-cast Concrete
94.20m Surround
Cover Slab
Geosynthetic
Vent encapsulating
pipe Polystorm Cells Polystorm Cells
Catchpit 1200
Concrete
Chamber surround
Nom.
300
Pipe bed Headwall
400
& surround Min 100
800
Ridgidrain
Typically Ridgidrain inlet Polystorm cell Either: discharge pipe
900 Sump Coarse sand
Class 6H selected
granular material
Base plate welded Pre-installed
(100% passing 5mm sieve) Ridgidrain pipe
base of chamber wall Vortex Unit
Polystorm cells
Pre-fabricated Polypipe
Stormcheck Chamber
Figure 28
Ridgidrain 45° bend
Please visit www.polypipewms.co.uk for downloadable Auto CAD files of all Polystorm Structures and manifold details.
48 49
Installation 5.0
5.0 Installation -
for attenuation and soakaway systems
Installation
Contents
Page
Connections 5.2 56 - 57
Ventilation 5.3 58 - 60
Maintenance 5.5 63
The following section outlines site best practice for the installation of
50 51
Installation 5.1
• Provide pre-construction information to designers the installed Polystorm cells. Ensure that the ground bearing capacity at the
• Place packs of cells on level ground: DO NOT stack
and contractors formation level is sufficient for the proposed operational loads. The base of
filled pallets on-site
the excavation should be smooth and level, free of large or sharp stones and soft
Designers
• Store loose individual cells NO MORE THAN 5 cells high
spots to avoid punctures or tears of the geomembrane. Any soft spots should be
• Eliminate hazards and reduce risks during design
• Ensure a well positioned and secure stand for platform excavated and replaced with suitable compacted granular material. Place and
• Provide information about remaining risks issued to remove the top layer of Polystorm cells from compact a minimum 100mm thick layer of bedding material (typically coarse sand).
the pallet If required, line the base and sides of the excavation with a protective geotextile
Contractors
• Although Polystorm cells contain an inhibitor giving before placement of the impermeable geomembrane. Excavation should be carried
• Plan, manage and monitor own work and that
ultra violet resistance for up to 6 months, avoid out in accordance with BS6031, paying particular attention to safety procedures.
of workers
prolonged storage in direct sunlight
• Check competence of all their appointees and workers 5.1.6 Handling and installation
• DO NOT store cells near fuel bowsers, fuel tanks or
• Train own employees
any other solvents All materials used should be checked before and after installation for any damage
• Provide information to their workers • Although Polystorm cells are very robust and resistant
such as punctures or tears to the membrane. The type of geosynthetic material
used to encapsulate the Polystorm cells will determine the installation requirements.
• Comply with the specific requirements in Part 4 of to damage when handled normally, store in locations
the Regulations Please note the following information is generic and advice from the geosynthetic
where impacts from vehicles and site plant will
manufacturer should be sought to ensure that the appropriate protective measures
• Ensure there are adequate welfare facilities for workers be avoided
are taken to comply with any proprietary requirements.
It should be noted that additional legal duties are imposed • Ensure Polystorm cells are kept clean at all times
where construction work is notifiable. • Broken/cracked cells should not be installed. Broken/
Impermeable geomembrane
All installation activities should be carried out observing cracked cells should be recycled wherever possible
Physical properties
the requirements of The Health and Safety at Work Etc. • Individual Polystorm Lite cells weigh 7kg and
Thickness Min 0.75 to 1.0mm ASTM D5199
Act 1974; and The Management of Health and Safety at Polystorm 9kg so they can normally be safely lifted
Work Regulations 1999. on-site in accordance with current manual handling Density 900kg/m3 ASTM D1505
because the system avoids or reduces several risks associated • Care must be taken when placing the cells into
Puncture resistance Min 170N ASTM D4833
with the construction of traditional storage tanks which can the excavation
Tear resistance Min 67N ASTM D1004 Die C
involve deep excavations and construction of large • Install 1st layer of cells to minimise walking on the
Impact resistance Min 15 Joules ASTM 3998 mod
engineered structures. Specific advantages of Polystorm geomembrane textile
Stress crack resistance Min 200 hrs ASTM D5391 (SP=-NCTL)
in this respect are:
Permeability coefficient Max 2.0 x 10-12 ASTM D
• Individual Polystorm components are lightweight
- making it easier for individual lifting of Polystorm cells pH Resistant to all naturally occurring soil acids and alkalis
• Installation of Polystorm is quick - so open excavation Resistance to all substances found to naturally occur in soils and
Chemical/biological
time is minimised and high numbers of manpower rainwater. Detailed information would need to be provided to
resistance
geomembrane manufacturer in instances of contaminated land.
52 and machinery is reduced 53
Table 17
Installation 5.1
with additional geomembrane material and weld over damaged area. Ensure the
34
damaged area is overlapped by a minimum of 400mm.
150 Joint each sheet of
geomembrane together according to the suppliers’ recommendations.
Polystorm
30 Shear Connector
Figure 31
5.1.7 Polystorm cell installation
Before proceeding with the installation please ensure you carefully read and
Polystorm Clip understand the Good Practise Guidelines stated earlier in the document.
Shear Connector Polystorm
Ensure cells are arranged so that they are Connector
in the correct alignment with the
400
Vertical connections are formed adjoining pipework. Wherever possible, minimise the amount of walking on the
with the Polypipe shear connector. geomembrane to reduce the chances of punctures or tears to the material by
Figure 34
laying the first layer of cells.
1000
Figure 32
400
500
Polystorm cells are adjacently connected by clipping the two units together.
Clip
For connecting Polystorm
cells together modular cell
horizontally
Shear connector
For connecting
Polystorm Cell cells together
Polystorm Shear Connector
vertically
(see elevation) Plan
Figure 33
Elevation End
Pipe location
DIMENSION GRID connection
54 55
Installation 5.2
5.2 Connections
5.2.1 Types of connections 160mm – 300mm (direct to cells) 5.2.2 Types of connections 450mm – 600mm (direct to cells)
160mm EN 1401-1 pipes connect directly into the convenient knock-out incorporated in the end of each cell.
Polystorm cell with fabricated Polystorm stucture formed Polystorm cell with fabricated Polystorm stucture formed
Connection to 110mm EN 1401-1 pipes or other products is accommodated through the use of standard Polypipe adapters. 300mm Ø pipe connection from standard cells 300mm Ø pipe connection from standard cells
Polystorm cells are also available with either a 225mm or 300mm fabricated Ridgidrain pipe connection.
500 450 ID
Polypipe catchpit
END VIEW Typical Polystorm 450mm Ø Manifold detail
chamber
Figure 41 Typical Polystorm 450mm inlet manifold detail
Figure 36 Figure 37 Figure 38 450 ID
160/110mm invert level reducer 160mm diameter adaptor Polystorm cell 160mm diameter knockout Figure 42
Typical Polystorm 450mm
Typical Polystorm 450mm inlet
Ø Manifold manifold detail
detail
225mm Ø
coupler 300mm Ø Ridgidrain
flanged adaptor
300mm Ø 300mm Ø 400/300mm Ø Ridgidrain
Ridgidrain Ridgidrain invert level reducer
400 pipe pipe
400mm Ø Ridgidrain
45° bend
225mm Ø
coupler
400mm Ø
400mm Ø Ridgidrain pipe
Ridgidrain
ELEVATION
108 pipe
400/300mm Ø
Note: For inlets larger than 600mm
END VIEW Ridgidrain Y-junction
Polymer cell with fabricated 225mm Ø Ridgidrain Polystorm cell with fabricated Polystorm structure
300mm Ø 225mm Ø pipe connection flanged adaptor 300mm Ø pipe connection from standard cells
coupler
400 225mm Ø
Ridgidrain
pipe
300mm Ø 300mm Ø Ridgidrain
225mm Ø Ridgidrain 300mm Ø
300mm Ø Ridgidrain pipe Ridgidrain 300mm Ø flanged adaptor
Ridgidrain
coupler 45° bend pipe
pipe
225mm Ø 450/300mm Ø
500 Ridgidrain pipe Ridgidrain
ELEVATION invert level 300mm Ø
reducer Ridgidrain
118 400/225mm Ø
22.5°bend
END VIEW Ridgidrain invert 300mm Ø
level reducer 45° Ridgidrain pipe
400/300mm Ø Ridgidrain
Figure 40 Fabricated Polystorm cell allowing 300mm diameter pipe connection 400/300mm Ø
300mm Ø
invert level reducer
Ridgidrain
Ridgidrain 2 x Y-Junction
400 Ø Ridgidrain
Y-junction
450mm Ø 45° bend
Ridgidrain
400mm Ø pipe
Ridgidrain pipe
400/300mm Ø Ridgidrain
22.5°
45° Y-junction
Polypipe catchpit
chamber
600 ID
5.3 Ventilation
Every attenuation tank requires at least one vent to avoid stagnant water. An infiltration 5.3.2 Inlet and outlet connections and installations
A flange adapter is attached at both the inlet and outlet points as this gives a
tank does not need a vent. Large attenuation tanks need a vent for every 7500m2 of flat surface for the membrane to be attached to. The flange adaptor will require
a hole punching in each corner of the base. Ensure the flange adaptor is fastened
drained catchment area. The illustrations below show a vertical vent pipe with a cowl
securely to the cell using cable ties. Once the adaptor has been secured, insert
(SCV40) and a horizontal vent pipe that connects to a catchpit. the pipe and seal connection.
F.G.L. Cover & frame Seating Rings Pre-Cast concrete cover slab maintained throughout the process. For advice on procedures for testing joints
refer to CIRIA SP 124 – barriers, liners and cover systems for containment and
control of land contamination.
150mm Ø Ridgidrain Ridgidrain 150mm/160mm EN 1401-1 Adaptor Geosynthetic encapsulating
ventilation pipe (Product code: ARD150160) Polystorm Cells
225mm Ø Ridgidrain 225mm Ø Ridgidrain Either: Course sand OR 225mm Ø Ridgidrain Pipe bed
discharge pipe flanged adaptor Class 6H selected granular flanged adaptor & surround
material (100% passing 5mm sleeve)
58 59
Installation 5.3/5.4
5.3.8 Lightly trafficked (e.g. restricted access car park) Mechanical properties
CBR puncture resistance Min 1500N EN ISO 12236
Backfill with Class 1 or 2 material in accordance with MCHW, Volume 1, Series
600. Backfill material should be placed and compacted in layers not greater Peak tensile strength Min 8kN/m2 EN ISO 10319
than 150mm. Where the Polystorm cells are installed beneath a paved area, Hydraulic properties
the pavement sub-base may form part of the backfill material provided that Water flow rate normal
Min 100 l/m2 .s (@ 50mm Head) EN ISO 11058
minimum cover depths are maintained. Complete pavement construction or to plane
landscaping over the Polystorm system. Pore size O90 Typically 100 µm EN ISO 12956
After installation and prior to handover, any silt collection chambers or control All joints should be sealed, using proprietary methods recommended by the
manholes should be examined to ensure they are free from debris. All chambers manufacturer. Please refer to CIRIA SP 124 – Barriers, liners and cover systems for
and manholes require the insertion of bungs at the inlet and outlet to prevent containment and control of land contamination, for advice on seam testing
siltation during construction. Bungs should then be removed at commissioning. procedures. Before the cells are installed the geotextile should be laid over the
subgrade level. The sheet of geotextile should be large enough such that it can
overlap over the edge of the modules by 200mm.
60 61
Installation 5.4/5.5
5.4.3 Polystorm cell installation Where required, remaining excavated areas around the 5.5.1 Maintenance
cells should be backfilled with Class 6N or 6P selected
Place the Polystorm cells on the geotextile in accordance with The customer is responsible for maintenance
granular material, in accordance with MCHW, Volume 1,
the construction drawings and Polypipe connection details. For soakaways to individual houses, the only necessary
or similarly approved specification.
Ensure cells are arranged so that they are in the correct maintenance of the system is to keep gullies clear of
alignment with the adjoining pipework (see pages 54 & 55). Above the wrapped Polystorm cells, place and lightly debris such as leaves. For large installations or where the
compact a minimum 100mm thick layer of either coarse receiving waters are environmentally sensitive, a system
5.4.4 Shear connection sand or Class 6H selected granular material (with 100% of regular inspections should be established to prevent
Vertical connections are formed with the Polypipe shear passing the 5mm sieve), in accordance with MCHW, siltation of the system which, if allowed to develop,
connector (see pages 54 & 55). Volume 1, Series 600. would reduce effectiveness. They should also be inspected
Final backfilling of the installation and surfacing after every major storm event.
5.4.5 Clip connectors is dependent on the expected operational loads.
Polypipe clips connect horizontally adjacent cells (NB Compaction plant over and immediately adjacent
(see pages 54 & 55). to the Polystorm cells shall not exceed 2300 kg/m width).
160mm EN 1401-1 pipes connect directly into the pipework at the inlet to the tank (see Figure 47)
The backfill material that lies within 300mm above the
convenient knock-out incorporated in the end of each cell. there must be a maintenance plan that ensures regular
Polystorm cells should be free from particles exceeding
Connection to 110mm EN 1401-1 pipes or other products cleaning of the trap to ensure correct performance.
40mm in diameter, in accordance with Class 8 material
is accommodated through the use of standard Polypipe to Series 600, Volume 1, MCHW. Final backfilling up to
adapters. Polystorm cells are also available with either a Note: To download Auto CAD drawings and BBA certificates
finished ground level may be achieved using selected
225mm or 300mm fabricated Ridgidrain pipe connection please visit www.polypipewms.co.uk.
as-dug material. Backfill material should be placed and
(see pages 56 & 57). compacted in layers no greater than 300mm, or in
compliance with the approved specification.
5.4.7 Encasing geotextile
Complete the geosynthetic encapsulation of the entire 5.4.11 Lightly trafficked (e.g. restricted
Polystorm structure, forming joints where appropriate. access car park)
Re-examine the geomembrane and/or geotextile for Backfill with Class 1 or 2 material in accordance with
damage and joint integrity. MCHW, Volume 1, Series 600. Backfill material should be
Figure 47
placed and compacted in layers not greater than 150mm.
5.4.8 Lateral backfilling Where the Polystorm cells are installed beneath a paved
Backfill around the sides of the encapsulated cells, forming area, the pavement sub-base may form part of the
a 100mm thick layer of coarse sand or Class 6H selected backfill material provided that minimum cover depths
granular material immediately adjacent to the cells. are maintained. Complete pavement construction or
Where required, remaining excavated areas around the landscaping over the Polystorm system.
cells should be backfilled with Class 6N or 6P selected
granular material, in accordance with MCHW, Volume 1, 5.4.12 Inspection
or similarly approved specification. After installation and prior to handover, any silt collection
chambers or control manholes should be examined to
5.4.9 Cover backfilling ensure they are free from debris or contamination.
Backfill around the sides of the encapsulated cells, forming
a 100mm thick layer of coarse sand or Class 6H selected
granular material immediately adjacent to the cells.
62 63
Associated products 6.0
Associated products
Contents
Page
Stormcheck 6.1 66 - 67
Storm-X4 6.2 68 - 71
Fabrications 6.3 72 - 73
64 65
Associated products 6.1
6.1 Stormcheck
One aim of Sustainable Drainage Systems is to mimic Vortex 6.1.2 Chamber types
flow
Non-bypass chamber for sites where discharge rates
greenfield run-off rates from developed sites. One way controller Controlled
must be guaranteed and not exceeded.
outlet
Inlet
of achieving this aim is by stormwater storage and
Bypass 6.1.3 Manual bypass design
pipe
attenuation. The Stormcheck chamber allows precise Bypass flap Offers a bypass to the flow control device which is
manually operated from the surface. The activation of
control of site discharge rates and when combined with
Figure 48 Manual bypass design the bypass system opens a door in the head wall
our storage systems provides an industry recognised allowing water in the chamber to drain down via the
bypass pipe.
flow attenuation system.
6.1.4 Auto bypass design
Stormcheck chambers with automatic bypass systems
6.1.1 Stormcheck vortex flow control chamber
are also available, please contact the Polypipe WMS
The Stormcheck vortex flow control chamber comprises of a pre-fabricated plastic
Head wall Technical support team.
chamber, in a range of diameters, with integral vortex flow control device.
Vortex
Inlet
6.1.5 Key benefits
flow
controller A complete system will include the following items:
66 67
Associated products 6.2
The use of the Storm-X4 advanced four stage filtration system can dramatically improve 6.2.1 Function principles 1.
1. Contaminated surface water run-off is fed into the basal section of the filter.
the quality of the surface water entering the receiving water course, improving The angled inlet generates a radial flow pattern.
biodiversity and aiding with compliance of the Water Framework Directive. 2. The hydrodynamic separator converts the radial flow to generate particle
sedimentation to remove heavy debris and silt from the contaminated water.
The sediment is then retained in a silt trap chamber below the separator for 2.
easy maintenance and access.
4. Situated above the filter element is an oil retention unit which removes the
remaining contaminants from the surface water run-off. The clean water then
flows via the outlet to the soakaway or watercourse.
68 69
Associated products 6.2
Nutrients
6.2.5 Low maintenance 6.2.8 Storm-X4 1000 heavy traffic NH4 (mg/L) 0.5 2.3 – 0.5 – 0.3
The advanced four stage filtration system within • Surface water filter complying with DIN 1989-2 Type A NO3 (mg/L) 0.0 16.0 – 50.0 – –
Storm-X4 utilises no moving parts, providing a low • For drained traffic areas to 500m²
Heavy metals
maintenance solution for all surface water run-off • Connections: at DN150 or DN200
applications. The filters within the unit only need to be • 4 Filter Elements: Cd (µg/L) 0.3 13.0 1.0 5.0 5.0 <1.0
replaced on average every two years, providing an easily Material, Filter, Substrate, Heavy Traffic
Zn (µg/L) 120 2.000 500 – 500 <500
maintainable solution on-site. Weight per element: 32kg
Cu (µg/L) 97 104 20 2000 50 d
<50
6.2.6 Easy to install 6.2.9 Storm-X4 1000 roof d
Pb (µg/L) 11 525 50 10 25 <25
Polypipe WMS can supply Storm-X4 as a standalone unit, • Surface water filter complying with DIN 1989-2 Type A
or housed within a bespoke plastic chamber. When • For drained roof areas to 1000m 2 Ni (µg/L) 4 70 50 20 50 <20
housed within a chamber, the units are constructed • Connections: at DN150 or DN200 Cr (µg/L) 6 50 50 50 50 <20
off-site and delivered to site ready to install, making • 4 Filter Elements:
installation quicker, safer and easier with a much lower Organic substances
Material, Filter, Substrate, Roof
development footprint. Weight per element: 16kg PAH (EPA) (µg/L) 0.2 17.1 – 0.1 (6 Subst.) 0.2 <0.2
Table 19
70 71
Associated products 6.3
6.3 Fabrications
Polypipe WMS is in the unique position of being able to offer its customers
bespoke fabrications from its highly skilled in-house Fabrications team.
Due to the variety of solutions available from Polypipe WMS, the fabrications
department has become an integral part of the company. Whether you need a
bend with a specialist angle or a complex chamber. Polypipe WMS are able to
design and manufacture products to exact customer specifications. As well as
delivering the products to site as a complete unit, ready for installation.
72 73
Project solutions 7.0
Project solutions
Contents
Page
74 75
Project solutions 7.1/7.2
12 months of one another on adjoining sites in Lytham St. Annes - a BMW garage
The project, at the New Central Heywood Primary School was part of a
development to accommodate the integration of three local schools into one
site. Over 1100 Polystorm Lite cells, along with the Stormcheck Vortex Flow
Control Chamber were installed on the site to provide an integrated, robust and
durable attenuation tank system. Once locked together, the cell structure was
Working closely alongside contractor James West Ltd and consultant Atkinson wrapped in a geotextile membrane to prevent silt migration. With a capacity of
Peck, who specified the drainage on-site, Polypipe WMS supplied several cubic 350,000 litres and with a discharge rate set to ten litres per second, the
metres of Polystorm cells to provide an attenuation unit for absorbing vast Polystorm Lite cells were selected to provide the most effective SUDS solution
quantities of rainwater. The Polystorm cells were also installed on the area for the long-term future of the development.
surrounding the new car storage point, as this provided easy access to the large
outfall drain and would further reduce the possibility of water logging on-site.
200 metres of Polysewer and 4000 metres of general purpose duct were also
supplied alongside 400 metres of 150mm and 375 metres of Ridgidrain pipe.
76 77
Project solutions 7.3
Over 14,000 cells of Polystorm Lite and Polystorm were installed on the Knight A bespoke hybrid drainage system for the RAF Northolt Ministry of Defence site in
Build site as part of a bespoke hybrid SUDS attenuation solution. Cambridgeshire, utilising both its Polystorm Lite and Polystorm modular cell solutions.
The site, a former private school which has been developed into apartments,
consisted of various constraints meaning that the cells needed to be installed on
a slope. The solution was a hybrid modular system containing both Polystorm Lite
and Polystorm cells which accommodated the differing burial depths resulting in
2,700m³ of capacity.
Over 1800 metres of Ridgidrain pipes were supplied to facilitate the transportation
of drainage water to and from the tank structure. Whilst Polystorm Lite, Polystorm
and Ridgidrain can all be used effectively as standalone solutions, it was the ability
of the products to be integrated together which offered Knight Build the most
viable solution.
Approximately 3000 Polystorm Lite and Polystorm cells have been installed
on-site to provide an attenuation solution to cope with surface water run-off
from both hard standing and roof areas. The original project specification was
changed from a concrete box culvert due to issues with rising material costs
and concerns over the performance of the product in times of high-flow water
run-off. However, a solution was needed that was capable of storing the
required water capacity whilst accommodating difficult site constraints.
The modular construction of Polystorm Lite and Polystorm allows the cells to
be connected together to form almost any shape and storage capacity.
78 79
The company 8.0
80 81
The company 8.1
employs over 300 people, with 35 production lines producing over 20 different
product ranges consisting in excess of 1600 individual line items. With investment
levels of £11m in 2006/07 Polypipe Civils prides itself in having the most extensive
years to further enhance its market leading position. service levels and shorter lead times to its customers, Polypipe has made a further
commitment to extend its production capacity. This includes a 12,000 sq.ft.
extension to the Horncastle production line with 4 new injection lines and a fully
automated 6 axis robot system.
82 83
The company 8.2
84 85
The company 8.3
The Health and Safety of employees is an integral part of Polypipe’s business activities.
• We properly investigate environmental incidents re-use
Health and Safety is a responsibility and statutory duty that each and every
employee and visitor to our sites must share. To enable this, it is our intent that
• We monitor and review performance using appropriate measures recycle
and methods
responsibility for Health and Safety be accepted and effectively carried out at
all levels within our organisation. • We optimise the use of water and utilities
• There are good working relationships with regulatory authorities,
All Polypipe companies shall, as far as possible, ensure that: neighbours, customers, suppliers and stakeholders on Environmental matters,
• We provide a safe working environment for our employees, where hazard energy management and Conservation Policy
and risk are effectively assessed and eliminated or adequately controlled
• We use suitable and sufficient controls to ensure that non-employees who may be
affected by our activities are not exposed to risks to their Health and Safety
• We meet or exceed all current legislation and regulation relating to Health and Safety
• We monitor and review Health and Safety performance using appropriate measures
and methods
86 87
The company 8.4
88 89
The company 8.5
YES YES
A range of specific product literature is also available from Polypipe WMS each
Selection and
use stormwater stormwater
YES attenuation
attenuation
design
The Polypipe WMS website provides an overview, key benefits and a technical Design
rainfall data ground water
catchment area level an issue?
DETERMINE:
with further details and support information. The literature is also available on
rainfall data
NO catchment area
contractor with more detail and guidance when specifying. CAD downloads Is an overflow
discharge
solution
YES
design
BBA Certificates
calculate storage
required soakaway to:
volume required
BRE Digest 365
or
are available in both PDF and DWG format plus specification clauses,
CIRA report 156
NO
is compliance
with Sewers for
Adoption
ECO-VAT POLYSTORM required?
POLYSTORM XTRA
assessment forms and BBA certificates. Legislative guidance from the Water
POLYSTORM LITE
RIDGIDRAIN YES NO
Design Manuals from CIRIA, the BRE and much more. With FAQ’s on CAD Drawings
01509 217671 or visit www.polypipewms.co.uk and click into choice of product,
Rainstream, Ridgistorm-XL and an ‘Ask the Experts’ section, the website is
then ‘Request brochure’ which takes you to a simple request form. Complete the
a comprehensive and essential source of water management information.
form before you submit your brochure request then click onto the ‘Submit
Calculation Tools Request’ panel.
Polypipe Civils with an overview of proven case studies and market sectors.
Address:
Post Code:
Tel:
Fax:
Email:
Project Details:
Client::
(If different to section 1)
SECTION 2
Project Title:
Project Address:
(If different to section 1)
Type of Project: Private Housing / Social Housing / CIR / Agricultural / Educational / Leisure
(Circle as appropriate)
Construction Stage: Design / Tender / Order to Place
(Circle as appropriate)
Assessment Details:
POLYPIPE BUILDING PRODUCTS LTD SAFETY DATA SHEET
Do June
you2002
require a full
Considerations
Silicone Lubricant SG300 is for
made Use
up fromof
an Recycled Rainwater
aerosol of silicone oil suspended in aliphatic hydrocarbons
WC’s: Yes/No Washing Machines: Yes/No External Use*: Yes/No
Hazardous Component Cas No# Concentration
Number of Washing Estimated hours per
Number of WC’s
Butane 106-97-8 5 –10%
Propane 74-98-6 Machines 5 – 10% week
FlushHydrocarbons
Aliphatic Volume N/A Capacity >20% Vehicle Wash Down Yes/No
Urinals*: Yes/No Monthly usage (Commercial)*
Specification Clauses
3. HAZARDS IDENTIFICATION
Number of Urinals Personal Hygiene Yes/No Duty standby pump Yes/No
Classified as flammable under the CHIP regulations.
Eye contact: Irrigate with clean water. If irritation persists, seek medical advice
Skin contact: Wash thoroughly with soap and water.
Ingestion: If accidentally swallowed, obtain immediate medical attention. Keep at rest. Do not induce vomiting.
Inhalation : Remove to fresh air, if symptoms persist, seek medical advice
Extinguishing Media : Use water spray/mist, CO2, foam or dry powder. Do not use water jet.
Protective Equipment : Standard protective equipment. Use self-contained breathing apparatus.
Fire/explosion hazards : Fire will produce dense black smoke containing combustion products which may be a health hazard. Run
off from fire must not be allowed to enter drains. Spray containers with water to reduce risk of rupture/explosion. Contents of
aerosol will add to fuelling of fire
Legislative Guidance
Bespoke Fabrications Polypipe Civils Product Water Management
Brochure and System Selector Solutions Product and
System Selector
FAQ’s
All descriptions and illustrations in this publication are intended for guidance only and shall not constitute a ‘sale by description’. All dimensions given are
nominal and Polypipe may modify and change the information, products and specifications from time to time for a variety of reasons, without prior notice.
The information in this Technical Guide is provided ‘as is’ on May 2011. Updates will not be issued automatically. This information is not intended to have any
legal effect, whether by way of advice, representation or warranty (express or implied). We accept no liability whatsoever (to the extent permitted by law) if
you place any reliance on this Technical Guide and you must do so at your own risk. All rights reserved. Copyright in this publication belongs to Polypipe and
all such copyright may not be used, sold, copied or reproduced in whole or part in any manner in any media to any person without prior consent. is
a registered trademark of Polypipe. All Polypipe products are protected by Design Right under CDPA 1988. Copyright © 2011 Polypipe. All rights reserved.
90 91
WMS
Polypipe Civils
North Road
Loughborough
www.polypipewms.co.uk
FSC logo
and statement
www.polypipe.com
www.polypipe.com
Polystorm installations account for dynamic loads by applying a partial factor of safety to the estimated characteristic load, which helps allow for unforeseen variations of loading and the severity of limit states occurring . Specifically, a dynamic factor is applied as loads from traffic, such as from car wheels turning, can exert additional force during motion . A typical design load is obtained by applying these partial factors, which for ultimate limit states may include factors of 1.4 for dead loads and 1.6 for imposed live loads .
To minimize damage during construction, Polystorm cells are installed with considerations such as using a minimum cover of 0.5m to protect from construction loads . The backfill materials are carefully selected and compacted in layers to meet specific requirements, ensuring that the structure remains intact and functions properly . Moreover, the cells are lightweight, reducing risks during handling and installation .
The Polystorm units were selected for specific construction projects due to their robustness and resistance to environmental contaminants found in soil and rainwater, which makes them suitable for long-term use . Their lightweight yet strong nature reduces on-site plant requirements and therefore minimizes health and safety risks during handling and installation . Additionally, the modular and versatile nature of Polystorm allows for customizable storage capacity and integration into various site layouts, accommodating unique site constraints .
Polystorm's long-term performance under significant load variance is facilitated by its design, which incorporates substantial safety factors and the ability to withstand varying loads such as those imposed by heavy traffic . The units are designed with a compressive strength that exceeds typical traffic-induced pressures, ensuring that they remain stable over time . Additionally, low deflection rates under repeated loads imply that Polystorm can maintain performance standards, making it suitable for high-load areas such as under roadways or parking lots .
Polystorm's structural capacity is positively influenced by its material properties, namely its polypropylene composition which is highly resistant to environmental contaminants commonly found in soil and rainwater . This ensures durability and integrity even with variations in environmental conditions. The design accounts for temperature stability, anticipating negligible thermal expansion due to the modest ground temperature range, maintaining performance without special considerations for thermal variation . Overall, these properties allow Polystorm units to reliably handle both expected and unforeseen environmental stresses .
The British Standard BS 8110 influences the design of Polystorm systems by providing guidelines for partial safety factors applicable to load management in plastic storage systems, ensuring that they meet reliability standards similar to those applied to rigid materials like concrete . This ensures Polystorm systems are appropriately designed to handle both static and dynamic loads, with partial factors making allowances for unforeseen load variations and consequences, thereby maintaining structural integrity under various conditions .
The integration of Stormcheck flow control chambers into sustainable drainage systems enhances SUDS by enabling precise control over site discharge rates, ensuring that they mimic natural, unchecked runoff conditions . This is achieved through the vortex flow control device, which regulates water flow to prevent overwhelming drainage systems during heavy rainfall, thereby reducing the risk of flooding. When used alongside Polystorm storage systems, it creates a comprehensive and effective mechanism for managing stormwater, catering to sustainability objectives by decreasing site-specific flooding risks .
Key environmental resistance features of Polystorm units include their resilience to all soil and rainwater contaminants naturally occurring in temperate climates, like in the UK . This resistance ensures that the units maintain their structural integrity over time despite being exposed to such conditions, making them suitable for long-term applications in diverse environmental settings without specific damage testing being necessary .
Load management in Polystorm systems is particularly adapted by applying partial safety factors that take into account both static and dynamic scenarios . Unlike traditional concrete, Polystorm's design adapts more readily to soil and load-induced stress variations owing to its lightweight and modular structure. Concrete, being rigid, typically requires higher safety factors to avoid cracking under dynamic loads. Nevertheless, both systems use similar methodological approaches grounded in BS 8110 standards to ensure each material's suitability for the intended application within their own distinctive design constraints .
The modularity of Polystorm systems allows for considerable flexibility, enabling the creation of storage solutions that accommodate different shapes and storage capacities required by variable site constraints . This is particularly beneficial in urban settings where space is limited or needs to be efficiently utilized. The systems can be interlocked to form custom arrangements, offering efficient water management solutions for both surface runoff and roof drainage .