Case Study Rating Curves
Case Study Rating Curves
Volta-HYCOS PROJECT
The rating curve of the Senegal River at Gouina-upstream station is of a single value
stage/discharge relationship type, steady and without any anomaly. The station is located
upstream of a fall of about 10 meters, and therefore has a very efficient downstream control
section.
Numerous flow measurements have been carried out for mean water levels, for which the
water surface slope has been measured. The rating curve is well defined for mean water
levels, but the extension from a flow of 2 500 m3.s-1 to 7 000 m3.s-1 is quite difficult.
2.1 The first staff gauge was installed in 1925 by UHEA Company in charge of the hydro-
power dam project at the level of Gouina falls (height about 10 meters). The catchment area is
of 128 600 km².
2.2 Six different sections for the staff gauges have been used from 1925 to 1979 to monitor
the water levels of the river.
The cross section of the upstream station, for which the rating curve is studied in this
example, is of a quite complex shape (see fig. A2.3) with a double central canal, a maximum
depth of more than 20 meters for high water levels and a channel width of about 300 meters.
The river bed is rocky and perfectly steady.
2.3 The cross section levelling carried out by the UHEA Company was in 4th June 1951 and
allowed the definition, with a good accuracy, of the relationships W(h) (Wetted Area) and
R(h) (Hydraulique radius), h being the water level at the upstream water level recorder. Table
A2.1 shows the list of the 27 levelling points and all the geometric parameters of the cross
section.
Figure A2.6 shows the shape of the W(h) & R(h) curves. To facilitate the extension
calculations these two curves are given by the formula below:
Remark: We have drawn on figures A2.4 & A2.5 the variations in wetted area and in
hydraulic radius with the water level for the whole section. As the W curve is very regular, it
is very different for the R curve.
2.4 The gauging section for the mean and high water levels is located 1 040 m upstream and
at about 3 km upstream of the falls. The cross section profile is more regular and the section is
wider at the gauging section(see fig. A2. 3).
- Staff gauge N°1 installed in 1925 just upstream of the falls and made of a leaning rail
graduated from 0 to 5 meters;
- Staff gauge N°2 equipped the first reach at the foot of the falls. It is a vertical rail of 8
meters, fixed on a concrete pile against the rocky bank of the river;
- Staff gauge N°3 is located at the beginning of the second reach downstream the falls it
is also a vertical rail of 8 meters;
- Staff gauge N°3 equipped the third reach. It is located 900 meters downstream the
previous one in the area planed by UHEA for the tail water of the hydropower plan of
Gouina. It is a vertical rail of 9 meters.
3.2 UHEA has completed this equipment with two water level recorders in 1950:
- The first installation is called Gouina-upstream (Bär trade mark, mensual type) and is
located 2 km upstream of the falls. Its gauge Zero level is at an altitude of 63.35 meters MEFS
(Mission d’Etudes du Fleuve Senegal);
- The other installation is called Gouina-downstream (same trade mark) and is located on the
right bank at about 400 meters downstream of the staff gauge N°4. Its gauge Zero level is at
an altitude of 48.09 meters MEFS.
3.3 From 1953 the MAS (Mission d’Aménagement du Senegal) neglected the four staff
gauges of UHEA but monitored the two water level recorders and added to them auxiliary
staff gauges.
3.4 This historical summary of the Gouina station historical gives an idea of the work that has
been done to ensure a homogeneous water level time series: with six different sections the
problem must be complex.
The correspondence graphs, built in plotting the water levels at the staff gauges N°1, N°2,
N°4, against the water levels at the staff gauge N°3, show a high scattering of the results
which gave evidence of the wrong readings. As the readings have also a lot of gaps it has not
be possible to use them. So, despite the very nice and useful installations from a building
point of view as two staff gauges are always in a very good condition today, the readings
between 1925 and 1950 are useless.
This situation is due to the lack of staff gauges maintenance which were either badly
graduated or unreadable and to the fact that the gauge readers were inefficient. Nevertheless,
we have kept the maximum water levels data observed during this period. For Gouina-
4.2 From June 1950 to October 1952, UHEA took advantage of the whole set of staff gauges
of the 1st, 2nd and 3rd reaches and of both the upstream and downstream water level recorders.
The only missing information was the record of the peak flood in 1950.
4.3 From 1953 to 1956 the staff gauges at Gouina station were no more observed and the
monitoring of the water levels is hazardous. Despite this situation, we have corrected the
records and filled the gaps for the missing or bad data.
4.4 Data are then completed from 1953 to 1955. For 1954 two months of data are missing
(September and October). Since 1956 we have completed and accurate readings for the 2nd
reach staff gauges, installed by the M.A.S. After two years of good monitoring (1956 &
1957), the water level recorders were no more monitored.
4.5 During the period for which records are available in the ORSTOM files, i.e. from June1st
1955 to December 31st 1979, the maximum water levels recorded at Gouina-upstream are:
- 692 cm on the 24/08/1958 for the maximum (978 cm at the 2nd reach staff gauge)
- 626 cm on the 04/06/1964
- 613 cm on the 23/08/1964
- The minimum water level of 25 cm occurred in 1976 (no date).
For the gauging in mean and high water levels, the water surface profiles were levelled each
time with respect to the benchmark N°11 (alt. 70.84 m MEFS); So, are known the difference
in level between the gauging point and the recorder sections (distance 1 040 m). For the low
water levels, gaugings were carried out at Dipari village (6 km upstream of Galougo). A
control measurement has been carried out at this section by ORSTOM in 1965.
5.2 The 61 gaugings carried out by UHEA ware undertaken between October 1950 and June
1952. The ORSTOM gauging carried out in February 1965 is of a high importance as it is the
single one during the period of records. It is a chance that the calibration is steady and that the
upstream and downstream staff gauges relationship is well known.
On the other hand, the two gauging carried out on 3rd & 4th of October 1951 are not usable
due to cable breaking over the cross section. Despite this, the two gauging are very important
as the water surface slope was measured.
The results of the discharge measurements are very good and gave an excellent rating curve
between the stage 0.65 and 4.20 m (6 to 2 300 m3.s-1). The curve is very regular (Fig. A2. 7),
The single value stage/discharge relationship type at this station is confirmed by the graph as
it was expected due to the location upstream of the falls.
The mean deviation between the measured discharges and the calculated one is of 3.3% for
the 60 gaugings carried out by UHEA & IRD and 2.3 % for the gauging out of the stage 1.50
m. This shows the excellent quality of the gauging carried out by UHEA.
If the water level range were just a little bit more than the maximum gauging the extension of
the rating curve of Gouina upstream would be easy, but the curve has to be extrapolated to the
level 6.92 m (i.e. an additional 2.70 m).
A gauging carried out by a Russian team in 1965 doesn’t appear in the list, as it was known
only after this study. So, the value was not used in establishing the rating curve but for
validation.
Taking into account the three usual methods for rating curve extension, it will be useful to
check the limits of use for each one and to make his own judgment if the constraints are
respected or not.
The use constraints are the same as for the previous method and, as for this one the gauging
are not enough to well define the curve of discharges. Figure A2.9 shows this deficiency
better than in the figure A2.8, maybe due to logarithmic coordinates? The extension of the
discharge curve may or may not give good results :
- The extension has to be made according to the line (1), fitted with the gauging points
between 1 000 & 2 300 m3.s1, the result for the maximum discharge is 6 150 m3.s1 for
the stage 692cm;
- The Stevens method doesn’t allow the extension following the curve (2) which brings
to the result of the log. Method;
Even if the wetted area is fully defined till the maximum level, the extension of the
relationship U(h) (U = mean velocity) is not possible (see fig; A2.10). So, it is necessary to
use the Strickler’s formula, accordingly we known the value of the surface water slope for all
complete gauging and also for the two incomplete one carried out for stages 489 & 557 cm.
The two parameters that we have to calculate are the roughness coefficient (K) and the water
surface slope. Figure A2.11 shows the distribution of the K coefficient for all the gauging. We
have retained the value of K + 19 which correspond to the two maximum gauging stages. It
will be possible also to select the value K = 1_ which correspond to the median value, but it
seems that K is not yet stabilized for the stage 420 cm.
On figure A2. 12 the relationship J(h) is represented, the two values of the water surface slope
measured for the stages 489 & 557 are of a high interest to guide the extension of the curve to
the stage 692 cm. The extension is made quasi-linear as we don’t have any more information.
The extension consists in the estimation of the K value and the drawing of the J(h) curve to
the 692 range.
With K = 19 and the value of the surface water slope read on the figure A2. 12, we have to
calculate the discharges for the maximum stages by using the Strickler formula:
Remark: The shape of the U(h) & KJ1/2 curves (fig. A2.10 & A2.13) are a little bit strange, in
fact, this is regular as the K value is not yet stabilized and the value of J increased more
slowly.
This also shows the importance of carrying out levelling on each station as well as cross
section and longitudinal profiles.
Stage Wetted Area Wetted perimeter Width Hydraulic radius Mean depth
CM M² M M M Mm
0 1261.09 232.51 226.99 5.42 5.56
25 1318.12 234.73 229.15 5.62 5.75
50 1375.66 236.81 231.17 5.81 5.95
75 1433.7 238.99 233.19 6.00 6.15
100 1492.25 240.97 235.21 6.19 6.34
125 1551.29 242.82 236.98 6.39 6.55
150 1610.72 244.37 238.42 6.59 6.76
175 1670.50 245.91 239.86 6.79 6.97
200 1730.62 247.19 241.03 7.00 7.18
225 1791.02 248.48 242.20 7.21 7.40
250 1851.71 249.76 243.37 7.41 7.61
275 1912.70 251.05 244.54 7.62 7.82
300 1973.98 252.33 245.71 7.82 8.03
325 2035.55 253.61 246.88 8.03 8.25
350 2097.42 254.90 248.05 8.23 8.46
375 2159.58 256.17 249.21 8.43 8.67
400 2222.01 257.34 250.26 8.63 8.88
425 2284.71 258.52 251.31 8.84 9.09
450 2347.67 259.69 252.36 9.04 9.30
475 2410.89 260.86 253.42 9.24 9.51
500 2474.38 262.03 254.47 9.44 9.72
525 2538.15 263.53 255.87 9.63 9.92
550 2602.32 265.24 257.21 9.81 10.11
575 2666.90 266.96 259.14 9.99 10.29
600 2731.89 268.67 260.78 10.17 10.48
625 2797.30 270.61 262.65 10.34 10.65
650 2863.29 273.28 265.26 10.48 10.79
675 2930.21 277.95 269.89 10.54 10.86
700 2998.21 281.88 273.80 10.64 10.95
downstream
WLR
Reaches
SIBITOU village
Falls
Staff gauges
WLR upstream G1 G2 G3 G4
Values of limit height HP(L) and intermediates HINT (L) & limit discharges Q(L)
& intermediates QINT (L)
1 0.68 6.500
2 0.85 10.000
1.00 20.000
3 1.15 36.800
1.30 60.500
4 1.50 105.000
1.74 180.000
5 2.10 317.000
2.50 495.000
6 3.20 1010.000
4.20 2320.000
7 5.50 4100.000
6.92 7400.000
Fig-A2-4- Variation of the wetted area Fig-A2-5- Variation of the hydraulic radius
h upstream WLR
h upstream WLR
Logarithmic method
max. level
upstream WLR
_
A VR
log-log value
Q = 9400m3/s
Extension calculated
Q = 7400m3 /s
Regular extension
Q = 6150m3 /s
max.water level
observed
complete gauging
incomplete gauging but slope measured
extension
incomplete gauging
calculated discharge
maximum level
extended part