Unit 2 - TYPES OF ESTIMATE
Unit 2 - TYPES OF ESTIMATE
Plinth area: area bounded by the out wall at plinth level of the building.
5. Technical Sanction:
After the acceptance of the proposal the engineering department prepares the detailed
estimate, design, planning and calculations & costing of various items and is taken to
the competence authorizes of the engineering department for sanctioning called
technical sanction. After technical sanction, tendering process is carried out for the
construction of the project by contracting.
Numerical:
1. Prepare a preliminary estimate of a office building having total
carpet area of 2000 sq.m. for obtaining the administrative
approval of a government using the following data's.
• 40 % of built up area will be taken up by corridors, staircase,
toilet, store etc.
• 10% of built up portion is covered by walls
• The plinth area rate of that locality is Rs. 8000/m2
• Extra architechiral treatment for 7% of building cost
• Extra for w/s & sanitation is 8% respectively
• Service & supervision charge is 5%
• Contingencies 3%
Numerical:
Solution:
Using plinth area estimate:
Let x be the plinth area of building
We know
Plinth area= carpet area + circulation are + wall area
x= 2000m2 + 40% of x + 10% of x
X= 2000+0.4x + 0.1x
0.5x= 2000
X= 2000/ 0.5 = 4000 m2
Cost of building = 4000 m2 * Rs. 8000/m2
= Rs. 3,20,00,000
architechiral treatment @ 7% of building cost = 0.07 * 3,20,00,000
= Rs. 22,40,000
w/s & sanitation @ 8% = 0.08 * 3,20,00,000
= Rs. 25,60,000
Total = Rs. 3,68,00,000
Supervision & service charge @ 5% of total= 0.05*36800000 = Rs. 18,40,000
Contingencies @ 3% of total = 0.03*36800000 = Rs. 11,04,000
Grand Total= Rs. 39744000
Numerical:
2. Prepare a preliminary estimate of five
story building having carpet area of
each floor 150 m2 & floor height of 3 m,
the area required for circulation is 35 %,
wall area 10%, if the cube rate of
building is 20,000/m3. Assume the
necessary provision for electrification
and water supply sanitation is 20% of
the building cost.
Solution:
Using cube rate estimate:
Given:
5 story building
Let x be the plinth area of building
We know that
Plinth area= carpet area + circulation are + wall area
x= 150m2 + 35% of x + 10% of x
X= 150+0.35x + 0.1x
0.55x= 150
X= 150/ 0.55 = 272.72 m2
Volume of each floor= 272.72 m2 * 3 m
= 818.16 m3
Total volume of 5 story building = 5 * 818.16 = 4090.8 m3
Total cost of plinth area = 4090.8 * 20,000
= Rs. 81816000
Electrical & sanitation cost= Rs. 81816000 * 0.2 =Rs. 16363200
Total cost of the building = Rs. (81816000 + 16363200)
= Rs. 98179200
Thank You