SCHEDULE OF FOOTING
FOOTING REINFORCEMENTS
DEPTH ( D ) LENGTH WIDTH THICKNESS
MARK
(L) (W) (T) REMARKS
MINIMUM SHORT BARS LONG BARS
( mm ) ( mm ) ( mm ) ( mm ) BOTTOM BOTTOM
Provide Top Bars Ø12 @
F-1 1800 4000 2500 300 Ø16 @200 O.C. Ø16 @200 O.C.
200 o.c. Both Ways
Provide Top Bars Ø12 @
F-1 1800 3600 1500 300 Ø16 @250 O.C. Ø16 @250 O.C.
250 o.c. Both Ways
WF-1 1800 925 800 200 Ø12 @ 200 O.C. 4 - Ø12
PROJECT
MCC CITICORE CONSTRUCTION INC.
C:\Users\piotr\Downloads\MCC CCI LOGO.jpg
ARAYAT 50MW (AC) SPP
GREENCORE POWER SOLUTIONS 3
FIREWALL FOUNDATION DETAIL TITLE
FIREWALL FOUNDATION DETAIL DRAWING NO. STATUS
PRELIMINARY
PROJECT PHASE
PRELIMINARY
DRAWN BY SIGNATURE DATE SCALE FORMAT REVISION
Joanne Christine B. German 06.30.2021 NTS A3 B