Project Plan For: Communitywide Health Insurance Customer Management System

This document provides a work breakdown structure (WBS) for a project to develop a Communitywide Health Insurance Customer Management system. The WBS defines deliverables across 5 phases: project management, business requirements, application development, testing, and deployment. It also includes a communication management plan and resource procurement plan for the first month.

Uploaded by

Lens New
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
143 views

Project Plan For: Communitywide Health Insurance Customer Management System

This document provides a work breakdown structure (WBS) for a project to develop a Communitywide Health Insurance Customer Management system. The WBS defines deliverables across 5 phases: project management, business requirements, application development, testing, and deployment. It also includes a communication management plan and resource procurement plan for the first month.

Uploaded by

Lens New
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Project plan

For

Communitywide Health Insurance Customer


Management system

This document provides project managers with a work breakdown structure


(WBS), which defines all of the application development project’s critical
deliverables.

December 2020
WBS for Communitywide Health Insurance Management system | 2020

1. Work breakdown structure

Project Start Monday, December 14, 2020


Assigne
Start End
No Tasks Weeks d Status Notes
Date Date
to
1 Phase 1: Project Management        

1.1  Communication management plan Addisu Dec 14  Dec 20  Done

 Resource procurement and


1.2 Addisu Dec 18   Dec 20   Done
management plan

1.3  Scope development Week 1 Dec 21   Dec 25   0%

1.4  Risk Management Plan Henok Dec 21   Dec 25   0%

1.5  Quality Management Plan Dec 21   Dec 25   0%

2 Phase 2: Business Requirements        


 Business Requirements
o Document all existing users
and user roles
2.1
o Regulatory compliance
o Business Process
All
o Reporting
Team
2.2  Define new business rules Week 1 Members Dec 26  May 29  InProgress

2.3  Define new workflow

2.5  Define specific UI requirements


 Define specific technology
2.6
requirements
2.7  Requirements Documentation

3 Phase 3: Application Development        

3.1  Development environment setup Week All    


2 up to Team     0%
 User Management Module 9 Members May 30  Feb 28  

University of Gondar – ICT Directorate, Software Team


WBS for Communitywide Health Insurance Management system | 2020

3.2  Setups Module

3.3  Organization Registration

3.4  Dashboard
   
3.5  Individual Customer Registration    

3.6  Reporting

4 Phase 4: Testing        

4.1  Test Environment Setup

4.2  Test Plan All


Team
 Unit testing Week March
4.3 Members Feb 29   0%
10 6

4.4  UAT

4.5  Results reporting

5 Phase 5: Deployment        

5.1  Production Data Migration

 Documentation
o End User Documentation
o Application Administration All
5.2    
Documentation Team
Week March March
Members 0%
o System Administrator 11 & 12 7  13 
   
Documentation
 Training
o End User Training
5.3
o System Administrator
Training
 Project End Friday March 13, 2021

University of Gondar – ICT Directorate, Software Team


WBS for Communitywide Health Insurance Management system | 2020

2. Communication Management Plane

Communication Plan

Project Name: Addisu Desalegn Beginning Date: December 14, 2020

Project Manager: Communitywide Health Insurance Customer


Completion Date: March 13, 2021
Management system

Project Objective
 Define to various woredas as well as governmental and non-governmental
organizations.
 Recording information about the Patients that come.
 Recording information related to diagnosis given to Patients.
 Keeping record of the Immunization provided to patients.
 Keeping information about various diseases and medicines available to cure them.
 Generating bills and any required reports.

Stakeholders

Stakeholders - target audience (list)


 University of Gondar Hospital
 UoG ICT software team
 Addis Abeba University
 Tikur Anbesa Hospital

Planning

University of Gondar – ICT Directorate, Software Team


WBS for Communitywide Health Insurance Management system | 2020

3. Resource procurement and management plan for first month

Total
No Items Months Quty Unit Unit Price
Price

1 Mobile card for 7members 7 No 200 1,400

2 Marker 5 Pack 50 250

3 Pen 5 Pack 250 1,280

4 Coffee/tea for 7 * 30 No 10 2,100


Month 1
5 Face Mask for 7 members 7*5 No 35 1,225

6 Water For 7 members 7 * 60 No 10 4,200

7 Internet for 7 developers 7 No 700 4,900

8 Internet Investment for 7 members 7 No 1500 10,500

9 Flash disk (64GB) 7 No 1500 10,500

Total 36,355