Risk Assessment For .Testing and Commissioning of Fire Damper
Risk Assessment For .Testing and Commissioning of Fire Damper
Title Risk assessment for Testing and Commissioning of Fire Dampers Risk Assesssment No.00482
Company OMEGA ENGINEERING W.L.L Department MEP Date:27/02/2020
Location Lusail Project Applicable to use: LUS-CP7B-QDSBG-MST-MC-00482
Discription of Activity/Task: Testing and Commissioning of Fire Dampers
GENERAL RISK ASSESSMENT
Ref Risk Rating Residual
. Activities Potential/Hazards Persons at Risk Risk Rating
No:
Control Measures
L S R L S R
Attempting to
access fire Repetitive activities. The TBT (Tool Box Talk), followed by (Daily Safety Task)
damper to Poor illumination. person Ensure correct assessment of edges to identify sharp
remove the Sharp edges. undertakin edges prior to inserting the hand.
7. Fusible Link. Body posture. g the test. Approach task cautiously to avoid cuts from sharp
. edges. 2 2 4
4 4 16 Ensure suitable and sufficient lighting standard are
made available at testing and commissioning area.
Adequate level of supervision.
Give adequate rest breaks and employ job rotation to
minimize fatigue.
Ensure provision & use of required PPEs especially
hand gloves.
. Health, Safety and Environtmantal Risk Assessment.
Title Risk assessment for Testing and Commissioning of Fire Dampers Risk Assesssment No.00482
Company OMEGA ENGINEERING W.L.L Department MEP Date:27/02/2020
Location Lusail Project Applicable to use: LUS-CP7B-QDSBG-MST-MC-00482
Discription of Activity/Task: Testing and Commissioning of Fire Dampers
GENERAL RISK ASSESSMENT
Ref Risk Rating Residual
. Activities Potential/Hazards Persons at Risk Risk Rating
No:
Control Measures
L S R L S R
Unsecured energy
sources.
Unsafe conditions
created by the activity All Shorting down by competent/authorized person.
Work
such as wall/floor workers Ensure all control devices are adequately
completion, managed/controlled as per plans.
opening are closed. who may
Housekeeping Ensure supplies to unwanted area are prevented by
Obstruction of work in
& energy isolation and then apply isolation procedure.
emergency control, the
8. security All sources of energy must be secure and locked with
firefighting equipment. affected
4 4 16 LOTO lock by authorised person only and tagged. 2 2 4
area.
Physical hazards Good standard of housekeeping to be maintained at
Superviso
Fire hazards due to the end and clean up spillages with content of spill kit
rs, and dispose waste appropriately.
human error.
foremen, Accesses/egresses to be properly managed, those
Environmental hazards. Engineers meant to be open must be kept open and those
Spillage, Contaminated . planned to be closed must be closed.
waste (hazardous), All emergency control must not be obstructed with
Flammable/explosive materials and emergency devices must not be
atmosphere. bypassed,
All potentially flying, falling material to be removed or
secured properly.
Observe, maintain safe and proper storage of
materials/equipment used, maintenance of PPEs after
use.
Post emergency contact at relevant locations.
. Health, Safety and Environtmantal Risk Assessment.
Title Risk assessment for Testing and Commissioning of Fire Dampers Risk Assesssment No.00482
Company OMEGA ENGINEERING W.L.L Department MEP Date:27/02/2020
Location Lusail Project Applicable to use: LUS-CP7B-QDSBG-MST-MC-00482
Discription of Activity/Task: Testing and Commissioning of Fire Dampers
GENERAL RISK ASSESSMENT
Ref Risk Rating Residual
. Activities Potential/Hazards Persons at Risk Risk Rating
No:
Control Measures
L S R L S R
Additional comment/Information: